Permit GraphShortlistSan Francisco building permits since 2000

William Walters

License
C20271
Look the license up with the state
Listed as
architect, authorized agent-others, designer, engineer, pmt consultant/expediter
Firm
Walters Architecture
Based in
San Francisco
On San Francisco permits
Jul 2000 to Jul 2026

234 permits since 2000 (architect on 217 permits, authorized agent-others on 12 permits, engineer on 5 permits, designer on 2 permits, pmt consultant/expediter on 1 permit): 147 completed, 1 in progress, 27 never finaled, 59 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

Showing the 100 most recent of 234.

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jul 16, 2026Expired or cancelled
cancelled Sep 2026
1038 Capitol AvCarter's Devco Llcrev 202509296283: additiion of full bath on g/f. add new lighting, powerl and plumbing. replce (e) footing and partition between new bath and flex room on g/f due to inadequate foundation and framing dry rot discovery.
Details
Permit
202607165151
Status
cancelled
Filed
Jul 16, 2026
Permit issued
Jul 21, 2026
Declared cost
$22,500
Address
1038 Capitol Av

rev 202509296283: additiion of full bath on g/f. add new lighting, powerl and plumbing. replce (e) footing and partition between new bath and flex room on g/f due to inadequate foundation and framing dry rot discovery.

Open the permit page

$22,500
Aug 8, 2025Completed
final sign-off Jun 2026
1527 Sanchez StEdri Construction Inc *See Notes*replacement in kind of (e) wood framed egress staircase with new conc footings & the addition of a 1-hour firewall at side property line location.
Details
Permit
202507150810
Status
complete
Filed
Aug 8, 2025
Permit issued
Oct 28, 2025
Final sign-off
Jun 11, 2026
Declared cost
$60,000
Address
1527 Sanchez St

replacement in kind of (e) wood framed egress staircase with new conc footings & the addition of a 1-hour firewall at side property line location.

Open the permit page

$60,000
Feb 3, 2025In progress
issued Jul 2025
3723 Anza StGolden Gate Construction Llcrepair and replace existing exterior deck and staircase in the rear. demo existing stair and landing and replace with new stair and landing shown on plans.
Details
Permit
202502039545
Status
issued
Filed
Feb 3, 2025
Permit issued
Jul 16, 2025
Declared cost
$1,000
Address
3723 Anza St

repair and replace existing exterior deck and staircase in the rear. demo existing stair and landing and replace with new stair and landing shown on plans.

Open the permit page

$1,000
Aug 22, 2023Completed
final sign-off May 2025
1905 Union Stto comply with nov 202286294 & 202286803. existing roof deck expansion. comply with 2022-000732enf (newly construction deck exceeds that allowed under pa 202201206346 & 201404163371).
Details
Permit
202308224942
Status
complete
Filed
Aug 22, 2023
Permit issued
Oct 30, 2024
Final sign-off
May 12, 2025
Declared cost
$12,000
Address
1905 Union St

to comply with nov 202286294 & 202286803. existing roof deck expansion. comply with 2022-000732enf (newly construction deck exceeds that allowed under pa 202201206346 & 201404163371).

Open the permit page

$12,000
Jan 6, 2023Never finaled
filed Jan 2023, never issued
704 Geary StApex America Gc Increvision of extg bldg pa#201911278358. remove portion of the front door to make more space and install double glass door.
Details
Permit
202301069747
Status
filed
Filed
Jan 6, 2023
Declared cost
$3,000
Address
704 Geary St

revision of extg bldg pa#201911278358. remove portion of the front door to make more space and install double glass door.

Open the permit page

$3,000
Nov 27, 2019Expired or cancelled
expired Jan 2026
704 Geary StApex America Gc Inctenant improvement 327 sq ft. accessory use for 700 geary cafe. service counter w/ kitchen equip for juices/coffee. (n) sheetrock all demising walls & ceiling. (n) soffit/equip platform. plubming & elect work. (n) opening to 700 geary cafe.
Details
Permit
201911278358
Status
expired
Filed
Nov 27, 2019
Permit issued
Mar 23, 2022
Declared cost
$40,000
Address
704 Geary St

tenant improvement 327 sq ft. accessory use for 700 geary cafe. service counter w/ kitchen equip for juices/coffee. (n) sheetrock all demising walls & ceiling. (n) soffit/equip platform. plubming & elect work. (n) opening to 700 geary cafe.

Open the permit page

$40,000
May 23, 2019Never finaled
issued Jun 2019, no final
233 Sansome StRudolph Commercial Interiors Inc, Rciti-demo (e) offices & conf rm. construct new offices, install new ceiling and light fixtures, modify (e) hvac as reqd, upgrade (e) 2nd flr mens toilet to all gender. install sprinkler/fire/life safety under sep permit
Details
Permit
201905231500
Status
issued
Filed
May 23, 2019
Permit issued
Jun 3, 2019
Declared cost
$145,000
Address
233 Sansome St

ti-demo (e) offices & conf rm. construct new offices, install new ceiling and light fixtures, modify (e) hvac as reqd, upgrade (e) 2nd flr mens toilet to all gender. install sprinkler/fire/life safety under sep permit

Open the permit page

$145,000
Jan 24, 2019Completed
final sign-off Nov 2019
550 Battery StC B 2 Builders Incorporatedmaintenance repair - replace (e)trash chute with new discharge door and chute from 1st thru 22nd fls. remove (e) non-structural partitions as reqiured, construct new partition, replace in kind. maher n/a.
Details
Permit
201901241120
Status
complete
Filed
Jan 24, 2019
Permit issued
Jan 29, 2019
Final sign-off
Nov 13, 2019
Declared cost
$65,000
Address
550 Battery St

maintenance repair - replace (e)trash chute with new discharge door and chute from 1st thru 22nd fls. remove (e) non-structural partitions as reqiured, construct new partition, replace in kind. maher n/a.

Open the permit page

$65,000
Sep 13, 2018Completed
final sign-off Dec 2018
233 Sansome StRudolph Commercial Interiors Inc, Rci3/f: suite 300: t.i. interior work only. demo of (e) non-structural partitions. construct (n) partitions as indicated; relocate (e) light fixtures, convert (e) womens toilet to accessible all gender toilet room. separate to let entrance from stairwell. sprinkler & l/s under sep permit. maher n/a.
Details
Permit
201809139931
Status
complete
Filed
Sep 13, 2018
Permit issued
Oct 4, 2018
Final sign-off
Dec 5, 2018
Declared cost
$82,000
Address
233 Sansome St

3/f: suite 300: t.i. interior work only. demo of (e) non-structural partitions. construct (n) partitions as indicated; relocate (e) light fixtures, convert (e) womens toilet to accessible all gender toilet room. separate to let entrance from stairwell. sprinkler & l/s under sep permit. maher n/a.

Open the permit page

$82,000
Aug 13, 2018Completed
final sign-off Feb 2019
95 Jefferson StP M Constructiontenant improvement. new partition for stockroom, new lighting, suspended ceiling. interior paint throught. no plumbing work.**maher n/a**
Details
Permit
201808137178
Status
complete
Filed
Aug 13, 2018
Permit issued
Sep 24, 2018
Final sign-off
Feb 27, 2019
Declared cost
$50,000
Address
95 Jefferson St

tenant improvement. new partition for stockroom, new lighting, suspended ceiling. interior paint throught. no plumbing work.**maher n/a**

Open the permit page

$50,000
Jul 30, 2018Completed
final sign-off May 2019
2350 Market StIvan Alberto Rivera Rivasreconfiguration of building exit stairways, new stairway to exist mezzanine, reconsturction of street facade, new roof deck
Details
Permit
201807305827
Status
complete
Filed
Jul 30, 2018
Permit issued
Jul 31, 2018
Final sign-off
May 15, 2019
Declared cost
$30,000
Address
2350 Market St

reconfiguration of building exit stairways, new stairway to exist mezzanine, reconsturction of street facade, new roof deck

Open the permit page

$30,000
Jun 11, 2018Completed
final sign-off Jul 2018
233 Sansome StRudolph Commercial Interiors Inc, Rci9th fl: revision to app #201803274687, construct three new offices and one conference room, adhust lighting per new layout. sprinkker & life saftey under sep. permit.
Details
Permit
201806111487
Status
complete
Filed
Jun 11, 2018
Permit issued
Jun 12, 2018
Final sign-off
Jul 30, 2018
Declared cost
$30,000
Address
233 Sansome St

9th fl: revision to app #201803274687, construct three new offices and one conference room, adhust lighting per new layout. sprinkker & life saftey under sep. permit.

Open the permit page

$30,000
Jan 26, 2018Completed
final sign-off Mar 2018
155 Jackson StC B 2 Builders Incorporatedapt 2504: to comply with complaint 201833171: remove (e) door between bed 2 & living room,in-fill door opening with gyp board partition,construct new partition in bedroom 2 to create 3rd bedroom.replace (e) toilets with h.e, new shower finishes & water proofing. maher n/a.
Details
Permit
201801269641
Status
complete
Filed
Jan 26, 2018
Permit issued
Jan 26, 2018
Final sign-off
Mar 30, 2018
Declared cost
$10,000
Address
155 Jackson St

apt 2504: to comply with complaint 201833171: remove (e) door between bed 2 & living room,in-fill door opening with gyp board partition,construct new partition in bedroom 2 to create 3rd bedroom.replace (e) toilets with h.e, new shower finishes & water proofing. maher n/a.

Open the permit page

$10,000
Nov 16, 2017Completed
final sign-off Jul 2018
1611 Oak StRudolph Commercial Interiors Inc, Rcivoluntary accessibility upgrade: construct concrete ramp to provide access from 1611 oak street to courtyard of 1025 masonic ave.
Details
Permit
201711164124
Status
complete
Filed
Nov 16, 2017
Permit issued
Nov 28, 2017
Final sign-off
Jul 13, 2018
Declared cost
$25,000
Address
1611 Oak St

voluntary accessibility upgrade: construct concrete ramp to provide access from 1611 oak street to courtyard of 1025 masonic ave.

Open the permit page

$25,000
Nov 16, 2017Completed
final sign-off Jul 2018
1025 Masonic AvRudolph Commercial Interiors Inc, Rcivoluntary accessibility upgrade: construct concrete ramp to provide access from courtyard of 1025 masonic to 1611 oak st.
Details
Permit
201711164123
Status
complete
Filed
Nov 16, 2017
Permit issued
Nov 28, 2017
Final sign-off
Jul 13, 2018
Declared cost
$40,000
Address
1025 Masonic Av

voluntary accessibility upgrade: construct concrete ramp to provide access from courtyard of 1025 masonic to 1611 oak st.

Open the permit page

$40,000
Oct 27, 2017Never finaled
issued Sep 2020, no final
743 Vermont Stto comply w/ nov #201928061, demo rear portion of (e)house on 3rd fl and portions of 2nd fl. extension to rear (east) and north for addition of 136 sf to bldb footprint. relocation of interior stairway and remodel kitchen, master bedrm, baths, closet areas
Details
Permit
201710272504
Status
reinstated
Filed
Oct 27, 2017
Permit issued
Sep 26, 2020
Declared cost
$200,000
Address
743 Vermont St

to comply w/ nov #201928061, demo rear portion of (e)house on 3rd fl and portions of 2nd fl. extension to rear (east) and north for addition of 136 sf to bldb footprint. relocation of interior stairway and remodel kitchen, master bedrm, baths, closet areas

Open the permit page

$200,000
Oct 19, 2017Completed
final sign-off Jun 2021
1177 California StSf Contractorunit 630: remodel to include water isolation valves, bath/kitchen cabinets, countertops, fixtures, appliances, replace but with shower pan, update plubming/electrical, install led lighting, new floor finishes, no structural work.
Details
Permit
201710191742
Status
complete
Filed
Oct 19, 2017
Permit issued
Oct 19, 2017
Final sign-off
Jun 3, 2021
Declared cost
$43,000
Address
1177 California St

unit 630: remodel to include water isolation valves, bath/kitchen cabinets, countertops, fixtures, appliances, replace but with shower pan, update plubming/electrical, install led lighting, new floor finishes, no structural work.

Open the permit page

$43,000
Oct 18, 2017Never finaled
issued Oct 2017, no final
1177 California StSf Contractorrevision to previously issued pa #201706270483. new lighting fixtures, washer/dryer, connections to building mechanical systems. new int. doors, new finishes. no structural.
Details
Permit
201710181586
Status
issued
Filed
Oct 18, 2017
Permit issued
Oct 19, 2017
Address
1177 California St

revision to previously issued pa #201706270483. new lighting fixtures, washer/dryer, connections to building mechanical systems. new int. doors, new finishes. no structural.

Open the permit page

Sep 29, 2017Completed
final sign-off Nov 2017
233 Sansome StRudolph Commercial Interiors Inc, Rci#508:interior work only soft demo to remove extg non-structural partitions. t.i. to be performed under seperate app#2017-0815-4800 in pre-application review. n/a for maher. ab-017. alarm/sprinkler deferred.
Details
Permit
201709299968
Status
complete
Filed
Sep 29, 2017
Permit issued
Oct 6, 2017
Final sign-off
Nov 30, 2017
Declared cost
$15,000
Address
233 Sansome St

#508:interior work only soft demo to remove extg non-structural partitions. t.i. to be performed under seperate app#2017-0815-4800 in pre-application review. n/a for maher. ab-017. alarm/sprinkler deferred.

Open the permit page

$15,000
Aug 15, 2017Completed
final sign-off Feb 2018
233 Sansome StRudolph Commercial Interiors Inc, Rcisuite 508, 5th fl: ti interior remodel, demo (e) office & conference rooms - construct new offices, install new ceiling & lights. convert (e) women's toilet room to accessible all gender toilet room. install sprinkler on entire fl, sprinker & fire life safety under seperate permit. maher na
Details
Permit
201708154800
Status
complete
Filed
Aug 15, 2017
Permit issued
Nov 14, 2017
Final sign-off
Feb 23, 2018
Declared cost
$180,000
Address
233 Sansome St

suite 508, 5th fl: ti interior remodel, demo (e) office & conference rooms - construct new offices, install new ceiling & lights. convert (e) women's toilet room to accessible all gender toilet room. install sprinkler on entire fl, sprinker & fire life safety under seperate permit. maher na

Open the permit page

$180,000
Jun 27, 2017Completed
final sign-off Jul 2017
550 Battery StC B 2 Builders Incorporatedmaintenance & repair, responding to nov #201780471, item #4. remove (e) non-structural partition for maintenance & repair of trash chute, construct new partitions, replace in kind.
Details
Permit
201706270436
Status
complete
Filed
Jun 27, 2017
Permit issued
Jun 28, 2017
Final sign-off
Jul 7, 2017
Declared cost
$8,500
Address
550 Battery St

maintenance & repair, responding to nov #201780471, item #4. remove (e) non-structural partition for maintenance & repair of trash chute, construct new partitions, replace in kind.

Open the permit page

$8,500
Nov 16, 2016Completed
final sign-off Feb 2017
2188 15th StCornerstone Dba Ag Constructionremodel of extg bathroom and washer and dryer. extension of extg wall to property line in lightwell. addition of new plumbing fixtures and finishes. structural work. replace an overhead (dryrot) beam between (e) kitchen & dining room in kind. revision to pa#201609289093
Details
Permit
201611162918
Status
complete
Filed
Nov 16, 2016
Permit issued
Nov 22, 2016
Final sign-off
Feb 1, 2017
Declared cost
$20,000
Address
2188 15th St

remodel of extg bathroom and washer and dryer. extension of extg wall to property line in lightwell. addition of new plumbing fixtures and finishes. structural work. replace an overhead (dryrot) beam between (e) kitchen & dining room in kind. revision to pa#201609289093

Open the permit page

$20,000
Nov 15, 2016Never finaled
issued Nov 2016, no final
495 Geary StRudolph Commercial Interiors Inc, Rcimezzanine - ti- remove 30" wide door, modify (e) partition, install new 36" wide door. remove portions (e) gyp board ceiling, patch/repairs required - all work in mechanical room. ref pa 2016-0809-4518. maher na
Details
Permit
201611152725
Status
issued
Filed
Nov 15, 2016
Permit issued
Nov 30, 2016
Declared cost
$8,000
Address
495 Geary St

mezzanine - ti- remove 30" wide door, modify (e) partition, install new 36" wide door. remove portions (e) gyp board ceiling, patch/repairs required - all work in mechanical room. ref pa 2016-0809-4518. maher na

Open the permit page

$8,000
Nov 8, 2016Completed
final sign-off May 2017
303 02nd St7/f #750- commercial t.i. to unoccupied suite, demo finishes & millwork, new non structural partitions, glazing, millwork & finishes includes accessibility upgrades to restrooms. n/a ordinance #155-13
Details
Permit
201611082280
Status
complete
Filed
Nov 8, 2016
Permit issued
Nov 21, 2016
Final sign-off
May 18, 2017
Declared cost
$38,400
Address
303 02nd St

7/f #750- commercial t.i. to unoccupied suite, demo finishes & millwork, new non structural partitions, glazing, millwork & finishes includes accessibility upgrades to restrooms. n/a ordinance #155-13

Open the permit page

$38,400
Sep 16, 2016Never finaled
issued Oct 2016, no final
1 Daniel Burnham CtRossi Builders Inc.arch/mep ti on 3rd floor - expand (e) dr. office (350c) into adjacent suite (345c). new space will add 5 exam rooms, new office, sterilizating room and open consulting area. no structural work maher na, 3 new duct smoke detectors, fire under separate permit
Details
Permit
201609167928
Status
issued
Filed
Sep 16, 2016
Permit issued
Oct 14, 2016
Declared cost
$180,000
Address
1 Daniel Burnham Ct

arch/mep ti on 3rd floor - expand (e) dr. office (350c) into adjacent suite (345c). new space will add 5 exam rooms, new office, sterilizating room and open consulting area. no structural work maher na, 3 new duct smoke detectors, fire under separate permit

Open the permit page

$180,000
Jul 14, 2016Completed
final sign-off Jul 2017
758 Natoma Stto change dormitory changed per app #8511648 back to a warehouse. no construction under this permit. reference no.8511648 ** maher: n/a **
Details
Permit
201607142354
Status
complete
Filed
Jul 14, 2016
Permit issued
May 24, 2017
Final sign-off
Jul 20, 2017
Address
758 Natoma St

to change dormitory changed per app #8511648 back to a warehouse. no construction under this permit. reference no.8511648 ** maher: n/a **

Open the permit page

Jan 28, 2016Completed
final sign-off Apr 2018
2180 Harrison StSkyline Construction2nd flr: t.i. remove (e) non-structural partitions, construct new gyp board, partitions as shown on plan, modify existing acoustical ceiling,separate permit sprinkler, life safety, mechanical & electrical; maher n/a
Details
Permit
201601288211
Status
complete
Filed
Jan 28, 2016
Permit issued
Mar 9, 2016
Final sign-off
Apr 24, 2018
Declared cost
$95,000
Address
2180 Harrison St

2nd flr: t.i. remove (e) non-structural partitions, construct new gyp board, partitions as shown on plan, modify existing acoustical ceiling,separate permit sprinkler, life safety, mechanical & electrical; maher n/a

Open the permit page

$95,000
Aug 4, 2015Completed
final sign-off Oct 2015
7 Lee AvDarc Ventures Inc Dba Spl Construction Srevision to pa 2015 0312 0616 - add 1/2 bath
Details
Permit
201508043279
Status
complete
Filed
Aug 4, 2015
Permit issued
Aug 4, 2015
Final sign-off
Oct 5, 2015
Declared cost
$5,000
Address
7 Lee Av

revision to pa 2015 0312 0616 - add 1/2 bath

Open the permit page

$5,000
Jul 31, 2015Completed
final sign-off Dec 2015
460 Ellis StCornerstone Dba Ag Constructionadditional plans for title 24 for lighting for 201505196703. n/a maher ord. # 155-13
Details
Permit
201507312980
Status
complete
Filed
Jul 31, 2015
Permit issued
Jul 31, 2015
Final sign-off
Dec 18, 2015
Declared cost
$250
Address
460 Ellis St

additional plans for title 24 for lighting for 201505196703. n/a maher ord. # 155-13

Open the permit page

$250
May 19, 2015Completed
final sign-off Dec 2015
460 Ellis StCornerstone Dba Ag Constructiondemo of ground floor office partitions and restroom construction of new walls and new accessible restroom. n/a for the maher.
Details
Permit
201505196703
Status
complete
Filed
May 19, 2015
Permit issued
Jun 8, 2015
Final sign-off
Dec 18, 2015
Declared cost
$40,000
Address
460 Ellis St

demo of ground floor office partitions and restroom construction of new walls and new accessible restroom. n/a for the maher.

Open the permit page

$40,000
Mar 17, 2015Completed
final sign-off Aug 2016
1312 Jackson StPatrick Uniackesoft story structural upgrade. install bolting and shear walls per soft story ordinance sfbc chapter 34b.
Details
Permit
201503171025
Status
complete
Filed
Mar 17, 2015
Permit issued
Aug 14, 2015
Final sign-off
Aug 4, 2016
Declared cost
$18,000
Address
1312 Jackson St

soft story structural upgrade. install bolting and shear walls per soft story ordinance sfbc chapter 34b.

Open the permit page

$18,000
Mar 12, 2015Completed
final sign-off Oct 2015
2642 40th AvCornerstone Dba Ag Constructiondemo of ground floor walls + slab portions. construction of ground floor bedroom, full bath & rec. room, construction of 215 sq ft of new ground flr area under exist extension as a fam room. ground floor apppliance & fixture upgrades.
Details
Permit
201503120611
Status
complete
Filed
Mar 12, 2015
Permit issued
Apr 29, 2015
Final sign-off
Oct 20, 2015
Declared cost
$90,000
Address
2642 40th Av

demo of ground floor walls + slab portions. construction of ground floor bedroom, full bath & rec. room, construction of 215 sq ft of new ground flr area under exist extension as a fam room. ground floor apppliance & fixture upgrades.

Open the permit page

$90,000
Mar 12, 2015Completed
final sign-off Oct 2015
7 Lee AvDarc Ventures Inc Dba Spl Construction Sremoval of portions of ground floor conc slab. repouring of slab & new footings. ocnstruction of 117 sq ft of new ocnditioned area below (e) extension. addition of new inteiror stair to connect floors. const. of new utility closet & master bedroom & full bath (suite) on ground floor.
Details
Permit
201503120616
Status
complete
Filed
Mar 12, 2015
Permit issued
Apr 29, 2015
Final sign-off
Oct 5, 2015
Declared cost
$50,000
Address
7 Lee Av

removal of portions of ground floor conc slab. repouring of slab & new footings. ocnstruction of 117 sq ft of new ocnditioned area below (e) extension. addition of new inteiror stair to connect floors. const. of new utility closet & master bedroom & full bath (suite) on ground floor.

Open the permit page

$50,000
Mar 9, 2015Completed
final sign-off Jul 2015
235 Oak Stsoft story structural upgrading. install shearwalls and grade beams per soft story ordinance sfbc ch 34 b
Details
Permit
201503090253
Status
complete
Filed
Mar 9, 2015
Permit issued
Mar 16, 2015
Final sign-off
Jul 28, 2015
Declared cost
$37,000
Address
235 Oak St

soft story structural upgrading. install shearwalls and grade beams per soft story ordinance sfbc ch 34 b

Open the permit page

$37,000
Feb 20, 2015Completed
final sign-off May 2015
205 Bonview Stnew kitchen appliances, fixtures & counters, patch sheetrock gyp. board, ceiling - damaged areas. no structural work.
Details
Permit
201502208842
Status
complete
Filed
Feb 20, 2015
Permit issued
Feb 20, 2015
Final sign-off
May 8, 2015
Declared cost
$11,000
Address
205 Bonview St

new kitchen appliances, fixtures & counters, patch sheetrock gyp. board, ceiling - damaged areas. no structural work.

Open the permit page

$11,000
Jan 26, 2015Completed
final sign-off Mar 2015
353 03rd AvDarc Ventures Inc Dba Spl Construction Scomply with cc 7747 excluding item 2, and add 6 skylights to 353 3rd ave.; item 1 front stair repair less than 50%; (a separate permit will be submitted for item 2 for ground floor walls & second mean of egress removal).
Details
Permit
201501266653
Status
complete
Filed
Jan 26, 2015
Permit issued
Jan 29, 2015
Final sign-off
Mar 9, 2015
Declared cost
$12,500
Address
353 03rd Av

comply with cc 7747 excluding item 2, and add 6 skylights to 353 3rd ave.; item 1 front stair repair less than 50%; (a separate permit will be submitted for item 2 for ground floor walls & second mean of egress removal).

Open the permit page

$12,500
Jan 22, 2015Expired or cancelled
cancelled Mar 2020
318 Spear Stt.i new cafe & h.c toilet. non bearing partitions, mech. elec. & plumbing work food service equipment. interior finishes. maher ordinance n/a.
Details
Permit
201501226430
Status
cancelled
Filed
Jan 22, 2015
Declared cost
$65,000
Address
318 Spear St

t.i new cafe & h.c toilet. non bearing partitions, mech. elec. & plumbing work food service equipment. interior finishes. maher ordinance n/a.

Open the permit page

$65,000
Jan 20, 2015Completed
final sign-off Jan 2017
50 Shrader StR D Sherrill Incdemo and replace defective retaining wall in order to replace rear exterior stair. original stair to be demolished after replacement stair is constructed. maher not req
Details
Permit
201501206152
Status
complete
Filed
Jan 20, 2015
Permit issued
Oct 23, 2015
Final sign-off
Jan 24, 2017
Declared cost
$238,000
Address
50 Shrader St

demo and replace defective retaining wall in order to replace rear exterior stair. original stair to be demolished after replacement stair is constructed. maher not req

Open the permit page

$238,000
Dec 23, 2014Expired or cancelled
cancelled Aug 2016
2180 Harrison StParadigm General Contractorsvoluntary barrier removal to facilities accessed by general public - accessible parking, curb ramp in private parking lot, reception counter, toilet rooms on floors 1,2 and 3, and signage. maher n/a.
Details
Permit
201412234414
Status
cancelled
Filed
Dec 23, 2014
Permit issued
Mar 13, 2015
Declared cost
$30,000
Address
2180 Harrison St

voluntary barrier removal to facilities accessed by general public - accessible parking, curb ramp in private parking lot, reception counter, toilet rooms on floors 1,2 and 3, and signage. maher n/a.

Open the permit page

$30,000
Sep 24, 2014Completed
final sign-off Mar 2016
3609 Sacramento StPatrick Uniacke3/f only -revision to on going work for pa#201404304545 fire damaged bldg. additional work on 3/f wall changes, ceiling work & accessibility upgrade.
Details
Permit
201409247162
Status
complete
Filed
Sep 24, 2014
Permit issued
Sep 25, 2014
Final sign-off
Mar 15, 2016
Declared cost
$12,500
Address
3609 Sacramento St

3/f only -revision to on going work for pa#201404304545 fire damaged bldg. additional work on 3/f wall changes, ceiling work & accessibility upgrade.

Open the permit page

$12,500
Sep 17, 2014Never finaled
issued Sep 2014, no final
490 Post StSf Contractorsuite 900 - light demolition of extg walls and counters. construction of 2 new assistants offices, relocation of interior doors. accessible upgrades to extg h.c. restroom. breakroom and hallways and to one exam room.
Details
Permit
201409176536
Status
issued
Filed
Sep 17, 2014
Permit issued
Sep 17, 2014
Declared cost
$45,000
Address
490 Post St

suite 900 - light demolition of extg walls and counters. construction of 2 new assistants offices, relocation of interior doors. accessible upgrades to extg h.c. restroom. breakroom and hallways and to one exam room.

Open the permit page

$45,000
Sep 17, 2014Completed
final sign-off Dec 2015
215 Market StParadigm General Contractorsgrnd floor, t.i. demo existing gyp board partitions as shown. construct new gyp bd partitions for new conference rooms, relocate (e) light fixtures, interior work only - mep separate permit. sprinkler and life safety under separate permits; maher n/a
Details
Permit
201409176520
Status
complete
Filed
Sep 17, 2014
Permit issued
Sep 22, 2014
Final sign-off
Dec 30, 2015
Declared cost
$23,000
Address
215 Market St

grnd floor, t.i. demo existing gyp board partitions as shown. construct new gyp bd partitions for new conference rooms, relocate (e) light fixtures, interior work only - mep separate permit. sprinkler and life safety under separate permits; maher n/a

Open the permit page

$23,000
Aug 26, 2014Expired or cancelled
cancelled Dec 2017
3611 Sacramento Stchange of hours of outdoor operation for rear yard use by ground floor cafe. existing approved hours from 8:00 pm to 10:00 pm.
Details
Permit
201408264724
Status
cancelled
Filed
Aug 26, 2014
Address
3611 Sacramento St

change of hours of outdoor operation for rear yard use by ground floor cafe. existing approved hours from 8:00 pm to 10:00 pm.

Open the permit page

Jul 22, 2014Completed
final sign-off Aug 2014
116 Divisadero StCornerstone Dba Ag Constructionnew permit to accompany/revision to 201407070549 for kitchen remodel. new beam at 10' long wall opening at kitchen.
Details
Permit
201407221896
Status
complete
Filed
Jul 22, 2014
Permit issued
Jul 23, 2014
Final sign-off
Aug 18, 2014
Declared cost
$1,500
Address
116 Divisadero St

new permit to accompany/revision to 201407070549 for kitchen remodel. new beam at 10' long wall opening at kitchen.

Open the permit page

$1,500
Jun 9, 2014Never finaled
issued Sep 2014, no final
2131 Folsom StArdo Construction Co.tenant improvement for new cannabis nursery/greenhouse. n/a maher ordinance 155-13
Details
Permit
201406097854
Status
issued
Filed
Jun 9, 2014
Permit issued
Sep 12, 2014
Declared cost
$20,000
Address
2131 Folsom St

tenant improvement for new cannabis nursery/greenhouse. n/a maher ordinance 155-13

Open the permit page

$20,000
May 19, 2014Completed
final sign-off Oct 2016
2000 Van Ness AvGrand Electric & Construction Co.electrical service upgrade-new transformer vault in aerial bsmt on public right of way sidewalk. 1200 amp 3 phase service. vault enclosure - 3 masonry walls with fire rated door. above ground incidental hatch doors per pg&e specifications.
Details
Permit
201405196168
Status
complete
Filed
May 19, 2014
Permit issued
Mar 26, 2015
Final sign-off
Oct 20, 2016
Declared cost
$50,000
Address
2000 Van Ness Av

electrical service upgrade-new transformer vault in aerial bsmt on public right of way sidewalk. 1200 amp 3 phase service. vault enclosure - 3 masonry walls with fire rated door. above ground incidental hatch doors per pg&e specifications.

Open the permit page

$50,000
Apr 30, 2014Completed
final sign-off Mar 2016
3609 Sacramento StPatrick Uniackevacant 3-story com'l bldg, interior stripped to wall & floor framing, provide g/f shear @ front & structure support @ rear, new g/f accessible entry & new access. restroom, provide new insulation & drywall throughout, provide new windows & doors throughout, provide 1 hr. walls & new ext. siding.
Details
Permit
201404304545
Status
complete
Filed
Apr 30, 2014
Permit issued
May 8, 2014
Final sign-off
Mar 15, 2016
Declared cost
$225,000
Address
3609 Sacramento St

vacant 3-story com'l bldg, interior stripped to wall & floor framing, provide g/f shear @ front & structure support @ rear, new g/f accessible entry & new access. restroom, provide new insulation & drywall throughout, provide new windows & doors throughout, provide 1 hr. walls & new ext. siding.

Open the permit page

$225,000
Dec 17, 2013Never finaled
issued Dec 2013, no final
77 Beale StSiemens Industry, Inc.2nd fl. t.i. install electrified lock at existing elevator lobby doors, to comply w/ section 1008.1.4.6 of 2010 sfbc. life safety work under separate permit.
Details
Permit
201312174375
Status
issued
Filed
Dec 17, 2013
Permit issued
Dec 18, 2013
Declared cost
$1,200
Address
77 Beale St

2nd fl. t.i. install electrified lock at existing elevator lobby doors, to comply w/ section 1008.1.4.6 of 2010 sfbc. life safety work under separate permit.

Open the permit page

$1,200
Dec 17, 2013Completed
final sign-off Jun 2014
231 Divisadero Stminor demolitoin of interior walls & construction of new walls for the addition of a new bathroom + laundry room. no structural work this permit.
Details
Permit
201312174345
Status
complete
Filed
Dec 17, 2013
Permit issued
Dec 23, 2013
Final sign-off
Jun 16, 2014
Declared cost
$18,000
Address
231 Divisadero St

minor demolitoin of interior walls & construction of new walls for the addition of a new bathroom + laundry room. no structural work this permit.

Open the permit page

$18,000
Nov 12, 2013Completed
final sign-off Feb 2014
411 Greenwich StTom Can Constructiondisassemble the (e) deck with fence, remove (e) doors (2) replace w/fixed glass windows. replace (2) window with (1) sliding glass doors. add new deck, wood fence, metal rail fence & 42" high rated wall @ property line. (under separate permit replace with new roof).
Details
Permit
201311121658
Status
complete
Filed
Nov 12, 2013
Permit issued
Nov 12, 2013
Final sign-off
Feb 28, 2014
Declared cost
$20,000
Address
411 Greenwich St

disassemble the (e) deck with fence, remove (e) doors (2) replace w/fixed glass windows. replace (2) window with (1) sliding glass doors. add new deck, wood fence, metal rail fence & 42" high rated wall @ property line. (under separate permit replace with new roof).

Open the permit page

$20,000
Oct 23, 2013Completed
final sign-off Nov 2013
42 Orben PlClayton Valley Construction, Inccondo conversion work per physcal insp #7313-install 2 layer of 5/8" drywall to exposed ceiling in breezewy, install new concrete step & handrail @rear stairs, remove window security bars, repair framing @breezway. install battery smoke alarms provided ventilation, comp w/all items for units per ltr
Details
Permit
201310239985
Status
complete
Filed
Oct 23, 2013
Permit issued
Oct 25, 2013
Final sign-off
Nov 13, 2013
Declared cost
$20,000
Address
42 Orben Pl

condo conversion work per physcal insp #7313-install 2 layer of 5/8" drywall to exposed ceiling in breezewy, install new concrete step & handrail @rear stairs, remove window security bars, repair framing @breezway. install battery smoke alarms provided ventilation, comp w/all items for units per ltr

Open the permit page

$20,000
Sep 9, 2013Completed
final sign-off Oct 2013
1042 Grant AvNovo Construction Inct.i.- construct drywall partitions as shown, install new ceiling and lights, mechanical & title 24 under seperate permits.
Details
Permit
201309096270
Status
complete
Filed
Sep 9, 2013
Permit issued
Sep 17, 2013
Final sign-off
Oct 15, 2013
Declared cost
$179,334
Address
1042 Grant Av

t.i.- construct drywall partitions as shown, install new ceiling and lights, mechanical & title 24 under seperate permits.

Open the permit page

$179,334
Jun 14, 2013Completed
final sign-off Jul 2013
2180 Harrison StParadigm General Contractorsoffice t.i. involving demo only. remove 10 lf of drywall partiton. remove door and frame. non structural partiton
Details
Permit
201306149563
Status
complete
Filed
Jun 14, 2013
Permit issued
Jun 18, 2013
Final sign-off
Jul 25, 2013
Declared cost
$1,500
Address
2180 Harrison St

office t.i. involving demo only. remove 10 lf of drywall partiton. remove door and frame. non structural partiton

Open the permit page

$1,500
Feb 4, 2013Completed
final sign-off Mar 2015
1177 California StSf Contractorfinish upgrades to guest room w/new fixtures. extenstion to master bath by 60 sf. also finish upgrades. extension of hallway by 4.5 ft to allow access to bedrooms. no strucutral work or t-24 required.
Details
Permit
201302049383
Status
complete
Filed
Feb 4, 2013
Permit issued
Feb 4, 2013
Final sign-off
Mar 2, 2015
Declared cost
$25,000
Address
1177 California St

finish upgrades to guest room w/new fixtures. extenstion to master bath by 60 sf. also finish upgrades. extension of hallway by 4.5 ft to allow access to bedrooms. no strucutral work or t-24 required.

Open the permit page

$25,000
Dec 21, 2012Expired or cancelled
cancelled Jan 2016
215 Market StC B 2 Builders Incorporated(roof level)install new housekeeping pad at roof level for mechanical equipment. extend (e) emergency generator exhaust ducts, install new exhaust fans.
Details
Permit
201212216768
Status
cancelled
Filed
Dec 21, 2012
Declared cost
$85,000
Address
215 Market St

(roof level)install new housekeeping pad at roof level for mechanical equipment. extend (e) emergency generator exhaust ducts, install new exhaust fans.

Open the permit page

$85,000
Nov 27, 2012Completed
final sign-off Mar 2013
1555 Burke AvPacific Green Constructionmechanical only. ref. 201209180035; new residental type exhaust hood, provide exhaust ductwork from hood to existing 10" exhaust stub-up
Details
Permit
201211274921
Status
complete
Filed
Nov 27, 2012
Permit issued
Nov 28, 2012
Final sign-off
Mar 6, 2013
Address
1555 Burke Av

mechanical only. ref. 201209180035; new residental type exhaust hood, provide exhaust ductwork from hood to existing 10" exhaust stub-up

Open the permit page

Oct 29, 2012Completed
final sign-off Apr 2013
1177 California StSf Contractorremoval of bathroom door and adjacent closet. expansion of bathroom to include a new bidet. relocation of bathroom pocket foor. relocation of vanity. provide exhaust fan. remodel of existing kitchen.
Details
Permit
201210292966
Status
complete
Filed
Oct 29, 2012
Permit issued
Oct 29, 2012
Final sign-off
Apr 30, 2013
Declared cost
$25,000
Address
1177 California St

removal of bathroom door and adjacent closet. expansion of bathroom to include a new bidet. relocation of bathroom pocket foor. relocation of vanity. provide exhaust fan. remodel of existing kitchen.

Open the permit page

$25,000
Jul 16, 2012Expired or cancelled
expired Oct 2013
77 Beale StParadigm General Contractors19kth floor minor t.i. - remove (e) drywall partitions & doors, construct new gyp bd partitions & new doors at indicated to enlarge office #1974 & add #1974a. sprinkler & life safety, hvac under separate permits.
Details
Permit
201207164890
Status
expired
Filed
Jul 16, 2012
Permit issued
Aug 1, 2012
Declared cost
$16,000
Address
77 Beale St

19kth floor minor t.i. - remove (e) drywall partitions & doors, construct new gyp bd partitions & new doors at indicated to enlarge office #1974 & add #1974a. sprinkler & life safety, hvac under separate permits.

Open the permit page

$16,000
May 24, 2012Completed
final sign-off Nov 2012
1177 California StSf Contractorrev. to 2012-0303-5694 - revise new wall construction to delete wall in hallway. replace existing acoustic ceiling tiles with new in existing grid system. new swismic 12 ga supports to existing light fixtures, grid and ceiling fixtures. provide new exit sign emergency lighting.
Details
Permit
201205241165
Status
complete
Filed
May 24, 2012
Permit issued
Jun 4, 2012
Final sign-off
Nov 6, 2012
Declared cost
$6,000
Address
1177 California St

rev. to 2012-0303-5694 - revise new wall construction to delete wall in hallway. replace existing acoustic ceiling tiles with new in existing grid system. new swismic 12 ga supports to existing light fixtures, grid and ceiling fixtures. provide new exit sign emergency lighting.

Open the permit page

$6,000
Nov 28, 2011Completed
final sign-off Dec 2011
2398 Pine StH S Construction And Associates Coprovide 28 lin.ft. of wall 7'-0" a.f.f.. add exit sign. ref pa#201110116432.
Details
Permit
201111289568
Status
complete
Filed
Nov 28, 2011
Permit issued
Nov 28, 2011
Final sign-off
Dec 13, 2011
Declared cost
$1,600
Address
2398 Pine St

provide 28 lin.ft. of wall 7'-0" a.f.f.. add exit sign. ref pa#201110116432.

Open the permit page

$1,600
Oct 18, 2011Completed
final sign-off Jan 2012
2114 Judah StArpol Incvomply w/nov 201154447 - rebuild existing exterior stairway & landings. no changes to size & location. stairs are located on west property line of bldg, replace in kind.
Details
Permit
201110187015
Status
complete
Filed
Oct 18, 2011
Permit issued
Oct 19, 2011
Final sign-off
Jan 5, 2012
Declared cost
$5,600
Address
2114 Judah St

vomply w/nov 201154447 - rebuild existing exterior stairway & landings. no changes to size & location. stairs are located on west property line of bldg, replace in kind.

Open the permit page

$5,600
Oct 11, 2011Completed
final sign-off Apr 2012
2398 Pine Stprovide new accessible power operated door with min 32" clr opening at entry. demo of walls and fixtures at existing restroom area and construction of new unisex restroom and privacy wall, 7ft high
Details
Permit
201110116432
Status
complete
Filed
Oct 11, 2011
Permit issued
Oct 18, 2011
Final sign-off
Apr 18, 2012
Declared cost
$12,000
Address
2398 Pine St

provide new accessible power operated door with min 32" clr opening at entry. demo of walls and fixtures at existing restroom area and construction of new unisex restroom and privacy wall, 7ft high

Open the permit page

$12,000
Aug 16, 2011Completed
final sign-off Feb 2013
77 Beale StC B 2 Builders Incorporatedoffice ti on level b1. install doors and turnstile with card reader access, exit doors to be free exiting, demo existing concrete ramp, install new concrete ramp at secured entry. build new partitions,relocate existing light fixtures and install new ceiling. no mechanical work.
Details
Permit
201108162535
Status
complete
Filed
Aug 16, 2011
Permit issued
Aug 17, 2011
Final sign-off
Feb 5, 2013
Declared cost
$69,000
Address
77 Beale St

office ti on level b1. install doors and turnstile with card reader access, exit doors to be free exiting, demo existing concrete ramp, install new concrete ramp at secured entry. build new partitions,relocate existing light fixtures and install new ceiling. no mechanical work.

Open the permit page

$69,000
Jul 5, 2011Completed
final sign-off Nov 2011
231 Grant Avremove existing stair, fill with floor to match existing. add 3' partition, patch walls after demo of office. space currently not occupied
Details
Permit
201107059469
Status
complete
Filed
Jul 5, 2011
Permit issued
Jul 6, 2011
Final sign-off
Nov 4, 2011
Declared cost
$6,595
Address
231 Grant Av

remove existing stair, fill with floor to match existing. add 3' partition, patch walls after demo of office. space currently not occupied

Open the permit page

$6,595
Jun 8, 2011Completed
final sign-off Dec 2011
4080 24th StTom Ehlinereplacement of storefront, enlargement of entry, stucco, ramp @ entry.
Details
Permit
201106087705
Status
complete
Filed
Jun 8, 2011
Permit issued
Jul 18, 2011
Final sign-off
Dec 9, 2011
Declared cost
$20,000
Address
4080 24th St

replacement of storefront, enlargement of entry, stucco, ramp @ entry.

Open the permit page

$20,000
May 19, 2011Completed
final sign-off Jun 2011
77 Beale StC B 2 Builders Incorporatedrevsion to appl.#201101128263 - provide epoxy coating to generator room locate roof on 5th fl. generator and fuel piping under separate permit.
Details
Permit
201105196365
Status
complete
Filed
May 19, 2011
Permit issued
May 19, 2011
Final sign-off
Jun 3, 2011
Declared cost
$15,000
Address
77 Beale St

revsion to appl.#201101128263 - provide epoxy coating to generator room locate roof on 5th fl. generator and fuel piping under separate permit.

Open the permit page

$15,000
May 19, 2011Completed
final sign-off Sep 2011
445 Bush StRudolph Commercial Interiors Inc, Rci1st floor - soft demolition permit - remove existing non-structural partitions (per ab-017). tenant improvements to be submitted separately.per ab-017
Details
Permit
201105196374
Status
complete
Filed
May 19, 2011
Permit issued
May 19, 2011
Final sign-off
Sep 30, 2011
Declared cost
$8,900
Address
445 Bush St

1st floor - soft demolition permit - remove existing non-structural partitions (per ab-017). tenant improvements to be submitted separately.per ab-017

Open the permit page

$8,900
Apr 14, 2011Completed
final sign-off Aug 2011
1 Daniel Burnham CtLoughville Company3rd floor-unit #388c-demo of 65 lin ft of interior partition in vacant space. construction of new partition for 5 new exam rooms, office, storage, reception & waiting area. addition of 2 new sidelights by entry doors. minor changes to ceiling mechanical, 3fd floor, suite 388c
Details
Permit
201104144049
Status
complete
Filed
Apr 14, 2011
Permit issued
Apr 27, 2011
Final sign-off
Aug 10, 2011
Declared cost
$25,000
Address
1 Daniel Burnham Ct

3rd floor-unit #388c-demo of 65 lin ft of interior partition in vacant space. construction of new partition for 5 new exam rooms, office, storage, reception & waiting area. addition of 2 new sidelights by entry doors. minor changes to ceiling mechanical, 3fd floor, suite 388c

Open the permit page

$25,000
Dec 30, 2010Completed
final sign-off Apr 2011
147 Monterey Blrevision to pa# 2008-1014-4050: addition of cabinets & refrigerator in nook, deletion of 2 windows in office, deletion of closet in office & smaller windows, same location in office
Details
Permit
201012307626
Status
complete
Filed
Dec 30, 2010
Permit issued
Jan 7, 2011
Final sign-off
Apr 13, 2011
Declared cost
$100
Address
147 Monterey Bl

revision to pa# 2008-1014-4050: addition of cabinets & refrigerator in nook, deletion of 2 windows in office, deletion of closet in office & smaller windows, same location in office

Open the permit page

$100
Dec 28, 2010Completed
final sign-off Jul 2011
1 Daniel Burnham CtLoughville Company3rd floor suite 265c - demo of 40" of interior wall, installation of 2 pocket doors, construction of 9 linear feet of new full height walls, installation of sidelight. installation of 2 new sinks, new hvac supply register & 1 new exit sign
Details
Permit
201012287481
Status
complete
Filed
Dec 28, 2010
Permit issued
Jan 19, 2011
Final sign-off
Jul 8, 2011
Declared cost
$18,000
Address
1 Daniel Burnham Ct

3rd floor suite 265c - demo of 40" of interior wall, installation of 2 pocket doors, construction of 9 linear feet of new full height walls, installation of sidelight. installation of 2 new sinks, new hvac supply register & 1 new exit sign

Open the permit page

$18,000
Nov 22, 2010Completed
final sign-off Jun 2011
25 Beale StC B 2 Builders Incorporatedconstruct 2-hr rated electrical closet on ground floor lobby space, interior work only
Details
Permit
201011225431
Status
complete
Filed
Nov 22, 2010
Permit issued
Nov 22, 2010
Final sign-off
Jun 3, 2011
Declared cost
$4,700
Address
25 Beale St

construct 2-hr rated electrical closet on ground floor lobby space, interior work only

Open the permit page

$4,700
Oct 18, 2010Never finaled
issued Oct 2010, no final
45 Beale StC B 2 Builders Incorporatedconstruct 2 hour rated enclosure around new electrical pull can, install 2 hr rated door and frame assembly at enclosure. not affecting any stair enclosure
Details
Permit
201010183208
Status
issued
Filed
Oct 18, 2010
Permit issued
Oct 18, 2010
Declared cost
$4,500
Address
45 Beale St

construct 2 hour rated enclosure around new electrical pull can, install 2 hr rated door and frame assembly at enclosure. not affecting any stair enclosure

Open the permit page

$4,500
Aug 10, 2010Expired or cancelled
expired May 2013
1 Daniel Burnham CtLoughville Companyperform work only on 150c: demo of storage room wall. removal of a sink, hot water htr. and shelf. construction of 12 lin. ft of new partitions and two doors. no struc, lighting. life safety (sprinklers and fire alarm) if necessary will be on separate permit.
Details
Permit
201008108459
Status
expired
Filed
Aug 10, 2010
Permit issued
Aug 24, 2010
Declared cost
$4,000
Address
1 Daniel Burnham Ct

perform work only on 150c: demo of storage room wall. removal of a sink, hot water htr. and shelf. construction of 12 lin. ft of new partitions and two doors. no struc, lighting. life safety (sprinklers and fire alarm) if necessary will be on separate permit.

Open the permit page

$4,000
Jun 24, 2010Never finaled
issued Oct 2010, no final
745 Marina BlHouseworks Enterprises Inc.revision to 200806134355: demolition of spanish tile mansard parapet. expand roof deck 194 sf with new tempered glass and painted metal guard railing. replace 3rd story window to match 2nd story windows.
Details
Permit
201006245194
Status
issued
Filed
Jun 24, 2010
Permit issued
Oct 25, 2010
Declared cost
$15,000
Address
745 Marina Bl

revision to 200806134355: demolition of spanish tile mansard parapet. expand roof deck 194 sf with new tempered glass and painted metal guard railing. replace 3rd story window to match 2nd story windows.

Open the permit page

$15,000
Mar 15, 2010Expired or cancelled
cancelled Jan 2014
718 Tehama Stpermitting of kitchen on 2nd floor & conversion from office to residential unit.
Details
Permit
201003158211
Status
cancelled
Filed
Mar 15, 2010
Address
718 Tehama St

permitting of kitchen on 2nd floor & conversion from office to residential unit.

Open the permit page

Aug 10, 2009Never finaled
issued Aug 2009, no final
851 Van Ness Avreplace existing lobby door with new glazed door
Details
Permit
200908104453
Status
issued
Filed
Aug 10, 2009
Permit issued
Aug 21, 2009
Declared cost
$6,000
Address
851 Van Ness Av

replace existing lobby door with new glazed door

Open the permit page

$6,000
Jun 1, 2009Expired or cancelled
cancelled Jan 2026
745 Marina Bladdition of roof deck wood burning fireplace-pre manufactured & flue. addition of slate deck finish & drain. this work added to previously approved pa# 2008-0613-4355/s1. this permit is for the wood burning fireplace only
Details
Permit
200906019449
Status
cancelled
Filed
Jun 1, 2009
Declared cost
$5,000
Address
745 Marina Bl

addition of roof deck wood burning fireplace-pre manufactured & flue. addition of slate deck finish & drain. this work added to previously approved pa# 2008-0613-4355/s1. this permit is for the wood burning fireplace only

Open the permit page

$5,000
Dec 3, 2008Completed
final sign-off Jan 2009
1 Embarcadero CenterD Kelly Construction Inc.24th floor -revision to appl #200810093800 - change 12 x 12 concealed spline ceiling to new 2 x 4 at data room drop in acoustic ceiling, break room ceiling to run through continous, walls to remain ceiling height.
Details
Permit
200812037683
Status
complete
Filed
Dec 3, 2008
Permit issued
Dec 3, 2008
Final sign-off
Jan 13, 2009
Declared cost
$2,360
Address
1 Embarcadero Center

24th floor -revision to appl #200810093800 - change 12 x 12 concealed spline ceiling to new 2 x 4 at data room drop in acoustic ceiling, break room ceiling to run through continous, walls to remain ceiling height.

Open the permit page

$2,360
Nov 6, 2008Completed
final sign-off Apr 2009
115 Mason Strevision to existing permit #2008/0926/2728. construction of new storefront entry door, accessible. insert front windows into existing framed openings.
Details
Permit
200811066000
Status
complete
Filed
Nov 6, 2008
Permit issued
Nov 7, 2008
Final sign-off
Apr 2, 2009
Declared cost
$2,000
Address
115 Mason St

revision to existing permit #2008/0926/2728. construction of new storefront entry door, accessible. insert front windows into existing framed openings.

Open the permit page

$2,000
Oct 31, 2008Expired or cancelled
cancelled Jan 2020
82 Rockridge Dr12' addition to the rear of the house and decks on 2 levels with fire stairs. remodel & relocate kitchen and bathrooms
Details
Permit
200810315604
Status
cancelled
Filed
Oct 31, 2008
Declared cost
$300,000
Address
82 Rockridge Dr

12' addition to the rear of the house and decks on 2 levels with fire stairs. remodel & relocate kitchen and bathrooms

Open the permit page

$300,000
Oct 22, 2008Expired or cancelled
expired Jun 2010
1094 De Haro Stto obtain final inspection for work approved under pa#200707126593. all work has been completed.
Details
Permit
200810224832
Status
expired
Filed
Oct 22, 2008
Permit issued
Oct 22, 2008
Address
1094 De Haro St

to obtain final inspection for work approved under pa#200707126593. all work has been completed.

Open the permit page

Oct 14, 2008Completed
final sign-off Apr 2011
147 Monterey Blrevision to 200801142408. changes to ground floor bathroom and bedroom closets. elimination of exterior spiral stair. revisions to exterior windows and doors.
Details
Permit
200810144050
Status
complete
Filed
Oct 14, 2008
Permit issued
Oct 14, 2008
Final sign-off
Apr 15, 2011
Address
147 Monterey Bl

revision to 200801142408. changes to ground floor bathroom and bedroom closets. elimination of exterior spiral stair. revisions to exterior windows and doors.

Open the permit page

Oct 9, 2008Completed
final sign-off Jan 2009
1 Embarcadero CenterD Kelly Construction Inc.24th floor:tenant improvement to existing space, expansion demo/wall openings.
Details
Permit
200810093800
Status
complete
Filed
Oct 9, 2008
Permit issued
Oct 9, 2008
Final sign-off
Jan 13, 2009
Declared cost
$98,000
Address
1 Embarcadero Center

24th floor:tenant improvement to existing space, expansion demo/wall openings.

Open the permit page

$98,000
Oct 1, 2008Expired or cancelled
cancelled Aug 2018
1794 San Jose Avcomplete remodel of ground floor dental offices. addition to new second floor to include two new residential units. addition to partial third floor for second residential unit.
Details
Permit
200810013092
Status
cancelled
Filed
Oct 1, 2008
Declared cost
$100,000
Address
1794 San Jose Av

complete remodel of ground floor dental offices. addition to new second floor to include two new residential units. addition to partial third floor for second residential unit.

Open the permit page

$100,000
Sep 26, 2008Completed
final sign-off May 2009
115 Mason Stupgrades to 2 (e) restreooms to confirm to t-24 accessibility upgrades. reverse swing of main entry doors for building code compliance, rpovdie accessibility signage requirements
Details
Permit
200809262728
Status
complete
Filed
Sep 26, 2008
Permit issued
Sep 26, 2008
Final sign-off
May 20, 2009
Declared cost
$15,000
Address
115 Mason St

upgrades to 2 (e) restreooms to confirm to t-24 accessibility upgrades. reverse swing of main entry doors for building code compliance, rpovdie accessibility signage requirements

Open the permit page

$15,000
Jul 28, 2008Expired or cancelled
cancelled Apr 2012
2650 Sloat Blvertical addition of attic/storage on roof of building approx 396 sq.ft.
Details
Permit
200807287734
Status
cancelled
Filed
Jul 28, 2008
Declared cost
$17,000
Address
2650 Sloat Bl

vertical addition of attic/storage on roof of building approx 396 sq.ft.

Open the permit page

$17,000
Jul 22, 2008Never finaled
issued Jul 2008, no final
2650 Sloat Blfoundation upgrades, addition of shearwalls and two wide flange beams in ceiling.
Details
Permit
200807227303
Status
issued
Filed
Jul 22, 2008
Permit issued
Jul 22, 2008
Declared cost
$13,000
Address
2650 Sloat Bl

foundation upgrades, addition of shearwalls and two wide flange beams in ceiling.

Open the permit page

$13,000
Jun 24, 2008Completed
final sign-off Jun 2008
1206 18th Strenew expired pa# 2007/06/18/4244 for final inspection only.
Details
Permit
200806245193
Status
complete
Filed
Jun 24, 2008
Permit issued
Jun 24, 2008
Final sign-off
Jun 27, 2008
Address
1206 18th St

renew expired pa# 2007/06/18/4244 for final inspection only.

Open the permit page

Jun 13, 2008Expired or cancelled
expired Jan 2011
745 Marina Blvertical addition of 4th floor with gabled roof and 2 dormers, 4th floor to have a bedroom, game room, bath and stairway up from 3rd floor
Details
Permit
200806134355
Status
expired
Filed
Jun 13, 2008
Permit issued
Feb 13, 2009
Declared cost
$180,000
Address
745 Marina Bl

vertical addition of 4th floor with gabled roof and 2 dormers, 4th floor to have a bedroom, game room, bath and stairway up from 3rd floor

Open the permit page

$180,000
Jun 6, 2008Never finaled
issued Jun 2008, no final
3126 Lawton Stconstruction of new property line window on grouond level.
Details
Permit
200806063816
Status
issued
Filed
Jun 6, 2008
Permit issued
Jun 6, 2008
Declared cost
$500
Address
3126 Lawton St

construction of new property line window on grouond level.

Open the permit page

$500
May 28, 2008Completed
final sign-off Oct 2010
155 Terrace Drnew retaining wall at rear of lot (see delta 2 only), revision to pa# 2007-0611-3545
Details
Permit
200805283005
Status
complete
Filed
May 28, 2008
Permit issued
May 28, 2008
Final sign-off
Oct 13, 2010
Declared cost
$5,000
Address
155 Terrace Dr

new retaining wall at rear of lot (see delta 2 only), revision to pa# 2007-0611-3545

Open the permit page

$5,000
Apr 23, 2008Completed
final sign-off Jul 2008
608 Texas Stper complaint #200123325 & #200340781. relocate existing fence 3' from front property line.
Details
Permit
200804230465
Status
complete
Filed
Apr 23, 2008
Permit issued
Jun 6, 2008
Final sign-off
Jul 31, 2008
Declared cost
$250
Address
608 Texas St

per complaint #200123325 & #200340781. relocate existing fence 3' from front property line.

Open the permit page

$250
Apr 21, 2008Completed
final sign-off Feb 2010
532 Folsom Stinstallation of slab to slab chain-link fence to secure storage area in basement. new area including entrances to be accessible.
Details
Permit
200804210261
Status
complete
Filed
Apr 21, 2008
Permit issued
May 7, 2008
Final sign-off
Feb 2, 2010
Declared cost
$10,000
Address
532 Folsom St

installation of slab to slab chain-link fence to secure storage area in basement. new area including entrances to be accessible.

Open the permit page

$10,000
Apr 11, 2008Completed
final sign-off Oct 2008
495 Jefferson Stconstruction of 35 lin ft of 2x4 partition to create separate retail/office space.- installation of two new doors, demolition of counters/shelves in hallway. mechanical, hvac & lighting on seperate permit.
Details
Permit
200804119465
Status
complete
Filed
Apr 11, 2008
Permit issued
Apr 15, 2008
Final sign-off
Oct 1, 2008
Declared cost
$40,000
Address
495 Jefferson St

construction of 35 lin ft of 2x4 partition to create separate retail/office space.- installation of two new doors, demolition of counters/shelves in hallway. mechanical, hvac & lighting on seperate permit.

Open the permit page

$40,000
Mar 31, 2008Completed
final sign-off Aug 2008
1 Daniel Burnham Ctconstruction of new partition walls to create new operation room, exam room and two offices. new soffit in reception area and addition of 8 new sinks in doctor's office on the 4th floor
Details
Permit
200803318344
Status
complete
Filed
Mar 31, 2008
Permit issued
Apr 9, 2008
Final sign-off
Aug 20, 2008
Declared cost
$35,000
Address
1 Daniel Burnham Ct

construction of new partition walls to create new operation room, exam room and two offices. new soffit in reception area and addition of 8 new sinks in doctor's office on the 4th floor

Open the permit page

$35,000
Mar 28, 2008Completed
final sign-off Dec 2008
125 Kearny Stremove all interior partitions, finshes and display construction. remove toilet and temporarily cap for future tenant. remove soffits. ab 017. no exterior work. +
Details
Permit
200803288221
Status
complete
Filed
Mar 28, 2008
Permit issued
Mar 28, 2008
Final sign-off
Dec 9, 2008
Declared cost
$3,000
Address
125 Kearny St

remove all interior partitions, finshes and display construction. remove toilet and temporarily cap for future tenant. remove soffits. ab 017. no exterior work. +

Open the permit page

$3,000
Mar 25, 2008Never finaled
issued Jul 2008, no final
125 Kearny Strevision appl#200805091773 (expand scope of work) new storefront window & door system including new ada accessible entrance with ramp and entry wall.
Details
Permit
200803257970
Status
issued
Filed
Mar 25, 2008
Permit issued
Jul 10, 2008
Declared cost
$4,000
Address
125 Kearny St

revision appl#200805091773 (expand scope of work) new storefront window & door system including new ada accessible entrance with ramp and entry wall.

Open the permit page

$4,000
Feb 1, 2008Completed
final sign-off Feb 2008
1500 Sutter StSf Contractorcomply with physical inspection report# 3r-4817. for administrative purpose only. no work required. all work performed under pa# 2007/09/28/3991 & pa# 2007/06/20/4489.
Details
Permit
200802013855
Status
complete
Filed
Feb 1, 2008
Permit issued
Feb 1, 2008
Final sign-off
Feb 5, 2008
Address
1500 Sutter St

comply with physical inspection report# 3r-4817. for administrative purpose only. no work required. all work performed under pa# 2007/09/28/3991 & pa# 2007/06/20/4489.

Open the permit page

Jan 31, 2008Completed
final sign-off May 2008
115 Carl Stprovide decorative sheet metal-12 guage to fire escape railings and at face of building. provide slate tiles to bottom face of bldg. provide new garage door of horiz. wood facing.
Details
Permit
200801313659
Status
complete
Filed
Jan 31, 2008
Permit issued
Feb 12, 2008
Final sign-off
May 28, 2008
Declared cost
$18,000
Address
115 Carl St

provide decorative sheet metal-12 guage to fire escape railings and at face of building. provide slate tiles to bottom face of bldg. provide new garage door of horiz. wood facing.

Open the permit page

$18,000
Jan 17, 2008Completed
final sign-off Jun 2008
1 Daniel Burnham Ctunit #330; 4th floor-construction of 1 hr demising wall to divide office space. no mep
Details
Permit
200801172704
Status
complete
Filed
Jan 17, 2008
Permit issued
Jan 17, 2008
Final sign-off
Jun 30, 2008
Declared cost
$2,500
Address
1 Daniel Burnham Ct

unit #330; 4th floor-construction of 1 hr demising wall to divide office space. no mep

Open the permit page