30 permits since 2000 (engineer on 29 permits, designer on 1 permit): 23 completed, 2 in progress, 5 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 28, 2026 | In progress filed Sep 2026, not yet issued | 4 Embarcadero Center | Gci, Inc | level 16 - 18: finish and guardrail work to (e) stair.Details
level 16 - 18: finish and guardrail work to (e) stair. | $29,000 |
| May 20, 2026 | In progress filed May 2026, not yet issued | 1255 Battery St | seismic retrofit only and associated patching and repairing due to seismic upgrades.Details
seismic retrofit only and associated patching and repairing due to seismic upgrades. | $500,000 | |
| Oct 14, 2025 | Completed final sign-off Nov 2025 | 1160 Battery St | Bcci Construction Company | 4/fl-revision to pa# 2024-0626-5338. removal of structural work and special inspections from scope to reflect as built conditions.Details
4/fl-revision to pa# 2024-0626-5338. removal of structural work and special inspections from scope to reflect as built conditions. | |
| Jul 16, 2025 | Completed final sign-off Apr 2026 | 3 Embarcadero Center | Principal Builders Inc. | 25th fl,ste 2500 -ti includes demo of non structural partitions & building new non structural partitions.(n) operable partition; upgrades incude (n) millwork, lighting & finishes throuhgout. all (n) or revised meps under separate permmit. bldg fully sprinklered. (lifeDetails
25th fl,ste 2500 -ti includes demo of non structural partitions & building new non structural partitions.(n) operable partition; upgrades incude (n) millwork, lighting & finishes throuhgout. all (n) or revised meps under separate permmit. bldg fully sprinklered. (life | $3,678,028 |
| Nov 20, 2023 | Completed final sign-off Aug 2024 | 1160 Battery St | roof - structural work related to hvac upgradesDetails
roof - structural work related to hvac upgrades | $50,000 | |
| Apr 27, 2023 | Completed final sign-off Mar 2025 | 140 New Montgomery St | Bcci Construction Company | 10/f: deferred structural permit for operable partition, partition shown on approved architectural. ref pa# 202212158443.Details
10/f: deferred structural permit for operable partition, partition shown on approved architectural. ref pa# 202212158443. | $15,000 |
| Dec 16, 2022 | Completed final sign-off Aug 2023 | 116 New Montgomery St | Swinerton Builders | 1/f & 2/f: revision to pa# 202208080111. revision to 1st & 2nd floor interior stair.Details
1/f & 2/f: revision to pa# 202208080111. revision to 1st & 2nd floor interior stair. | |
| Nov 29, 2022 | Completed final sign-off Nov 2024 | 1255 Battery St | Bcci Construction Company | 5th flr - structural strengthening of the (e) roof framing gravity system to support hvac equipment. no new mechanical equipment or change to roof under this permit.Details
5th flr - structural strengthening of the (e) roof framing gravity system to support hvac equipment. no new mechanical equipment or change to roof under this permit. | $188,000 |
| Aug 26, 2022 | Never finaled issued Sep 2022, no final | 355 Fulton St | remove (8) (e) non fire rated interior doors in the building common areas and replace w/new fire rated doors.Details
remove (8) (e) non fire rated interior doors in the building common areas and replace w/new fire rated doors. | $8,000 | |
| Aug 24, 2022 | Never finaled issued Dec 2022, no final | 900 North Point St | Swinerton Builders | clock tower: demo of partitions only per ab-017. space (3rd and 4th floor) to remain vacant- stair to remain. remaining build out to be under sep permit. no exterior work under this permit.Details
clock tower: demo of partitions only per ab-017. space (3rd and 4th floor) to remain vacant- stair to remain. remaining build out to be under sep permit. no exterior work under this permit. | $660,750 |
| Aug 8, 2022 | Completed final sign-off Jan 2024 | 116 New Montgomery St | Swinerton Builders | construct new interior egress corridor and stair from 2/f to the g/f. stair connects 2 stories and is enclosed in 1-hr rated corridor per cbc 1023.2. no work at historic facade, stair, and balcony on this permit.Details
construct new interior egress corridor and stair from 2/f to the g/f. stair connects 2 stories and is enclosed in 1-hr rated corridor per cbc 1023.2. no work at historic facade, stair, and balcony on this permit. | $210,000 |
| Jul 27, 2022 | Completed final sign-off Jan 2023 | 140 New Montgomery St | Truebeck Construction | 18th fl: structural support/analysis for mep equipment in server room and anchorage details and analysis of loads on (e) structure.Details
18th fl: structural support/analysis for mep equipment in server room and anchorage details and analysis of loads on (e) structure. | |
| Mar 29, 2022 | Completed final sign-off Jul 2023 | 55 Francisco St | Swinerton Builders | installation of structural steel support the new ahu that is being installed on the roof.Details
installation of structural steel support the new ahu that is being installed on the roof. | $105,000 |
| Nov 18, 2021 | Completed final sign-off Jul 2022 | 398 Haight St | International Waterproofing | dry rot repair replace of rotted header beam @ bldg entrance and post supports as well. non structural, repair existing cornice and pilaster @ entrance. no work at exterior except patching anchor holes. "like-for-like replacement"Details
dry rot repair replace of rotted header beam @ bldg entrance and post supports as well. non structural, repair existing cornice and pilaster @ entrance. no work at exterior except patching anchor holes. "like-for-like replacement" | $22,000 |
| Mar 15, 2021 | Completed final sign-off Oct 2021 | 1160 Battery St | Bcci Construction Company | 1st fl: demo and rebuild back of non-structural partitions. m.e.p./structural included. ref pa# 202011068411. water sump closed. 6'x6'x5'.Details
1st fl: demo and rebuild back of non-structural partitions. m.e.p./structural included. ref pa# 202011068411. water sump closed. 6'x6'x5'. | $40,000 |
| Dec 20, 2019 | Completed final sign-off Mar 2021 | 50 Bowling Green Dr | Azul Works, Inc. | revision to hvac & electrical work issued under pa 2018-0514-9026Details
revision to hvac & electrical work issued under pa 2018-0514-9026 | |
| Nov 21, 2019 | Completed final sign-off Dec 2020 | 900 North Point St | replacement electric single faced sign ghiaradelliDetails
replacement electric single faced sign ghiaradelli | $10,000 | |
| Nov 21, 2019 | Completed final sign-off Nov 2020 | 900 North Point St | Swinerton Builders | rehabiltation of historic vintage ghiradelli roof top sign per conditional use authorization 201700875 cua. work includes replacement of letters, illumination, and structural work as required to repair deteriorated membersDetails
rehabiltation of historic vintage ghiradelli roof top sign per conditional use authorization 201700875 cua. work includes replacement of letters, illumination, and structural work as required to repair deteriorated members | $10,000 |
| Jun 11, 2019 | Never finaled issued Jun 2019, no final | 16 West Clay St | Rock And Rose Landscaping & Birkmyer | landscaping including site retaining walls.Details
landscaping including site retaining walls. | $60,000 |
| Jan 31, 2019 | Never finaled issued May 2019, no final | 55 Francisco St | Swinerton Builders | voluntary structural upgrade for the (e) office building.the work is specific to the 4th floor & roof of the 4th floor annex bldg. ** maher: n/a **Details
voluntary structural upgrade for the (e) office building.the work is specific to the 4th floor & roof of the 4th floor annex bldg. ** maher: n/a ** | $45,000 |
| Nov 6, 2018 | Completed final sign-off Jan 2021 | 1390 Market St | Plant Construction Co, Lp | 1st and 2nd flr. t.i, demo on non-structural partitions and building (n) non-structural partitions. all (n) or revised mep, life safety and sprinklers under separate permit. building not fully sprinkleredDetails
1st and 2nd flr. t.i, demo on non-structural partitions and building (n) non-structural partitions. all (n) or revised mep, life safety and sprinklers under separate permit. building not fully sprinklered | $900,000 |
| Oct 1, 2018 | Completed final sign-off Mar 2020 | 235 02nd St | Novo Construction Inc | basement - structural work for ti ref 201806071269Details
basement - structural work for ti ref 201806071269 | $5,000 |
| May 14, 2018 | Completed final sign-off Jun 2021 | 50 Bowling Green Dr | erect an one story type 5 construction recreation and officeDetails
erect an one story type 5 construction recreation and office | $17,013,752 | |
| Feb 26, 2018 | Completed final sign-off Jun 2018 | 77 Maiden Ln | Novo Construction Inc | single wood framed bearing wall w/header is being replaced with new wood framed bearing wall with a longer header. in same location for increased opening opening, ref pa201712085908Details
single wood framed bearing wall w/header is being replaced with new wood framed bearing wall with a longer header. in same location for increased opening opening, ref pa201712085908 | $5,000 |
| Oct 5, 2017 | Completed final sign-off Aug 2018 | 16 West Clay St | Bjlgc Inc | removal of (2) load bearing (non lfrs) walls from the lower level & a voluntary local strengthening of the lower level via the addition of plywood shearwalls.Details
removal of (2) load bearing (non lfrs) walls from the lower level & a voluntary local strengthening of the lower level via the addition of plywood shearwalls. | $250,000 |
| Jul 7, 2017 | Completed final sign-off Sep 2018 | 398 Haight St | revision to soft story retrofit #201609218345. new foundation work and elimination of waterproofing work at n & w exterior walls. maher naDetails
revision to soft story retrofit #201609218345. new foundation work and elimination of waterproofing work at n & w exterior walls. maher na | ||
| Jun 23, 2017 | Never finaled issued Jun 2017, no final | 150 Post St | Crane Construction Company Inc. | administrative correction of special structural inspection form to correct actual inspections, needed and performed. no work under this permit.Details
administrative correction of special structural inspection form to correct actual inspections, needed and performed. no work under this permit. | |
| Apr 5, 2017 | Completed final sign-off Jul 2018 | 1800 Mission St | Yerba Buena Builders Inc | 1/f- revisioon to pa#201607142293, relocate gender inclusive restroom in different area of the project on level 1 (same floor). n/a ordinance #155-13Details
1/f- revisioon to pa#201607142293, relocate gender inclusive restroom in different area of the project on level 1 (same floor). n/a ordinance #155-13 | |
| Sep 21, 2016 | Completed final sign-off Aug 2017 | 1607 Howard St | Cornerstone Dba Ag Construction | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. soft story being performed on only residential building. there are two buildings on this lot. n/a maher ordinanceDetails
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. soft story being performed on only residential building. there are two buildings on this lot. n/a maher ordinance | $60,000 |
| Sep 21, 2016 | Completed final sign-off Sep 2018 | 398 Haight St | soft story retrofit per sfbc chapter asce7-10. n/a ordinance #155-13Details
soft story retrofit per sfbc chapter asce7-10. n/a ordinance #155-13 | $200,000 |