Block 3736, lot 006
246 01st St
- City’s use
- Commercial Office
- Built
- 1900
- Stories
- 7
- Building
- 100,800 sq ft
- Lot
- 13,650 sq ft
- Zoning
- C3OSD
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
111 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 20, 2026 | In progress filed May 2026, not yet issued | 246 01st St | a modification of (e) verizon wirless unmanned telecommunication facility, removing (6) (e) antennas & adding (5), and associated antenna mount and other eq removal and installation. patch, repair, paint building face and parapet wall after antennas, mounts, cables & cable trays removed.Details
a modification of (e) verizon wirless unmanned telecommunication facility, removing (6) (e) antennas & adding (5), and associated antenna mount and other eq removal and installation. patch, repair, paint building face and parapet wall after antennas, mounts, cables & cable trays removed. | $145,000 | |
| Jan 26, 2023 | Completed final sign-off Mar 2023 | 246 01st St | barrier removal: install accessibility route directional signage to new designated accessible entry at tehama street. install exit only signage at two doors along 1st st. abe # 201805180531Details
barrier removal: install accessibility route directional signage to new designated accessible entry at tehama street. install exit only signage at two doors along 1st st. abe # 201805180531 | $3,000 | |
| Apr 19, 2021 | Completed final sign-off Sep 2021 | 246 01st St | Metropolitan Electrical Construction | replace existing errcs bda to bring to 2019 frequencies. the new bda will be installed in the same location as the current, no structural changes. the donor antenna will be installed at the same location as the current donor no structural changes.Details
replace existing errcs bda to bring to 2019 frequencies. the new bda will be installed in the same location as the current, no structural changes. the donor antenna will be installed at the same location as the current donor no structural changes. | $22,390 |
| Aug 7, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | administrative permit to document sffd assembly (a-3) permit within an office (b occupancy) for pa 2018-1102-4845 no work under this permit.Details
administrative permit to document sffd assembly (a-3) permit within an office (b occupancy) for pa 2018-1102-4845 no work under this permit. | |
| Jun 11, 2019 | Never finaled issued Jun 2019, no final | 246 01st St | Thomas Swan Sign Co Inc | to erect one (38"x130") set of halo illuminated electrical channel sign (sofi)Details
to erect one (38"x130") set of halo illuminated electrical channel sign (sofi) | $12,000 |
| May 20, 2019 | Completed final sign-off Jun 2019 | 246 01st St | Bilcor Inc | fls tenant improvement. install 49 ceiling strobes, 33 ceiling forn strobe, 15 wall strobe, 71 wall horn strobe, 1 weatherproof wall strobe, 40 smoke det w base, 8 duct detectors, 11 control relays, 3 booster panel, power supply, ref 201905130465, 2019105130464, mep 201905080110Details
fls tenant improvement. install 49 ceiling strobes, 33 ceiling forn strobe, 15 wall strobe, 71 wall horn strobe, 1 weatherproof wall strobe, 40 smoke det w base, 8 duct detectors, 11 control relays, 3 booster panel, power supply, ref 201905130465, 2019105130464, mep 201905080110 | $113,520 |
| May 13, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | basement, 1st, 2nd fl - new power & data, new breakrooms, new lighting & controls.Details
basement, 1st, 2nd fl - new power & data, new breakrooms, new lighting & controls. | $30,000 |
| May 13, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | basement, 1st & 2nd fl - install new vrv fancoil system, new branch selector box, new supply and return diffusers. ref pa #201905080110.Details
basement, 1st & 2nd fl - install new vrv fancoil system, new branch selector box, new supply and return diffusers. ref pa #201905080110. | $85,000 |
| May 13, 2019 | Completed final sign-off Jun 2019 | 246 01st St | Bcci Construction Company | 3rd, 4th, 5th, 6th fl - mechanical, electrical, plumbing, permit to install new fancoil system, branch selector, supply & return diffusers. new power, data, new lighting & controls. ref pa #201905080099.Details
3rd, 4th, 5th, 6th fl - mechanical, electrical, plumbing, permit to install new fancoil system, branch selector, supply & return diffusers. new power, data, new lighting & controls. ref pa #201905080099. | $85,000 |
| May 8, 2019 | Completed final sign-off Jun 2019 | 246 01st St | Bcci Construction Company | revision to app#201811024847 and app#201902122695 to change rating on equipment rooms walls and doors only. n/a for maherDetails
revision to app#201811024847 and app#201902122695 to change rating on equipment rooms walls and doors only. n/a for maher | |
| May 8, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | revision to app#201811024845. revised locations of sump pump 015 and lactation room 014. n/a for maherDetails
revision to app#201811024845. revised locations of sump pump 015 and lactation room 014. n/a for maher | |
| Apr 12, 2019 | Never finaled issued Apr 2019, no final | 246 01st St | street spaceDetails
street space | ||
| Apr 10, 2019 | Never finaled issued Apr 2019, no final | 246 01st St | Schaper Company | street spaceDetails
street space | |
| Mar 27, 2019 | Completed final sign-off Jun 2019 | 1 Tehama St | Ayoob & Peery Plumbing Co Inc | ref pa# 201812269126; field as builtDetails
ref pa# 201812269126; field as built | |
| Mar 26, 2019 | Never finaled issued Mar 2019, no final | 246 01st St | mta metersDetails
mta meters | ||
| Mar 20, 2019 | Never finaled issued Mar 2019, no final | 1 Tehama St | street spaceDetails
street space | ||
| Mar 11, 2019 | Completed final sign-off Jul 2019 | 1 Tehama St | Ayoob & Peery Plumbing Co Inc | ref # 2018-1221-8963: add/relocate and remove fire sprinkler per tenant improvements. 21 added, 66 relocated, and 33 removed total.(basement to 2nd floor)Details
ref # 2018-1221-8963: add/relocate and remove fire sprinkler per tenant improvements. 21 added, 66 relocated, and 33 removed total.(basement to 2nd floor) | $25,875 |
| Mar 11, 2019 | Completed final sign-off Jun 2019 | 1 Tehama St | Ayoob & Peery Plumbing Co Inc | ref # 2018-1226-9126: add/relocate and remove fire sprinkler per tenant improvements. 70 added, 103 relocated, and 75 removed total.(3rd to 6th floor)Details
ref # 2018-1226-9126: add/relocate and remove fire sprinkler per tenant improvements. 70 added, 103 relocated, and 75 removed total.(3rd to 6th floor) | $59,925 |
| Feb 12, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | revision to pa 201811024847. conference rooms modificationsDetails
revision to pa 201811024847. conference rooms modifications | |
| Feb 12, 2019 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | revision to pa 201811024845. modifications to pantry and storage roomDetails
revision to pa 201811024845. modifications to pantry and storage room | |
| Jan 11, 2019 | Never finaled issued Jan 2019, no final | 1 Tehama St | street spaceDetails
street space | ||
| Dec 26, 2018 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | mep's for pa 201811024847 architectural drawings. install new vav boxes, new supply & return diffusers and independent air & water balancing. n/a for maher.Details
mep's for pa 201811024847 architectural drawings. install new vav boxes, new supply & return diffusers and independent air & water balancing. n/a for maher. | $150,000 |
| Dec 21, 2018 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | basement, 1st & 2nd flrs. install new vrv fancoil system, branch selector box, new supply and return diffuser and independent air & water balancing. ref 201811024845. n/a for maher.Details
basement, 1st & 2nd flrs. install new vrv fancoil system, branch selector box, new supply and return diffuser and independent air & water balancing. ref 201811024845. n/a for maher. | $190,000 |
| Nov 28, 2018 | Never finaled issued Nov 2018, no final | 246 01st St | street spaceDetails
street space | ||
| Nov 28, 2018 | Never finaled issued Nov 2018, no final | 1 Tehama St | street spaceDetails
street space | ||
| Nov 20, 2018 | Completed final sign-off Feb 2019 | 246 01st St | Bilcor Inc | emergency responder radio coverage system(errcs) monitoring. install (1) smoke detector, (1) dedicated led annunciator for (errs) monitoring, and (6) dual monitor modules.Details
emergency responder radio coverage system(errcs) monitoring. install (1) smoke detector, (1) dedicated led annunciator for (errs) monitoring, and (6) dual monitor modules. | $4,800 |
| Nov 9, 2018 | Completed final sign-off Feb 2019 | 246 01st St | Dome Construction Corp | revision to app#201507272516 s1. add urinal partitions. n/a for maherDetails
revision to app#201507272516 s1. add urinal partitions. n/a for maher | |
| Nov 2, 2018 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | t.i. of four floors for single tenant to include new non-load bearing partitions. mep deffered. n/a for maherDetails
t.i. of four floors for single tenant to include new non-load bearing partitions. mep deffered. n/a for maher | $4,000,000 |
| Nov 2, 2018 | Completed final sign-off Nov 2019 | 246 01st St | Bcci Construction Company | ti of a full 3 floors for a single tenant to include new non-load bearing partitions mep deferredDetails
ti of a full 3 floors for a single tenant to include new non-load bearing partitions mep deferred | $3,000,000 |
| Oct 31, 2018 | Completed final sign-off May 2019 | 246 01st St | Dome Construction Corp | revision to 201507272516 & 201711174290. to show new electrical data riser closet; smoke curtain under orginal permit 201507272516. 1 hr rated usg-shaftwall.Details
revision to 201507272516 & 201711174290. to show new electrical data riser closet; smoke curtain under orginal permit 201507272516. 1 hr rated usg-shaftwall. | |
| Oct 25, 2018 | Never finaled issued Oct 2018, no final | 246 01st St | street spaceDetails
street space | ||
| Oct 1, 2018 | Never finaled filed Oct 2018, never issued | 1 Tehama St | street space | ||
| Sep 25, 2018 | Never finaled issued Sep 2018, no final | 246 01st St | street space.Details
street space. | ||
| Sep 19, 2018 | Completed final sign-off Jan 2019 | 246 01st St | Redrock Security & Cabling Inc | installing emergency responder radio coverage system (errcs) throughout building. basement-roof.Details
installing emergency responder radio coverage system (errcs) throughout building. basement-roof. | $60,000 |
| Aug 1, 2018 | Completed final sign-off May 2019 | 246 01st St | Dome Construction Corp | fill in existing vaults in conjunction wiht dpw street improvementsDetails
fill in existing vaults in conjunction wiht dpw street improvements | $152,000 |
| May 8, 2018 | Never finaled issued May 2018, no final | 246 01st St | street spaceDetails
street space | ||
| Apr 26, 2018 | Never finaled issued Jun 2019, no final | 246 01st St | Apex Site Solutions Inc | remove verizon wireless sheltor on roof, install new platform on roof for view. verizon wireless outdoor equipment, install new 400 amp utility service for verizon wireless. no change to (e) antennasDetails
remove verizon wireless sheltor on roof, install new platform on roof for view. verizon wireless outdoor equipment, install new 400 amp utility service for verizon wireless. no change to (e) antennas | $250,000 |
| Apr 26, 2018 | Completed final sign-off Feb 2019 | 246 01st St | Bilcor Inc | install new fa system and 2-way ecs per 2016 codesDetails
install new fa system and 2-way ecs per 2016 codes | $30,000 |
| Feb 13, 2018 | Never finaled issued Feb 2018, no final | 246 01st St | Dome Construction Corp | administrative permit - roof deck assembly permit for a3 use (1st time). 191 occupants. ref pa 201507272516 s1/r1. maher n/aDetails
administrative permit - roof deck assembly permit for a3 use (1st time). 191 occupants. ref pa 201507272516 s1/r1. maher n/a | |
| Feb 7, 2018 | Completed final sign-off Dec 2018 | 246 01st St | Anderson, Rowe & Buckley, Inc. | existing fire sprinkler system t.i. 446 changed out sprinklers and 138 relocated sprinklers.ref app#201706018176, 201507272516, & 201711174290 n/a for maherDetails
existing fire sprinkler system t.i. 446 changed out sprinklers and 138 relocated sprinklers.ref app#201706018176, 201507272516, & 201711174290 n/a for maher | $116,800 |
| Nov 30, 2017 | Never finaled issued Nov 2017, no final | 1 Tehama St | per pa #201507272516, add address to block 3736, lot 006 as; 1 tehama streetDetails
per pa #201507272516, add address to block 3736, lot 006 as; 1 tehama street | ||
| Nov 17, 2017 | Completed final sign-off Feb 2019 | 246 01st St | Dome Construction Corp | revision to app#201507272516. relocate bldg elec room, data and elec closets and new gas meter room. n/a for maher.Details
revision to app#201507272516. relocate bldg elec room, data and elec closets and new gas meter room. n/a for maher. | |
| Oct 31, 2017 | Never finaled issued Oct 2017, no final | 246 01st St | street spaceDetails
street space | ||
| Jun 1, 2017 | Completed final sign-off Feb 2019 | 246 01st St | Dome Construction Corp | tenant improvement at 2nd, 3rd, 4th, and 5th floors including office partitions, break area and new drinking fountains. updated fire rated doors/partition walls, @ stair vestibules n/a for maher.Details
tenant improvement at 2nd, 3rd, 4th, and 5th floors including office partitions, break area and new drinking fountains. updated fire rated doors/partition walls, @ stair vestibules n/a for maher. | $1,500,000 |
| Mar 11, 2016 | Expired or cancelled cancelled Jan 2026 | 246 01st St | supplemental to 201311212559 to cover additonal scope. install concrete extension to existing column on roof of building at site maher not reqDetails
supplemental to 201311212559 to cover additonal scope. install concrete extension to existing column on roof of building at site maher not req | $2,500 | |
| Dec 24, 2015 | Never finaled issued Jan 2016, no final | 246 01st St | Ridge Communications Inc | verizon purpose to install two (2) new rrus-12/a2 units in an existing equipment room on the roof of the building at the site. n/a ordinance #155-13. temporary installation to be removed on later than 6/15/2016.Details
verizon purpose to install two (2) new rrus-12/a2 units in an existing equipment room on the roof of the building at the site. n/a ordinance #155-13. temporary installation to be removed on later than 6/15/2016. | $10,000 |
| Nov 12, 2015 | Never finaled issued Mar 2016, no final | 246 01st St | Walker Cellular Inc | roof: modification of an (e) t-mobile wireless telecom facility (wts) on bldg consisting of: removal of (2) (e) panel antennas from bldg facade; installation of (3) new antennas on antenna mounts concealed by frp screening, (3) new rrus, & (1) new antenna triped w/radome. n/a maher ordinanceDetails
roof: modification of an (e) t-mobile wireless telecom facility (wts) on bldg consisting of: removal of (2) (e) panel antennas from bldg facade; installation of (3) new antennas on antenna mounts concealed by frp screening, (3) new rrus, & (1) new antenna triped w/radome. n/a maher ordinance | $20,000 |
| Jul 27, 2015 | Completed final sign-off May 2019 | 246 01st St | Dome Construction Corp | demo of (e) mezzanine, new 2nd floor in its place. demo (e) freight elevator, install new passenger elevator. new ada restrooms on 2nd floor. new roof deck & stair access to roof. structural upgrades as well. (n) windows on south facade. ** maher: compliance with ordinance no# 155-13 not required **Details
demo of (e) mezzanine, new 2nd floor in its place. demo (e) freight elevator, install new passenger elevator. new ada restrooms on 2nd floor. new roof deck & stair access to roof. structural upgrades as well. (n) windows on south facade. ** maher: compliance with ordinance no# 155-13 not required ** | $4,500,000 |
| Aug 8, 2014 | Completed final sign-off Dec 2014 | 246 01st St | L.D. Strobel Co Ltd | for planning documentation purposes: 201405226512 to change plannings temporary installation date to january 31,2015. verizon wireless temporary 2 foot microwave. to extend permit onlyDetails
for planning documentation purposes: 201405226512 to change plannings temporary installation date to january 31,2015. verizon wireless temporary 2 foot microwave. to extend permit only | |
| Jul 1, 2014 | Completed final sign-off Oct 2014 | 246 01st St | Westower Communications | remove shelter, antennas, coax, mounts, & radio equipment, for nextel. n/a maher ordinance. nextelDetails
remove shelter, antennas, coax, mounts, & radio equipment, for nextel. n/a maher ordinance. nextel | $10,000 |
| May 22, 2014 | Completed final sign-off Dec 2014 | 246 01st St | install on roof 1 tripod with 1 2 ft microwave dish. power will come from existing cell site. from 6-1-14 to 6-30-14.Details
install on roof 1 tripod with 1 2 ft microwave dish. power will come from existing cell site. from 6-1-14 to 6-30-14. | $2,500 | |
| Nov 21, 2013 | Never finaled issued Aug 2015, no final | 246 01st St | Costrotta Construc Management Inc | verizon 6 antennas, add rrh units, raycap units, hybrid & ret cables, coax cabinets, add (n) stealth's screens, 3 new similar antennas in new location 18" back from parapet. abc painted to match..Details
verizon 6 antennas, add rrh units, raycap units, hybrid & ret cables, coax cabinets, add (n) stealth's screens, 3 new similar antennas in new location 18" back from parapet. abc painted to match.. | $18,000 |
| Apr 19, 2012 | Never finaled issued Apr 2012, no final | 246 01st St | Anderson, Rowe & Buckley, Inc. | 2nd, 3rd, 4th, roof - install (n) rooftop ac unit, boiler, hhw system & tie into (e) ductwork in (e) tenant spaces.Details
2nd, 3rd, 4th, roof - install (n) rooftop ac unit, boiler, hhw system & tie into (e) ductwork in (e) tenant spaces. | $150,000 |
| Apr 16, 2012 | Completed final sign-off Feb 2013 | 246 01st St | Double T Electric | install electrical for new ac unit, boiler pump & smoke & fire damper.Details
install electrical for new ac unit, boiler pump & smoke & fire damper. | $15,000 |
| Dec 27, 2011 | Expired or cancelled expired Dec 2014 | 246 01st St | Anderson, Rowe & Buckley, Inc. | create new mechanical shaft for future rooftop. airhanddler. permit to include shaft construction, shaft duct and pipe install. shaft to be fire rated.Details
create new mechanical shaft for future rooftop. airhanddler. permit to include shaft construction, shaft duct and pipe install. shaft to be fire rated. | $45,000 |
| Dec 20, 2011 | Never finaled issued Apr 2014, no final | 234 01st St | Metropolitan Electrical Construction | unmanned wireless facility consisting of 12 panel antennas and associated equipment on the roof of the subject buildingDetails
unmanned wireless facility consisting of 12 panel antennas and associated equipment on the roof of the subject building | $120,000 |
| Mar 10, 2011 | Expired or cancelled withdrawn Jan 2016 | 246 01st St | remove 1 (e) t-mobile cabinet & replace with 1 new t-mobile cabinet in same location on roof.Details
remove 1 (e) t-mobile cabinet & replace with 1 new t-mobile cabinet in same location on roof. | $3,500 | |
| Feb 8, 2011 | Expired or cancelled withdrawn Mar 2019 | 246 01st St | A Mc Carthy Engineering Inc | window infill at west wall property line due to new adjacent construction at 19 tehama st. original opening to be covered by this new construction. 2 window openings at 2nd, 3rd & 4th floor to be infilled.2 windows openings at 5th floor. partial infill new smaller window.Details
window infill at west wall property line due to new adjacent construction at 19 tehama st. original opening to be covered by this new construction. 2 window openings at 2nd, 3rd & 4th floor to be infilled.2 windows openings at 5th floor. partial infill new smaller window. | $39,000 |
| Nov 2, 2010 | Completed final sign-off Sep 2011 | 246 01st St | revision to 201008108460. change to da checklist, include 28" clear at toilet, plan at mezzanine to exclude lockers, solid 2 hr partiton wall to replace permitted glass wallDetails
revision to 201008108460. change to da checklist, include 28" clear at toilet, plan at mezzanine to exclude lockers, solid 2 hr partiton wall to replace permitted glass wall | ||
| Oct 26, 2010 | Never finaled issued Oct 2010, no final | 246 01st St | Anderson, Rowe & Buckley, Inc. | 2nd floor-tenant improvements to (e) fire sprinkler system-14 removed sprinklers & 11 new pendent sprinklersDetails
2nd floor-tenant improvements to (e) fire sprinkler system-14 removed sprinklers & 11 new pendent sprinklers | $1,000 |
| Aug 10, 2010 | Completed final sign-off Dec 2011 | 246 01st St | revision to 201007015738. reconfigure proposed walls to allow for toilets above e exterior alcove at 1st flDetails
revision to 201007015738. reconfigure proposed walls to allow for toilets above e exterior alcove at 1st fl | ||
| Jul 1, 2010 | Completed final sign-off Sep 2011 | 246 01st St | mezzanine level bathroom remodel. new walls reconfigured for code compliance. construction of locker room. all work internal.Details
mezzanine level bathroom remodel. new walls reconfigured for code compliance. construction of locker room. all work internal. | $55,000 | |
| Feb 11, 2010 | Expired or cancelled cancelled Jun 2013 | 234 01st St | Jemcom | relocate (e) facade-mounted antennas to pole-mount on inside of parapet, 3 antennas to be relocated.Details
relocate (e) facade-mounted antennas to pole-mount on inside of parapet, 3 antennas to be relocated. | $5,000 |
| May 14, 2009 | Completed final sign-off Oct 2009 | 246 01st St | Park Place Contractors, N S A Wireless Inc | replacement of (6) existing 4' antennas with (6) new 4' antennas. swap like for like antennas.Details
replacement of (6) existing 4' antennas with (6) new 4' antennas. swap like for like antennas. | $2,500 |
| Jan 9, 2009 | Completed final sign-off May 2010 | 246 01st St | Anderson, Rowe & Buckley, Inc. | remove detector check v.a. add backflow preventer (e) 6" fire serviceDetails
remove detector check v.a. add backflow preventer (e) 6" fire service | $4,000 |
| Dec 17, 2008 | Never finaled issued Dec 2008, no final | 246 01st St | sidewalk permit only.Details
sidewalk permit only. | ||
| Oct 15, 2008 | Expired or cancelled cancelled Mar 2012 | 246 01st St | modification to (e) wireless facility consisting of removing & replacing (2) existing antennas & adding 2 (n) antennas and adding (n) frp screen at sector "a".Details
modification to (e) wireless facility consisting of removing & replacing (2) existing antennas & adding 2 (n) antennas and adding (n) frp screen at sector "a". | $30,000 | |
| Nov 6, 2007 | Completed final sign-off Feb 2008 | 246 01st St | Anderson, Rowe & Buckley, Inc. | fire sprinkler system on 2nd fl. remove 8 sprinkler heads, reinstall 1, and add 11 heads.Details
fire sprinkler system on 2nd fl. remove 8 sprinkler heads, reinstall 1, and add 11 heads. | $3,000 |
| Sep 27, 2007 | Completed final sign-off Feb 2008 | 246 01st St | t/i 2nd floor restroom upgrade.mep under separate application. barrior removal only.Details
t/i 2nd floor restroom upgrade.mep under separate application. barrior removal only. | $30,000 | |
| Oct 12, 2006 | Completed final sign-off Oct 2006 | 246 01st St | to renew for final only #200509294328, #200510175737, #200509294327.Details
to renew for final only #200509294328, #200510175737, #200509294327. | ||
| Oct 6, 2006 | Completed final sign-off Oct 2006 | 246 01st St | to renew expired permit. pa# 2005/12/08/9847, pa# 2005/02/22/5916 & pa# 2005/03/29/8631 for final inspection.Details
to renew expired permit. pa# 2005/12/08/9847, pa# 2005/02/22/5916 & pa# 2005/03/29/8631 for final inspection. | ||
| Dec 15, 2005 | Completed final sign-off Apr 2006 | 246 01st St | Anderson, Rowe & Buckley, Inc. | expansion & t.i. (e) fire sprinkler system. 73 relocated sprinklers. 60 new sprinklers. no increase in area.Details
expansion & t.i. (e) fire sprinkler system. 73 relocated sprinklers. 60 new sprinklers. no increase in area. | $26,000 |
| Dec 8, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | rev. to pa#2005/02/22/5916 - no additional costDetails
rev. to pa#2005/02/22/5916 - no additional cost | ||
| Oct 17, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | addendum to applicatio 200502225916 add framing plan for existing mezzanine levelfor voluntary upgradeDetails
addendum to applicatio 200502225916 add framing plan for existing mezzanine levelfor voluntary upgrade | $8,000 | |
| Sep 29, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | tenant improvement. mechanical ventilation. work @ground floor & mezzanine @ suite# 100 only.Details
tenant improvement. mechanical ventilation. work @ground floor & mezzanine @ suite# 100 only. | $35,000 | |
| Sep 29, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | tenant improvement. mechanical. hvac work only at suite# 101 under this permit.Details
tenant improvement. mechanical. hvac work only at suite# 101 under this permit. | $30,000 | |
| Mar 29, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | oti-1 1st/fl-el,me, ls,sp.Details
oti-1 1st/fl-el,me, ls,sp. | $100,000 | |
| Feb 22, 2005 | Expired or cancelled expired Oct 2006 | 246 01st St | oti-1, 1st floor, el, me, ls, sp.Details
oti-1, 1st floor, el, me, ls, sp. | $76,800 | |
| Jan 28, 2005 | Completed final sign-off Jun 2006 | 246 01st St | L.D. Strobel Co Ltd | replace all antenna on gamma sector. replacing center antennas on beta sector. total of 6 antenna-3 antenna sector @ corner of 1st st & tehama st, 3-antenna sector @ west elevation.comply complaint #200010137 bid-insp.Details
replace all antenna on gamma sector. replacing center antennas on beta sector. total of 6 antenna-3 antenna sector @ corner of 1st st & tehama st, 3-antenna sector @ west elevation.comply complaint #200010137 bid-insp. | $2,500 |
| Feb 3, 2004 | Expired or cancelled expired Oct 2006 | 246 01st St | final inspection per app #200010203609 at 2nd floorDetails
final inspection per app #200010203609 at 2nd floor | ||
| Dec 19, 2003 | Never finaled issued Dec 2003, no final | 234 01st St | permit to renew 9518777 for final inspection and certificate of completion. to abate complaint 93003Details
permit to renew 9518777 for final inspection and certificate of completion. to abate complaint 93003 | ||
| Nov 4, 2003 | Expired or cancelled expired Oct 2006 | 246 01st St | Anderson, Rowe & Buckley, Inc. | provide tenant fire protection work 2nd floor toilet roomsDetails
provide tenant fire protection work 2nd floor toilet rooms | $4,000 |
| Jul 25, 2003 | Completed final sign-off Mar 2004 | 246 01st St | 3rd floor barrier removal & restroom remodelDetails
3rd floor barrier removal & restroom remodel | $30,000 | |
| Jul 11, 2003 | Completed final sign-off Mar 2004 | 246 01st St | Anderson, Rowe & Buckley, Inc. | 3/f- provide tenant fire protection. restrm-add/remove/relocate (e)15 sprinklers, pipe scheduleDetails
3/f- provide tenant fire protection. restrm-add/remove/relocate (e)15 sprinklers, pipe schedule | $4,200 |
| Feb 18, 2003 | Expired or cancelled expired Aug 2005 | 246 01st St | renew expired permit app 200105159207Details
renew expired permit app 200105159207 | ||
| Aug 27, 2002 | Expired or cancelled cancelled Aug 2002 | 234 01st St | paint signDetails
paint sign | ||
| Jul 10, 2002 | Expired or cancelled expired Aug 2005 | 246 01st St | Anderson, Rowe & Buckley, Inc. | provide tenant fire protection work ground floor, fire sprinkler plan only at 1st fl only.Details
provide tenant fire protection work ground floor, fire sprinkler plan only at 1st fl only. | $8,400 |
| May 17, 2002 | Expired or cancelled expired Aug 2005 | 246 01st St | Kent M Lim & Company Inc | mech hvac installation on 1st floor. architectural work under 2002/05/13/6358.Details
mech hvac installation on 1st floor. architectural work under 2002/05/13/6358. | $23,000 |
| May 13, 2002 | Expired or cancelled expired Aug 2005 | 246 01st St | office tenant improvment add mens/womens shower/lockers mech/ltg permit separateDetails
office tenant improvment add mens/womens shower/lockers mech/ltg permit separate | $150,000 | |
| Feb 28, 2002 | Expired or cancelled expired Aug 2005 | 246 01st St | revision to app #200105159207/change to walls and doors at basement print shopDetails
revision to app #200105159207/change to walls and doors at basement print shop | $100 | |
| Jan 28, 2002 | Expired or cancelled expired Jul 2002 | 246 01st St | lobby renovation: (n) front door. add wall @ (e) stairDetails
lobby renovation: (n) front door. add wall @ (e) stair | $20,000 | |
| Jan 22, 2002 | Completed final sign-off Jul 2002 | 246 01st St | install 3 new panel antenas and replace one extg panel antenna on north facadeDetails
install 3 new panel antenas and replace one extg panel antenna on north facade | $5,000 | |
| Dec 7, 2001 | Expired or cancelled expired Aug 2005 | 246 01st St | update plans to reflect site conditions #200103305685 no increase of office spaceDetails
update plans to reflect site conditions #200103305685 no increase of office space | $1,500 | |
| Jul 18, 2001 | Expired or cancelled expired Oct 2003 | 246 01st St | Anderson, Rowe & Buckley, Inc. | provide tenant fire protection work 1st and 5th floors per app #200103305685Details
provide tenant fire protection work 1st and 5th floors per app #200103305685 | $3,760 |
| May 15, 2001 | Expired or cancelled expired Aug 2005 | 246 01st St | demo non partitions, add two and upgrade exit handrailDetails
demo non partitions, add two and upgrade exit handrail | $2,500 | |
| Apr 27, 2001 | Completed final sign-off Dec 2001 | 246 01st St | (5th floor only) restrm upgrade-barrier removal onlyDetails
(5th floor only) restrm upgrade-barrier removal only | $30,000 | |
| Apr 11, 2001 | Expired or cancelled expired Sep 2003 | 246 01st St | Trim Fit Constr. - O'reilly Engineering | revision to 200011095340 delete shower at womens restroomDetails
revision to 200011095340 delete shower at womens restroom | $100 |
| Apr 10, 2001 | Expired or cancelled expired Apr 2002 | 246 01st St | street spaceDetails
street space | ||
| Mar 30, 2001 | Expired or cancelled expired Sep 2001 | 246 01st St | add 1 hr. rated partition on 1/fl. at west side of bldg. & 1 hr. door & 20 min. door at b asementDetails
add 1 hr. rated partition on 1/fl. at west side of bldg. & 1 hr. door & 20 min. door at b asement | $6,000 | |
| Mar 30, 2001 | Completed final sign-off Aug 2001 | 246 01st St | Metropolitan Electrical Construction | install 1 compact antenna on the bldg. facade & related equipment on the roofDetails
install 1 compact antenna on the bldg. facade & related equipment on the roof | $35,000 |
| Feb 2, 2001 | Expired or cancelled expired Nov 2002 | 246 01st St | Ledda Plumbing Inc | run new main 8 new hds at 246 1st 4thflrDetails
run new main 8 new hds at 246 1st 4thflr | $800 |
| Dec 26, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | oti-3 4th flr sp onlyDetails
oti-3 4th flr sp only | $50,000 | |
| Dec 1, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | oti-2 4/f el meDetails
oti-2 4/f el me | $40,000 | |
| Nov 30, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | Potter Fire Protection | relocate 37 fire sprinkler heads on 4th floorDetails
relocate 37 fire sprinkler heads on 4th floor | $6,000 |
| Nov 21, 2000 | Expired or cancelled expired Jul 2003 | 234 01st St | Trim Fit Constr. - O'reilly Engineering | sheetrock walls fire tape.Details
sheetrock walls fire tape. | $2,500 |
| Nov 14, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | oti-1 4th floor electrical,mechanical, sprinkler,Details
oti-1 4th floor electrical,mechanical, sprinkler, | $200,000 | |
| Nov 9, 2000 | Completed final sign-off Apr 2001 | 246 01st St | accessble ug to rest rooms on 4th fl. and unisex shower. barier removal onlyDetails
accessble ug to rest rooms on 4th fl. and unisex shower. barier removal only | $45,000 | |
| Oct 20, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | office renovation. wall,door,millwork equipment. install walls,partitions,doors,finishes,paint.lightDetails
office renovation. wall,door,millwork equipment. install walls,partitions,doors,finishes,paint.light | $25,000 | |
| Oct 13, 2000 | Expired or cancelled expired Nov 2002 | 246 01st St | Star Plumbing & Fire Const Co. | install two new fire sprinklers heads on roofDetails
install two new fire sprinklers heads on roof | $800 |
| Aug 3, 2000 | Expired or cancelled expired Dec 2000 | 246 01st St | street space useDetails
street space use | ||
| May 11, 2000 | Expired or cancelled expired Jul 2003 | 246 01st St | building prefab shelter on roof w/antennas below bldg heightDetails
building prefab shelter on roof w/antennas below bldg height | $65,000 |