| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 31, 2026 | In progress issued Jul 2026 | 750 Kearny St | removal of kearny street pedestrian bridge that connects sf rec and park property to hilton hotel. | $950,000 | |
| Jan 9, 2026 | In progress filed Jan 2026, not yet issued | 750 Kearny St | revision 202405162280- t- mobile modification under 6409 elegible facility request simplifed upgrade to antennas and ancillary equipment within (e) lease area | $60,000 | |
| Mar 24, 2025 | Completed final sign-off Mar 2026 | 750 Kearny St | 2/f & 3/f - modification of four fire/life safety egress doors. | $8,000 | |
| May 16, 2024 | In progress issued Jan 2025 | 750 Kearny St | Metropolitan Electrical Construction | t-mobile remove all (e) cabinets; install 2(n) cabinets; remove & replace 6 antennas; install (n) frp screen; install 12(n) batteries; install (n) conduits for cabinets | $75,000 |
| Jun 14, 2019 | Expired or cancelled withdrawn May 2024 | 750 Kearny St | t-mobile. install 2 antenna mounts, install 2 antennas, remove & replace 2 antennas, remove rbs cabinets. install hybrid cables. n/a for maher | $25,000 | |
| Feb 26, 2019 | Never finaled issued Mar 2019, no final | 750 Kearny St | Swinerton Builders | non structural interior demo, drywell, doors, frames & hardware, plumbing fixtures reinstaled into previous location, finishes, create 2 model rooms on 23rd fl & 25th fl.(2 units only) | $165,000 |
| Oct 17, 2018 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | 25th floor: non-structural interior demolition, drywall, doors, frames, and hardware, plumbing fixtures reinstalled into previous locations, finishes. one unit only on 25th floor. mep on deferred permits, sprinkler & fire on seperate permits. n/a for maher | $75,000 | |
| Jun 27, 2018 | Completed final sign-off Aug 2019 | 750 Kearny St | abatement of nov 201633401 - remove unpermitted wood face decking & planters at roof. removing cooking counter at roof. | $25,000 | |
| May 29, 2018 | Completed final sign-off Oct 2020 | 750 Kearny St | Access Systems & Solutions Inc | install track system on facade of building and davit systems/equipments at roof to secure window washing equipment and light exterior maintenance. | $200,000 |
| Jan 31, 2018 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | sidewalk improvement for (e) hotel valet driveway revert (e) shuttle parking zone to original curb cut for access from valet driveway to washington street refer to permit # 201107210773. for original curb cut. | $6,000 | |
| Dec 21, 2017 | Never finaled issued May 2019, no final | 750 Kearny St | 5/f: minor non-structural demolition, drywall, doors, frames and hardware, plmg fixtures reinstalled into previous locations. n/a for maher. | $145,000 | |
| May 24, 2016 | Expired or cancelled withdrawn May 2018 | 750 Kearny St | Access Systems & Solutions Inc | install new aluminum tracks on the north, west and south elevation exteriors to provide stability anchors for window washing equiptment. | $291,500 |
| Nov 17, 2015 | Never finaled issued Dec 2015, no final | 750 Kearny St | Viking Sign Installations | install electric projecting illuminated wall sign, double faced. maher na | $5,000 |
| Nov 17, 2015 | Never finaled issued Dec 2015, no final | 750 Kearny St | Viking Sign Installations | install illuminated electric wall sign, single faced. maher na | $8,000 |
| Jul 21, 2015 | Completed final sign-off Dec 2017 | 750 Kearny St | Costrotta Construc Management Inc | t-mobile macro wts facility: remove (2) (e)panel antennas & install (2) 4'-0" panel antennas. install 4 new ericsson rrus-. remove (4) (e) tma's install (4) new tmas in place. t-mobile macro wts facility | $20,000 |
| Oct 2, 2014 | Never finaled issued Mar 2015, no final | 750 Kearny St | Vinculums Services Inc | verizon idas uses exterior antenna to serve indoor das system installation includes: one(1)dc power plant and two(2) 19" wide racks for radio equipment, one(1) antenna mounting pipe for one(1) gps qantenna and one(1) donor antenna | $30,000 |
| Aug 27, 2014 | Completed final sign-off Nov 2014 | 750 Kearny St | Johnson Controls Fire | 5th floor: fire alarm t.i. to provide and install 6 new speaker/strobes. ref app#201408224540. n/a for the maher ordinance #155-13 | $6,000 |
| Aug 22, 2014 | Never finaled issued Aug 2014, no final | 750 Kearny St | W. Wong Construction Co. Inc. | 5th flr: remodel (e) fitness center, remodel (e) sales office become spa treatment center, works include demolition, new walls, and ceiling, new cabinet, new ada bathroom, mepp and fire sprinkler, fire alarm under separate permit. maher n/a | $100,000 |
| Aug 12, 2014 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | 27th floor balcony and roof level to install exterior building maintenance equipment for suspension of permanent powered platform. maher n/a. | ||
| Aug 6, 2014 | Completed final sign-off Nov 2014 | 750 Kearny St | Johnson Controls Fire | fire alarm modification to ground floor, relocate 7 existing notification appliances, relocate 1 existing smoke detector, demo 5 existing appliances, demo 1 heat detector. t.i. pa#201312164313, n/a ordinance #155-13 | $8,500 |
| Jul 22, 2014 | Never finaled filed Jul 2014, never issued | 750 Kearny St | install 4 flagpoles along private pedestrian bridge that will display banners for chinese cultural center | ||
| Jul 22, 2014 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | 4 banner signs | $5,000 | |
| Jul 22, 2014 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | install 4 flagpoles along private pedestrian bridge that will display banners for chinese cultural cetner | $5,000 | |
| Jul 22, 2014 | Expired or cancelled cancelled Jan 2026 | 750 Kearny St | 4 banner signs | $5,000 | |
| Jun 13, 2014 | Completed final sign-off Sep 2014 | 750 Kearny St | B H Chen Inc | ground floor; relocate and replace 45 sprinkler heads on extg system. no new meter needed. app#201312164313. n/a maher ordinance # 155-13 | $9,500 |
| Jun 10, 2014 | Never finaled issued Jul 2014, no final | 750 Kearny St | W. Wong Construction Co. Inc. | provide, mechanical, electrical layout for remodelling of (e) spa to change to new meeting rooms and office; ref pa 201312164313. | $10,000 |
| Jan 13, 2014 | Never finaled issued Jan 2014, no final | 750 Kearny St | street space w/mta | ||
| Dec 16, 2013 | Never finaled issued Dec 2013, no final | 750 Kearny St | 5th floor - demolish (e) office walls. install (n) walls and ceiling to match (e) ceiling height. install (n) lighting, cabinetry, finishes and ada accessible bathroom. electrical, plumbing and sprinkler modifications under seperate permits | $5,000 | |
| Dec 16, 2013 | Never finaled issued Apr 2014, no final | 750 Kearny St | W. Wong Construction Co. Inc. | ground floor - demolish (e) spa area on ground floor. install (n) walls, ceilings, lighting and cabinetry. electrical, plumbing and sprinkler modifications will be performed under separate permits. ** maher: compliance with ordinance no# 155-13 not required ** | $290,000 |
| Nov 18, 2013 | Never finaled issued Nov 2013, no final | 750 Kearny St | comply with high rise sprinkler ordinance (377-93). to abate nov#200993154. | $150,000 | |
| Oct 25, 2013 | Never finaled issued Jan 2014, no final | 750 Kearny St | Tot'l Environm'l /Pwer Sym Inc Dba:Teps | revision to app#201211073765. revise plan page a-1 to update batteries on site to 16 m12v 155ft and remove nsb100 ft from a-1 page per fire dept. inspector james. | |
| May 30, 2013 | Never finaled issued May 2013, no final | 750 Kearny St | W. Wong Construction Co. Inc. | install partition wall & door for storage room on 3rd floor mezzanine plan. | $1,500 |
| May 24, 2013 | Never finaled issued May 2013, no final | 750 Kearny St | Simplexgrinnell Lp. | add new single interlock preaction system for new unmannd communications facility on level "a" parking of exgt. hilton hotel. also relocate branch line and 3 sprinklers, for coverage, around new room. 6 total fire sprinklers. ref app#201211073765. | $13,800 |
| Apr 25, 2013 | Never finaled issued Jun 2013, no final | 750 Kearny St | Simplexgrinnell Lp. | garage level a:add one facp 4100 u and one release control module, 2 smoke detectors, 5 iam monitors, one horn/strobe, one maintenance switch, one coil supervisory module for pre-action sprinkler system, garage level a equipment room. monitor of pre-action sprinkler system. | $13,000 |
| Apr 1, 2013 | Expired or cancelled withdrawn May 2024 | 750 Kearny St | Mt2 Telecom L P | a modification to an existing unmanned telecommunication facility conisting of adding a new vam and ciena unit a new telco box, a new nid box, a new fdp box, a new gfi box, and new fiber conduit. no antennas are associated with this project. | $2,000 |
| Mar 14, 2013 | Completed final sign-off Oct 2013 | 750 Kearny St | W. Wong Construction Co. Inc. | to comply with nov 201259521. convert 3rd fl bath to storage room. enlarge electrical closet at 5th fl | $5,000 |
| Feb 19, 2013 | Never finaled issued Feb 2013, no final | 750 Kearny St | install 2 new condensing boilers into existing system. install new thermostatic mixing valve. | $150,000 | |
| Nov 7, 2012 | Completed final sign-off Jan 2014 | 750 Kearny St | an unmanned telecommunications facility consisting of 1 22'-0" x 11'-0" at&t lease area w/a battery rack, a 26" rack w/a dcpower system, (1) 19" rack w/(4) 6601 rbs units, (1) 19" rack w/cci equip, (2) 19" racks w/das equip, (1) 19" rack w/(2) ciena's & (2) uam's, (3) rru's 11"s, a gps antenna | $135,000 | |
| Oct 12, 2012 | Completed final sign-off Jan 2013 | 750 Kearny St | Cosco Fire Protection Inc. | to obtain final inspection for work approved under pa # 200601192514. all work is complete. | |
| Jul 9, 2012 | Completed final sign-off Aug 2012 | 750 Kearny St | correction to permit # 201107210769 guestroom count per hid, dbi is now 547 after removal of one room under same permit | ||
| Aug 23, 2011 | Completed final sign-off Oct 2011 | 750 Kearny St | Cosco Fire Protection Inc. | relocate 4-sprinklers as needed for tenant improvement, raise piping as needed for new ceiling heights, ref. arch permit #201107210769. | $7,950 |
| Aug 17, 2011 | Completed final sign-off Oct 2012 | 750 Kearny St | Simplex Grinnell | add 2 multi candela ceiling mount speakers/strobes. one multi candela wallmount strobe, 1 strobe sync model for honors lounge on the 26th floor | $3,000 |
| Jul 21, 2011 | Completed final sign-off Nov 2011 | 750 Kearny St | demolish banquettes & cabinetry in ground floor dinning area. construct new cabinetry & counter tops. relocate banquettes seating, modify & extend lighting electrical, plumbing, and sprinklers under seperate permit. | $100,000 | |
| Jul 21, 2011 | Completed final sign-off Aug 2012 | 750 Kearny St | demolish 1 guest room on floor 26 and combine with conceige lounge close off one hour door & modify other doors on hallway. construct new walls cabinets and counter tops, install built in banquette seating & cabinets, electrical, plumbing and sprinklers under seperate permit. | $300,000 | |
| Jan 8, 2010 | Completed final sign-off May 2010 | 750 Kearny St | Metropolitan Electrical Construction | revision to pa# 2008.03.14.7190 to install steel platform on roof shown on delta 10 of 12/3/2009 on sheets t-1 and d-1 | $8,000 |
| Dec 10, 2009 | Never finaled issued Dec 2009, no final | 750 Kearny St | street space permit | ||
| Nov 9, 2009 | Never finaled issued Nov 2009, no final | 750 Kearny St | street space & mta | ||
| Aug 28, 2009 | Expired or cancelled cancelled Jan 2012 | 750 Kearny St | Metropolitan Electrical Construction | wts facility installation. 1-bts equipment cabinet : 3 panel antennas, (4) internet service exchanges switch antenna and (1) gps antenna on the roof top. | $45,000 |
| Mar 14, 2008 | Never finaled issued Oct 2009, no final | 750 Kearny St | Metropolitan Electrical Construction | unmanned installation of 8 panel antennas flush mounted and steathed at roof top, paint to match. install 4 corresponding bts equipment cabinets at existing. roof on platform and enclosed. antenna coaxial transmission lines to be run from bts to antennas | $100,000 |
| Nov 15, 2007 | Expired or cancelled expired Feb 2009 | 750 Kearny St | convert (e) coffee bar area into wine bar, minor remodel includes millwork, lighthing, removal of (e) counter and sink. fire sprinklers and mep under separate permit. | $100,000 | |
| Apr 4, 2007 | Never finaled issued Apr 2007, no final | 750 Kearny St | street space | ||
| Mar 2, 2007 | Completed final sign-off Jul 2007 | 750 Kearny St | relocate kitchen exhust unit on roof revision :200506246055 | $40,000 | |
| Feb 23, 2007 | Never finaled issued Feb 2007, no final | 750 Kearny St | street space permit only. | ||
| Jan 19, 2007 | Never finaled issued Jan 2007, no final | 750 Kearny St | street space street space | ||
| Mar 10, 2006 | Completed final sign-off Aug 2007 | 750 Kearny St | rvision to 200506155180 and 200512200682. perbuilding field inspector, submit plan to show wall at kitchdn to be non rated instead of 1 hr rated | ||
| Feb 8, 2006 | Completed final sign-off Mar 2006 | 750 Kearny St | Simplex Grinnell | installation of new ul300 ansul system in kitchen on 2nd flr | $4,500 |
| Jan 24, 2006 | Completed final sign-off Mar 2006 | 750 Kearny St | install a 240 sq.ft. coffee kiosh in the lobby of an existing hotel lobby | $120,000 | |
| Jan 24, 2006 | Completed final sign-off Jan 2007 | 750 Kearny St | per building field inspector, modify existing corridor exhaust at floor 14-25. mechanical duct installation - exempt by sec 1134b.2.1 ex4. | $110,000 | |
| Jan 19, 2006 | Expired or cancelled expired Feb 2009 | 750 Kearny St | Cosco Fire Protection Inc. | automatic fire sprinkler tenant improvement at floors 23,24, and 25(1 suite each) floor #26(2 suites) and floor 27 (3 suites) approx 70 fire sprinkler hds/all work is interior with no increase in space nor change in occupancy | $28,000 |
| Dec 20, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | revision to pa# 2005/06/15/5180. remove (e) tile finish, relocate (e) handsink, demo (e) electrical devices & plumbing connection. kitchen @ 1st & 2nd floor per pa# 2005/06/15/5180. | $30,000 | |
| Dec 20, 2005 | Completed final sign-off Jul 2007 | 750 Kearny St | revision to pa# 2005/02/04/4896. reconfiguration rooms on 5th floor to 27th floor per plan. m & e under separate permit. | $500,000 | |
| Dec 12, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | modify (e) corridor exhaust. | $100,000 | |
| Dec 12, 2005 | Completed final sign-off Jun 2006 | 750 Kearny St | install fire feature with associated ventilation system. | $75,000 | |
| Dec 2, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Simplex Grinnell | funish & install ansul fire system in kitchen exhaust hood on the 1st floor. comply n.o.v. building-200342811 & plumbing-200121798. | $4,000 |
| Nov 22, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Simplex Grinnell | install smoke detectors in corridors, 5/f-27/f | $45,000 |
| Oct 28, 2005 | Expired or cancelled cancelled Nov 2024 | 750 Kearny St | sign permit - electric, single faced. | $35,000 | |
| Oct 13, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Cosco Fire Protection Inc. | retrofit to an (e) parking garage "a" and "b". add sprinkler system in both levels | $87,000 |
| Oct 4, 2005 | Completed final sign-off Sep 2006 | 750 Kearny St | provide mechanical, electrical & plumbing for basement. mep for 1st-5th floors done under pa#2005/06/24/6055 | $50,000 | |
| Aug 29, 2005 | Completed final sign-off Jun 2006 | 750 Kearny St | erect single faced electric wall sign | $5,000 | |
| Aug 23, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Simplex Grinnell | remove/replace (e)visual & audible/visual devices in (e)ada guestrooms,floors:5,7,8,9,11,12,15,16,17 | $15,000 |
| Jul 29, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Cosco Fire Protection Inc. | modify (e) fire sprinkler system to accommodate t.i. demo (e) mains & branch lines & replace with new piping.(e)standpipes & risers to remain. | $128,851 |
| Jul 8, 2005 | Completed final sign-off Aug 2006 | 750 Kearny St | to erect sign - ground electric single faced wall sign. | $120,000 | |
| Jul 5, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | Cahill Contractors Inc | structural demo + shoring (temporary). reference app#200505091949. | $5,000 |
| Jun 27, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | provide t.i per plan for 3rd fl and mezzanine. and to correct nov#200342811. including (n) partition | $700,000 | |
| Jun 24, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | provide mechanical,electrical,plumbing per plan for floors 1-5 & basement | $200,000 | |
| Jun 23, 2005 | Completed final sign-off Jun 2006 | 750 Kearny St | Decker Electric Co Inc Electrical Contra | install new audible/visual devices throughout the renovation floors 1 thru 3rd floor mez. provide | $20,000 |
| Jun 17, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | provide t.i. for fitness room at 5/f.work includes new door,mill work,partition wall | $50,000 | |
| Jun 15, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | upgrade (e) kitchen equipment per plan. | $350,000 | |
| Jun 13, 2005 | Completed final sign-off Mar 2006 | 750 Kearny St | provide tenant improvement per plan for 1st, 2nd and basement floor including partition walls, | $1,850,000 | |
| May 9, 2005 | Completed final sign-off Jun 2006 | 750 Kearny St | enclose 27 floors, balcony, provide accessibility ramp and accessibility door, reduce the front door | $350,000 | |
| May 9, 2005 | Completed final sign-off Oct 2005 | 750 Kearny St | remove non structual interior finish per plan. interior soft demo on 1st, 2nd, 3rd, mezz, 5th fl | $180,000 | |
| Apr 21, 2005 | Expired or cancelled withdrawn Apr 2005 | 750 Kearny St | remodel of interior lobbby, restaurant, bar, mtg rooms , ballrooms and associated w/the hotel. work | $8,000,000 | |
| Feb 4, 2005 | Completed final sign-off Jul 2007 | 750 Kearny St | Cahill Contractors Inc | remove/replace bathroom door on each room.minor sheetrock work.relocate (e)electrical outlets | $3,500,000 |
| Jun 9, 2004 | Expired or cancelled expired Dec 2005 | 750 Kearny St | Simplex Grinnell | fire alarm upgrade for secondary elevator recall | $6,900 |
| Apr 30, 2004 | Never finaled issued Apr 2004, no final | 750 Kearny St | street space permit | ||
| Jan 23, 2004 | Never finaled issued Jan 2004, no final | 750 Kearny St | street space permit | ||
| Dec 31, 2003 | Expired or cancelled expired Dec 2005 | 750 Kearny St | Gci, Inc | removal & replacement of (e) storefront (11) bays, 22' wide x 30' high at washington st. & merchant | $969,000 |
| Oct 10, 2003 | Expired or cancelled expired Jan 2006 | 750 Kearny St | g/f- comply w/nov#200342811 delete work stated on appl#200111273582 & legalize partition wall built | $4,000 | |
| Jun 4, 2003 | Never finaled issued Jun 2003, no final | 750 Kearny St | street space | ||
| May 21, 2003 | Expired or cancelled expired Jan 2006 | 750 Kearny St | provide new gate on holiday inn bridge as per plans | $5,000 | |
| May 6, 2003 | Never finaled issued May 2003, no final | 750 Kearny St | street space permit | ||
| May 1, 2003 | Expired or cancelled expired Jan 2006 | 750 Kearny St | Gabric Construction | accesibilty upgrade alter (e) stairs and handrails to comply w/code, buid planters on 2 (e) stairs | $160,000 |
| Apr 1, 2003 | Never finaled issued Apr 2003, no final | 750 Kearny St | street space | ||
| Mar 11, 2003 | Expired or cancelled expired Mar 2004 | 750 Kearny St | mechanical for 4th floor. hvac only. 2003/02/18/7634. | ||
| Mar 11, 2003 | Expired or cancelled expired Mar 2004 | 750 Kearny St | water tank support on roof | $3,000 | |
| Mar 4, 2003 | Expired or cancelled expired Dec 2005 | 750 Kearny St | Gci, Inc | hvac, elect, lifesafety, fire sprinkler. tenant improvement including treatment rooms, reception are | $270,000 |
| Feb 18, 2003 | Completed final sign-off Dec 2005 | 750 Kearny St | Gci, Inc | hvac commercial permit modifications for meeting room on 4/f non structural | $40,000 |
| Jan 31, 2003 | Expired or cancelled expired Mar 2004 | 750 Kearny St | Simplex Grinnell | 4/f- fire alarm system modification | $6,000 |
| Jan 8, 2003 | Expired or cancelled expired Dec 2005 | 750 Kearny St | Gci, Inc | 4/fl- fire sprinkler & electrical work only, architectural t.i. work under seperate permit | $62,000 |
| Dec 18, 2002 | Expired or cancelled cancelled Apr 2009 | 750 Kearny St | install one antenna and one cabinet 20"x19"x 48" | $45,000 | |
| Dec 12, 2002 | Expired or cancelled expired Mar 2004 | 750 Kearny St | R L H Fire Protection Inc | fire sprinkler tenant improvement at 4th floor/relocate 46 heads | $6,000 |
| Nov 6, 2002 | Expired or cancelled expired Dec 2005 | 750 Kearny St | convert (e) offices on 4th flr, into hotel conference rooms. add new m & f ada public toilet facilit | $211,004 | |
| Nov 6, 2002 | Completed final sign-off Jun 2003 | 750 Kearny St | convert(e)conference rooms to hotel health spa-mep under separate permit sprinkler under sep permit | $211,004 | |
| Aug 19, 2002 | Completed final sign-off Jun 2003 | 750 Kearny St | soft demo of portions of g/fl & 4/fl as indicated (e) liofe safety element to comply w/17-98 sf amen | $30,000 | |
| May 2, 2002 | Expired or cancelled expired Oct 2002 | 750 Kearny St | Nickell Fire Equipment | remove dry chemincal fire system in kitchen hood and install wet chemical system to bring up to curr | $3,500 |
| Nov 27, 2001 | Expired or cancelled expired May 2002 | 750 Kearny St | build a new full height wall bet the new gallery & (e)auditorium | $10,000 | |
| Feb 15, 2001 | Expired or cancelled expired Aug 2001 | 750 Kearny St | street space | ||
| Oct 20, 2000 | Expired or cancelled expired Feb 2001 | 750 Kearny St | Pribuss Engineering Inc | fire spkr t.i. - add 2 heads. | $2,150 |
| Sep 28, 2000 | Expired or cancelled expired Jan 2001 | 750 Kearny St | Pribuss Engineering Inc | omega sprinkler heads | $3,200 |