Block 0309, lot 011
180 Geary St
- City’s use
- Commercial Retail
- Built
- 1987
- Stories
- 7
- Rooms
- 14 bathrooms
- Building
- 44,500 sq ft
- Lot
- 5,445 sq ft
- Zoning
- C3R
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
148 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 3, 2026 | Completed final sign-off Sep 2026 | 180 Geary St | Elson Electric Holdings Inc | 1st floor: office lobby-added lights and receptacles. ref pa #202603097187Details
1st floor: office lobby-added lights and receptacles. ref pa #202603097187 | $90,000 |
| Mar 9, 2026 | Completed final sign-off Sep 2026 | 180 Geary St | C C I Commercial Construction & Improv | t.i. of existing floor at 1st floor lobby, non structural partitionDetails
t.i. of existing floor at 1st floor lobby, non structural partition | $180,000 |
| May 30, 2025 | Completed final sign-off Jan 2026 | 180 Geary St | Bevilacqua & Sons | remove existing sidewalk around existing elevator opening. attach new l 4x4 3/8 around inside of face of (e) sidewalk elevator opening concrete walls. weld (n) steel deck and place concrete topping over steel deck. place (n) sidewalk topping slab around (e) grade and over (n) opening elevatorDetails
remove existing sidewalk around existing elevator opening. attach new l 4x4 3/8 around inside of face of (e) sidewalk elevator opening concrete walls. weld (n) steel deck and place concrete topping over steel deck. place (n) sidewalk topping slab around (e) grade and over (n) opening elevator | $30,000 |
| Jan 27, 2022 | Completed final sign-off Jul 2022 | 180 Geary St | Ericsson Inc Dba E U S Inc | at&t: modification cell-site. remove and replace 6 panel antennas, relocate 1 rru, install 1 dc9 box per sector-total 3, install (3) #6 awg power trunk, install new rf safety signs, stripping/barriers at rooftop. remove (4) 160 ah batteries, install 3 rectifiers in (e) dcpp, 1 new dc012rm in (e)rackDetails
at&t: modification cell-site. remove and replace 6 panel antennas, relocate 1 rru, install 1 dc9 box per sector-total 3, install (3) #6 awg power trunk, install new rf safety signs, stripping/barriers at rooftop. remove (4) 160 ah batteries, install 3 rectifiers in (e) dcpp, 1 new dc012rm in (e)rack | $65,000 |
| May 22, 2020 | Completed final sign-off Apr 2021 | 180 Geary St | Metropolitan Electrical Construction | at&t proposes to modify an (e) facility as follows:remove & replace(6) antennas;remove & replace (3)rru's & install(3) (n) rru's, reloacte (3) rru's;install(3)(n)dc9 & (6)(n)dc power trucks;install(3)(n)filber trunk.Details
at&t proposes to modify an (e) facility as follows:remove & replace(6) antennas;remove & replace (3)rru's & install(3) (n) rru's, reloacte (3) rru's;install(3)(n)dc9 & (6)(n)dc power trucks;install(3)(n)filber trunk. | $38,000 |
| Oct 29, 2019 | Completed final sign-off Nov 2019 | 180 Geary St | Aaa Restaurant Fire Control/Dba Aaa Fire | as built for 5th and 6th floor: add/rlocate 28 uprights and 13 pendents. ref app#201908088258Details
as built for 5th and 6th floor: add/rlocate 28 uprights and 13 pendents. ref app#201908088258 | $8,200 |
| Aug 14, 2019 | Completed final sign-off Nov 2019 | 212 Stockton St | H C I Systems Inc | fire alarm as built ref 201601278093Details
fire alarm as built ref 201601278093 | |
| Aug 8, 2019 | Completed final sign-off Nov 2019 | 180 Geary St | Aaa Restaurant Fire Control/Dba Aaa Fire | 5th & 6th flrs - add/reloate 28 uprights & 10 pendent for new ceiling and walls tiDetails
5th & 6th flrs - add/reloate 28 uprights & 10 pendent for new ceiling and walls ti | $6,650 |
| Aug 1, 2019 | Completed final sign-off Nov 2019 | 180 Geary St | United Systems Fire And Security Llc | 5th and 6th flr fire alarm mod for t.i. addition of 11 duct smoke detectors and control relays for heat pumps. installation of 14 new notifications appliances for new floor play layout. ref pa 201905079997Details
5th and 6th flr fire alarm mod for t.i. addition of 11 duct smoke detectors and control relays for heat pumps. installation of 14 new notifications appliances for new floor play layout. ref pa 201905079997 | $14,000 |
| Jul 26, 2019 | Completed final sign-off Dec 2019 | 212 Stockton St | H C I Systems Inc | to obtain final inspection for work approved under pa 201601278093. all work is completeDetails
to obtain final inspection for work approved under pa 201601278093. all work is complete | |
| May 23, 2019 | Never finaled issued May 2019, no final | 212 Stockton St | Alain Hirsch Construction Corp | to obtain final inspection for work approved under pa#'s 2015-1014-9662, 2016-0125-7874 & 2016-0127-8093. all work is complete.Details
to obtain final inspection for work approved under pa#'s 2015-1014-9662, 2016-0125-7874 & 2016-0127-8093. all work is complete. | |
| May 23, 2019 | Never finaled issued May 2019, no final | 212 Stockton St | Alain Hirsch Construction Corp | to obtain final inspection for work approved under pa#'s 2015-0702-0584, 2015-1210-4687 & 2016-0316-2213. all work is complete.Details
to obtain final inspection for work approved under pa#'s 2015-0702-0584, 2015-1210-4687 & 2016-0316-2213. all work is complete. | |
| May 23, 2019 | Completed final sign-off Jan 2021 | 212 Stockton St | Alain Hirsch Construction Corp | to obtain final inspection for work approved under pa#2015-0710-1153, 2015-0710-1154, 2015-0710-1155. all work is completeDetails
to obtain final inspection for work approved under pa#2015-0710-1153, 2015-0710-1154, 2015-0710-1155. all work is complete | |
| May 23, 2019 | Completed final sign-off Jan 2021 | 212 Stockton St | Alain Hirsch Construction Corp | to obtain final inspection for work approved under pa#'s 2015-0710-1156 & 2015-0710-1157. all work is complete.Details
to obtain final inspection for work approved under pa#'s 2015-0710-1156 & 2015-0710-1157. all work is complete. | |
| May 7, 2019 | Completed final sign-off Dec 2019 | 180 Geary St | Rod Heisler Construction | 5th & 6th fl - remove and install selected non-load bearing partitions. remove selected t-bar ceiling. new casework @ pantry & appliances. new finishes/refresh throughout. new light fixture & mech equipment. remove toilet partition for ada upgrade. shifting plumbing fixture (urinal) to comply w/codeDetails
5th & 6th fl - remove and install selected non-load bearing partitions. remove selected t-bar ceiling. new casework @ pantry & appliances. new finishes/refresh throughout. new light fixture & mech equipment. remove toilet partition for ada upgrade. shifting plumbing fixture (urinal) to comply w/code | $1,200,000 |
| Nov 16, 2018 | Never finaled issued Nov 2018, no final | 200 Stockton St | Plant Construction Co, Lp | install temporary xmas signage decoration on building facade, decoration has 3 parts; 1 pendent and 2 branches. branch on stockton street shall not exceed 200 sf per planning code. remove by jan 25, 2019. n/a maherDetails
install temporary xmas signage decoration on building facade, decoration has 3 parts; 1 pendent and 2 branches. branch on stockton street shall not exceed 200 sf per planning code. remove by jan 25, 2019. n/a maher | $12,500 |
| Sep 19, 2018 | Never finaled issued Oct 2018, no final | 212 Stockton St | Alain Hirsch Construction Corp | revision to pa #201601257874 & 201510149662 with updated egress plan needed for permit close out inspection. & requested by inspectorDetails
revision to pa #201601257874 & 201510149662 with updated egress plan needed for permit close out inspection. & requested by inspector | |
| Mar 23, 2018 | Expired or cancelled cancelled Oct 2022 | 180 Geary St | installation of rectilinear led light fixture at the interior of each window opening on the 4th floor facing stockton & geary streets, light fixture to be installed internally behind existing glazingDetails
installation of rectilinear led light fixture at the interior of each window opening on the 4th floor facing stockton & geary streets, light fixture to be installed internally behind existing glazing | $25,000 | |
| Apr 20, 2017 | Completed final sign-off Apr 2018 | 180 Geary St | Electric Tech Construction Inc | att mobility:r&r (6) (e) antennas w/(6) (n) antennas, (3)(e) rrus w/(3) (n) rrus, and other small equip. install (3) (n) rrus, (n) 23" rack w/(3) (n) rrus inside (e) enclosure; remove unused equipment. paint (n) antennas to match penthouse.Details
att mobility:r&r (6) (e) antennas w/(6) (n) antennas, (3)(e) rrus w/(3) (n) rrus, and other small equip. install (3) (n) rrus, (n) 23" rack w/(3) (n) rrus inside (e) enclosure; remove unused equipment. paint (n) antennas to match penthouse. | $44,000 |
| Mar 21, 2017 | Completed final sign-off Mar 2017 | 172 Geary St | Build Group Inc. | revision to app#201611042027 to incorporate mep/ electrical changes. no exterior work.Details
revision to app#201611042027 to incorporate mep/ electrical changes. no exterior work. | |
| Mar 21, 2017 | Never finaled issued Mar 2017, no final | 172 Geary St | H C I Systems Inc | as builts to pa#201702038604 for removal of duct detector.Details
as builts to pa#201702038604 for removal of duct detector. | |
| Feb 3, 2017 | Never finaled issued Feb 2017, no final | 172 Geary St | H C I Systems Inc | installation of new power supply ps-1 in electrical closet 108. installation of new visual & audio/visual notification devices throughout to meet proper coverage per nfpa 72 requirement due to t.i. work. installlation of duct detector, control relay & multi-voltage control relay for air handlingDetails
installation of new power supply ps-1 in electrical closet 108. installation of new visual & audio/visual notification devices throughout to meet proper coverage per nfpa 72 requirement due to t.i. work. installlation of duct detector, control relay & multi-voltage control relay for air handling | $9,633 |
| Feb 1, 2017 | Never finaled issued Feb 2017, no final | 172 Geary St | Eco Fire Sprinklers Inc | relocate 16 sprinklers in 1st fl area of work for tenant improvement pa# 201611042027Details
relocate 16 sprinklers in 1st fl area of work for tenant improvement pa# 201611042027 | $7,200 |
| Nov 4, 2016 | Completed final sign-off Mar 2017 | 172 Geary St | Build Group Inc. | int ti (e) retail store including (n) fixtures finishes, ceiling, flooring/ mep/fire/life safety under sep permit. no exrterior workDetails
int ti (e) retail store including (n) fixtures finishes, ceiling, flooring/ mep/fire/life safety under sep permit. no exrterior work | $128,000 |
| Jun 16, 2016 | Expired or cancelled cancelled Jan 2026 | 212 Stockton St | H C I Systems Inc | revision to 201601278093. add 2 new emergency door release buttons and 2 new viking intercom 2wayDetails
revision to 201601278093. add 2 new emergency door release buttons and 2 new viking intercom 2way | |
| Mar 16, 2016 | Never finaled issued Mar 2016, no final | 212 Stockton St | Alain Hirsch Construction Corp | lighting revisions only for approved pa# 2015 1210 4687Details
lighting revisions only for approved pa# 2015 1210 4687 | |
| Jan 27, 2016 | Completed final sign-off Jan 2020 | 212 Stockton St | H C I Systems Inc | fire alarm: install 1 new booster panel, 7 new nac devices, 1 duct detector, all devices added to existing system. ref #201512104687.Details
fire alarm: install 1 new booster panel, 7 new nac devices, 1 duct detector, all devices added to existing system. ref #201512104687. | $5,500 |
| Jan 25, 2016 | Never finaled issued Mar 2016, no final | 212 Stockton St | Alain Hirsch Construction Corp | revision to 201510149662 and 201512104687. switche location of fitting room and elec room on 2nd flDetails
revision to 201510149662 and 201512104687. switche location of fitting room and elec room on 2nd fl | |
| Jan 21, 2016 | Completed final sign-off Jul 2016 | 212 Stockton St | Battalion One Fire Protection | 1st flr: relocate 20 and add 3 sprinkler heads, (20 (e) hds-23 total with ti).relocate 15 (e)sprinkler hds & (15 existing heads -with ti 2nd fl. ti 201510149662Details
1st flr: relocate 20 and add 3 sprinkler heads, (20 (e) hds-23 total with ti).relocate 15 (e)sprinkler hds & (15 existing heads -with ti 2nd fl. ti 201510149662 | $10,500 |
| Dec 10, 2015 | Never finaled issued Dec 2015, no final | 212 Stockton St | Alain Hirsch Construction Corp | mep for retail store -ti approved pa 2015-1014-9662Details
mep for retail store -ti approved pa 2015-1014-9662 | $50,000 |
| Oct 14, 2015 | Never finaled issued Dec 2015, no final | 212 Stockton St | Alain Hirsch Construction Corp | tenant improvement to existing space. no change to exteriorDetails
tenant improvement to existing space. no change to exterior | $500,000 |
| Sep 16, 2015 | Completed final sign-off May 2016 | 180 Geary St | Triton Tower Inc | att modification to install one new dus 41, remove and replace 3 extg antennas with 3 new antennas, rplc & remove 3 extg rruw-01 with 3 nw rrus-32, paint all new antennas, nw ancillary equipment, exposed cable st match extg penthouse, rotate 2 e antennas to nw azimuth, sector a.Details
att modification to install one new dus 41, remove and replace 3 extg antennas with 3 new antennas, rplc & remove 3 extg rruw-01 with 3 nw rrus-32, paint all new antennas, nw ancillary equipment, exposed cable st match extg penthouse, rotate 2 e antennas to nw azimuth, sector a. | $18,000 |
| Aug 20, 2015 | Expired or cancelled cancelled Nov 2024 | 212 Stockton St | install wireless telecommuications facility(wts) consist 9 new panel antennas & 12 rrhs concealed behind a new frp screen wall, 2 charles cube cabinets & one 1 new dc generator mounted on (e) steel platform & 1 gps antenna on cable tray.Details
install wireless telecommuications facility(wts) consist 9 new panel antennas & 12 rrhs concealed behind a new frp screen wall, 2 charles cube cabinets & one 1 new dc generator mounted on (e) steel platform & 1 gps antenna on cable tray. | $300,000 | |
| Jul 24, 2015 | Completed final sign-off Dec 2015 | 212 Stockton St | Dickinson Cameron Construction Company I | 1st & 2nd flrs: interior only non structural soft demo for tenant improvement. sfab-017Details
1st & 2nd flrs: interior only non structural soft demo for tenant improvement. sfab-017 | $10,000 |
| Jul 10, 2015 | Expired or cancelled expired Jan 2021 | 212 Stockton St | to erect electric, wall, single faced sign.Details
to erect electric, wall, single faced sign. | $3,000 | |
| Jul 10, 2015 | Expired or cancelled expired Jan 2021 | 212 Stockton St | to erect non-electric, wall, single faced sign.Details
to erect non-electric, wall, single faced sign. | $6,000 | |
| Jul 10, 2015 | Expired or cancelled expired Jan 2021 | 212 Stockton St | to erect electric, wall, single faced sign.Details
to erect electric, wall, single faced sign. | $5,000 | |
| Jul 10, 2015 | Expired or cancelled expired Jan 2021 | 212 Stockton St | Alain Hirsch Construction Corp | to erect non-electric, single faced, window sign.Details
to erect non-electric, single faced, window sign. | $1,500 |
| Jul 10, 2015 | Expired or cancelled expired Jan 2021 | 212 Stockton St | Alain Hirsch Construction Corp | to erect non-electric, single faced sign on (e) awning.Details
to erect non-electric, single faced sign on (e) awning. | $2,000 |
| Jul 2, 2015 | Never finaled issued Apr 2016, no final | 212 Stockton St | Alain Hirsch Construction Corp | new awning for (n) retail tenant. new entry lighting. signage (shown as reference) under separate permit.Details
new awning for (n) retail tenant. new entry lighting. signage (shown as reference) under separate permit. | $20,000 |
| Feb 20, 2015 | Never finaled issued Aug 2015, no final | 200 Stockton St | Ainor Signs Inc | installation of individual illuminated lettered sign over entry door single faced.Details
installation of individual illuminated lettered sign over entry door single faced. | $1,750 |
| Dec 3, 2014 | Never finaled issued Mar 2015, no final | 174 Geary St | Deforest Construction Inc | ada upgrades for retail store in cellar (basement) floor, and ground floor. front door signage and misc. bathroom upgrades.Details
ada upgrades for retail store in cellar (basement) floor, and ground floor. front door signage and misc. bathroom upgrades. | $10,000 |
| Sep 25, 2014 | Never finaled issued Sep 2014, no final | 180 Geary St | street space permitDetails
street space permit | ||
| Aug 27, 2014 | Never finaled issued Nov 2014, no final | 200 Stockton St | Plant Construction Company Lp | cosmetic repair water damaged areas in cellar and sub-cellar areas. painting and patching - no structural work.Details
cosmetic repair water damaged areas in cellar and sub-cellar areas. painting and patching - no structural work. | $3,000 |
| Aug 12, 2014 | Never finaled issued Aug 2014, no final | 180 Geary St | L.V.I. Enviromental Svrs. | remove wet molded drywall from all walls in sub basement, no wirings, no structural, remove ceiling tile in sub basement due to water damage. remvoe wet molded drywall on lower level basement walls, clean areas. all drywall removed 2 to 4 ft from floor, plus wall insulation.Details
remove wet molded drywall from all walls in sub basement, no wirings, no structural, remove ceiling tile in sub basement due to water damage. remvoe wet molded drywall on lower level basement walls, clean areas. all drywall removed 2 to 4 ft from floor, plus wall insulation. | $200,000 |
| Apr 9, 2014 | Completed final sign-off Jan 2016 | 200 Stockton St | Plant Construction Co, Lp | interior ti to subdivide (e) retail space into 2 tenant spaces on 2 floors. work includes new demising wall, millwork finishes, furnishings, lighting, and power. no mech changes. no exterior work. fire protection under separate permit.Details
interior ti to subdivide (e) retail space into 2 tenant spaces on 2 floors. work includes new demising wall, millwork finishes, furnishings, lighting, and power. no mech changes. no exterior work. fire protection under separate permit. | $120,000 |
| Nov 25, 2013 | Completed final sign-off Oct 2015 | 180 Geary St | Walker Cellular Inc | a modification to an (e) unmanned at&t telecommunication facility consisting of installing three (n) rrus-ii's, three (n) dc-2 surge suppressors and a (n) two-inch innerduct for fiber and dc power. no other scope of work.Details
a modification to an (e) unmanned at&t telecommunication facility consisting of installing three (n) rrus-ii's, three (n) dc-2 surge suppressors and a (n) two-inch innerduct for fiber and dc power. no other scope of work. | $6,000 |
| Feb 13, 2013 | Expired or cancelled withdrawn Sep 2015 | 180 Geary St | a modification to an (e) unmanned telecommunication facility conststing of removing & replace 9 (e) at & t antenas with 9 new at & t antennas. also adding a new two foot penthouse parapet extension.Details
a modification to an (e) unmanned telecommunication facility conststing of removing & replace 9 (e) at & t antenas with 9 new at & t antennas. also adding a new two foot penthouse parapet extension. | $60,000 | |
| Jan 7, 2013 | Never finaled issued Jan 2013, no final | 180 Geary St | Maguire Inc Dba Lahue And Associates | 4th floor evacuation signs (3)Details
4th floor evacuation signs (3) | $900 |
| Dec 5, 2012 | Never finaled issued Dec 2012, no final | 180 Geary St | C B F Inc | 4th floor: install 7 horn strobes, 7 stronbes 4 duct detectors, 4 control relays, new strobes to existing strobe circuit tie speakers to existing speaker loopDetails
4th floor: install 7 horn strobes, 7 stronbes 4 duct detectors, 4 control relays, new strobes to existing strobe circuit tie speakers to existing speaker loop | $8,000 |
| Nov 29, 2012 | Never finaled issued Feb 2013, no final | 180 Geary St | Maguire Inc Dba Lahue And Associates | erect (2) an electric single faced wall sign.Details
erect (2) an electric single faced wall sign. | $5,500 |
| Nov 29, 2012 | Never finaled issued Feb 2013, no final | 180 Geary St | Maguire Inc Dba Lahue And Associates | erect (1) an electric single faced wall sign.Details
erect (1) an electric single faced wall sign. | $1,200 |
| Nov 13, 2012 | Completed final sign-off Jan 2013 | 180 Geary St | R L H Fire Protection Inc | 4th floor. fire sprinkler permit. relocate 42, add 9 and delete 3 pendent sprinklers. t.i app#201209079178Details
4th floor. fire sprinkler permit. relocate 42, add 9 and delete 3 pendent sprinklers. t.i app#201209079178 | $25,500 |
| Nov 8, 2012 | Expired or cancelled cancelled Feb 2013 | 180 Geary St | Western Awnings And Canvas | non-electric, single faced, existing awning. (qty: 4) non-structural signDetails
non-electric, single faced, existing awning. (qty: 4) non-structural sign | $200 |
| Nov 8, 2012 | Expired or cancelled cancelled Feb 2013 | 180 Geary St | Western Awnings And Canvas | replace (12) existing 4th floor awnings w/complete new smaller awnings. frames are constructed of 1-1/2" sf square galv steel tubings.Details
replace (12) existing 4th floor awnings w/complete new smaller awnings. frames are constructed of 1-1/2" sf square galv steel tubings. | $12,340 |
| Nov 8, 2012 | Expired or cancelled cancelled Feb 2013 | 180 Geary St | Western Awnings And Canvas | non-electric, single faced, existing awning. (qty: 4) non-structural signDetails
non-electric, single faced, existing awning. (qty: 4) non-structural sign | $200 |
| Nov 8, 2012 | Expired or cancelled cancelled Feb 2013 | 180 Geary St | Western Awnings And Canvas | non-electric, single faced, existing awning. (qyt: 4) non-structural signDetails
non-electric, single faced, existing awning. (qyt: 4) non-structural sign | $200 |
| Nov 2, 2012 | Completed final sign-off Jan 2013 | 180 Geary St | Michilli Inc | revision to pa# 201209079178. minor layout change to women's restroom, sheet ex1.2 due to existing piping location.Details
revision to pa# 201209079178. minor layout change to women's restroom, sheet ex1.2 due to existing piping location. | |
| Oct 29, 2012 | Never finaled issued Oct 2012, no final | 180 Geary St | street space & mta parking meterDetails
street space & mta parking meter | ||
| Oct 15, 2012 | Never finaled issued Oct 2012, no final | 180 Geary St | street space and mta parkingDetails
street space and mta parking | ||
| Sep 7, 2012 | Completed final sign-off Jan 2013 | 180 Geary St | Michilli Inc | retail tenant improvement to existing space including new partitions, new restrooms, new ceiling, new lighting, rework existing hvac and new floor and wall finishesDetails
retail tenant improvement to existing space including new partitions, new restrooms, new ceiling, new lighting, rework existing hvac and new floor and wall finishes | $850,000 |
| Jul 11, 2012 | Never finaled issued Jul 2012, no final | 180 Geary St | 4th floor - demolition of non-struct items only, demo existing interior aprtitions, doors & frames, plbg fixtures, existing ceiling & light fixtures, remvoal of all finishes include carpet, vct, base, tile, paint & wallcoverings throughout,Details
4th floor - demolition of non-struct items only, demo existing interior aprtitions, doors & frames, plbg fixtures, existing ceiling & light fixtures, remvoal of all finishes include carpet, vct, base, tile, paint & wallcoverings throughout, | $15,000 | |
| Oct 21, 2011 | Never finaled issued Oct 2011, no final | 180 Geary St | Carter Brothers Fire & Life Safety | fire alarm as builts for pa# 2011.06.17.8375- leaving sd in elevator lobby- removing 2 sd and 1 horn strobe under sidewalkDetails
fire alarm as builts for pa# 2011.06.17.8375- leaving sd in elevator lobby- removing 2 sd and 1 horn strobe under sidewalk | |
| Jun 17, 2011 | Never finaled issued Jun 2011, no final | 180 Geary St | Carter Brothers Fire & Life Safety | remove existing fire alarm devices in the new subway easement area. this includes 2 smoke detectors & 1 horn strobes.Details
remove existing fire alarm devices in the new subway easement area. this includes 2 smoke detectors & 1 horn strobes. | $4,400 |
| May 23, 2011 | Never finaled issued Jun 2011, no final | 212 Stockton St | Skyline Construction | structural infill of two wall openings in the basement at sub-sidewalk area. sfmta requires bldg to give back space new unions street station.Details
structural infill of two wall openings in the basement at sub-sidewalk area. sfmta requires bldg to give back space new unions street station. | $65,000 |
| Dec 14, 2010 | Completed final sign-off May 2011 | 180 Geary St | Cba Site Services Inc. | remove & replace 3 antennas, add (6) rrv's, (3) surge suppressor, (n) gps antenne, (n) 6601 cabinet, (n) cable tray & innner ducts.Details
remove & replace 3 antennas, add (6) rrv's, (3) surge suppressor, (n) gps antenne, (n) 6601 cabinet, (n) cable tray & innner ducts. | $35,000 |
| Nov 16, 2010 | Completed final sign-off Aug 2012 | 212 Stockton St | install electric, single faced, illuminated wall signs, loro pianaDetails
install electric, single faced, illuminated wall signs, loro piana | $3,500 | |
| Oct 6, 2010 | Completed final sign-off Oct 2010 | 180 Geary St | Field Construction Inc. | 6th floor - furnish & install (6) new downlights, (2) power receptacles, no mechanical work, o fire sprinkler work, no life safety work, existing to remain.Details
6th floor - furnish & install (6) new downlights, (2) power receptacles, no mechanical work, o fire sprinkler work, no life safety work, existing to remain. | $2,500 |
| Sep 9, 2010 | Never finaled issued Sep 2010, no final | 180 Geary St | Field Construction Inc. | 6th floor-restroom remodel-relocate & replace plumbing fixtures, toilet partitions, new finishes throughoutDetails
6th floor-restroom remodel-relocate & replace plumbing fixtures, toilet partitions, new finishes throughout | $54,000 |
| Aug 25, 2010 | Completed final sign-off Oct 2010 | 180 Geary St | Field Construction Inc. | 6th floor tenant improvements to space for electrical & mechanical permit - connecting power to new or relocated light fixtures, power outlets, tenant equipment & hvac drawing. reference pa #201007065980. life safety & fire sprinkler under separate permit.Details
6th floor tenant improvements to space for electrical & mechanical permit - connecting power to new or relocated light fixtures, power outlets, tenant equipment & hvac drawing. reference pa #201007065980. life safety & fire sprinkler under separate permit. | $149,500 |
| Aug 19, 2010 | Completed final sign-off Oct 2010 | 180 Geary St | Carter Brothers Fire & Life Safety | 6th floor - add to an existing fire alarm system, new devices in a new t.i. space (t.i.#201007065980). this includes 5 new horn/strobes & 6 new strobes.Details
6th floor - add to an existing fire alarm system, new devices in a new t.i. space (t.i.#201007065980). this includes 5 new horn/strobes & 6 new strobes. | $5,700 |
| Jul 8, 2010 | Completed final sign-off Oct 2010 | 180 Geary St | Ayoob & Peery Plumbing Co Inc | relocate and remove fire sprk heads per tenant improvements (46 relocated) (10 removed)Details
relocate and remove fire sprk heads per tenant improvements (46 relocated) (10 removed) | $16,800 |
| Jul 6, 2010 | Completed final sign-off Oct 2010 | 180 Geary St | Field Construction Inc. | 6th. flr. t.i. includes the demolition o nonstructural partitions & building (n) nonstructural partitions. all (n) or revised hvac, elec., plumbing & life safety work will be design build & submitted for permit separately. bldg. is full sprinklered.Details
6th. flr. t.i. includes the demolition o nonstructural partitions & building (n) nonstructural partitions. all (n) or revised hvac, elec., plumbing & life safety work will be design build & submitted for permit separately. bldg. is full sprinklered. | $175,000 |
| Jun 15, 2010 | Completed final sign-off Aug 2010 | 180 Geary St | Field Construction Inc. | 6th floor - office. interior dem only of non structural partitions, carpet, ceiling grid per ab-017 exception to requirements for disabled access to vacant spaces.Details
6th floor - office. interior dem only of non structural partitions, carpet, ceiling grid per ab-017 exception to requirements for disabled access to vacant spaces. | $28,000 |
| Mar 4, 2010 | Expired or cancelled cancelled Dec 2017 | 180 Geary St | Metropolitan Electrical Construction | remove and replace six (e) antennas and install three dtma's, six new coax cables and a 3206 equipment cabinet inside (e) equipment shelterDetails
remove and replace six (e) antennas and install three dtma's, six new coax cables and a 3206 equipment cabinet inside (e) equipment shelter | $25,000 |
| Jan 11, 2010 | Expired or cancelled withdrawn Nov 2011 | 212 Stockton St | Plant Construction Company Lp | lighting and mechanical revisions to approved pa# 2008.10.20.4620. no new construction. no exterior work. sprinkler/life safety under separate permit.Details
lighting and mechanical revisions to approved pa# 2008.10.20.4620. no new construction. no exterior work. sprinkler/life safety under separate permit. | $25,000 |
| Oct 14, 2009 | Never finaled issued Oct 2009, no final | 212 Stockton St | street space permit.Details
street space permit. | ||
| Jun 26, 2009 | Completed final sign-off Aug 2010 | 212 Stockton St | Allied Fire Protection | relocate 107 sprinklers, add 24 speakers per tenant improvement. install new electric fire pump& new backflow preventer. 1st fl, 1st mezz, cellar, cellar mezzanine.Details
relocate 107 sprinklers, add 24 speakers per tenant improvement. install new electric fire pump& new backflow preventer. 1st fl, 1st mezz, cellar, cellar mezzanine. | $85,000 |
| Jun 10, 2009 | Completed final sign-off Nov 2009 | 212 Stockton St | Thomas Swan Sign Co Inc | install 3 electric single faced wall signsDetails
install 3 electric single faced wall signs | $10,000 |
| Jun 4, 2009 | Completed final sign-off Nov 2009 | 212 Stockton St | Plant Construction Company Lp | revision to pa# 2008.05.28.3073. structural framing for (n) elevator shaft for bulgari store. location of new shaft shown on sheet s101 on approved pa# 2008.05.28.3073. no exterior work.Details
revision to pa# 2008.05.28.3073. structural framing for (n) elevator shaft for bulgari store. location of new shaft shown on sheet s101 on approved pa# 2008.05.28.3073. no exterior work. | $360,000 |
| May 8, 2009 | Never finaled issued May 2009, no final | 212 Stockton St | street space permitDetails
street space permit | ||
| May 5, 2009 | Never finaled issued May 2009, no final | 212 Stockton St | street space permit only.Details
street space permit only. | ||
| Apr 22, 2009 | Completed final sign-off Aug 2010 | 180 Geary St | Carter Brothers Fire & Life Safety | 1st,mezz,2 basements - add new fire alarm devices to an (e) fire alarm system includes 44 smoke detectors, 1 duct det, 3 heats, 2 pull stations, 16 wall horn strobes, 1 strobes & 4 ceiling horn storbes. t.i. under pa #200807146642, mep under #200810204620.Details
1st,mezz,2 basements - add new fire alarm devices to an (e) fire alarm system includes 44 smoke detectors, 1 duct det, 3 heats, 2 pull stations, 16 wall horn strobes, 1 strobes & 4 ceiling horn storbes. t.i. under pa #200807146642, mep under #200810204620. | $11,200 |
| Feb 6, 2009 | Completed final sign-off Jun 2009 | 180 Geary St | L.D. Strobel Co Ltd | at&t wireless proposes to modify an existing telecom facility by adding (4) new coax cable and (2) remote electronic tilts (rets) at antenna position 1.Details
at&t wireless proposes to modify an existing telecom facility by adding (4) new coax cable and (2) remote electronic tilts (rets) at antenna position 1. | $5,000 |
| Jan 13, 2009 | Completed final sign-off Nov 2009 | 212 Stockton St | temporary shoring in advance of structural work under seperate pa# 2008-0528-3073Details
temporary shoring in advance of structural work under seperate pa# 2008-0528-3073 | $7,500 | |
| Dec 10, 2008 | Completed final sign-off Mar 2009 | 180 Geary St | Skyline Construction | renew pa# 2007/08/23/0691 to obtain final inspection. all work has been completed.Details
renew pa# 2007/08/23/0691 to obtain final inspection. all work has been completed. | |
| Dec 10, 2008 | Completed final sign-off Mar 2009 | 180 Geary St | Skyline Construction | renew pa# 2007/07/03/5921 to obtain final inspection. all work has been completed.Details
renew pa# 2007/07/03/5921 to obtain final inspection. all work has been completed. | |
| Dec 10, 2008 | Completed final sign-off Mar 2009 | 180 Geary St | Skyline Construction | renew pa# 2008/03/06/6552 to obtain final inspection. all work has been completed.Details
renew pa# 2008/03/06/6552 to obtain final inspection. all work has been completed. | |
| Dec 4, 2008 | Completed final sign-off Nov 2009 | 212 Stockton St | Plant Construction Company Lp | 2 foundation walls in sub sidewalk space. sfmta requires the space for union st . muni station.Details
2 foundation walls in sub sidewalk space. sfmta requires the space for union st . muni station. | $65,000 |
| Nov 24, 2008 | Completed final sign-off Mar 2009 | 180 Geary St | Skyline Construction | revised path of travel drawings on pa# 2007-0703-5921. move men's rm partition @ 5th floor.Details
revised path of travel drawings on pa# 2007-0703-5921. move men's rm partition @ 5th floor. | |
| Oct 31, 2008 | Never finaled issued Oct 2008, no final | 212 Stockton St | street spaceDetails
street space | ||
| Oct 20, 2008 | Completed final sign-off Aug 2010 | 212 Stockton St | Plant Construction Company Lp | ti application under pa# 2008/07/14/6642. scope of work under this permit is installation of mechanical, electrical, plumbing systems.Details
ti application under pa# 2008/07/14/6642. scope of work under this permit is installation of mechanical, electrical, plumbing systems. | $135,000 |
| Oct 14, 2008 | Completed final sign-off Nov 2008 | 174 Geary St | Pwi Construction Inc | replacement of extg display cabinets and display lightingDetails
replacement of extg display cabinets and display lighting | $61,000 |
| Sep 23, 2008 | Completed final sign-off Nov 2009 | 212 Stockton St | interior soft demo on 3 floors and 2 basements of rental store. no structural or life safety to be touched (ab-017). no exterior or construction workDetails
interior soft demo on 3 floors and 2 basements of rental store. no structural or life safety to be touched (ab-017). no exterior or construction work | $20,000 | |
| Sep 9, 2008 | Completed final sign-off Nov 2009 | 212 Stockton St | interior non structural demo for ground floor & basement of new retail store. no exterior work. t.i. under app #200807146642Details
interior non structural demo for ground floor & basement of new retail store. no exterior work. t.i. under app #200807146642 | $26,000 | |
| Jul 14, 2008 | Completed final sign-off Jul 2010 | 212 Stockton St | Plant Construction Company Lp | sub-basement, basement & 1st floors-interior t.i. only including new walls, finishes, casework, ceiling. fire protection and m.e.p under seperate permits. exterior modifications under pa# 2008-0421-0271. seismic alterations under pa# 2008-0528-3073. lighting under separate permits.Details
sub-basement, basement & 1st floors-interior t.i. only including new walls, finishes, casework, ceiling. fire protection and m.e.p under seperate permits. exterior modifications under pa# 2008-0421-0271. seismic alterations under pa# 2008-0528-3073. lighting under separate permits. | $1,310,500 |
| May 28, 2008 | Completed final sign-off Nov 2009 | 212 Stockton St | structural alteration to sub basement, basement, ground floor and mezzanine in advance of tenant improvment application. no change to e exterior under this permitDetails
structural alteration to sub basement, basement, ground floor and mezzanine in advance of tenant improvment application. no change to e exterior under this permit | $750,000 | |
| Apr 21, 2008 | Completed final sign-off Nov 2009 | 212 Stockton St | Plant Construction Co, Lp | new storefront facade on g/f and 2nd fl along stockton st. for new retail store-buldari, no interior or other const work on this permit.Details
new storefront facade on g/f and 2nd fl along stockton st. for new retail store-buldari, no interior or other const work on this permit. | $360,000 |
| Mar 6, 2008 | Expired or cancelled expired Mar 2009 | 180 Geary St | Skyline Construction | 5th floor: revision to application 200707085921. apply the 20% rule this the approved permit. remodel mens's restroom to accessible compliance. hardship for women's restroom.Details
5th floor: revision to application 200707085921. apply the 20% rule this the approved permit. remodel mens's restroom to accessible compliance. hardship for women's restroom. | $11,000 |
| Oct 10, 2007 | Completed final sign-off Mar 2009 | 180 Geary St | Skyline Construction | mechanical work to include 14 new supply grills,11 new return grills,new duct work ,add 1 new heat pump, 1 exhaust fan, relocate 2 heat pumps,Details
mechanical work to include 14 new supply grills,11 new return grills,new duct work ,add 1 new heat pump, 1 exhaust fan, relocate 2 heat pumps, | $23,000 |
| Sep 10, 2007 | Completed final sign-off Mar 2009 | 180 Geary St | Ayoob & Peery Plumbing Co Inc | 5th floor-relocate & remove heads per tenant improvements-relocate 19, remove 3Details
5th floor-relocate & remove heads per tenant improvements-relocate 19, remove 3 | $4,275 |
| Aug 23, 2007 | Expired or cancelled expired Mar 2009 | 180 Geary St | Carter Brothers Fire & Life Safety | fire alarm system(t.i.), 4 ceiling mount horn, 6 strobes, 1 smoke detector, and 1 control, all installation in tenant improvement space.Details
fire alarm system(t.i.), 4 ceiling mount horn, 6 strobes, 1 smoke detector, and 1 control, all installation in tenant improvement space. | $6,000 |
| Aug 13, 2007 | Never finaled issued Aug 2007, no final | 180 Geary St | relocate 1 water heat pump. install 7 new supply grilles and 6 return grillesDetails
relocate 1 water heat pump. install 7 new supply grilles and 6 return grilles | $13,000 | |
| Jul 24, 2007 | Never finaled issued Jul 2007, no final | 180 Geary St | Skyline Construction | electrical /lighting work on the 5th floorDetails
electrical /lighting work on the 5th floor | $17,000 |
| Jul 3, 2007 | Expired or cancelled expired Mar 2009 | 180 Geary St | Skyline Construction | 5th floor-partial floor tenant improvement including selective soft demolition , partition, ceiling and finishes. m.e.p and life safety to be designed/built under separate permits.Details
5th floor-partial floor tenant improvement including selective soft demolition , partition, ceiling and finishes. m.e.p and life safety to be designed/built under separate permits. | $50,000 |
| Mar 13, 2006 | Expired or cancelled expired Jan 2007 | 174 Geary St | to paint non-structural signDetails
to paint non-structural sign | ||
| Mar 13, 2006 | Expired or cancelled expired Jan 2007 | 174 Geary St | install one awning above entry door size 4'-0" dx 2'-2" h x 10'-10" wDetails
install one awning above entry door size 4'-0" dx 2'-2" h x 10'-10" w | $3,500 | |
| Feb 17, 2006 | Never finaled issued Feb 2006, no final | 172 Geary St | street spaceDetails
street space | ||
| Nov 16, 2005 | Never finaled issued Nov 2005, no final | 180 Geary St | Magna Enterprises Construction | electrical service upgrade. removal of all outdoor equipment and install of 1 new sunwest equipment enclosure on the roof of an existing building.Details
electrical service upgrade. removal of all outdoor equipment and install of 1 new sunwest equipment enclosure on the roof of an existing building. | $15,000 |
| Oct 25, 2005 | Expired or cancelled expired Mar 2007 | 200 Stockton St | Metcalf Signs | to erect non-electric wall single faced sign.Details
to erect non-electric wall single faced sign. | $1,500 |
| Jun 1, 2005 | Expired or cancelled expired Jan 2007 | 174 Geary St | revision 200501253932 work to provide additoinal details for approved communicating stair betweenDetails
revision 200501253932 work to provide additoinal details for approved communicating stair between | ||
| Apr 15, 2005 | Expired or cancelled cancelled Jul 2006 | 180 Geary St | Comfort Dynamics Inc. | service replacement of bac closed circuit cooling tower. new unit & (e) unit same size.Details
service replacement of bac closed circuit cooling tower. new unit & (e) unit same size. | $24,570 |
| Mar 30, 2005 | Never finaled issued Mar 2005, no final | 174 Geary St | street space permit only.Details
street space permit only. | ||
| Mar 14, 2005 | Expired or cancelled expired Aug 2011 | 174 Geary St | Potter Fire Protection | rekicate (38) fir sprinklers to accomdate the construction of a new dental office/retail facility.Details
rekicate (38) fir sprinklers to accomdate the construction of a new dental office/retail facility. | $9,500 |
| Mar 4, 2005 | Never finaled issued Mar 2005, no final | 174 Geary St | add new fire alarm devices to an (e) f.a. system in a new t.i area. @ lower level & grd level.Details
add new fire alarm devices to an (e) f.a. system in a new t.i area. @ lower level & grd level. | $12,000 | |
| Feb 11, 2005 | Never finaled issued Feb 2005, no final | 174 Geary St | revision to previously approd app 200501253932 work is to add custom built design pods for client chDetails
revision to previously approd app 200501253932 work is to add custom built design pods for client ch | $45,000 | |
| Jan 25, 2005 | Expired or cancelled expired Aug 2011 | 174 Geary St | ti work includesartitions, fixtures, equipment, stairs, bathrooms, ligting & mechanical.Details
ti work includesartitions, fixtures, equipment, stairs, bathrooms, ligting & mechanical. | $650,000 | |
| Oct 20, 2004 | Completed final sign-off Oct 2004 | 180 Geary St | Edwards Systems Technology Inc/Est Servi | renew app #200405063225Details
renew app #200405063225 | |
| May 6, 2004 | Expired or cancelled expired Oct 2004 | 180 Geary St | Edwards Systems Technology Inc/Est Servi | renewal for final inspection for app 200210259961 onlyDetails
renewal for final inspection for app 200210259961 only | |
| Feb 5, 2004 | Expired or cancelled expired Nov 2004 | 174 Geary St | t.i -adding 1 horn/ strobe, 1 pull station & 2 duct smoke detector to (e) system @ grd fl onlyDetails
t.i -adding 1 horn/ strobe, 1 pull station & 2 duct smoke detector to (e) system @ grd fl only | $4,900 | |
| Jan 15, 2004 | Expired or cancelled expired Aug 2011 | 174 Geary St | interior t/i for minor remodel, work includes new lighting, new finishes, new casework, new sheetrocDetails
interior t/i for minor remodel, work includes new lighting, new finishes, new casework, new sheetroc | $30,000 | |
| Nov 19, 2003 | Expired or cancelled cancelled Oct 2017 | 180 Geary St | change existing antenna & add two equipment cabinetsDetails
change existing antenna & add two equipment cabinets | $33,000 | |
| Oct 22, 2003 | Expired or cancelled expired Oct 2004 | 180 Geary St | R L H Fire Protection Inc | fire sprinkler t/i to ground and basement floors relocate 4 and add 1Details
fire sprinkler t/i to ground and basement floors relocate 4 and add 1 | $1,200 |
| Oct 15, 2003 | Completed final sign-off Nov 2003 | 180 Geary St | add fire alarm devices to (e)fa system to provide coverage to a new tenant spaceDetails
add fire alarm devices to (e)fa system to provide coverage to a new tenant space | $6,500 | |
| Oct 7, 2003 | Completed final sign-off Nov 2003 | 172 Geary St | Cosco Fire Protection Inc. | relocate 15 heads in basementDetails
relocate 15 heads in basement | $2,600 |
| Aug 26, 2003 | Completed final sign-off Sep 2003 | 212 Stockton St | Amer. Canvas & Awning | sign permitDetails
sign permit | |
| Aug 26, 2003 | Completed final sign-off Sep 2003 | 212 Stockton St | Amer. Canvas & Awning | manufacture & install 4 awnings over 3 windows and 1 door of businessDetails
manufacture & install 4 awnings over 3 windows and 1 door of business | $4,000 |
| Aug 18, 2003 | Completed final sign-off Nov 2003 | 174 Geary St | erect a single faced, non-electric wall signDetails
erect a single faced, non-electric wall sign | ||
| Aug 18, 2003 | Completed final sign-off Nov 2003 | 174 Geary St | tenant improvement of retail space, remodel of (e) tenant space, all sinage on separate permit, no eDetails
tenant improvement of retail space, remodel of (e) tenant space, all sinage on separate permit, no e | $120,000 | |
| Aug 7, 2003 | Expired or cancelled expired Nov 2004 | 180 Geary St | install new horn strobe and detectors in new tenant space new devices will be part of an (e) fireDetails
install new horn strobe and detectors in new tenant space new devices will be part of an (e) fire | $12,400 | |
| Jul 25, 2003 | Never finaled issued Aug 2003, no final | 212 Stockton St | mechanical, electrical work for tenant improvement under app#200304101918Details
mechanical, electrical work for tenant improvement under app#200304101918 | ||
| Jul 17, 2003 | Never finaled issued Jul 2003, no final | 212 Stockton St | Cosco Fire Protection Inc. | sprinkler ti 1st & 2nd fl, relocate (24), add 5 & plum (5) sspDetails
sprinkler ti 1st & 2nd fl, relocate (24), add 5 & plum (5) ssp | $5,000 |
| May 5, 2003 | Never finaled issued May 2003, no final | 212 Stockton St | street spaceDetails
street space | ||
| May 5, 2003 | Completed final sign-off Jun 2003 | 212 Stockton St | Fine Line Group Inc | soft demolition to interior of this bldgDetails
soft demolition to interior of this bldg | $300,000 |
| Apr 10, 2003 | Never finaled issued Jun 2003, no final | 212 Stockton St | Fine Line Group Inc | renovation/alteration of existing retail space including architectural, electrical, structl & sprklrDetails
renovation/alteration of existing retail space including architectural, electrical, structl & sprklr | $300,000 |
| Mar 3, 2003 | Expired or cancelled expired Nov 2004 | 180 Geary St | t/i add 3 horn strobes and 2 waterflow tamper modulesDetails
t/i add 3 horn strobes and 2 waterflow tamper modules | $8,000 | |
| Feb 7, 2003 | Expired or cancelled expired Nov 2004 | 174 Geary St | t.i. at gr. fl. & basement level, work includes new partitions/ceiling/electrical/finishes.Details
t.i. at gr. fl. & basement level, work includes new partitions/ceiling/electrical/finishes. | $98,000 | |
| Feb 6, 2003 | Expired or cancelled expired Nov 2004 | 174 Geary St | R L H Fire Protection Inc | fire sprinkler tenant improvements to ground and basement levelsDetails
fire sprinkler tenant improvements to ground and basement levels | $3,800 |
| Oct 25, 2002 | Expired or cancelled expired Oct 2004 | 180 Geary St | repl of (e)fire alarm panel bring bldg system up to code on all floorsDetails
repl of (e)fire alarm panel bring bldg system up to code on all floors | $70,000 | |
| May 2, 2002 | Expired or cancelled cancelled Oct 2017 | 180 Geary St | Stc Netcom Inc. | modification of exist telecommincation facility replace 3 antennas w smaller, add 1 equip cabinet onDetails
modification of exist telecommincation facility replace 3 antennas w smaller, add 1 equip cabinet on | $15,000 |
| Jun 22, 2001 | Expired or cancelled expired Dec 2001 | 180 Geary St | Plant Construction | demo minor stair work 1st level in fill stair opening 1st levelDetails
demo minor stair work 1st level in fill stair opening 1st level | $25,000 |
| Dec 7, 2000 | Expired or cancelled expired Jan 2002 | 180 Geary St | Jfc Construction Inc. | bacts currently operates a cellular telephone base station at this property, ext. antennas to remainDetails
bacts currently operates a cellular telephone base station at this property, ext. antennas to remain | $30,000 |
| Sep 25, 2000 | Completed final sign-off Oct 2000 | 212 Stockton St | Sure Fire Protection | add 2 sprinkler relocate 2 sprinkler.Details
add 2 sprinkler relocate 2 sprinkler. | $2,000 |
| Sep 18, 2000 | Completed final sign-off Nov 2000 | 212 Stockton St | fire/life safety upgrade to 6th fl to bring up to nfpa 72 standards.Details
fire/life safety upgrade to 6th fl to bring up to nfpa 72 standards. | $6,500 | |
| Aug 31, 2000 | Completed final sign-off Oct 2000 | 212 Stockton St | to demo wall on street & cellar levels. interior non-structural demolition only.Details
to demo wall on street & cellar levels. interior non-structural demolition only. | $50,000 | |
| Jul 27, 2000 | Completed final sign-off Oct 2000 | 212 Stockton St | office tenant improvement-change 6th floor retail space to office space.Details
office tenant improvement-change 6th floor retail space to office space. | $139,000 | |
| Jul 19, 2000 | Expired or cancelled withdrawn May 2001 | 212 Stockton St | Fine Line Group Inc | revision to application#9918747: add sheetrock fire proofing at stair openingDetails
revision to application#9918747: add sheetrock fire proofing at stair opening | $500 |
| Jan 20, 2000 | Completed final sign-off Dec 2000 | 200 Stockton St | addition of 5 & relocation of 1 fire sprinklerDetails
addition of 5 & relocation of 1 fire sprinkler | $5,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.