- 6 permits filed
516 permits since 2000: 335 completed, 8 in progress, 81 never finaled, 92 expired or cancelled.
Of the 81 never-finaled permits, 9 are 5 to 10 years old, 72 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 516.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 26, 2026 | In progress filed Jun 2026, not yet issued | 333 Bryant St | 3/fl- ref 202403067701 for mep submittalDetails
3/fl- ref 202403067701 for mep submittal | $75,000 |
| Apr 23, 2026 | In progress issued Sep 2026 | 550 Battery St | 1/f: t.i include interior re-finishes of existing resid. tower main lobby, no change of use occupancy, occ load or egrewss replace in kind new front entry doors. (n) floor covering and all finishes. all (n) or revised mep and life safety work will be design build and submitted sepately.Details
1/f: t.i include interior re-finishes of existing resid. tower main lobby, no change of use occupancy, occ load or egrewss replace in kind new front entry doors. (n) floor covering and all finishes. all (n) or revised mep and life safety work will be design build and submitted sepately. | $315,000 |
| Apr 20, 2026 | In progress issued Sep 2026 | 405 Davis Ct | (leverl 1) t.i. includes interior re-finished of (e) residential tower main lobby. no change in use occupancy, occ. load or egress. replace in kind new front entry doors, new floor vocering and wall finishes. all new or revised mep's and life safety work will be design build and submited separately.Details
(leverl 1) t.i. includes interior re-finished of (e) residential tower main lobby. no change in use occupancy, occ. load or egress. replace in kind new front entry doors, new floor vocering and wall finishes. all new or revised mep's and life safety work will be design build and submited separately. | $340,000 |
| Apr 10, 2026 | In progress issued Sep 2026 | 440 Davis Ct | level 1, tenant improvment includes interior refinishes of e residential tower main lobby. no change in use occupancy, occ load or egrees. replace in kind new front entry doors. new floor covering and wall finishes. all new or revised meps and life safety work will be design build,submitted separateDetails
level 1, tenant improvment includes interior refinishes of e residential tower main lobby. no change in use occupancy, occ load or egrees. replace in kind new front entry doors. new floor covering and wall finishes. all new or revised meps and life safety work will be design build,submitted separate | $154,000 |
| Aug 11, 2025 | In progress filed Aug 2025, not yet issued | 333 Market St | 335 sqft. area of work water roofing remediation of basement wall structure due to water intrusion. remove (e) pavers/slab/soil to access and repair/replace waterproofing membrane. provide temporary shoring of during excavation. restore (e) sidwald pavers andDetails
335 sqft. area of work water roofing remediation of basement wall structure due to water intrusion. remove (e) pavers/slab/soil to access and repair/replace waterproofing membrane. provide temporary shoring of during excavation. restore (e) sidwald pavers and | $175,000 |
| Mar 14, 2025 | In progress issued Mar 2025 | 333 07th St | excavate 5' x 5' x 3' deep pit in kitchen corner to expose footing. space to remain vacantDetails
excavate 5' x 5' x 3' deep pit in kitchen corner to expose footing. space to remain vacant | $11,208 |
| Mar 25, 2024 | In progress issued Mar 2024 | 1351 24th Av | remove and replace 39 aluminum windows with vinyl inserts. not street facing windows. all at rear and rear sides of building. max u-factor=0.58, max rshgc=0.41, min vt fixed=0.46/operable=0.32Details
remove and replace 39 aluminum windows with vinyl inserts. not street facing windows. all at rear and rear sides of building. max u-factor=0.58, max rshgc=0.41, min vt fixed=0.46/operable=0.32 | $245,472 |
| Mar 6, 2024 | In progress issued Mar 2024 | 333 Bryant St | tenant improvement for 1460 sqft office space on 3rd fl. expansion of existing architect's office into the adjacent suite taking up 1/3 of the space. new conference room. bathroom upgradesDetails
tenant improvement for 1460 sqft office space on 3rd fl. expansion of existing architect's office into the adjacent suite taking up 1/3 of the space. new conference room. bathroom upgrades | $167,373 |
| Jan 25, 2024 | Expired or cancelled withdrawn Jun 2026 | 333 Bryant St | the project consists of approx 145 sf situated on the 1/f.. the current closet area will be transformed into a new conference room, the existing mep systems will be extended into the new space.Details
the project consists of approx 145 sf situated on the 1/f.. the current closet area will be transformed into a new conference room, the existing mep systems will be extended into the new space. | $5,000 |
| Jul 12, 2023 | Completed final sign-off Aug 2024 | 1001 Polk St | application of liquid applied traffic coating at geary, polk, and cedar st. sidewalks.Details
application of liquid applied traffic coating at geary, polk, and cedar st. sidewalks. | $110,000 |
| Mar 3, 2023 | Completed final sign-off Jun 2023 | 515 Spruce St | revision to pa# 202107144350, remove unused showers and create 2 phot-therapy offices.Details
revision to pa# 202107144350, remove unused showers and create 2 phot-therapy offices. | $15,000 |
| Feb 23, 2023 | Completed final sign-off Aug 2023 | 1509 Taraval St | per nov/complaint# 202301230: replace missing section of fire rated ceiling (2 layers of 5/8" type x gypboard) in garage 20' x 4' area.Details
per nov/complaint# 202301230: replace missing section of fire rated ceiling (2 layers of 5/8" type x gypboard) in garage 20' x 4' area. | $10,000 |
| Dec 21, 2021 | Completed final sign-off Oct 2022 | 444 06th St | t.i. consisting of 1)selective demo of interior non-structural elements. 2) replace of aluminum framed entry doors & repair of windows, as indicated. 3) nw accessibility-complaint level landing at main entrance. 4)nw framed walls, doors, door frames, int. windows, plmg fixtures paint/flooringDetails
t.i. consisting of 1)selective demo of interior non-structural elements. 2) replace of aluminum framed entry doors & repair of windows, as indicated. 3) nw accessibility-complaint level landing at main entrance. 4)nw framed walls, doors, door frames, int. windows, plmg fixtures paint/flooring | $679,831 |
| Jul 14, 2021 | Completed final sign-off Jun 2023 | 515 Spruce St | seismic strengthening of existing structure and accessibility upgrades.Details
seismic strengthening of existing structure and accessibility upgrades. | $423,000 |
| Dec 7, 2020 | Completed final sign-off Apr 2021 | 1890 Sutter St | emergency permit to perform dry rot remediation at all corners and west side platform. install footings for new post at north cornersDetails
emergency permit to perform dry rot remediation at all corners and west side platform. install footings for new post at north corners | $20,000 |
| Oct 3, 2020 | Completed final sign-off Jan 2021 | 550 California St | rooftop: furnish & install stell catwalk on top of (e) steel structure on the roof.Details
rooftop: furnish & install stell catwalk on top of (e) steel structure on the roof. | $60,000 |
| Jan 8, 2020 | Completed final sign-off Apr 2020 | 582 Market St | as built permit for errcs. replace bda & yagi antenna & reprogram new frequencies. reference pa #2019-0222-3640Details
as built permit for errcs. replace bda & yagi antenna & reprogram new frequencies. reference pa #2019-0222-3640 | |
| Nov 4, 2019 | Never finaled issued Nov 2019, no final | 1661 Pine St | remove & replace (e) tile flooring, toilet(2) urinals (2) and 2 lavysinks. new frp wall panels throughout. g1 west mens bathroom. all walls and ceiling remain. repalce existing electrical devices replace existing recessed lights/led.Details
remove & replace (e) tile flooring, toilet(2) urinals (2) and 2 lavysinks. new frp wall panels throughout. g1 west mens bathroom. all walls and ceiling remain. repalce existing electrical devices replace existing recessed lights/led. | $50,000 |
| Oct 23, 2019 | Never finaled issued Jan 2020, no final | 582 Market St | elevator modernization. 13th fl elevator machine room demolished & reconstructed to align to 13th fl. (n) machine room walls and doors. new elevator equipment & controlsDetails
elevator modernization. 13th fl elevator machine room demolished & reconstructed to align to 13th fl. (n) machine room walls and doors. new elevator equipment & controls | $228,237 |
| Sep 27, 2019 | Completed final sign-off Oct 2021 | 1200 04th St | ste c: ti of (n) dental office.build (n) non-bearing part. walls for reception area, 6 operatories,dr office staff lounge & other support areas.(n) gyp board ceiling & soffits.operatory room sinks & services, sinks will be installed throughout including 2 ada restrms, equip platform will be providedDetails
ste c: ti of (n) dental office.build (n) non-bearing part. walls for reception area, 6 operatories,dr office staff lounge & other support areas.(n) gyp board ceiling & soffits.operatory room sinks & services, sinks will be installed throughout including 2 ada restrms, equip platform will be provided | $252,800 |
| Mar 6, 2019 | Never finaled issued Mar 2019, no final | 1661 Pine St | remove and replace existing tile, flooring, toilets (3), urinal (1), and (2) shower pans. new frp wall panels throughout except showers. all walls & ceilings stay in same locations. remove and replace (4) sinks. replace existing electrical devices. upgrade existing recessed lighting to ledDetails
remove and replace existing tile, flooring, toilets (3), urinal (1), and (2) shower pans. new frp wall panels throughout except showers. all walls & ceilings stay in same locations. remove and replace (4) sinks. replace existing electrical devices. upgrade existing recessed lighting to led | $50,000 |
| Feb 22, 2019 | Completed final sign-off Mar 2020 | 582 Market St | installation of emergency responder radio coverage system.Details
installation of emergency responder radio coverage system. | $49,000 |
| Dec 14, 2018 | Completed final sign-off Jun 2023 | 333 Market St | upgrade of the existing fuel system. replacement of existing pumps, piping, and day tanks. **maher n/a**Details
upgrade of the existing fuel system. replacement of existing pumps, piping, and day tanks. **maher n/a** | $400,000 |
| Sep 17, 2018 | Expired or cancelled cancelled Jan 2019 | 2235 Hayes St | add a high low drinking fountation to current project ref 201612225752Details
add a high low drinking fountation to current project ref 201612225752 | $10,000 |
| Jun 14, 2018 | Completed final sign-off Feb 2019 | 45 Castro St | combine (e) suites 415 & 418; remove wall between (e)exam & (e) reception to add business office, add (n) accessible exam room, relocate reception, expand (e) toilet to be accessible, add (n) make-up room, and reconfigure (e) exam 4 into (n) accessible exam / treatment room. n/a for maher.Details
combine (e) suites 415 & 418; remove wall between (e)exam & (e) reception to add business office, add (n) accessible exam room, relocate reception, expand (e) toilet to be accessible, add (n) make-up room, and reconfigure (e) exam 4 into (n) accessible exam / treatment room. n/a for maher. | $58,000 |
| May 10, 2018 | Completed final sign-off Feb 2019 | 1455 Market St | 1st fl - ti to include demo of non-structural partitions. new non-structural partitions mep & fire life safety under separate permitDetails
1st fl - ti to include demo of non-structural partitions. new non-structural partitions mep & fire life safety under separate permit | $150,000 |
| Apr 16, 2018 | Completed final sign-off Oct 2018 | 1455 Market St | 7th fl: minor interior remodel to add a private office and change existing light fixtures. maher naDetails
7th fl: minor interior remodel to add a private office and change existing light fixtures. maher na | $15,000 |
| Apr 10, 2018 | Completed final sign-off Sep 2018 | 1455 Market St | install 6' high windscreen barrier system at extg exterior breezeway seating area of sidewalk. n/a for maherDetails
install 6' high windscreen barrier system at extg exterior breezeway seating area of sidewalk. n/a for maher | $100,000 |
| Apr 2, 2018 | Completed final sign-off Nov 2018 | 45 Castro St | remove wall between reception and waiting room make (2) existing exam rooms into (1) access exam room enlarge storage into office (n) finishes throughout.Details
remove wall between reception and waiting room make (2) existing exam rooms into (1) access exam room enlarge storage into office (n) finishes throughout. | $153,000 |
| Jan 17, 2018 | Never finaled issued Jan 2018, no final | 555 Buckingham Wy | revision to app#201706129059. fire sprinkler status update. n/a for maherDetails
revision to app#201706129059. fire sprinkler status update. n/a for maher | |
| Jan 17, 2018 | Never finaled issued Jan 2018, no final | 595 Buckingham Wy | 4th floor: revision to app#201706129058. fire sprinkler status update. n/a for maherDetails
4th floor: revision to app#201706129058. fire sprinkler status update. n/a for maher | |
| Jan 17, 2018 | Never finaled issued Jan 2018, no final | 595 Buckingham Wy | 3rd floor: revision to app#201706129061. fire sprinkler status update. n/a for maherDetails
3rd floor: revision to app#201706129061. fire sprinkler status update. n/a for maher | |
| Jan 17, 2018 | Never finaled issued Jan 2018, no final | 585 Buckingham Wy | ground floor: revision to app#201706129057. fire sprinkler status update. maher n/aDetails
ground floor: revision to app#201706129057. fire sprinkler status update. maher n/a | |
| Dec 15, 2017 | Completed final sign-off Dec 2017 | 3555 Cesar Chavez St | to obtain a final inspeciton for work already approved under pa# 201407231968 & 201405155923, all work is completeDetails
to obtain a final inspeciton for work already approved under pa# 201407231968 & 201405155923, all work is complete | |
| Dec 8, 2017 | Completed final sign-off Nov 2018 | 1455 Market St | south side of bldg - 1st fl/lower level b upgrade the (e) facade of 1455 market st, ste 200. adding (n) store front windows. new storefront entrance and awning on mission st. new bldg lighting on 11 & mission. (n) drinking fountainDetails
south side of bldg - 1st fl/lower level b upgrade the (e) facade of 1455 market st, ste 200. adding (n) store front windows. new storefront entrance and awning on mission st. new bldg lighting on 11 & mission. (n) drinking fountain | $1,650,000 |
| Nov 22, 2017 | Completed final sign-off Feb 2018 | 1455 Market St | 7th fl: revision to pa #201705156621, to add glass doors to replace (e) wood doors, and to convert a private office into a small training room. no change to (e) occupncy or egress. maher naDetails
7th fl: revision to pa #201705156621, to add glass doors to replace (e) wood doors, and to convert a private office into a small training room. no change to (e) occupncy or egress. maher na | $15,000 |
| Nov 14, 2017 | Completed final sign-off Aug 2018 | 1455 Market St | 1st fl ti to include consturction of new cold shell office space with new accessible restrooms and shower/changing room. building fully sprinklered all open area hvac, el, plumbing other than restrooms, will be stubbed for future tis. fire under separate permits all work is engineeredDetails
1st fl ti to include consturction of new cold shell office space with new accessible restrooms and shower/changing room. building fully sprinklered all open area hvac, el, plumbing other than restrooms, will be stubbed for future tis. fire under separate permits all work is engineered | $495,000 |
| Sep 27, 2017 | Completed final sign-off Aug 2018 | 1455 Market St | demolish non structural partitons, acoustical ceilings, light fixtures, hvac units ductwork. sprinkler permit 201709138033Details
demolish non structural partitons, acoustical ceilings, light fixtures, hvac units ductwork. sprinkler permit 201709138033 | $250,000 |
| Jun 12, 2017 | Completed final sign-off Aug 2018 | 595 Buckingham Wy | 3rd flr: 2400 sf remodel of 5 story medical office bld. work in suite 300-312 maher naDetails
3rd flr: 2400 sf remodel of 5 story medical office bld. work in suite 300-312 maher na | $292,632 |
| Jun 12, 2017 | Completed final sign-off Dec 2018 | 555 Buckingham Wy | remodel of (e) garage 553 buckingham and retail 555 buckingham bld into a medical office suite. new floor slab to provide level floor across the suite maher naDetails
remodel of (e) garage 553 buckingham and retail 555 buckingham bld into a medical office suite. new floor slab to provide level floor across the suite maher na | $441,386 |
| Jun 12, 2017 | Completed final sign-off Aug 2018 | 595 Buckingham Wy | 3380 sf remodel on 4th flr of a 5 story bld - medical office. work in suite 415-430 maher naDetails
3380 sf remodel on 4th flr of a 5 story bld - medical office. work in suite 415-430 maher na | $412,123 |
| Jun 12, 2017 | Completed final sign-off Aug 2018 | 585 Buckingham Wy | remodel of 3 seperate store front suites to 1 4935 sq.ft. first floor suite inside a 128,064 sq.ft. five story medical office bld. maher naDetails
remodel of 3 seperate store front suites to 1 4935 sq.ft. first floor suite inside a 128,064 sq.ft. five story medical office bld. maher na | $601,724 |
| Jun 9, 2017 | Completed final sign-off Sep 2017 | 1455 Market St | exterior facade alteration consisting of a new structural band with overhead infrared electric heaters. electrical work defered. maher naDetails
exterior facade alteration consisting of a new structural band with overhead infrared electric heaters. electrical work defered. maher na | $106,000 |
| May 15, 2017 | Completed final sign-off Feb 2018 | 1455 Market St | 7th fl: minor remodel to convert storage & accessory spaces to offices at suites 731/733 and 726. amep plans, fire sprinklers and alarms under separate permit. maher naDetails
7th fl: minor remodel to convert storage & accessory spaces to offices at suites 731/733 and 726. amep plans, fire sprinklers and alarms under separate permit. maher na | $200,000 |
| Mar 10, 2017 | Completed final sign-off Oct 2017 | 160 Pacific Av | 1st flr suite 3008: commerical ti for office space about 1900 sq ft - new partitions, finishes, casework, electrical & plumbing. 1 hr corridor with 20 min door. mech/elec, fire under separate permit. maher naDetails
1st flr suite 3008: commerical ti for office space about 1900 sq ft - new partitions, finishes, casework, electrical & plumbing. 1 hr corridor with 20 min door. mech/elec, fire under separate permit. maher na | $260,250 |
| Mar 8, 2017 | Never finaled issued Apr 2018, no final | 582 Market St | window replacement only. exterior window replacement in the renovated restrooms in 3rd thru 12th floors. ref pa# 2015/03/27/2142.Details
window replacement only. exterior window replacement in the renovated restrooms in 3rd thru 12th floors. ref pa# 2015/03/27/2142. | $76,100 |
| Jan 26, 2017 | Completed final sign-off May 2017 | 1661 Pine St | unit #636. 2 baths & 1 kitchen remodel new cabinets & plumbing fixts throughout. 2 new shower pans. no walls removed or relocated. no lighting change. n/a for maher.Details
unit #636. 2 baths & 1 kitchen remodel new cabinets & plumbing fixts throughout. 2 new shower pans. no walls removed or relocated. no lighting change. n/a for maher. | $40,000 |
| Jan 26, 2017 | Never finaled issued Jan 2017, no final | 1661 Pine St | unit #528. 1 1/2 bath & 1 kitchen remodel new cabinets & plumbing fixts throughout. new shower pan. no walls removed or relocated. no lighting change. n/a for maher.Details
unit #528. 1 1/2 bath & 1 kitchen remodel new cabinets & plumbing fixts throughout. new shower pan. no walls removed or relocated. no lighting change. n/a for maher. | $30,000 |
| Jan 11, 2017 | Completed final sign-off Sep 2019 | 460 Stanyan St | ada barrier removal at mri building. ** maher: n/a **Details
ada barrier removal at mri building. ** maher: n/a ** | $33,018 |
| Dec 22, 2016 | Completed final sign-off Oct 2019 | 2235 Hayes St | ada barrier removal. (no exterior work). to remove architectural barriers to provide a greater degree of accessibility to the features & amenties @ the dignity health, st. mary's medical center which includes: elevator control panel adj., signage replacement, restroom remodel & door hardward updatesDetails
ada barrier removal. (no exterior work). to remove architectural barriers to provide a greater degree of accessibility to the features & amenties @ the dignity health, st. mary's medical center which includes: elevator control panel adj., signage replacement, restroom remodel & door hardward updates | $115,230 |
| Dec 22, 2016 | Completed final sign-off Sep 2019 | 1 Shrader St | ada barrier removal.(no exterior work).Details
ada barrier removal.(no exterior work). | $278,059 |
| Dec 22, 2016 | Completed final sign-off Sep 2019 | 2250 Hayes St | ada barrier removal. ** maher: n/a **Details
ada barrier removal. ** maher: n/a ** | $92,106 |
| Dec 5, 2016 | Expired or cancelled cancelled Jan 2026 | 160 Pacific Av | add shower area in gr fl parking garage bldg 3. work includes new walls, doors, frame. finishes, plumbing, elec. no structural workDetails
add shower area in gr fl parking garage bldg 3. work includes new walls, doors, frame. finishes, plumbing, elec. no structural work | $175,000 |
| Nov 15, 2016 | Expired or cancelled expired Nov 2017 | 1661 Pine St | # 1144: amend 201610170507. change unit number 513 to unit # 1144. sam scope of work. n/a maherDetails
# 1144: amend 201610170507. change unit number 513 to unit # 1144. sam scope of work. n/a maher | |
| Oct 17, 2016 | Completed final sign-off Dec 2016 | 1661 Pine St | unit #1143: one bath remodel. new cabinets & plumbing fixtures throughout. one shower pan. no walls, window, or door removed or relocated.Details
unit #1143: one bath remodel. new cabinets & plumbing fixtures throughout. one shower pan. no walls, window, or door removed or relocated. | $12,000 |
| Oct 17, 2016 | Completed final sign-off Jan 2017 | 1661 Pine St | unit #426: two baths and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. two shower pans. no walls, window, or door removed or relocated.Details
unit #426: two baths and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. two shower pans. no walls, window, or door removed or relocated. | $21,000 |
| Oct 17, 2016 | Expired or cancelled expired Nov 2017 | 1661 Pine St | unit #513: one bath and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. no walls, window, or door removed or relocated.Details
unit #513: one bath and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. no walls, window, or door removed or relocated. | $18,000 |
| Oct 17, 2016 | Completed final sign-off Dec 2016 | 1661 Pine St | unit #526: one bath and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. one shower pan. no walls, windows, or door removed or relocated.Details
unit #526: one bath and 1 kitchen remodel. new cabinets & plumbing fixtures throughout. one shower pan. no walls, windows, or door removed or relocated. | $18,000 |
| Sep 13, 2016 | Completed final sign-off Jan 2017 | 582 Market St | shell improvement only. new wood entery door with sidelite. new wall to create elevator lobby. new radiator casework. n drop ceiling. furring frame at all e conc columns. box frame to conceal plumbing pipes. new lighting fixtures. new carpet tiles and solid surface countertopDetails
shell improvement only. new wood entery door with sidelite. new wall to create elevator lobby. new radiator casework. n drop ceiling. furring frame at all e conc columns. box frame to conceal plumbing pipes. new lighting fixtures. new carpet tiles and solid surface countertop | $148,000 |
| Sep 7, 2016 | Completed final sign-off Nov 2016 | 560 Davis St | ste. #1003: revision to pa 201606099525: removal of soffit & grid in break area. maher naDetails
ste. #1003: revision to pa 201606099525: removal of soffit & grid in break area. maher na | $3,000 |
| Aug 31, 2016 | Completed final sign-off Sep 2016 | 75 Broadway | 1st floor: revision to ref pa 201606099520 expansion at break room areaDetails
1st floor: revision to ref pa 201606099520 expansion at break room area | $15,000 |
| Aug 30, 2016 | Expired or cancelled expired Nov 2017 | 1661 Pine St | unit # 513, 1 bath , 1 kitchen new cabinets & plumbing fixtures throughout, 1 shower pan no wall removed or relocatedDetails
unit # 513, 1 bath , 1 kitchen new cabinets & plumbing fixtures throughout, 1 shower pan no wall removed or relocated | $18,000 |
| Aug 30, 2016 | Completed final sign-off Oct 2016 | 1661 Pine St | unit # 935, 1 bath , 1 kitchen new cabinets & plumbing fixtures throughout, 1 shower pan no wall removed or relocatedDetails
unit # 935, 1 bath , 1 kitchen new cabinets & plumbing fixtures throughout, 1 shower pan no wall removed or relocated | $18,000 |
| Aug 22, 2016 | Completed final sign-off Nov 2016 | 1500 Owens St | partial 1st, 3rd & 4th floor - add plumbing, casework, & electrical to convert 3 (e) clinic rooms into exam rooms. add interior partition to storage room. add plumbing for hand sink in relocated medical equipment room. n/a maher ordinanceDetails
partial 1st, 3rd & 4th floor - add plumbing, casework, & electrical to convert 3 (e) clinic rooms into exam rooms. add interior partition to storage room. add plumbing for hand sink in relocated medical equipment room. n/a maher ordinance | $150,000 |
| Aug 12, 2016 | Completed final sign-off Nov 2016 | 560 Davis St | revision to pa 2016-0615-0033 - addition of structural detail for replacment of concrete slabDetails
revision to pa 2016-0615-0033 - addition of structural detail for replacment of concrete slab | $15,000 |
| Aug 12, 2016 | Completed final sign-off Nov 2016 | 560 Davis St | suite 1003 - revision to pa 2016-0609-9525, addition of structural detail for suspended soffit. maher naDetails
suite 1003 - revision to pa 2016-0609-9525, addition of structural detail for suspended soffit. maher na | $1,000 |
| Aug 12, 2016 | Completed final sign-off Sep 2016 | 160 Pacific Av | revision to pa 2016-0609-9520 - addition of structural detail for a suspended soffit. maher naDetails
revision to pa 2016-0609-9520 - addition of structural detail for a suspended soffit. maher na | $1,000 |
| Aug 1, 2016 | Completed final sign-off Jan 2017 | 1661 Pine St | #339: (1) bath/(1) kitchen remodel. new cabinet & plumbing fixtures throughout. new shower pan. no walls removed or relocated, no lighting change.Details
#339: (1) bath/(1) kitchen remodel. new cabinet & plumbing fixtures throughout. new shower pan. no walls removed or relocated, no lighting change. | $18,000 |
| Aug 1, 2016 | Completed final sign-off Oct 2016 | 1414 Lyon St | (1) bath remoel at top level. new cabinet & plumbing fixtures. new shower pan. no walls removed or relocated, high efficacy lighting or controlled by manuel sensor with high efficacy main light.Details
(1) bath remoel at top level. new cabinet & plumbing fixtures. new shower pan. no walls removed or relocated, high efficacy lighting or controlled by manuel sensor with high efficacy main light. | $18,000 |
| Aug 1, 2016 | Completed final sign-off Sep 2016 | 1661 Pine St | #1023: (2) bath/(1) kitchen remodeling. new cabinet & plumbing fixtures throughout. new shower pan. no walls removed or relocated, no lighting change.Details
#1023: (2) bath/(1) kitchen remodeling. new cabinet & plumbing fixtures throughout. new shower pan. no walls removed or relocated, no lighting change. | $21,000 |
| Jun 15, 2016 | Never finaled issued Jun 2016, no final | 560 Davis St | 1st level - (2) new unisex restrooms to be built work includes minor demolitoin, new partitoins, doors, plumbing fixtues ceiling, lighting & finishes. this is an additional restroom to pa #201509086385. n/a maher ordinanceDetails
1st level - (2) new unisex restrooms to be built work includes minor demolitoin, new partitoins, doors, plumbing fixtues ceiling, lighting & finishes. this is an additional restroom to pa #201509086385. n/a maher ordinance | $140,200 |
| Jun 15, 2016 | Completed final sign-off Aug 2016 | 1661 Pine St | unit 716: (2) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not requiredDetails
unit 716: (2) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not required | $18,000 |
| Jun 15, 2016 | Completed final sign-off Sep 2016 | 1661 Pine St | unit 341: (2) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not requiredDetails
unit 341: (2) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not required | $25,000 |
| Jun 15, 2016 | Completed final sign-off Sep 2016 | 1661 Pine St | unit 344: (1) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not required.Details
unit 344: (1) bath/(1) kitchen; new cabinets & plumbing fixtures throughout, (1) new shower pan, no walls removed/relocated; compliance with maher ordinance no 155-13 not required. | $18,000 |
| Jun 10, 2016 | Completed final sign-off Nov 2016 | 650 Davis St | suite #2003: this is a commercial t.i. on a single floor, work includes new partitions, doors and frames, ceiling, lighting, finishes, casework, electrical and mechanical. f/a and sprinklers under separate permit.Details
suite #2003: this is a commercial t.i. on a single floor, work includes new partitions, doors and frames, ceiling, lighting, finishes, casework, electrical and mechanical. f/a and sprinklers under separate permit. | $310,000 |
| Jun 10, 2016 | Completed final sign-off Aug 2016 | 560 Davis St | 1/f- revision to pa#201605066778, door relocation in structural concrete wall. n/a ordinance #155-13.Details
1/f- revision to pa#201605066778, door relocation in structural concrete wall. n/a ordinance #155-13. | $14,000 |
| Jun 9, 2016 | Completed final sign-off Nov 2016 | 560 Davis St | suite #1003 - commercial tenant improvementon single floor work includes new partitions, finishes, casework, electrical & plumbing. this is not a medical office space. n/a maher ordinance. mep/alarm/sprinkler deferred.Details
suite #1003 - commercial tenant improvementon single floor work includes new partitions, finishes, casework, electrical & plumbing. this is not a medical office space. n/a maher ordinance. mep/alarm/sprinkler deferred. | $850,000 |
| Jun 9, 2016 | Completed final sign-off Sep 2016 | 160 Pacific Av | suite #3015 - commercial tenant improvement work includes new partitions, finishes, casework, electrical & plumbing. this is not a medicla office space. n/a maher ordinanceDetails
suite #3015 - commercial tenant improvement work includes new partitions, finishes, casework, electrical & plumbing. this is not a medicla office space. n/a maher ordinance | $300,000 |
| Jun 7, 2016 | Completed final sign-off Sep 2016 | 560 Davis St | #55- commercial ti on a single floor. includes new partitions, finishes, casework, elec and plumb. upgrade. add sinks for consulting purposes. not medical officeDetails
#55- commercial ti on a single floor. includes new partitions, finishes, casework, elec and plumb. upgrade. add sinks for consulting purposes. not medical office | $65,000 |
| May 20, 2016 | Completed final sign-off Aug 2016 | 1603 Pine St | remove & bar ceiling drywall ceiling & partition walls; all fire rated assemblies to remain.Details
remove & bar ceiling drywall ceiling & partition walls; all fire rated assemblies to remain. | $7,000 |
| May 6, 2016 | Completed final sign-off Aug 2016 | 560 Davis St | 1st floor: revision to ref pa 2016 0908 6385: restroom upgrade on 1st floor. work includes plumbing fixtures, ceiling, lighting and finishes. maher naDetails
1st floor: revision to ref pa 2016 0908 6385: restroom upgrade on 1st floor. work includes plumbing fixtures, ceiling, lighting and finishes. maher na | |
| Mar 24, 2016 | Completed final sign-off Jul 2016 | 1661 Pine St | apt #837: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated.Details
apt #837: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off May 2016 | 1661 Pine St | apt #824: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated.Details
apt #824: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off Jun 2016 | 1661 Pine St | apt #844: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated.Details
apt #844: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off May 2016 | 1661 Pine St | apt #615: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated.Details
apt #615: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off Jun 2016 | 1661 Pine St | apt #833: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated.Details
apt #833: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off Jun 2016 | 1661 Pine St | apt #810: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated.Details
apt #810: 1 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 1 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Mar 24, 2016 | Completed final sign-off Jul 2016 | 1661 Pine St | apt #1112: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated.Details
apt #1112: 2 bathroom & 1 kitchen: new cabinets & plumbing fixtures througout. 2 new shower pan. like for like. no walls removed or relocated. | $18,000 |
| Feb 25, 2016 | Completed final sign-off Jul 2017 | 3555 Cesar Chavez St | project is strictly a voluntary access barrier removal to add accessible van parking stall & restripe existing parking lot. final count with 2 van accessible & 2 standard accessible parking stalls.Details
project is strictly a voluntary access barrier removal to add accessible van parking stall & restripe existing parking lot. final count with 2 van accessible & 2 standard accessible parking stalls. | $25,000 |
| Feb 23, 2016 | Never finaled issued Feb 2016, no final | 1580 Valencia St | revision to pa 2015-0407-3006, change to door header framing detail.Details
revision to pa 2015-0407-3006, change to door header framing detail. | |
| Feb 17, 2016 | Completed final sign-off Aug 2016 | 560 Davis St | mechanical permit only. ref arch drawing #201509086385Details
mechanical permit only. ref arch drawing #201509086385 | $53,300 |
| Feb 2, 2016 | Completed final sign-off Aug 2016 | 560 Davis St | this is a new restroom to be built on 1st level work includes new plumbing fixtures, ceiling , lighting and finishes. revision to approved permit 2015-0908-6385Details
this is a new restroom to be built on 1st level work includes new plumbing fixtures, ceiling , lighting and finishes. revision to approved permit 2015-0908-6385 | $50,000 |
| Jan 20, 2016 | Completed final sign-off May 2016 | 1661 Pine St | apt 713: remodel 2 bathroms, 1 kitchen. new cabinets & plumbing fixtures throughout. 2 new shower pans.Details
apt 713: remodel 2 bathroms, 1 kitchen. new cabinets & plumbing fixtures throughout. 2 new shower pans. | $21,000 |
| Jan 20, 2016 | Completed final sign-off Nov 2016 | 1661 Pine St | apt 313: remodel 1 bathroms, 1 kitchen. new cabinets & plumbing fixtures throughout. 1 new shower pans.Details
apt 313: remodel 1 bathroms, 1 kitchen. new cabinets & plumbing fixtures throughout. 1 new shower pans. | $18,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 1661 Pine St | apt 936: retile 2 bathrooms.Details
apt 936: retile 2 bathrooms. | $10,000 |
| Dec 29, 2015 | Completed final sign-off Aug 2016 | 560 Davis St | revision to existing approved permit 201512185462 & 201512185462 addition of structural detail; maher n/aDetails
revision to existing approved permit 201512185462 & 201512185462 addition of structural detail; maher n/a | $1,000 |
| Dec 18, 2015 | Completed final sign-off Aug 2016 | 560 Davis St | revision to existing approved pa 2015-0908-6385. remove portion of accoustic ceiling to create "open ceiling"; enlarge window sidelites. maher naDetails
revision to existing approved pa 2015-0908-6385. remove portion of accoustic ceiling to create "open ceiling"; enlarge window sidelites. maher na | $30,000 |
| Dec 1, 2015 | Completed final sign-off Dec 2015 | 45 Castro St | revision to bpa# 201505206827. to clear no sprinklers are installed in this buildin, as per application 201505206827 sheet fs2.1 shows sprinkelrs.; maher n/aDetails
revision to bpa# 201505206827. to clear no sprinklers are installed in this buildin, as per application 201505206827 sheet fs2.1 shows sprinkelrs.; maher n/a | |
| Nov 13, 2015 | Completed final sign-off Aug 2016 | 560 Davis St | mech permit only. t.i. framed partitions, bathroom remodel, mechanical replace under ref app#201509086385Details
mech permit only. t.i. framed partitions, bathroom remodel, mechanical replace under ref app#201509086385 | $510,200 |
| Oct 16, 2015 | Completed final sign-off Nov 2016 | 1661 Pine St | unit #618: bath and kitchen remodel. new cabinets and plumbing fixtures throughout. new shower pan.Details
unit #618: bath and kitchen remodel. new cabinets and plumbing fixtures throughout. new shower pan. | $18,000 |