Permit GraphShortlistSan Francisco building permits since 2000

Block 0714, lot 017

1188 Franklin St

City’s use
Commercial Office
Built
1973
Stories
4
Rooms
7 bathrooms
Building
40,470 sq ft
Lot
18,000 sq ft
Zoning
NC3
Construction type
A

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

25 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Apr 16, 2026Completed
final sign-off Jul 2026
1188 Franklin StNovo Construction Incto obtain final inspection for work approved under pa#: 202409050136. all work is complete
Details
Permit
202604169555
Permit issued
Apr 16, 2026
Final sign-off
Jul 8, 2026

to obtain final inspection for work approved under pa#: 202409050136. all work is complete

Open the permit page

Dec 4, 2025Completed
final sign-off Jun 2026
1188 Franklin StApex Site Solutions Increcommencement and completion of work approved under pa#202007230746
Details
Permit
202512040981
Permit issued
Dec 4, 2025
Final sign-off
Jun 17, 2026

recommencement and completion of work approved under pa#202007230746

Open the permit page

$30,000
Feb 13, 2025Completed
final sign-off Jul 2026
1188 Franklin StNovo Construction Incsuite 201- revised scope of work to permit#2024-1118-5224 1) include rated ceiling at entry vestibule 2) confirmation of compliant accessible elevator call button.
Details
Permit
202502130282
Permit issued
Mar 19, 2025
Final sign-off
Jul 8, 2026

suite 201- revised scope of work to permit#2024-1118-5224 1) include rated ceiling at entry vestibule 2) confirmation of compliant accessible elevator call button.

Open the permit page

Nov 18, 2024Completed
final sign-off Jul 2026
1188 Franklin StNovo Construction Incsuite 201; expansion of existing suite including new non-bearing portiions, lighting, suspended ceiling electrical and finishes. mech and electrical work under separate permit.
Details
Permit
202411185224
Permit issued
Nov 22, 2024
Final sign-off
Jul 8, 2026

suite 201; expansion of existing suite including new non-bearing portiions, lighting, suspended ceiling electrical and finishes. mech and electrical work under separate permit.

Open the permit page

$320,000
Sep 5, 2024Expired or cancelled
expired Jul 2026
1188 Franklin StNovo Construction Inc2nd fl - expansion of existing office including new suite entry, non bearing partitions, new doors & exit signs
Details
Permit
202409050136
Permit issued
Sep 25, 2024

2nd fl - expansion of existing office including new suite entry, non bearing partitions, new doors & exit signs

Open the permit page

$98,000
Jan 20, 2023Completed
final sign-off May 2023
1188 Franklin StDave's Lock Service, Terocons Inccomply with abe program per ord 51-16. barrier removeal at e exterior ramp and primary entry. technical infeasibility and equiv facilitation per ord 51-16. no structural work. no sidewalk work, no mep. abe 201911228634. (all exterior work to be done b a-contractor; door operator by c-28 contractor).
Details
Permit
202301200442
Permit issued
Apr 13, 2023
Final sign-off
May 15, 2023

comply with abe program per ord 51-16. barrier removeal at e exterior ramp and primary entry. technical infeasibility and equiv facilitation per ord 51-16. no structural work. no sidewalk work, no mep. abe 201911228634. (all exterior work to be done b a-contractor; door operator by c-28 contractor).

Open the permit page

$25,000
Feb 24, 2022Completed
final sign-off Jun 2022
1188 Franklin StEricsson Inc Dba E U S Incat&t: remove and replace 6 antennas. remove 6 rrus, relocate 3 rrus. install 3 new dc9 boxes, (3) 6awg dc power trunks to new dc9's. install 1 new stackable battery enclosure w/ 8 new 190ah batteries within. 4 new rectifiers in (e) dcpp. remove (12) 155ah, 2 duw and (1) 5216. install 3 support beams
Details
Permit
202202248588
Permit issued
Apr 12, 2022
Final sign-off
Jun 22, 2022

at&t: remove and replace 6 antennas. remove 6 rrus, relocate 3 rrus. install 3 new dc9 boxes, (3) 6awg dc power trunks to new dc9's. install 1 new stackable battery enclosure w/ 8 new 190ah batteries within. 4 new rectifiers in (e) dcpp. remove (12) 155ah, 2 duw and (1) 5216. install 3 support beams

Open the permit page

$55,000
Jul 23, 2020Never finaled
issued Jan 2021, no final
1188 Franklin StEricsson Inc Dba E U S Incremoval & upgrade of panel antennas, rrus, battery strings as well as other upgrades at equipment level/in cabinet.
Details
Permit
202007230746
Permit issued
Jan 25, 2021

removal & upgrade of panel antennas, rrus, battery strings as well as other upgrades at equipment level/in cabinet.

Open the permit page

$30,000
Feb 27, 2020Expired or cancelled
cancelled Jan 2026
1188 Franklin Stto comply w/abe program per ord 51-16 barrier removal @ existing exterior ramp & primary entry. technical infeasibility & equivalent facilitation per ord 51-16. no structural work. no mep work, no sidewalk work
Details
Permit
202002275560

to comply w/abe program per ord 51-16 barrier removal @ existing exterior ramp & primary entry. technical infeasibility & equivalent facilitation per ord 51-16. no structural work. no mep work, no sidewalk work

Open the permit page

$25,000
Apr 14, 2017Completed
final sign-off Aug 2017
1188 Franklin StElectric Tech Construction Incatt modification: r&r 6(e) antennas, w/6 new antennas,9(e) rrus w/6 new rrus; install 2 new xmu, 2 new fiber, remove unused equip. paint antennad to match
Details
Permit
201704144042
Permit issued
Jun 5, 2017
Final sign-off
Aug 1, 2017

att modification: r&r 6(e) antennas, w/6 new antennas,9(e) rrus w/6 new rrus; install 2 new xmu, 2 new fiber, remove unused equip. paint antennad to match

Open the permit page

$33,000
Nov 16, 2015Completed
final sign-off May 2016
1188 Franklin StElectric Tech Construction Incat&t modification to (e) telecom facility: install 3(n)rrus-32; install 3(n)dcg surge suppressors;(n)inner duct,(n)dc12 surge suppressor &hoffman box,(n)6601 v2 chassis w/(n)dus41;r&r 3 antennas w/(3)(n)antennas;relocate rrus,remove dcg surge from (e)rba72.
Details
Permit
201511162680
Permit issued
Feb 25, 2016
Final sign-off
May 5, 2016

at&t modification to (e) telecom facility: install 3(n)rrus-32; install 3(n)dcg surge suppressors;(n)inner duct,(n)dc12 surge suppressor &hoffman box,(n)6601 v2 chassis w/(n)dus41;r&r 3 antennas w/(3)(n)antennas;relocate rrus,remove dcg surge from (e)rba72.

Open the permit page

$22,000
May 9, 2014Expired or cancelled
withdrawn Aug 2014
1188 Franklin Stmodifcation to e att telecommunication facility consisting of removing and replaceing 3 e att antennas with 3 new att antennas and adding 3 new rrus. 11 units with 3 new a2 modules, new dus 41 inside an e purcell cabinet
Details
Permit
201405095427

modifcation to e att telecommunication facility consisting of removing and replaceing 3 e att antennas with 3 new att antennas and adding 3 new rrus. 11 units with 3 new a2 modules, new dus 41 inside an e purcell cabinet

Open the permit page

$11,200
Mar 18, 2014Completed
final sign-off Jul 2014
1188 Franklin StWestern Roofing Servicereroofing
Details
Permit
201403181043
Permit issued
Mar 18, 2014
Final sign-off
Jul 31, 2014

reroofing

Open the permit page

$140,000
Dec 18, 2013Completed
final sign-off Nov 2014
1188 Franklin StRoebuck Constructiont.i. of 2nd floor unoccupied offices and reconfiguration of the common corridor to connect this space to an occupied suite. plumbing & electrical under separate permit.
Details
Permit
201312184484
Permit issued
Mar 11, 2014
Final sign-off
Nov 25, 2014

t.i. of 2nd floor unoccupied offices and reconfiguration of the common corridor to connect this space to an occupied suite. plumbing & electrical under separate permit.

Open the permit page

$124,000
Jul 19, 2012Never finaled
issued Jul 2012, no final
1188 Franklin Ststreet space permit.
Details
Permit
M336308
Permit issued
Jul 19, 2012

street space permit.

Open the permit page

Mar 19, 2012Completed
final sign-off Feb 2013
1188 Franklin StTerralink Communications Inc.(n) unmanned telecom facility consisting of(n)8'-9"x 27'-8" at&t equip platform w/2(n)2206 rbs cabinets. 6 (n) 6601 umts rbs equipment units, (n) 6601 lte rbs equipment unit, & (n) dc power plant inside (n) sunwest cabinet, (n) telco parcell cabinet, (n) ciena unit
Details
Permit
201203196372
Permit issued
Jul 12, 2012
Final sign-off
Feb 14, 2013

(n) unmanned telecom facility consisting of(n)8'-9"x 27'-8" at&t equip platform w/2(n)2206 rbs cabinets. 6 (n) 6601 umts rbs equipment units, (n) 6601 lte rbs equipment unit, & (n) dc power plant inside (n) sunwest cabinet, (n) telco parcell cabinet, (n) ciena unit

Open the permit page

$115,000
May 15, 2007Completed
final sign-off May 2008
1188 Franklin Stoti-1, leonard carder, 2nd fl, el, me.
Details
Permit
200705151268
Permit issued
Jun 8, 2007
Final sign-off
May 15, 2008

oti-1, leonard carder, 2nd fl, el, me.

Open the permit page

$160,000
Feb 9, 2004Completed
final sign-off Dec 2004
1188 Franklin StCity Building Inc.demo of metal stud wall and dry walls, adding elevator smoke doors
Details
Permit
200402095920
Permit issued
Jun 22, 2004
Final sign-off
Dec 27, 2004

demo of metal stud wall and dry walls, adding elevator smoke doors

Open the permit page

$350,000
Dec 5, 2003Completed
final sign-off Aug 2004
1188 Franklin StCity Building Inc.renew:200205086063 ready for final inspection
Details
Permit
200312051718
Permit issued
Dec 5, 2003
Final sign-off
Aug 18, 2004

renew:200205086063 ready for final inspection

Open the permit page

Jun 11, 2003Completed
final sign-off Jul 2003
1188 Franklin StRoebuck Constructionvoluntary handicap ugrade of the existing unisex restroom on 4th floor
Details
Permit
200306116830
Permit issued
Jun 11, 2003
Final sign-off
Jul 30, 2003

voluntary handicap ugrade of the existing unisex restroom on 4th floor

Open the permit page

$16,500
May 8, 2002Expired or cancelled
expired Aug 2004
1188 Franklin StCity Building Inc.install new metal stud and drywall paritions w/new electrical ,new kitchen w/appliances/cabinets,pai
Details
Permit
200205086063
Permit issued
Jul 22, 2002

install new metal stud and drywall paritions w/new electrical ,new kitchen w/appliances/cabinets,pai

Open the permit page

$94,000
Feb 28, 2002Expired or cancelled
cancelled Jun 2003
1188 Franklin StCity Building Inc.tenant improvement to include studwall framing /dryrot/plmg/millwork paint and carpet
Details
Permit
200202280311

tenant improvement to include studwall framing /dryrot/plmg/millwork paint and carpet

Open the permit page

$480,000
Jan 24, 2002Completed
final sign-off Mar 2002
1188 Franklin StCity Building Inc.demo of metal stud & drywall walls, floor finishes
Details
Permit
200201247650
Permit issued
Jan 24, 2002
Final sign-off
Mar 7, 2002

demo of metal stud & drywall walls, floor finishes

Open the permit page

$9,200
Aug 1, 2000Completed
final sign-off Dec 2000
1188 Franklin Stchange work description from lobby revision to grouond floor hallway revisions
Details
Permit
200008016611
Permit issued
Aug 1, 2000
Final sign-off
Dec 4, 2000

change work description from lobby revision to grouond floor hallway revisions

Open the permit page

Jun 14, 2000Expired or cancelled
expired Jul 2001
1188 Franklin Stlobby revisions
Details
Permit
200006142622
Permit issued
Jul 24, 2000

lobby revisions

Open the permit page

$75,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
City Building Inc. (5), Novo Construction Inc (4), Electric Tech Construction Inc (2), Ericsson Inc Dba E U S Inc (2), Roebuck Construction (2), Apex Site Solutions Inc, Dave's Lock Service, Terocons Inc, Terralink Communications Inc., Western Roofing Service
Architects
Ashley Miller (3), Michael Steiner (2), Aston Pereira
Engineers
James Spore, Jesse Smith, Li Wen Li, Matthew Chang, Steve Marquis
Designers
Ashley Miller

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.