Albert Teng
- Listed as
- architect, designer, engineer
- Firm
- Delta Groups Engineering Inc.
- Based in
- Pleasanton
- On San Francisco permits
- May 2008 to May 2017
29 permits since 2000 (engineer on 16 permits, architect on 12 permits, designer on 1 permit): 14 completed, 3 never finaled, 12 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 26, 2017 | Completed final sign-off Oct 2018 | 600 Stockton St | Mc Millan Electric | installation of equipment racks inside existing storage room, includes battery rack with less than 50 gallons of electrolytes. installation of one air conditioning unit. maher ord 155-13 na.Details
installation of equipment racks inside existing storage room, includes battery rack with less than 50 gallons of electrolytes. installation of one air conditioning unit. maher ord 155-13 na. | $20,000 |
| Aug 22, 2016 | Expired or cancelled cancelled Jan 2026 | 333 Market St | upgrade (e) electrical panel for (1) 19" rack for radio equipment to be installed. (1) h-frame for (6) mrru's & associating cabling. no exterior antennas or modifications are proposed. ** maher: n/a **Details
upgrade (e) electrical panel for (1) 19" rack for radio equipment to be installed. (1) h-frame for (6) mrru's & associating cabling. no exterior antennas or modifications are proposed. ** maher: n/a ** | $40,000 | |
| Apr 4, 2016 | Completed final sign-off Apr 2016 | 2633 Lombard St | Transceive Communications Inc. | remove of (e) at&t mobility wireless communications facility from 1st floor garage & 2 omni antennas on roof & ancillary cable & equipment. paint & patch to matchDetails
remove of (e) at&t mobility wireless communications facility from 1st floor garage & 2 omni antennas on roof & ancillary cable & equipment. paint & patch to match | $1,800 |
| Dec 24, 2015 | Never finaled issued Jan 2016, no final | 246 01st St | Ridge Communications Inc | verizon purpose to install two (2) new rrus-12/a2 units in an existing equipment room on the roof of the building at the site. n/a ordinance #155-13. temporary installation to be removed on later than 6/15/2016.Details
verizon purpose to install two (2) new rrus-12/a2 units in an existing equipment room on the roof of the building at the site. n/a ordinance #155-13. temporary installation to be removed on later than 6/15/2016. | $10,000 |
| Dec 11, 2015 | Completed final sign-off Jun 2016 | 1881 Post St | Ridge Communications Inc | verizon proposes to install 3 new rrus 12's and 3 new diplexers in existing equipment room in basement of building at site. also proposing to relocate 3 existing rrus 12's and remove 1 existing radio cabinet from with in same roomDetails
verizon proposes to install 3 new rrus 12's and 3 new diplexers in existing equipment room in basement of building at site. also proposing to relocate 3 existing rrus 12's and remove 1 existing radio cabinet from with in same room | $15,000 |
| Oct 8, 2015 | Expired or cancelled cancelled Dec 2016 | 333 Ofarrell St | Communication Technology Services Llc | proposal to install verizon wireless: das system, including 2 new equipment racks, 1 equipment cabinet, and 6 wall -mounted radios. all within extg head end room. no antennas are proposed. no exterior work is proposed. n/a maher.Details
proposal to install verizon wireless: das system, including 2 new equipment racks, 1 equipment cabinet, and 6 wall -mounted radios. all within extg head end room. no antennas are proposed. no exterior work is proposed. n/a maher. | $20,000 |
| Feb 12, 2015 | Expired or cancelled cancelled Jan 2026 | 525 Market St | verizoni das uses ext. antenna to serve indoor das system. proposed installation consists: dc power plant equip to occupy one(1) existing equip rack, radio equip to occupy two (2) existing equip racks, one(1) gps antenna & one(1) down antenna mounted to a new mounting pipe. associated wiring as reqdDetails
verizoni das uses ext. antenna to serve indoor das system. proposed installation consists: dc power plant equip to occupy one(1) existing equip rack, radio equip to occupy two (2) existing equip racks, one(1) gps antenna & one(1) down antenna mounted to a new mounting pipe. associated wiring as reqd | $30,000 | |
| Dec 18, 2014 | Completed final sign-off Nov 2016 | 1355 Market St | Communication Technology Services Llc | installation for the colocation of verision wireless equipment onto (e) indoor distributed antenna system consisting 1 gps antenna, 1 donor antenna mounted to a new mounting pipe and radio equipments mounted to 2 existing racks, associated communications and utilities wiring as required. maher n/a.Details
installation for the colocation of verision wireless equipment onto (e) indoor distributed antenna system consisting 1 gps antenna, 1 donor antenna mounted to a new mounting pipe and radio equipments mounted to 2 existing racks, associated communications and utilities wiring as required. maher n/a. | $30,000 |
| Dec 9, 2014 | Expired or cancelled cancelled Jan 2026 | 1 Embarcadero Center | verizon wireless, parking level 4- modification of an unmanned wireless facility consisting of: radio equipment mounted on (2) existing equipment racks, install dc power in existing rack. n/a ordinance #155-13Details
verizon wireless, parking level 4- modification of an unmanned wireless facility consisting of: radio equipment mounted on (2) existing equipment racks, install dc power in existing rack. n/a ordinance #155-13 | $25,000 | |
| Dec 1, 2014 | Expired or cancelled cancelled Mar 2020 | 1 Bush St | installation of a verizon wireless idas system consisting of 1-dc power plant, 1-radio equipment rack, 1-donor antenna, 1-gps antennaDetails
installation of a verizon wireless idas system consisting of 1-dc power plant, 1-radio equipment rack, 1-donor antenna, 1-gps antenna | $35,000 | |
| Oct 7, 2014 | Expired or cancelled cancelled Jul 2024 | 2 New Montgomery St | installation of a verizon wireless indoor distributed antenna (idas') system. 1 dc power plant & 2-19" radio racks. 1 gps antenna & 1 donor antenna. associated utilities & wiring as needed. ** maher: compliance with ordinance no# 155-13 not required **Details
installation of a verizon wireless indoor distributed antenna (idas') system. 1 dc power plant & 2-19" radio racks. 1 gps antenna & 1 donor antenna. associated utilities & wiring as needed. ** maher: compliance with ordinance no# 155-13 not required ** | $35,000 | |
| Oct 2, 2014 | Expired or cancelled cancelled Jan 2026 | 101 02nd St | idas uses exterior antenna to serve indoor das sym. installation includes:one(1)dc power plant and one(1)19" wide rack for radio equipmt,one(1)radio equipment boxmounted on a new h frame, one(1)wall mounted ac fan unit, one(1)condensing unit mounted on a new support frame,one(1) antenna mountingDetails
idas uses exterior antenna to serve indoor das sym. installation includes:one(1)dc power plant and one(1)19" wide rack for radio equipmt,one(1)radio equipment boxmounted on a new h frame, one(1)wall mounted ac fan unit, one(1)condensing unit mounted on a new support frame,one(1) antenna mounting | $30,000 | |
| Oct 2, 2014 | Never finaled issued Mar 2015, no final | 750 Kearny St | Vinculums Services Inc | verizon idas uses exterior antenna to serve indoor das system installation includes: one(1)dc power plant and two(2) 19" wide racks for radio equipment, one(1) antenna mounting pipe for one(1) gps qantenna and one(1) donor antennaDetails
verizon idas uses exterior antenna to serve indoor das system installation includes: one(1)dc power plant and two(2) 19" wide racks for radio equipment, one(1) antenna mounting pipe for one(1) gps qantenna and one(1) donor antenna | $30,000 |
| Oct 2, 2014 | Completed final sign-off Apr 2016 | 101 California St | Communication Technology Services Llc | idas uses exterior antenna to serve an indoor das system. proposed installation consists of: one(1)dc power plant, radio equipments mounted to two(2)existing racks, one(1)gps antenna and one(1)donor antenna mounted to a new mounting pipe (comply with maher ordinance extended ordinance no.155-13 notDetails
idas uses exterior antenna to serve an indoor das system. proposed installation consists of: one(1)dc power plant, radio equipments mounted to two(2)existing racks, one(1)gps antenna and one(1)donor antenna mounted to a new mounting pipe (comply with maher ordinance extended ordinance no.155-13 not | $30,000 |
| Oct 2, 2014 | Completed final sign-off Nov 2016 | 50 Fremont St | Communication Technology Services Llc | idas uses exterior antenna to serve indoor das system proposed installation consists of: one(1) dc power plant, radio equipments mounted to two(2) existing racks, one(1) gps antenna and one(1)donor antenna mounted to a new mounting pipe (comply with maher ordinance extended no.155-13 not required)Details
idas uses exterior antenna to serve indoor das system proposed installation consists of: one(1) dc power plant, radio equipments mounted to two(2) existing racks, one(1) gps antenna and one(1)donor antenna mounted to a new mounting pipe (comply with maher ordinance extended no.155-13 not required) | $30,000 |
| Sep 26, 2014 | Completed final sign-off Apr 2016 | 345 Stockton St | Communication Technology Services Llc | installation of verizon indoor distributed antenna (idas) system. install 1 radio rack in (e) communication room (20" x 15" x 60"). install 1 dc power plant. install 1 ad-pa-1921-18-20 hfb antenna. install 1 gps antenna.Details
installation of verizon indoor distributed antenna (idas) system. install 1 radio rack in (e) communication room (20" x 15" x 60"). install 1 dc power plant. install 1 ad-pa-1921-18-20 hfb antenna. install 1 gps antenna. | $35,000 |
| Sep 26, 2014 | Expired or cancelled cancelled Mar 2020 | 55 02nd St | installation of verizon indoor distributed antenna (idas) system. install 1 radio rack in (e) communication room (20" x 15" x 60"). install 1 dc power plant. install 1 adpa-1921-18-20 hfb antenna. install 1 gps antenna. ** maher: compliance with ordinance no# 155-13 not required **Details
installation of verizon indoor distributed antenna (idas) system. install 1 radio rack in (e) communication room (20" x 15" x 60"). install 1 dc power plant. install 1 adpa-1921-18-20 hfb antenna. install 1 gps antenna. ** maher: compliance with ordinance no# 155-13 not required ** | $35,000 | |
| Jan 16, 2014 | Never finaled issued Jan 2014, no final | 101 California St | Young Electric Co | installation of telecom equipment inside extg room at basement.Details
installation of telecom equipment inside extg room at basement. | $50,000 |
| Feb 5, 2013 | Completed final sign-off Apr 2014 | 1 Sansome St | Metropolitan Electrical Construction | installation of an unmanned telecommunications equipment rooms @ lower level.Details
installation of an unmanned telecommunications equipment rooms @ lower level. | $85,000 |
| Feb 27, 2012 | Completed final sign-off Mar 2012 | 6221 Geary Bl | Cccs, Inc | new layout for installation of lte cabinet per pa#201004089881Details
new layout for installation of lte cabinet per pa#201004089881 | $3,000 |
| May 24, 2011 | Completed final sign-off Jun 2011 | 430 Bush St | Roebbelen Contracting Inc | t-mobile. re attach two panel antennas previously approved under pa# 9520623Details
t-mobile. re attach two panel antennas previously approved under pa# 9520623 | $3,000 |
| Sep 10, 2010 | Completed final sign-off Feb 2011 | 890 Jackson St | Delta Groups Construction Inc | installation of proposed wireless facility including 7 panel antennas and 1 gps antenna at rooftop of building, 4 microcell cabinets at basement of building, associated utilities and coax cablesDetails
installation of proposed wireless facility including 7 panel antennas and 1 gps antenna at rooftop of building, 4 microcell cabinets at basement of building, associated utilities and coax cables | $150,000 |
| Oct 13, 2009 | Completed final sign-off Jul 2010 | 1160 Illinois St | Delta Groups Construction Inc, Transceive Communications Inc. | install 6 panel antennas and 1 gps antenna to exterior penthouse wall and 1 panel antenna to east side building parapet wall. install cabling from new antennas through roof penetration to new equip area 1 floor below roof level. partition off with wood framing and drywall and air condition aDetails
install 6 panel antennas and 1 gps antenna to exterior penthouse wall and 1 panel antenna to east side building parapet wall. install cabling from new antennas through roof penetration to new equip area 1 floor below roof level. partition off with wood framing and drywall and air condition a | $75,000 |
| Mar 30, 2009 | Completed final sign-off Feb 2011 | 611 Folsom St | Roebbelen Contracting Inc | modification to (e) t-mobile tele communications facility, including relocation of (1) bts equipment cabinet from inside (e) elevator penthouse to (e) t-mobile equipment area located outside of penthouse. equipment will not be visible from public view.Details
modification to (e) t-mobile tele communications facility, including relocation of (1) bts equipment cabinet from inside (e) elevator penthouse to (e) t-mobile equipment area located outside of penthouse. equipment will not be visible from public view. | $5,000 |
| Mar 17, 2009 | Expired or cancelled cancelled Feb 2012 | 1250 Columbus Av | add 1 equipment cabinet on roof and replace 3 antennas at extg wireless telecommunications faucility(t-mobile)Details
add 1 equipment cabinet on roof and replace 3 antennas at extg wireless telecommunications faucility(t-mobile) | $20,000 | |
| Jun 5, 2008 | Completed final sign-off Apr 2011 | 1 Mccoppin St | Roebbelen Contracting Inc | modify existing t-mobile wireless telecommunications facility. replace 1 equipment cabinet at roof top. replace 3 existing antennas and add 2 additional antennas.Details
modify existing t-mobile wireless telecommunications facility. replace 1 equipment cabinet at roof top. replace 3 existing antennas and add 2 additional antennas. | $20,000 |
| May 29, 2008 | Expired or cancelled cancelled Jul 2016 | 2324 Market St | modify existing t-mobile wireless site. add 1 equipment cbinet and replace 6 antennas at rooftop.Details
modify existing t-mobile wireless site. add 1 equipment cbinet and replace 6 antennas at rooftop. | $20,000 | |
| May 29, 2008 | Expired or cancelled cancelled Jul 2015 | 2696 Geary Bl | modify existing t-mobile site, add 1 equipment cabinet & replace 6 antennas at rooftop.Details
modify existing t-mobile site, add 1 equipment cabinet & replace 6 antennas at rooftop. | $20,000 | |
| May 29, 2008 | Expired or cancelled cancelled Jun 2014 | 915 Folsom St | modify existing t-mobile site, add 1 equipment cabinet & replace 6 antennas at rooftop.Details
modify existing t-mobile site, add 1 equipment cabinet & replace 6 antennas at rooftop. | $20,000 |