Peter Birkholz
- Listed as
- architect, designer, engineer
- Firm
- Page & Turnbull
- Based in
- Sf
- On San Francisco permits
- Oct 2016 to Mar 2026
19 permits since 2000 (architect on 17 permits, designer on 1 permit, engineer on 1 permit): 11 completed, 2 in progress, 4 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 2, 2026 | In progress issued Mar 2026 | 2390 Bush St | Plant Construction Co, Lp | voluntary barrier removal to 1 bathroom on basement lvl, relocate lav, mep upgradeDetails
voluntary barrier removal to 1 bathroom on basement lvl, relocate lav, mep upgrade | $10,000 |
| Mar 24, 2025 | Completed final sign-off Mar 2026 | 750 Kearny St | 2/f & 3/f - modification of four fire/life safety egress doors.Details
2/f & 3/f - modification of four fire/life safety egress doors. | $8,000 | |
| Nov 13, 2023 | In progress issued Jan 2024 | 2389 Bush St | Kunkel Construction | voluntary structural strengthening and associated ada upgrades. infill portion of crawl space below entry. per asce 41-17Details
voluntary structural strengthening and associated ada upgrades. infill portion of crawl space below entry. per asce 41-17 | $150,000 |
| Jun 26, 2023 | Never finaled issued Jul 2023, no final | 760 02nd St | as built drawings for carbo dioxide linesDetails
as built drawings for carbo dioxide lines | ||
| May 25, 2023 | Completed final sign-off Dec 2023 | 2390 Bush St | Hp Build | voluntary structural. repair work at church bell tower structural work includes replacment of carroded steel bracing which was added during the 1990 seismic rehabiltation of the church. accessiblility upgrades: signage at parking lot, restroom, restroom work. maher n/a.Details
voluntary structural. repair work at church bell tower structural work includes replacment of carroded steel bracing which was added during the 1990 seismic rehabiltation of the church. accessiblility upgrades: signage at parking lot, restroom, restroom work. maher n/a. | $1,185,000 |
| Dec 20, 2022 | Never finaled filed Dec 2022, never issued | 760 Market St | project includes the rehabilitation & voluntary structural upgrade of the historic penthouse residence on the roof of 760 market. work includes interior and exterior rehabilitions of walls, windows, doors, roof ornament skylights, kitchen, bath and all associated mep. per coa motion n o 0459Details
project includes the rehabilitation & voluntary structural upgrade of the historic penthouse residence on the roof of 760 market. work includes interior and exterior rehabilitions of walls, windows, doors, roof ornament skylights, kitchen, bath and all associated mep. per coa motion n o 0459 | $1,200,000 | |
| Oct 2, 2020 | Completed final sign-off Jan 2022 | 1170 Sacramento St | Herrero Builders Incorporated | rev to pa201907246871; to incorporate misc. changes to details & scope additions under delta 4. maher n/a.Details
rev to pa201907246871; to incorporate misc. changes to details & scope additions under delta 4. maher n/a. | |
| Feb 25, 2020 | Completed final sign-off Nov 2022 | 760 02nd St | installation of an exterior canopy for outdoor seating for restaurant. self-supporting & partially attached to building. located along king st side of bldg, taking up most of raised plaza area on southeast side of main entry. remove (e) awnings. (e) wall at removed awning will be patched & painted.Details
installation of an exterior canopy for outdoor seating for restaurant. self-supporting & partially attached to building. located along king st side of bldg, taking up most of raised plaza area on southeast side of main entry. remove (e) awnings. (e) wall at removed awning will be patched & painted. | $15,000 | |
| Jul 24, 2019 | Completed final sign-off Jan 2022 | 1170 Sacramento St | Herrero Builders Incorporated | voluntary seismic upgrade to (e) 19-story residential building. ** maher; n/a **Details
voluntary seismic upgrade to (e) 19-story residential building. ** maher; n/a ** | $2,500,000 |
| Mar 22, 2019 | Never finaled issued Mar 2019, no final | 1 Grant Av | Jimenez Drywall Corporation | new back bar & cafe at level 1 and beverage bar with island back bar and shelving at mezzanine. mep under separate permit to pa2019 0319 5615 (e) hvac & lighting system to remain.Details
new back bar & cafe at level 1 and beverage bar with island back bar and shelving at mezzanine. mep under separate permit to pa2019 0319 5615 (e) hvac & lighting system to remain. | $60,000 |
| Feb 6, 2019 | Completed final sign-off Apr 2019 | 170 Maiden Ln | Hp Build | selective interior t.i. limited to construction of 2 new offices and modification of a conference room to make 2 smaller conference rooms and casework addition at extg break area. work on 5th floor. total work area 573 sq ftDetails
selective interior t.i. limited to construction of 2 new offices and modification of a conference room to make 2 smaller conference rooms and casework addition at extg break area. work on 5th floor. total work area 573 sq ft | $188,000 |
| Dec 11, 2018 | Completed final sign-off Aug 2021 | 1360 Jones St | replacement of deteriorated wood window with wood window with similar style and rail dimensions.selective demolition of interior finishes to accommodate replacement windows.localized interior and exterior painting around windows.windows shall not encroached into public way at its fully open positionDetails
replacement of deteriorated wood window with wood window with similar style and rail dimensions.selective demolition of interior finishes to accommodate replacement windows.localized interior and exterior painting around windows.windows shall not encroached into public way at its fully open position | $80,000 | |
| Nov 16, 2018 | Never finaled issued Nov 2018, no final | 200 Stockton St | Plant Construction Co, Lp | install temporary xmas signage decoration on building facade, decoration has 3 parts; 1 pendent and 2 branches. branch on stockton street shall not exceed 200 sf per planning code. remove by jan 25, 2019. n/a maherDetails
install temporary xmas signage decoration on building facade, decoration has 3 parts; 1 pendent and 2 branches. branch on stockton street shall not exceed 200 sf per planning code. remove by jan 25, 2019. n/a maher | $12,500 |
| Jul 12, 2018 | Expired or cancelled withdrawn Oct 2020 | 1170 Sacramento St | voluntary seismic upgrade. structural strengthening of exterior lobby & garage lvl exterior columns w/ frp structural wrap. structural strengthening of (e) elevator core interior & exterior shaft. strengthening of exterior stairwell balcony concrete curbs. strengthening of 1st lvl garage ceilingDetails
voluntary seismic upgrade. structural strengthening of exterior lobby & garage lvl exterior columns w/ frp structural wrap. structural strengthening of (e) elevator core interior & exterior shaft. strengthening of exterior stairwell balcony concrete curbs. strengthening of 1st lvl garage ceiling | $850,000 | |
| Mar 23, 2018 | Expired or cancelled cancelled Oct 2022 | 180 Geary St | installation of rectilinear led light fixture at the interior of each window opening on the 4th floor facing stockton & geary streets, light fixture to be installed internally behind existing glazingDetails
installation of rectilinear led light fixture at the interior of each window opening on the 4th floor facing stockton & geary streets, light fixture to be installed internally behind existing glazing | $25,000 | |
| Jul 11, 2017 | Completed final sign-off Aug 2017 | 1 Grant Av | Jimenez Drywall Corporation | revision to pa 2017-0621-9963 removal of 5'-0" wode section of structural concrete wall at basement level as indicated by keynote 8 on drawing 1/d2.00Details
revision to pa 2017-0621-9963 removal of 5'-0" wode section of structural concrete wall at basement level as indicated by keynote 8 on drawing 1/d2.00 | |
| Jul 10, 2017 | Completed final sign-off Sep 2017 | 1 Grant Av | Jimenez Drywall Corporation | non structural interior alterations to the e structure. new interior walls, ceiling repairs, doors, finishes. mep lighting, fire sprinkler, life safety devices to be design build under separate permit. demo under bpa#201706219963Details
non structural interior alterations to the e structure. new interior walls, ceiling repairs, doors, finishes. mep lighting, fire sprinkler, life safety devices to be design build under separate permit. demo under bpa#201706219963 | $50,000 |
| Apr 19, 2017 | Completed final sign-off Sep 2021 | 1076 Howard St | Centric Construction Inc | conversion of factory bldg with partial mezzanine to a 2 story office bldg within the extg bldg envelope. work to include selective demo, change of use, seismic upgrade and foundation improvements. core and shell improvements including mechanical, electrical, & plmg upgrades. n/a for maherDetails
conversion of factory bldg with partial mezzanine to a 2 story office bldg within the extg bldg envelope. work to include selective demo, change of use, seismic upgrade and foundation improvements. core and shell improvements including mechanical, electrical, & plmg upgrades. n/a for maher | $750,000 |
| Oct 19, 2016 | Completed final sign-off Dec 2016 | 180 Sansome St | Rudolph And Sletten Inc | 3rd floor tenant improvement limited to non-structural interior walls & floor finishes. meps, life safety etc will be design build & submitted separately, n/a ordinance #155-13Details
3rd floor tenant improvement limited to non-structural interior walls & floor finishes. meps, life safety etc will be design build & submitted separately, n/a ordinance #155-13 | $342,244 |