- 3 permits filed
35 permits since 2000: 22 completed, 8 never finaled, 5 expired or cancelled.
Of the 8 never-finaled permits, 2 are 3 to 5 years old, 3 are 5 to 10 years old, 3 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Feb 25, 2026 | Completed final sign-off Mar 2026 | 220 Golden Gate Av | revision to 202410163026: install new bars to security gate approved under 202410163026. repair due to on goinng security issue on site.Details
revision to 202410163026: install new bars to security gate approved under 202410163026. repair due to on goinng security issue on site. | $5,000 |
| Sep 24, 2025 | Completed final sign-off Jan 2026 | 330 Ellis St | reroofing patch job. no torch down remove existing terra cotta tile and replace in same place after re-roofing. using same tile and replacing where needed.Details
reroofing patch job. no torch down remove existing terra cotta tile and replace in same place after re-roofing. using same tile and replacing where needed. | $80,000 |
| Oct 16, 2024 | Completed final sign-off Mar 2026 | 220 Golden Gate Av | install new security gate at leavenworth street office entrance.Details
install new security gate at leavenworth street office entrance. | $25,000 |
| May 11, 2023 | Completed final sign-off Feb 2024 | 100 Masonic Av | within preschool classroom- removing extg step in the slab to even out the floor for ada accessibility pour of 3" of concrete on the extg slab to level with adjacent corridor for ada pour new partial concrete slab where old step is removed. revision ot 202205315241Details
within preschool classroom- removing extg step in the slab to even out the floor for ada accessibility pour of 3" of concrete on the extg slab to level with adjacent corridor for ada pour new partial concrete slab where old step is removed. revision ot 202205315241 | $80,000 |
| Aug 12, 2022 | Completed final sign-off Oct 2022 | 3796 Sacramento St | recommencement and completion of work approved under pa# 201803264590.Details
recommencement and completion of work approved under pa# 201803264590. | $8,000 |
| Aug 12, 2022 | Completed final sign-off Oct 2022 | 3794 Sacramento St | recommencement and completion of work approved under pa# 201803264589.Details
recommencement and completion of work approved under pa# 201803264589. | $20,000 |
| Jul 12, 2022 | Never finaled issued Jul 2022, no final | 1802 09th Av | like for like dry rot at stairs repairs. to comply w/ nov 202292135.Details
like for like dry rot at stairs repairs. to comply w/ nov 202292135. | $5,000 |
| May 31, 2022 | Completed final sign-off Feb 2024 | 100 Masonic Av | prop h: minor interior remodel only, and includes replacing existing finishes with new standard finishes. no structural change or modification is proposed.Details
prop h: minor interior remodel only, and includes replacing existing finishes with new standard finishes. no structural change or modification is proposed. | $170,000 |
| Dec 20, 2021 | Expired or cancelled withdrawn Jan 2023 | 1 Burnett Ave North Av | in kind repair of framing at common area stair 2 and 3 and less than 50% repair in kind of stairs. per murphy burr curry structural assessment dated 07/20/2020.Details
in kind repair of framing at common area stair 2 and 3 and less than 50% repair in kind of stairs. per murphy burr curry structural assessment dated 07/20/2020. | $801,833 |
| Nov 18, 2021 | Completed final sign-off Jul 2022 | 398 Haight St | dry rot repair replace of rotted header beam @ bldg entrance and post supports as well. non structural, repair existing cornice and pilaster @ entrance. no work at exterior except patching anchor holes. "like-for-like replacement"Details
dry rot repair replace of rotted header beam @ bldg entrance and post supports as well. non structural, repair existing cornice and pilaster @ entrance. no work at exterior except patching anchor holes. "like-for-like replacement" | $22,000 |
| Oct 5, 2021 | Never finaled issued Oct 2021, no final | 3790 Sacramento St | new bathroom and closetDetails
new bathroom and closet | $10,000 |
| Jun 4, 2021 | Completed final sign-off Oct 2021 | 1601 Howard St | to comply with nov #202060611 - tighten existing beam to post connection as needed. replace (e) sill plate, replace curb. repair in kindDetails
to comply with nov #202060611 - tighten existing beam to post connection as needed. replace (e) sill plate, replace curb. repair in kind | $70,000 |
| Jan 5, 2021 | Completed final sign-off Jan 2021 | 3043 Clay St | administrative permit to correct the incorrect lot # in current application # 202012151009. lot 70.Details
administrative permit to correct the incorrect lot # in current application # 202012151009. lot 70. | |
| Dec 29, 2020 | Completed final sign-off Jan 2021 | 3043 Clay St | administration permit to correct the incorrect lot # on pa 2020 1215 1009. the correct lot # is 071Details
administration permit to correct the incorrect lot # on pa 2020 1215 1009. the correct lot # is 071 | |
| Dec 15, 2020 | Completed final sign-off Jan 2021 | 3043 Clay St | rev to pa# 202012030168; discovery of additional dryrot increasing area of work at rer siding to approx 800 sqft and approx 150 of parapet all work to be in kind at rear (no street front)Details
rev to pa# 202012030168; discovery of additional dryrot increasing area of work at rer siding to approx 800 sqft and approx 150 of parapet all work to be in kind at rear (no street front) | $97,000 |
| Dec 3, 2020 | Completed final sign-off Jan 2021 | 3043 Clay St | misc dryrot repair at rear of building (wall approx 150 sqft) including less than 50% of stairs repair in kindDetails
misc dryrot repair at rear of building (wall approx 150 sqft) including less than 50% of stairs repair in kind | $18,000 |
| Feb 13, 2020 | Completed final sign-off Jan 2021 | 7 Seymour St | reroofingDetails
reroofing | $33,000 |
| Dec 3, 2018 | Never finaled issued Dec 2018, no final | 333 Bush St | replace failed sealant at vertical panels, install new concrete pavers, fix leakage at sliding doors.Details
replace failed sealant at vertical panels, install new concrete pavers, fix leakage at sliding doors. | $30,000 |
| Aug 7, 2018 | Completed final sign-off Aug 2018 | 2330 Larkin St | to comply complaint#201717413. spalling concrete & waterproofing item#5. n/a for maher.Details
to comply complaint#201717413. spalling concrete & waterproofing item#5. n/a for maher. | $25,000 |
| Jun 7, 2018 | Never finaled issued Jun 2018, no final | 48 Stockton St | elevator door infill at sidewalkDetails
elevator door infill at sidewalk | $32,000 |
| Mar 23, 2018 | Completed final sign-off Feb 2019 | 154 South Van Ness Av | voluntary removal of abandonded billboard frame. remove all steel members below roof parapet wall. sign height 24 ft. maher naDetails
voluntary removal of abandonded billboard frame. remove all steel members below roof parapet wall. sign height 24 ft. maher na | $2,750 |
| Nov 20, 2017 | Never finaled issued Nov 2017, no final | 44 Mcallister St | re-roofingDetails
re-roofing | $26,000 |
| Oct 4, 2017 | Completed final sign-off Nov 2017 | 34 Turk St | install fire rated door (replace) in first floor hallway supply closet.Details
install fire rated door (replace) in first floor hallway supply closet. | $3,000 |
| Sep 28, 2016 | Completed final sign-off Jun 2017 | 25 Mason St | repair spalled concrete and falling bricks to match existing. visable to street to comply complaint #201630751Details
repair spalled concrete and falling bricks to match existing. visable to street to comply complaint #201630751 | $68,000 |
| Dec 26, 2014 | Completed final sign-off Feb 2015 | 55 Mason St | replace any damaged/deteriorated bricks repoint mortar in-kind. preivate additional securing of bricks w/stainless steel, epoxy anchors horizontally to hold mesh for stucco. approx. 60 linear feet total w/waterproofing. compliance with maher ordinance 155-13 not required.Details
replace any damaged/deteriorated bricks repoint mortar in-kind. preivate additional securing of bricks w/stainless steel, epoxy anchors horizontally to hold mesh for stucco. approx. 60 linear feet total w/waterproofing. compliance with maher ordinance 155-13 not required. | $30,000 |
| Oct 14, 2014 | Never finaled issued Oct 2014, no final | 55 Mason St | remove & install mortar @ south & east side of exterior bldg. approx 100 lf/ 5 stories. high.Details
remove & install mortar @ south & east side of exterior bldg. approx 100 lf/ 5 stories. high. | $220 |
| Jul 25, 2014 | Completed final sign-off Aug 2014 | 55 Cyril Magnin St | reroofingDetails
reroofing | $30,000 |
| Sep 20, 2013 | Completed final sign-off Aug 2014 | 278 Post St | relocate (2) doorways farther back in (e) alcove such that leaves do not swing out over public right of way, fire sprinkler under separate permit, encroachment permit being processed by dpw (same dwgs). ** maher: compliance with ordinance no# 155-13 not required **Details
relocate (2) doorways farther back in (e) alcove such that leaves do not swing out over public right of way, fire sprinkler under separate permit, encroachment permit being processed by dpw (same dwgs). ** maher: compliance with ordinance no# 155-13 not required ** | $40,000 |
| Nov 21, 2012 | Completed final sign-off Feb 2013 | 55 Mason St | removal of (e) concrete about 4" repair/replace waterproofing/replace topping concrete ,embassador deck level per icc esr 2785 w/plycoat products or equivalent deck @ 2nd level on west side.Details
removal of (e) concrete about 4" repair/replace waterproofing/replace topping concrete ,embassador deck level per icc esr 2785 w/plycoat products or equivalent deck @ 2nd level on west side. | $45,000 |
| Apr 14, 2008 | Never finaled issued Apr 2008, no final | 685 Market St | repair cracked roof slab and add reinforcing steel beams. patch roof membraineDetails
repair cracked roof slab and add reinforcing steel beams. patch roof membraine | $30,000 |
| Sep 28, 2007 | Expired or cancelled expired Nov 2013 | 685 Market St | repair brick wall cracking and rusted beam at interior courtyard.Details
repair brick wall cracking and rusted beam at interior courtyard. | $123,000 |
| Aug 18, 2005 | Expired or cancelled expired Jun 2008 | 3780 Sacramento St | reroofingDetails
reroofing | $9,700 |
| Aug 18, 2005 | Never finaled issued Aug 2005, no final | 2200 Hyde St | reroofingDetails
reroofing | $4,800 |
| Jun 1, 2001 | Expired or cancelled expired Dec 2001 | 114 Sansome St | reroofingDetails
reroofing | $14,000 |
| Nov 10, 2000 | Expired or cancelled expired May 2001 | 211 Sutter St | install waterproof to sidewalkDetails
install waterproof to sidewalk | $22,000 |