7 permits since 2000 (engineer on 6 permits, architect on 1 permit): 7 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 4, 2016 | Completed final sign-off Sep 2016 | 1744 Armstrong Av | at&t mobile, remove & replace 9 (e) antennas with (6) (n) antennas; install (3) (n) rrus-11 w/a-2; install (3)(n) rrus-32; install (3)(n) dc6 surge suppressors; install (n) dvs41in (e) purcell; install (n) xmv inside (e) purcell; install (n) fiber & dc power trunks; remove (e) gsm cabinetDetails
at&t mobile, remove & replace 9 (e) antennas with (6) (n) antennas; install (3) (n) rrus-11 w/a-2; install (3)(n) rrus-32; install (3)(n) dc6 surge suppressors; install (n) dvs41in (e) purcell; install (n) xmv inside (e) purcell; install (n) fiber & dc power trunks; remove (e) gsm cabinet | $30,000 | |
| Feb 16, 2016 | Completed final sign-off Nov 2016 | 103 Carl St | Metropolitan Electrical Construction, Electric Tech Construction Inc | att modification, install 3 new rrus 32, install new xmu inside e 19" rack, r and r 6 e antennes with 6 new antennas, relocate 2 e rrus-11 with a2, relocate e rrus-11Details
att modification, install 3 new rrus 32, install new xmu inside e 19" rack, r and r 6 e antennes with 6 new antennas, relocate 2 e rrus-11 with a2, relocate e rrus-11 | $19,000 |
| Dec 4, 2015 | Completed final sign-off Sep 2016 | 920 North Point St | Electric Tech Construction Inc | modification to an (e) at&t facil include r&r 3 antennas, 1 surge suppressors & install 6 new surge supps. & relocate 3 (e) rrvs, install 1 (n) purcell cabinet & install 3 (n) 2" innerducts with fiber/power cables.also remove all unused equipment include coax cables, tma units & diplexers.Details
modification to an (e) at&t facil include r&r 3 antennas, 1 surge suppressors & install 6 new surge supps. & relocate 3 (e) rrvs, install 1 (n) purcell cabinet & install 3 (n) 2" innerducts with fiber/power cables.also remove all unused equipment include coax cables, tma units & diplexers. | $30,000 |
| Nov 16, 2015 | Completed final sign-off May 2016 | 1188 Franklin St | Electric Tech Construction Inc | at&t modification to (e) telecom facility: install 3(n)rrus-32; install 3(n)dcg surge suppressors;(n)inner duct,(n)dc12 surge suppressor &hoffman box,(n)6601 v2 chassis w/(n)dus41;r&r 3 antennas w/(3)(n)antennas;relocate rrus,remove dcg surge from (e)rba72.Details
at&t modification to (e) telecom facility: install 3(n)rrus-32; install 3(n)dcg surge suppressors;(n)inner duct,(n)dc12 surge suppressor &hoffman box,(n)6601 v2 chassis w/(n)dus41;r&r 3 antennas w/(3)(n)antennas;relocate rrus,remove dcg surge from (e)rba72. | $22,000 |
| Oct 16, 2015 | Completed final sign-off Feb 2016 | 121 Steuart St | Electric Tech Construction Inc | at&t mobility modification to (e) telecommunication facility & install (1) (n) xmu inside (e) 19" rack; install (3) (n) rrus-32 units; install (n) 2" innerduct for fiber & dc cables; r&r (4) (e) antennas w/(4) (n) antennas. n/a maher ordinanceDetails
at&t mobility modification to (e) telecommunication facility & install (1) (n) xmu inside (e) 19" rack; install (3) (n) rrus-32 units; install (n) 2" innerduct for fiber & dc cables; r&r (4) (e) antennas w/(4) (n) antennas. n/a maher ordinance | $12,500 |
| Jun 25, 2015 | Completed final sign-off May 2016 | 22 Battery St | Triton Tower Inc | modification of an(e) at&t facility including: remove/replace 3 (e) antennas with 3 (n) antennas of similar size; remove/replace 3(e) surge supressors; install 3 (n) rrus and 3 (n) dtmas near antennas; other minor improvements to equipment including (n) innerduct & (n) dvs 41 unit.n/a maher ordinancDetails
modification of an(e) at&t facility including: remove/replace 3 (e) antennas with 3 (n) antennas of similar size; remove/replace 3(e) surge supressors; install 3 (n) rrus and 3 (n) dtmas near antennas; other minor improvements to equipment including (n) innerduct & (n) dvs 41 unit.n/a maher ordinanc | $16,000 |
| Apr 28, 2015 | Completed final sign-off Feb 2017 | 833 Mission St | Metropolitan Electrical Construction | modification to e att facility consisting of remove & replace 1 e antenna innerduct for fiber and dc cables, new rrus 32 unit, r+r 1 e dc2 surge supp. with new dc6 surge supp. 1 e antenna with 1 n antenna, remove e rruw-01 unit, e duplex with e unistruct frame, remove all unsused coax cable. removeDetails
modification to e att facility consisting of remove & replace 1 e antenna innerduct for fiber and dc cables, new rrus 32 unit, r+r 1 e dc2 surge supp. with new dc6 surge supp. 1 e antenna with 1 n antenna, remove e rruw-01 unit, e duplex with e unistruct frame, remove all unsused coax cable. remove | $12,500 |