Block 3736, lot 123
235 02nd St
- City’s use
- Commercial Office
- Built
- 2001
- Lot
- 40,625 sq ft
- Zoning
- C3OSD
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
77 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 16, 2026 | In progress issued Sep 2026 | 235 02nd St | Bcci Construction Company | revision to issued 202606253898. changes include elminating level 2 - lobby and copy room scope. eliminating level 3 unisex toilet and shower scope. minor reunions to light fixtures. millwork, finishes, and schedules.Details
revision to issued 202606253898. changes include elminating level 2 - lobby and copy room scope. eliminating level 3 unisex toilet and shower scope. minor reunions to light fixtures. millwork, finishes, and schedules. | |
| Aug 10, 2026 | Completed final sign-off Sep 2026 | 235 02nd St | Premier Structures Inc | to obtain final inspection for work approved under pa# 202504023592. all work is complete.Details
to obtain final inspection for work approved under pa# 202504023592. all work is complete. | |
| Aug 10, 2026 | In progress issued Aug 2026 | 235 02nd St | Premier Structures Inc | recommencement and completion of work approved under pa#'s 202410314101 and 202502261170.Details
recommencement and completion of work approved under pa#'s 202410314101 and 202502261170. | $18,750 |
| Jun 25, 2026 | In progress issued Jul 2026 | 235 02nd St | Bcci Construction Company | level 2 & 3 minor ti: project scope focuses on lobby, break rooms and toilets, non-structural demolition, non-structural partitions, new furnature and finishes throughout. existing egress systems, fire rated wall systems, elevators, structure, sprinklers, and existing use to remain.Details
level 2 & 3 minor ti: project scope focuses on lobby, break rooms and toilets, non-structural demolition, non-structural partitions, new furnature and finishes throughout. existing egress systems, fire rated wall systems, elevators, structure, sprinklers, and existing use to remain. | $2,900,000 |
| Mar 17, 2026 | Completed final sign-off Sep 2026 | 235 02nd St | Premier Structures Inc | ground floor ti for suite 1500 to include restroom on 1st floor of an (e) 6 story building. non structural demo, partitions, and (n) act ceiling tile and lighting fixtures, (n) and modified millwork and plumbing fixturesDetails
ground floor ti for suite 1500 to include restroom on 1st floor of an (e) 6 story building. non structural demo, partitions, and (n) act ceiling tile and lighting fixtures, (n) and modified millwork and plumbing fixtures | $525,000 |
| Feb 6, 2026 | Completed final sign-off Jun 2026 | 235 02nd St | Bilcor Inc | 5th & 6th fl ref pa # 2025-1112-9361 & 2025-0618-8982: install 1 rath master station, install 1 smart command boss, install 1 uninterruptible power supply, install 2 call station, install 2 monitor modules k, 2 control relays, 1 mushroom palm button, 1 install viking remote, 1 dual monitor moduleDetails
5th & 6th fl ref pa # 2025-1112-9361 & 2025-0618-8982: install 1 rath master station, install 1 smart command boss, install 1 uninterruptible power supply, install 2 call station, install 2 monitor modules k, 2 control relays, 1 mushroom palm button, 1 install viking remote, 1 dual monitor module | $30,008 |
| Nov 12, 2025 | In progress issued Dec 2025 | 235 02nd St | Premier Structures Inc | 5/f: new rated doors at passenger elevator lobby, card readers, and a door release button.Details
5/f: new rated doors at passenger elevator lobby, card readers, and a door release button. | $40,000 |
| Sep 5, 2025 | Completed final sign-off Sep 2025 | 235 02nd St | Bilcor Inc | 6th floor; install (46) ceiling mount strobes. install (10) wall mount horn strobe. install (16) ceiing mount horn strobe. install (2) control relays. arch t.i. 20250455292Details
6th floor; install (46) ceiling mount strobes. install (10) wall mount horn strobe. install (16) ceiing mount horn strobe. install (2) control relays. arch t.i. 20250455292 | $40,000 |
| Jun 26, 2025 | Completed final sign-off Sep 2025 | 235 02nd St | Anderson, Rowe & Buckley, Inc. | 6th floor. existing fire sprinkler system - tenant improvements. 73 relocated sprinklers. 4 removed sprinklers.Details
6th floor. existing fire sprinkler system - tenant improvements. 73 relocated sprinklers. 4 removed sprinklers. | $18,450 |
| Jun 18, 2025 | Completed final sign-off Jul 2026 | 235 02nd St | Premier Structures Inc | defer mech. & elec. drwngs - 202504255292. changes to exist. vav terminal units and rtus for 6th fl rms. power for workstations, breakroom, and pantry. new & updated lighting in select areas. revise scope to include new elevator lobby doors and card/emergency release devices and changes to rcp.Details
defer mech. & elec. drwngs - 202504255292. changes to exist. vav terminal units and rtus for 6th fl rms. power for workstations, breakroom, and pantry. new & updated lighting in select areas. revise scope to include new elevator lobby doors and card/emergency release devices and changes to rcp. | |
| Apr 25, 2025 | Completed final sign-off Jul 2026 | 235 02nd St | Premier Structures Inc | 6th/f:t.i. non structural partitions demo, ceilimg, flooring finishes demo. new non-structural partitions, new furnitures, finishes. revisions to main restrooms, new all gender restroom, new mother's room, new pantry, revision to breaks room, new conference & huddle rooms.Details
6th/f:t.i. non structural partitions demo, ceilimg, flooring finishes demo. new non-structural partitions, new furnitures, finishes. revisions to main restrooms, new all gender restroom, new mother's room, new pantry, revision to breaks room, new conference & huddle rooms. | $195,000 |
| Apr 22, 2025 | In progress issued Apr 2025 | 235 02nd St | Premier Structures Inc | ground floor-ti 202410314101 and 202502261170- deferred mechanical and electrical. ref ti 202410314101Details
ground floor-ti 202410314101 and 202502261170- deferred mechanical and electrical. ref ti 202410314101 | |
| Apr 22, 2025 | Completed final sign-off Oct 2025 | 235 02nd St | Premier Structures Inc | 5th/f: deferred mep & electrical for t.i. 202412237311Details
5th/f: deferred mep & electrical for t.i. 202412237311 | |
| Apr 2, 2025 | Expired or cancelled expired Sep 2026 | 235 02nd St | Premier Structures Inc | change of use from storage/loading dock to general office. total area of change is 3,482 gross sq ft. infill of existing roll-down garage door, non structural demo of loading dock door & new curtainwall infill of same, per planning commission motion 21168. loading dock area will become b-officeDetails
change of use from storage/loading dock to general office. total area of change is 3,482 gross sq ft. infill of existing roll-down garage door, non structural demo of loading dock door & new curtainwall infill of same, per planning commission motion 21168. loading dock area will become b-office | $40,000 |
| Mar 20, 2025 | In progress issued Mar 2025 | 235 02nd St | Premier Structures Inc | 6th fl-minor interior demo of a single story within 6 story building, scope includes non-structural partitions demolition, ceiling demolition, & flooring, finishes demolition. existing egress systems, fire rated wall systems, elevators, structural, sprinklers & existing use to remain. per ab-017,Details
6th fl-minor interior demo of a single story within 6 story building, scope includes non-structural partitions demolition, ceiling demolition, & flooring, finishes demolition. existing egress systems, fire rated wall systems, elevators, structural, sprinklers & existing use to remain. per ab-017, | $75,000 |
| Mar 14, 2025 | Completed final sign-off Apr 2025 | 235 02nd St | Madden Plumbing, Llc | 5th fl - existing fire sprinkler system relocate 2 sprinklers ref pa 202412237311Details
5th fl - existing fire sprinkler system relocate 2 sprinklers ref pa 202412237311 | $1,200 |
| Mar 14, 2025 | Completed final sign-off Jul 2025 | 235 02nd St | Madden Plumbing, Llc | 1st flr - existing fire sprinkler system tenant improvements. add 3 and relocate 3 sprinklers. apn: 202410314101Details
1st flr - existing fire sprinkler system tenant improvements. add 3 and relocate 3 sprinklers. apn: 202410314101 | $3,600 |
| Feb 26, 2025 | In progress issued Mar 2025 | 235 02nd St | Premier Structures Inc | revision to pa #202410314101 to include additional non structural demolition, nonstructural partition. new millwork and new act ceiling tile and lighting fixtures. mep deferred.Details
revision to pa #202410314101 to include additional non structural demolition, nonstructural partition. new millwork and new act ceiling tile and lighting fixtures. mep deferred. | $50,000 |
| Dec 23, 2024 | Completed final sign-off Oct 2025 | 235 02nd St | Premier Structures Inc | 5th floor; revision to pa#: 202407035769. new scope includes revisions main restrooms, all-gender restroom and the parents/mother room. mep deferred.Details
5th floor; revision to pa#: 202407035769. new scope includes revisions main restrooms, all-gender restroom and the parents/mother room. mep deferred. | $249,000 |
| Oct 31, 2024 | In progress issued Nov 2024 | 235 02nd St | Premier Structures Inc | ground floor- minor ti of a 6 story building to includes non structural demo, non structrual partitions and new millwork . (e) lighting, restroom fixtures, egress systems, fire rated wall systems , elevators, structure, and (e) use are to remain. mep deferredDetails
ground floor- minor ti of a 6 story building to includes non structural demo, non structrual partitions and new millwork . (e) lighting, restroom fixtures, egress systems, fire rated wall systems , elevators, structure, and (e) use are to remain. mep deferred | $75,000 |
| Jul 3, 2024 | Completed final sign-off Oct 2025 | 235 02nd St | Premier Structures Inc | 5th floor - office ti for minor improvement of a single story within a 6 story building. project scope includes non structrucal demo, non structural partitions, and new furniture and finishes thorughout. (e) restroom fixtures, egress, systems, fire rated wall system, elevators, structure & existingDetails
5th floor - office ti for minor improvement of a single story within a 6 story building. project scope includes non structrucal demo, non structural partitions, and new furniture and finishes thorughout. (e) restroom fixtures, egress, systems, fire rated wall system, elevators, structure & existing | $200,000 |
| Dec 26, 2023 | Expired or cancelled withdrawn Apr 2025 | 235 02nd St | core and shell improvement in fill 2 garage doors and enlarge 1 garage doorDetails
core and shell improvement in fill 2 garage doors and enlarge 1 garage door | $150,000 | |
| May 31, 2023 | Completed final sign-off Sep 2023 | 235 02nd St | Bcci Construction Company | 4/f: revision to pa# 202209273191 to show secondary egress route from assembly area.Details
4/f: revision to pa# 202209273191 to show secondary egress route from assembly area. | |
| Apr 4, 2023 | Completed final sign-off Apr 2023 | 235 02nd St | Bilcor Inc | 4/f: revision to pa# 2023-0307-3127, remove 9 ceiling mount strobes due to non-full height partitions in the restrooms.Details
4/f: revision to pa# 2023-0307-3127, remove 9 ceiling mount strobes due to non-full height partitions in the restrooms. | $5,940 |
| Mar 29, 2023 | Completed final sign-off Apr 2023 | 235 02nd St | Pribuss Engineering Inc | fire sprinkler as-built for pa# 202303244334, per field inspection condition, remove 6 heads from plans.Details
fire sprinkler as-built for pa# 202303244334, per field inspection condition, remove 6 heads from plans. | |
| Mar 24, 2023 | Completed final sign-off Apr 2023 | 235 02nd St | Pribuss Engineering Inc | fire sprinkler as-built revision to 202302101760, add total of 45 sprinklersDetails
fire sprinkler as-built revision to 202302101760, add total of 45 sprinklers | $22,500 |
| Mar 7, 2023 | Completed final sign-off Apr 2023 | 235 02nd St | Bilcor Inc | 4/f: install 1 wall mount horn-strobes, install 48 ceiling mount strobes. 35 ceiling mount horn strobes,install 3 smoke detectors.4 duct detectors, 4 control relay modules. arch 202209273191 mech, 202211025727Details
4/f: install 1 wall mount horn-strobes, install 48 ceiling mount strobes. 35 ceiling mount horn strobes,install 3 smoke detectors.4 duct detectors, 4 control relay modules. arch 202209273191 mech, 202211025727 | $63,270 |
| Feb 10, 2023 | Completed final sign-off Apr 2023 | 235 02nd St | Pribuss Engineering Inc | fire sprinkler as built revision to pa 2022-1209-7971 add 209 pendents to provide coverage above dropped ceilingsDetails
fire sprinkler as built revision to pa 2022-1209-7971 add 209 pendents to provide coverage above dropped ceilings | |
| Dec 9, 2022 | Completed final sign-off Apr 2023 | 235 02nd St | Pribuss Engineering Inc | modify sprinkler head and adjust branch liner to accomodate new office floor layout on 4th floor. total sprinklers 126Details
modify sprinkler head and adjust branch liner to accomodate new office floor layout on 4th floor. total sprinklers 126 | $64,764 |
| Nov 2, 2022 | Completed final sign-off Sep 2023 | 235 02nd St | Bcci Construction Company | 4th floor-mep to support approved arch for office ti. ref pa 202209273191.Details
4th floor-mep to support approved arch for office ti. ref pa 202209273191. | $198,000 |
| Sep 27, 2022 | Completed final sign-off Dec 2023 | 235 02nd St | Bcci Construction Company | 4/f: t.i., new partitions. finishes, ceilings, millwork. demo permit bpa#202209263134Details
4/f: t.i., new partitions. finishes, ceilings, millwork. demo permit bpa#202209263134 | $1,300,000 |
| Sep 26, 2022 | Completed final sign-off Sep 2023 | 235 02nd St | Bcci Construction Company | 4/f: demo only of interior partitions per ab-017Details
4/f: demo only of interior partitions per ab-017 | $100,000 |
| Nov 10, 2021 | Never finaled issued Nov 2021, no final | 235 02nd St | 6th fl:enclosure of an existing floor between floors 6 & 5.steel stud & gypsum board walls with transom glazing will be constructed on four sides at floor 6.no structural demolition or construction will occur.Details
6th fl:enclosure of an existing floor between floors 6 & 5.steel stud & gypsum board walls with transom glazing will be constructed on four sides at floor 6.no structural demolition or construction will occur. | $25,000 | |
| Mar 3, 2020 | Expired or cancelled cancelled Jan 2026 | 235 02nd St | the work is in responce to the accessible bldg entrance program addition of auto door operator push button/bar, restriping accessible parking spaces, adjusting door operating force.Details
the work is in responce to the accessible bldg entrance program addition of auto door operator push button/bar, restriping accessible parking spaces, adjusting door operating force. | $6,000 | |
| Mar 27, 2019 | Never finaled issued May 2019, no final | 235 02nd St | Swinerton Builders | maintenance permit to waterproof (e) fountain and replace (e) finishes wtih bronze tiles, no expansion of (e) fountain dimensions mep under separate permitDetails
maintenance permit to waterproof (e) fountain and replace (e) finishes wtih bronze tiles, no expansion of (e) fountain dimensions mep under separate permit | $100,000 |
| Nov 2, 2018 | Completed final sign-off Nov 2018 | 235 02nd St | Johnson Controls Security Solutions Llc | fire alarm tenant improvement for basement- construction plan 201809186437, mechanical- 2018-0820-7739. add 1 duct smoke detector, 1 area smoke detector, 2 relays, 14 strobes, 9 horn strobes, 1 power supply and new batteries. n/a for maher.Details
fire alarm tenant improvement for basement- construction plan 201809186437, mechanical- 2018-0820-7739. add 1 duct smoke detector, 1 area smoke detector, 2 relays, 14 strobes, 9 horn strobes, 1 power supply and new batteries. n/a for maher. | $30,000 |
| Oct 11, 2018 | Completed final sign-off Mar 2020 | 235 02nd St | Novo Construction Inc | revision to pa 201806071269 to revise door schedule and doors at private offices and conference rooms.Details
revision to pa 201806071269 to revise door schedule and doors at private offices and conference rooms. | |
| Oct 3, 2018 | Completed final sign-off Feb 2022 | 235 02nd St | Ayoob & Peery Plumbing Co Inc | basement. sprinklers, add 17, relocate 18 and plug 2 to conform w/ new wall / ceiling layout of tenant improvement. ref pa 201808207739, job # 18-724. maher n/aDetails
basement. sprinklers, add 17, relocate 18 and plug 2 to conform w/ new wall / ceiling layout of tenant improvement. ref pa 201808207739, job # 18-724. maher n/a | $12,975 |
| Oct 1, 2018 | Completed final sign-off Mar 2020 | 235 02nd St | Novo Construction Inc | basement - structural work for ti ref 201806071269Details
basement - structural work for ti ref 201806071269 | $5,000 |
| Aug 20, 2018 | Never finaled issued Aug 2018, no final | 235 02nd St | Novo Construction Inc | mep for tenant improvement at the basement ref pa# 201806071269Details
mep for tenant improvement at the basement ref pa# 201806071269 | $40,000 |
| Jun 7, 2018 | Completed final sign-off Mar 2020 | 235 02nd St | Novo Construction Inc | ti at the basement to include new interior partitions, doors finishes. mep, life safety & fire sprinkler under separate permitDetails
ti at the basement to include new interior partitions, doors finishes. mep, life safety & fire sprinkler under separate permit | $450,000 |
| Aug 2, 2017 | Completed final sign-off Oct 2018 | 235 02nd St | Swinerton Builders | exterior work only limited to painting, installation of eifs based thin-brick system, iefs build base, belt course and cornice, associated demolition- structural metal stud framing deferred. n/a for maher.Details
exterior work only limited to painting, installation of eifs based thin-brick system, iefs build base, belt course and cornice, associated demolition- structural metal stud framing deferred. n/a for maher. | $900,000 |
| Feb 16, 2017 | Completed final sign-off Mar 2017 | 235 02nd St | Novo Construction Inc | 4th & 6th flr: arch revision to 201608084427 & 201608084429 - change to stair door; maher naDetails
4th & 6th flr: arch revision to 201608084427 & 201608084429 - change to stair door; maher na | |
| Dec 8, 2016 | Never finaled issued Dec 2016, no final | 235 02nd St | Anderson, Rowe & Buckley, Inc. | flrs 4&6: existing fire sprinkler system-ti 201608084429 & 201608084427: 4th flr, 3 added pendants,25 relocate upright sprinklers and 5 added, 29 relocated; 6th flr: 23 relocated uprights,7added,48 relocated pendants 3 added pendants; maher n/aDetails
flrs 4&6: existing fire sprinkler system-ti 201608084429 & 201608084427: 4th flr, 3 added pendants,25 relocate upright sprinklers and 5 added, 29 relocated; 6th flr: 23 relocated uprights,7added,48 relocated pendants 3 added pendants; maher n/a | $25,000 |
| Nov 30, 2016 | Completed final sign-off Feb 2024 | 235 02nd St | H C I Systems Inc | 6th floor - hci is installing in 6th floor audio visual notification appliances to meet per nfpa 72 requirements (ref pa 2016-0808-4427); strobes 23, horns 7.Details
6th floor - hci is installing in 6th floor audio visual notification appliances to meet per nfpa 72 requirements (ref pa 2016-0808-4427); strobes 23, horns 7. | $4,000 |
| Nov 30, 2016 | Never finaled issued Dec 2016, no final | 235 02nd St | H C I Systems Inc | 4th floor - hci installing booster power supply to the 4th floor and audio visual notification appliances to the 4th floor to meet per nfpa 72 requirements (ref pa 2016-0808-4429); n/a maher; 18 strobes, 12 horn strobesDetails
4th floor - hci installing booster power supply to the 4th floor and audio visual notification appliances to the 4th floor to meet per nfpa 72 requirements (ref pa 2016-0808-4429); n/a maher; 18 strobes, 12 horn strobes | $4,000 |
| Aug 8, 2016 | Completed final sign-off Mar 2017 | 235 02nd St | Novo Construction Inc | 6th floor: scope of work to include demo of (e) ti , demo to include walls, doors, plumbing, ceiling, lighting, millwork and interior finsihes. new ti to include new partition walls, doors, finishes and ceiling assemblies (e) mechanical, av and fire sprinkler layouts to be reconfigured maher naDetails
6th floor: scope of work to include demo of (e) ti , demo to include walls, doors, plumbing, ceiling, lighting, millwork and interior finsihes. new ti to include new partition walls, doors, finishes and ceiling assemblies (e) mechanical, av and fire sprinkler layouts to be reconfigured maher na | $4,000,000 |
| Aug 8, 2016 | Completed final sign-off Sep 2017 | 235 02nd St | Novo Construction Inc | 4th floor: scope of work to include demo of (e) ti , demo to include walls, doors, plumbing, ceiling, lighting, millwork and interior finsihes. new ti to include new partition walls, doors, finishes and ceiling assemblies (e) mechanical, av and fire sprinkler layouts to be reconfigured maher naDetails
4th floor: scope of work to include demo of (e) ti , demo to include walls, doors, plumbing, ceiling, lighting, millwork and interior finsihes. new ti to include new partition walls, doors, finishes and ceiling assemblies (e) mechanical, av and fire sprinkler layouts to be reconfigured maher na | $4,000,000 |
| Jul 20, 2016 | Never finaled issued Jul 2016, no final | 235 02nd St | Johnson Controls Security Solutions Llc | 3rd floor: as built drawings fire alarm. ref pa 2016 0413 4684 maher naDetails
3rd floor: as built drawings fire alarm. ref pa 2016 0413 4684 maher na | |
| Jul 6, 2016 | Never finaled issued Jul 2016, no final | 235 02nd St | Johnson Controls Security Solutions Llc | 1st floor - adding 1 strobe and move 1 horn/strobe to cover t.i. work in office space - fire alarm work. ref #201604154863.Details
1st floor - adding 1 strobe and move 1 horn/strobe to cover t.i. work in office space - fire alarm work. ref #201604154863. | $5,000 |
| Jun 3, 2016 | Completed final sign-off Aug 2016 | 235 02nd St | True North Signs & Graphic Services | install ground sign - not illum. maher naDetails
install ground sign - not illum. maher na | $6,155 |
| Jun 3, 2016 | Completed final sign-off Aug 2016 | 235 02nd St | True North Signs & Graphic Services | install wall sign - not illum. maher naDetails
install wall sign - not illum. maher na | $2,160 |
| Apr 15, 2016 | Completed final sign-off Jul 2016 | 235 02nd St | Northern Sun Associates | 1st flr: ti from (e) office to new food service. new food perp partition wall, case work, interior lighting, plumbing and electrical. maher naDetails
1st flr: ti from (e) office to new food service. new food perp partition wall, case work, interior lighting, plumbing and electrical. maher na | $109,320 |
| Apr 13, 2016 | Completed final sign-off Oct 2016 | 235 02nd St | Johnson Controls Security Solutions Llc | 3rd flr: additional notification devices must be added to the system to cover the new wall layout and room usage; t.i. ref. 201601136929; maher n/a, install 88 new notification applianceDetails
3rd flr: additional notification devices must be added to the system to cover the new wall layout and room usage; t.i. ref. 201601136929; maher n/a, install 88 new notification appliance | $5,000 |
| Apr 13, 2016 | Completed final sign-off Apr 2016 | 235 02nd St | Johnson Controls Security Solutions Llc | 2nd flr: additional notification devices must be added to the system to cover the new wall layout and room usage, ref. t.i. 2015102160733; maher n/a. add (2) power supplies, 69 notification devices & (2) cetectors, u batteries.Details
2nd flr: additional notification devices must be added to the system to cover the new wall layout and room usage, ref. t.i. 2015102160733; maher n/a. add (2) power supplies, 69 notification devices & (2) cetectors, u batteries. | $5,000 |
| Apr 6, 2016 | Never finaled issued Apr 2016, no final | 235 02nd St | Young Electric Co, Dome Construction Corp | electrical work for ti on the 2nd floor, new light, new receptacles outlets. ref 201510260733Details
electrical work for ti on the 2nd floor, new light, new receptacles outlets. ref 201510260733 | $70,000 |
| Apr 6, 2016 | Never finaled issued Apr 2016, no final | 235 02nd St | Young Electric Co, Dome Construction Corp | 3/f: electrical work for ti on the 3rd floor, new light, control system, new receptacles outlets. ref 2016-0113-6939. compliance with maher ordinance no 155-1 not required.Details
3/f: electrical work for ti on the 3rd floor, new light, control system, new receptacles outlets. ref 2016-0113-6939. compliance with maher ordinance no 155-1 not required. | $70,000 |
| Apr 1, 2016 | Never finaled issued Apr 2016, no final | 235 02nd St | Acco Engineered Systems Inc. Dba Acco En | 3rd floor: demo all lowside duct, vav boxes, grilles, duct mains & hw piping. install new duct mains, vav boxes, water source, heat pumps and lowside duct on 3rd flr . install new hw condesner water & condensate piping. install 2 new fsd. ref pa 2016 0113 6939 maher naDetails
3rd floor: demo all lowside duct, vav boxes, grilles, duct mains & hw piping. install new duct mains, vav boxes, water source, heat pumps and lowside duct on 3rd flr . install new hw condesner water & condensate piping. install 2 new fsd. ref pa 2016 0113 6939 maher na | $195,000 |
| Mar 3, 2016 | Expired or cancelled cancelled Jan 2026 | 235 02nd St | Dome Construction Corp | demo all lowside duct, vav boxes, grilles, duct mains & hw piping on 3rd flr as shown on demo plans. install new duct main vav baxes water source heat pumps and low side duct on 3rd flr. install new hw, condenser water piping on 3rd flr.Details
demo all lowside duct, vav boxes, grilles, duct mains & hw piping on 3rd flr as shown on demo plans. install new duct main vav baxes water source heat pumps and low side duct on 3rd flr. install new hw, condenser water piping on 3rd flr. | $195,000 |
| Feb 17, 2016 | Never finaled issued Feb 2016, no final | 235 02nd St | Golden Gate Fire Protection Inc | 2nd & 3rd floors: fire sprinklers - relocate 376 pendents on 2nd floor, t.i. app#2015-10-26-0733. relocate 401 sprinklers on 3rd, t.i app# 2016-01-13-6939. maher naDetails
2nd & 3rd floors: fire sprinklers - relocate 376 pendents on 2nd floor, t.i. app#2015-10-26-0733. relocate 401 sprinklers on 3rd, t.i app# 2016-01-13-6939. maher na | $155,400 |
| Jan 13, 2016 | Completed final sign-off Nov 2016 | 235 02nd St | Dome Construction Corp | ti to level 3 of an (e) 6 floor midrise building. interior partions, doors, finishes, lighting, ceilings & existing restroom upgrades. architectural scope included only. mep to be submitted as deferred submittals. demotition under separate permit. maher naDetails
ti to level 3 of an (e) 6 floor midrise building. interior partions, doors, finishes, lighting, ceilings & existing restroom upgrades. architectural scope included only. mep to be submitted as deferred submittals. demotition under separate permit. maher na | $5,250,000 |
| Jan 7, 2016 | Never finaled issued Jan 2016, no final | 235 02nd St | Acco Engineered Systems Inc. Dba Acco En | demo all low side duct, vav boxes, and diffusers on 2nd floor. demo duct mains & hot water piping as shown on demo plan. install new duct, vavs, water source heat pumps & low side ductwork on 2nd floor. install new hot water, condensor water & condensate drain piping on 2nd floor. maher naDetails
demo all low side duct, vav boxes, and diffusers on 2nd floor. demo duct mains & hot water piping as shown on demo plan. install new duct, vavs, water source heat pumps & low side ductwork on 2nd floor. install new hot water, condensor water & condensate drain piping on 2nd floor. maher na | $850,462 |
| Jan 5, 2016 | Never finaled issued Jan 2016, no final | 235 02nd St | Dome Construction Corp | demo of partitions on level 3 per a1.03 a and b. tenant improvement under sep permit. n/a for maherDetails
demo of partitions on level 3 per a1.03 a and b. tenant improvement under sep permit. n/a for maher | $38,500 |
| Dec 9, 2015 | Never finaled issued Dec 2015, no final | 235 02nd St | Red Hawk Fire & Security Ca Llc | 2nd floor: add 35 horn/strobes and 37 strobes. ref app#201510260733 not issued yet. n/a maher ordinanceDetails
2nd floor: add 35 horn/strobes and 37 strobes. ref app#201510260733 not issued yet. n/a maher ordinance | $12,000 |
| Nov 10, 2015 | Never finaled issued Nov 2015, no final | 235 02nd St | Dome Construction Corp | level 2 - demo of interior partitions per ab-017. tenant improvement under separate permit.Details
level 2 - demo of interior partitions per ab-017. tenant improvement under separate permit. | $150,000 |
| Oct 26, 2015 | Completed final sign-off Nov 2016 | 235 02nd St | Dome Construction Corp | tenant improvement to level 2 of existing 6th fl, mid rise building, scope includes new interior partitions, doors, finishes, lighting, ceilings. architectural only, mep deferred maher not reqDetails
tenant improvement to level 2 of existing 6th fl, mid rise building, scope includes new interior partitions, doors, finishes, lighting, ceilings. architectural only, mep deferred maher not req | $4,700,500 |
| Oct 13, 2015 | Never finaled issued Oct 2015, no final | 235 02nd St | Johnson Controls Security Solutions Llc | ground level: adding 1 annunicator to (e) fire system, removing sub panel to dial. adding modem card to main facu as main communicator. maher naDetails
ground level: adding 1 annunicator to (e) fire system, removing sub panel to dial. adding modem card to main facu as main communicator. maher na | $3,500 |
| Oct 6, 2015 | Completed final sign-off Jan 2016 | 235 02nd St | Ayoob & Peery Plumbing Co Inc | add & relocate fire sprinklers per ti 1st floor - (1 add) (14 relocate), 5th floor (11 add) (22 relocate) ref pa 2015-0623-9632; 5th floor 2015-0629-0205Details
add & relocate fire sprinklers per ti 1st floor - (1 add) (14 relocate), 5th floor (11 add) (22 relocate) ref pa 2015-0623-9632; 5th floor 2015-0629-0205 | $10,272 |
| Sep 22, 2015 | Completed final sign-off Jul 2017 | 235 02nd St | Johnson Controls Security Solutions Llc | 1st & 5th floor fire alarm - add (29)-16 (n) strobes, 13 (n) horn/strobes, relocate (11) notification devices, add 2 power supply, 2 (n) modules, t.i. #2015-0623-9632 for 1st floor & t.i. #2015-0629-0205 for 5th floor. n/a maher ordinanceDetails
1st & 5th floor fire alarm - add (29)-16 (n) strobes, 13 (n) horn/strobes, relocate (11) notification devices, add 2 power supply, 2 (n) modules, t.i. #2015-0623-9632 for 1st floor & t.i. #2015-0629-0205 for 5th floor. n/a maher ordinance | $45,000 |
| Sep 22, 2015 | Completed final sign-off Jun 2016 | 235 02nd St | Novo Construction Inc | 1st floor: structural work for t.i. ref app#201506239632. n/a for maherDetails
1st floor: structural work for t.i. ref app#201506239632. n/a for maher | |
| Jun 29, 2015 | Completed final sign-off Jun 2016 | 235 02nd St | Novo Construction Inc | 5th floor: t.i. include partial demolition include partitions, ceiling and mep. new t.i. include new furnish and fixtures, selective build back of partitions, ceilings, millwork, doors. (e) mech, a/v. and fire sprinkler layout to be reconfigured per plan. maher n/a.Details
5th floor: t.i. include partial demolition include partitions, ceiling and mep. new t.i. include new furnish and fixtures, selective build back of partitions, ceilings, millwork, doors. (e) mech, a/v. and fire sprinkler layout to be reconfigured per plan. maher n/a. | $2,000,000 |
| Jun 23, 2015 | Completed final sign-off Jun 2016 | 235 02nd St | Novo Construction Inc | 1st flr: partial demolition(interior partitions, clg,mep). new t.i. includes all new ff&e and selective build back of partitions, ceilings, millwork, doors. extg mech a/v and fire sprinkler layouts to be reconfigured per new layout. see scope of work on sheet a011. n/a for maher.Details
1st flr: partial demolition(interior partitions, clg,mep). new t.i. includes all new ff&e and selective build back of partitions, ceilings, millwork, doors. extg mech a/v and fire sprinkler layouts to be reconfigured per new layout. see scope of work on sheet a011. n/a for maher. | $1,200,000 |
| May 29, 2014 | Never finaled issued May 2014, no final | 235 02nd St | street spaceDetails
street space | ||
| Jan 24, 2014 | Completed final sign-off Sep 2014 | 235 02nd St | Ayoob & Peery Plumbing Co Inc | 2nd floor: remove extg per-action valve and convert to wet system, counter to wet supply main.n/a for maher ordinance # 155-13Details
2nd floor: remove extg per-action valve and convert to wet system, counter to wet supply main.n/a for maher ordinance # 155-13 | $1,200 |
| Jan 22, 2014 | Expired or cancelled cancelled Feb 2020 | 235 02nd St | Intelligent Technologies & Services Inc | demo 2nd floor suppression system from server room and relocate fm200 control panel into 3rd floor data room. n/a for maher ordinance no. 155-13Details
demo 2nd floor suppression system from server room and relocate fm200 control panel into 3rd floor data room. n/a for maher ordinance no. 155-13 | $9,284 |
| May 31, 2012 | Completed final sign-off Aug 2012 | 235 02nd St | Novo Construction Inc | revision to 201204188614, revision to kitchenette on 1st floor. revision to booths, booths to be built inDetails
revision to 201204188614, revision to kitchenette on 1st floor. revision to booths, booths to be built in | $30,000 |
| Apr 18, 2012 | Completed final sign-off Jul 2012 | 235 02nd St | Novo Construction Inc | new employee lounge with kitchenette on first floor. new doors to basement office. demolish private offices in bsmt.Details
new employee lounge with kitchenette on first floor. new doors to basement office. demolish private offices in bsmt. | $300,000 |