On San Francisco permits
Apr 2018 to Aug 2026

27 permits since 2000 (engineer on 26 permits, architect on 1 permit): 23 completed, 3 in progress, 1 never finaled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Hathaway Dinwiddie Co. (5), Skyline Construction (5), Truebeck Construction (4), Dpr Construction A (2), Novo Construction Inc (2), Western Allied Mechanical Inc. (2), Clune Construction Company L P, Kukbo Design Usa Llc, Sc Builders, Inc
Architects
Levi J Rippy (4), Stanley H Lew (4), Adam Murphy, Daniel Craig Pamperin, David De Valeria, Donnie Lam, Joseph Fay, Kimberly O'dowd, Luda Hoe
Engineers
Joseph W. Fay (9), Robert Nixdorf (6), Hassan Ally (4), Andrew Aw, Barry Wenger, Jiwon Jung, Leo Panian, Mark Koenas

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Aug 5, 2026In progress
issued Sep 2026
1725 03rd StDpr Construction Apartial floor tenant improvement of the 3rd floor.
Details
Permit
202608056076
Permit issued
Sep 10, 2026

partial floor tenant improvement of the 3rd floor.

Open the permit page

$847,440
Jul 22, 2026In progress
issued Oct 2026
4 Embarcadero CenterClune Construction Company L P39th & 40th flrs: tenant improvement including: * selective demolition of offices and pantry * new non-load bearing partitions, ceiling, light fixtures & finishes * new operable partitions
Details
Permit
202606183547
Permit issued
Oct 19, 2026

39th & 40th flrs: tenant improvement including: * selective demolition of offices and pantry * new non-load bearing partitions, ceiling, light fixtures & finishes * new operable partitions

Open the permit page

$3,037,500
Jun 9, 2026Completed
final sign-off Oct 2026
505 Howard StHathaway Dinwiddie Co.mech revisions for 8th floor ti permit # 202510207678.
Details
Permit
202606092839
Permit issued
Jun 12, 2026
Final sign-off
Oct 26, 2026

mech revisions for 8th floor ti permit # 202510207678.

Open the permit page

Nov 17, 2025Completed
final sign-off Oct 2026
505 Howard StHathaway Dinwiddie Co.7th flr - tenant improvement including build out of new open work space, enclosed offices, meeting rooms, and restrooms.
Details
Permit
202510248150
Permit issued
Mar 11, 2026
Final sign-off
Oct 26, 2026

7th flr - tenant improvement including build out of new open work space, enclosed offices, meeting rooms, and restrooms.

Open the permit page

$4,123,250
Nov 10, 2025Completed
final sign-off Sep 2026
505 Howard StHathaway Dinwiddie Co.selective interior demo of (e) parttions, finishes, mep, demo pa linked to the following building applications: l6-202510288253, l7-202510248150, l8 202510207678
Details
Permit
202511109277
Permit issued
Nov 17, 2025
Final sign-off
Sep 30, 2026

selective interior demo of (e) parttions, finishes, mep, demo pa linked to the following building applications: l6-202510288253, l7-202510248150, l8 202510207678

Open the permit page

$275,000
Oct 28, 2025Completed
final sign-off Oct 2026
505 Howard StHathaway Dinwiddie Co.6th flr - tenant improvement including build out of new open work space, enclosed offices, meeting rooms, and restrooms.
Details
Permit
202510288253
Permit issued
Mar 11, 2026
Final sign-off
Oct 26, 2026

6th flr - tenant improvement including build out of new open work space, enclosed offices, meeting rooms, and restrooms.

Open the permit page

$4,163,600
Oct 8, 2025In progress
issued Oct 2025
1725 03rd StDpr Construction Areplacement of (e) duct supports w/ vibration isolator
Details
Permit
202510086979
Permit issued
Oct 14, 2025

replacement of (e) duct supports w/ vibration isolator

Open the permit page

$15,000
Jul 15, 2025Completed
final sign-off Jan 2026
1655 03rd StWestern Allied Mechanical Inc.floor 8-11: new mechanical dampers (bdlg mb4)
Details
Permit
202507150832
Permit issued
Jul 24, 2025
Final sign-off
Jan 6, 2026

floor 8-11: new mechanical dampers (bdlg mb4)

Open the permit page

$14,000
Jul 15, 2025Completed
final sign-off Jan 2026
1725 03rd StWestern Allied Mechanical Inc.floor 8-11: new mechanical dampers (bdlg mb4)
Details
Permit
202507150830
Permit issued
Jul 24, 2025
Final sign-off
Jan 6, 2026

floor 8-11: new mechanical dampers (bdlg mb4)

Open the permit page

$14,000
Oct 16, 2024Completed
final sign-off Aug 2025
555 California StTruebeck Construction6th fl mep defferal submital for pa # 2024-0816-8893
Details
Permit
202410163079
Permit issued
Dec 18, 2024
Final sign-off
Aug 11, 2025

6th fl mep defferal submital for pa # 2024-0816-8893

Open the permit page

$750,000
Jan 31, 2024Completed
final sign-off Feb 2025
300 Grant AvKukbo Design Usa Llc5/f:deferred submittal of mechanical, electrical & plumbing work only. ref ti pa# 202311150842.
Details
Permit
202401314984
Permit issued
Jun 13, 2024
Final sign-off
Feb 10, 2025

5/f:deferred submittal of mechanical, electrical & plumbing work only. ref ti pa# 202311150842.

Open the permit page

$600,000
Aug 16, 2023Completed
final sign-off Apr 2024
888 Brannan StHathaway Dinwiddie Co.4th fl - ti including construction of new non-structural partitions, new accoustical grid & tile ceilings & gyp board ceilings; new electrical & lighting, new finishes throughout, new mech, electrical & plumbing equipment
Details
Permit
202308164591
Permit issued
Sep 13, 2023
Final sign-off
Apr 26, 2024

4th fl - ti including construction of new non-structural partitions, new accoustical grid & tile ceilings & gyp board ceilings; new electrical & lighting, new finishes throughout, new mech, electrical & plumbing equipment

Open the permit page

$1,500,000
May 30, 2023Completed
final sign-off Dec 2023
100 01st StNovo Construction Inc13/f: interior t.i., open office area, meeting rooms, break area and training room. mep included. fire alarm/sprinklers deferred.
Details
Permit
202305308779
Permit issued
Jun 26, 2023
Final sign-off
Dec 13, 2023

13/f: interior t.i., open office area, meeting rooms, break area and training room. mep included. fire alarm/sprinklers deferred.

Open the permit page

$2,500,000
May 10, 2023Completed
final sign-off Jun 2023
300 Grant Av4/f: electrical and mechanical permit for 202304196033. install new lightings and new receptacle. revise (e) mechanical system to serve new conference room.
Details
Permit
202305107522
Permit issued
May 15, 2023
Final sign-off
Jun 23, 2023

4/f: electrical and mechanical permit for 202304196033. install new lightings and new receptacle. revise (e) mechanical system to serve new conference room.

Open the permit page

$47,520
Mar 8, 2023Completed
final sign-off Apr 2023
300 Grant Av4/f: install 2a/c diffuser, install 3 vent grille, ref pa# 202302212296 & 202303012831
Details
Permit
202303083291
Permit issued
Mar 9, 2023
Final sign-off
Apr 20, 2023

4/f: install 2a/c diffuser, install 3 vent grille, ref pa# 202302212296 & 202303012831

Open the permit page

$1,500
Mar 1, 2023Completed
final sign-off Nov 2023
160 Spear StSc Builders, Inc12/f: tenant imrpovement of existing space, minor demo and construction of new non-load bearing walls, ceilings, lighting & furniture.
Details
Permit
202303012833
Permit issued
Apr 26, 2023
Final sign-off
Nov 2, 2023

12/f: tenant imrpovement of existing space, minor demo and construction of new non-load bearing walls, ceilings, lighting & furniture.

Open the permit page

$350,000
Nov 15, 2021Completed
final sign-off Nov 2022
555 California StSkyline Constructionmechanical, electrical, plumbing system for 7th fl tenant improvement 202109178673
Details
Permit
202111152398
Permit issued
Jan 5, 2022
Final sign-off
Nov 4, 2022

mechanical, electrical, plumbing system for 7th fl tenant improvement 202109178673

Open the permit page

Sep 13, 2021Completed
final sign-off Nov 2022
555 California StSkyline Construction4/f:mechanical/electrical/plumbing system, t.i. for bpa#202107194659
Details
Permit
202109138277
Permit issued
Nov 15, 2021
Final sign-off
Nov 4, 2022

4/f:mechanical/electrical/plumbing system, t.i. for bpa#202107194659

Open the permit page

Sep 13, 2021Completed
final sign-off Nov 2022
555 California StSkyline Constructionmechanical, electrical, plumbing system for 10th fl t.i for pa# 202107194625
Details
Permit
202109138273
Permit issued
Oct 21, 2021
Final sign-off
Nov 4, 2022

mechanical, electrical, plumbing system for 10th fl t.i for pa# 202107194625

Open the permit page

Aug 25, 2021Completed
final sign-off Nov 2022
555 California StSkyline Construction8th floor: mechanical, electrical, and plumbing system. tenant improvement per permit app# 202106253245
Details
Permit
202108257098
Permit issued
Jan 5, 2022
Final sign-off
Nov 4, 2022

8th floor: mechanical, electrical, and plumbing system. tenant improvement per permit app# 202106253245

Open the permit page

$1,135,250
Jul 1, 2021Completed
final sign-off Dec 2022
555 California StSkyline Construction9/f: mechanical,electrical & plumbing system for 9/f. ref t.i. pa 202106243139. maher n/a. fire sprinkler under separate permit
Details
Permit
202107013587
Permit issued
Sep 3, 2021
Final sign-off
Dec 9, 2022

9/f: mechanical,electrical & plumbing system for 9/f. ref t.i. pa 202106243139. maher n/a. fire sprinkler under separate permit

Open the permit page

Jan 29, 2020Never finaled
issued Feb 2020, no final
1515 03rd StTruebeck Constructionmb2 4-7: revision to pa #2015-0824-5062: mb2 level 1-7 bulletin 18: updated smokre control supplement report for ti areas. show added smoke dampers by the base building.
Details
Permit
202001293055
Permit issued
Feb 18, 2020

mb2 4-7: revision to pa #2015-0824-5062: mb2 level 1-7 bulletin 18: updated smokre control supplement report for ti areas. show added smoke dampers by the base building.

Open the permit page

Sep 30, 2019Completed
final sign-off Apr 2021
1515 03rd Stmb2-l1 - revision to previously approved pa #201810032102. scope of work includes revisions to architectural walls, ceilings, structure and mep tsav. maher na
Details
Permit
201909303034
Permit issued
Dec 19, 2019
Final sign-off
Apr 5, 2021

mb2-l1 - revision to previously approved pa #201810032102. scope of work includes revisions to architectural walls, ceilings, structure and mep tsav. maher na

Open the permit page

Jun 20, 2019Completed
final sign-off Apr 2021
1455 03rd StTruebeck Constructionlevel 3 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na
Details
Permit
201906203975
Permit issued
Sep 25, 2019
Final sign-off
Apr 6, 2021

level 3 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na

Open the permit page

$2,300,000
Jun 20, 2019Completed
final sign-off Apr 2021
1455 03rd Stlevel 4 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na
Details
Permit
201906203977
Permit issued
Sep 11, 2019
Final sign-off
Apr 6, 2021

level 4 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na

Open the permit page

$2,400,000
Jun 20, 2019Completed
final sign-off Apr 2021
1455 03rd StTruebeck Constructionlevel 2 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na
Details
Permit
201906203971
Permit issued
Oct 16, 2019
Final sign-off
Apr 5, 2021

level 2 tenant improvement: new interior wall & floor. new finishes, mep, tech, secutiry, & av. maher na

Open the permit page

$2,300,000
Apr 10, 2018Completed
final sign-off Sep 2018
100 01st StNovo Construction Incmechanical & electrical for ti on the 14th fl. ref pa 2018-0312-3385
Details
Permit
201804105959
Permit issued
May 29, 2018
Final sign-off
Sep 25, 2018

mechanical & electrical for ti on the 14th fl. ref pa 2018-0312-3385

Open the permit page