Matthew Chang
- Listed as
- engineer
- Firm
- J5 Infrastructure
- Based in
- Irvine
- On San Francisco permits
- Nov 2021 to Apr 2022
13 permits since 2000 (engineer on 13 permits): 11 completed, 1 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 11, 2022 | Completed final sign-off Nov 2022 | 833 Mission St | Electric Tech Construction Inc | at&t (4th and mission): remove 1 panel antenna and 1 rru. relocate rru. install 2 panel antennas within frp screen. install 1 4478b12a and 2 diplexers. swap 1 dc6 box for dc9. install 1 power trunk and 1 fiber trunk within (e) cabletray. remove unused coax, install 1 6648 baseband unit and 1 purcellDetails
at&t (4th and mission): remove 1 panel antenna and 1 rru. relocate rru. install 2 panel antennas within frp screen. install 1 4478b12a and 2 diplexers. swap 1 dc6 box for dc9. install 1 power trunk and 1 fiber trunk within (e) cabletray. remove unused coax, install 1 6648 baseband unit and 1 purcell | $45,000 |
| Mar 24, 2022 | Completed final sign-off Nov 2022 | 1155 Bryant St | Electric Tech Construction Inc | mod cell site:r/r 6 antennas,3panel,3 air antennas;r/r 2 radomes.decom umts unit,remove 2 strings of 155ah batteries.remove 3 strongs of 155 batt from (e) rba-72 dcpp cabinet.install 2 new strings of 1900ah batteries in (e) inflight cab & 3 190ah in rba-72 cabinet.Details
mod cell site:r/r 6 antennas,3panel,3 air antennas;r/r 2 radomes.decom umts unit,remove 2 strings of 155ah batteries.remove 3 strongs of 155 batt from (e) rba-72 dcpp cabinet.install 2 new strings of 1900ah batteries in (e) inflight cab & 3 190ah in rba-72 cabinet. | $60,000 |
| Mar 14, 2022 | Expired or cancelled cancelled Jan 2026 | 2775 Van Ness Av | at&t: remove + replace 6 antennas behind (e) frp screen, decom umts 850. install new rf safety signs, battiers + stripping. remove 2 ex 2v battery system. install 1 distribution panel, 2 power extend converters, 1 new rack with 4 strings 190 ah batteries, 1 new 6648 bbu/mux in (e) rack.Details
at&t: remove + replace 6 antennas behind (e) frp screen, decom umts 850. install new rf safety signs, battiers + stripping. remove 2 ex 2v battery system. install 1 distribution panel, 2 power extend converters, 1 new rack with 4 strings 190 ah batteries, 1 new 6648 bbu/mux in (e) rack. | $45,000 | |
| Mar 10, 2022 | Completed final sign-off Oct 2022 | 2 Henry Adams St | Ericsson Inc Dba E U S Inc | at&t: remove + install 9 antennas, 3 rru's. install 6 new twin diplexers, 1 new antenna mount, rf safety signs, barriers + stripping. remove/replace 16 batteries. remove 1 5216 from rack. install 3 rectifiers, 4 new battery in (e) dcpp, 2 new seismic wall bracing. 1 6648 baseband in (e) rack.Details
at&t: remove + install 9 antennas, 3 rru's. install 6 new twin diplexers, 1 new antenna mount, rf safety signs, barriers + stripping. remove/replace 16 batteries. remove 1 5216 from rack. install 3 rectifiers, 4 new battery in (e) dcpp, 2 new seismic wall bracing. 1 6648 baseband in (e) rack. | $45,000 |
| Feb 24, 2022 | Completed final sign-off Jun 2022 | 1188 Franklin St | Ericsson Inc Dba E U S Inc | at&t: remove and replace 6 antennas. remove 6 rrus, relocate 3 rrus. install 3 new dc9 boxes, (3) 6awg dc power trunks to new dc9's. install 1 new stackable battery enclosure w/ 8 new 190ah batteries within. 4 new rectifiers in (e) dcpp. remove (12) 155ah, 2 duw and (1) 5216. install 3 support beamsDetails
at&t: remove and replace 6 antennas. remove 6 rrus, relocate 3 rrus. install 3 new dc9 boxes, (3) 6awg dc power trunks to new dc9's. install 1 new stackable battery enclosure w/ 8 new 190ah batteries within. 4 new rectifiers in (e) dcpp. remove (12) 155ah, 2 duw and (1) 5216. install 3 support beams | $55,000 |
| Feb 10, 2022 | Completed final sign-off Apr 2024 | 114 07th St | Invertice Inc | at&t: remove + replace 12 antennas. remove 4 (e) rrus 11b12. remove 4 rrus b5. install 4 rrus 4449 b5/b12. 4 dc6 squids. 4 #6 awg dc power trunks. (n) rf safety signs, barriers + stripping on rooftop. 3 rectifiers in (e) dcpp cabinet. 1 dc12 box.Details
at&t: remove + replace 12 antennas. remove 4 (e) rrus 11b12. remove 4 rrus b5. install 4 rrus 4449 b5/b12. 4 dc6 squids. 4 #6 awg dc power trunks. (n) rf safety signs, barriers + stripping on rooftop. 3 rectifiers in (e) dcpp cabinet. 1 dc12 box. | $65,000 |
| Jan 27, 2022 | Completed final sign-off Jul 2022 | 180 Geary St | Ericsson Inc Dba E U S Inc | at&t: modification cell-site. remove and replace 6 panel antennas, relocate 1 rru, install 1 dc9 box per sector-total 3, install (3) #6 awg power trunk, install new rf safety signs, stripping/barriers at rooftop. remove (4) 160 ah batteries, install 3 rectifiers in (e) dcpp, 1 new dc012rm in (e)rackDetails
at&t: modification cell-site. remove and replace 6 panel antennas, relocate 1 rru, install 1 dc9 box per sector-total 3, install (3) #6 awg power trunk, install new rf safety signs, stripping/barriers at rooftop. remove (4) 160 ah batteries, install 3 rectifiers in (e) dcpp, 1 new dc012rm in (e)rack | $65,000 |
| Jan 11, 2022 | Completed final sign-off May 2024 | 589 Howard St | Invertice Inc, Electric Tech Construction Inc | roof - unmanned cell site mod: r/r 2 panel antennas per sector (6 total). reloc 1 (e) antenna per sector (3 total). remove 3 rrus 11b12 and repl with 3 rru & 4478b12a. install (n) radomes to enclose antennas (9).install 4 rectifers in (e) dc power plan. 1 (n) 6648 bbu in (e) rack.Details
roof - unmanned cell site mod: r/r 2 panel antennas per sector (6 total). reloc 1 (e) antenna per sector (3 total). remove 3 rrus 11b12 and repl with 3 rru & 4478b12a. install (n) radomes to enclose antennas (9).install 4 rectifers in (e) dc power plan. 1 (n) 6648 bbu in (e) rack. | $85,000 |
| Jan 11, 2022 | Completed final sign-off Nov 2022 | 901 Market St | Metropolitan Electrical Construction | roof - cell site: mod to unmanned telecomm: r/r 3 panel antennas; remove 24-155ah batts & replace with 20(n) 190ah batts; 1(n) rectifer in (e) dc power plant. install 1 (n) 6448 baseband unit in (e) purcell cabinet.Details
roof - cell site: mod to unmanned telecomm: r/r 3 panel antennas; remove 24-155ah batts & replace with 20(n) 190ah batts; 1(n) rectifer in (e) dc power plant. install 1 (n) 6448 baseband unit in (e) purcell cabinet. | $85,000 |
| Dec 21, 2021 | Completed final sign-off Sep 2022 | 250 Clay St | Metropolitan Electrical Construction | at&t: replace 2 antennas, add 2 antennas, relocate 2 natennas, relocate 2 rru's, install 2 rru's, install 2 antennas mounts, install new rf safety signs and striping, install 1 rectifier, install 1 bbu.Details
at&t: replace 2 antennas, add 2 antennas, relocate 2 natennas, relocate 2 rru's, install 2 rru's, install 2 antennas mounts, install new rf safety signs and striping, install 1 rectifier, install 1 bbu. | $25,000 |
| Dec 3, 2021 | Completed final sign-off Oct 2022 | 726 Polk St | Metropolitan Electrical Construction | at&t :remove & replace 6 antennas, r&r 9 rru; with 6 nw rrus; 3 nw diplexers. remove 2 extg rbs 2206 cabinet, 1 dc power plant & install 1 nw 7100 dc power plant. install 20 155ah batteries in extg rack. install 12 190 ah batteries in nw 7100 dc, & 8 in extg battery rack, 11 rectifiers in 7100 cab,Details
at&t :remove & replace 6 antennas, r&r 9 rru; with 6 nw rrus; 3 nw diplexers. remove 2 extg rbs 2206 cabinet, 1 dc power plant & install 1 nw 7100 dc power plant. install 20 155ah batteries in extg rack. install 12 190 ah batteries in nw 7100 dc, & 8 in extg battery rack, 11 rectifiers in 7100 cab, | $90,000 |
| Nov 8, 2021 | Never finaled filed Nov 2021, never issued | 1625 Owens St | modify to (e) t-mobile telecommunication facility: install (n) 25 kwh diesel generator; (n) auto transfer switch(ats) on (n) cmu wall; (n) 6lb fire extinguisher on (n) cmu wall; (n) generator emergency e-stop on cmu wall; (n) cmu wall enclosure; (n) raised equipment pad.Details
modify to (e) t-mobile telecommunication facility: install (n) 25 kwh diesel generator; (n) auto transfer switch(ats) on (n) cmu wall; (n) 6lb fire extinguisher on (n) cmu wall; (n) generator emergency e-stop on cmu wall; (n) cmu wall enclosure; (n) raised equipment pad. | $40,000 | |
| Nov 3, 2021 | Completed final sign-off Feb 2023 | 701 Mission St | Electric Tech Construction Inc | modificaton of an (e) at&t wireless facility, antenna location: remove and replace (12) anatennas (4-new air anatennas and 8 new panel antennas) decomission units equipment, equipment location install (3) strings of 160 ah batteries in (e) cabs and (3) rectifers in (e) cabsDetails
modificaton of an (e) at&t wireless facility, antenna location: remove and replace (12) anatennas (4-new air anatennas and 8 new panel antennas) decomission units equipment, equipment location install (3) strings of 160 ah batteries in (e) cabs and (3) rectifers in (e) cabs | $185,000 |