Permit GraphShortlistSan Francisco building permits since 2000

Block 3721, lot 001

100 01st St

City’s use
Commercial Office
Built
1988
Stories
27
Building
460,577 sq ft
Lot
3,750 sq ft
Zoning
C3O
Construction type
A

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

The 200 most recent permits filed for this property.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Nov 9, 2026In progress
filed Nov 2026, not yet issued
100 01st Strenovation of existing restaurant into a take out restaurant including new equipment, lighting, plumbing, finishes and partitions. new entry door included in scope. no other exterior changes.
Details
Permit
202611090540

renovation of existing restaurant into a take out restaurant including new equipment, lighting, plumbing, finishes and partitions. new entry door included in scope. no other exterior changes.

Open the permit page

$125,000
Apr 24, 2026In progress
issued Apr 2026
100 01st StNovo Construction Inc6,7,9,14 & 15th fl - installation of 14 new prior booths (3) on floor 5; (4) on floor 6, (2) on floor 7 (1) on the floor 8, (2) on floor 14 and (2) on floor 15
Details
Permit
202604240035
Permit issued
Apr 28, 2026

6,7,9,14 & 15th fl - installation of 14 new prior booths (3) on floor 5; (4) on floor 6, (2) on floor 7 (1) on the floor 8, (2) on floor 14 and (2) on floor 15

Open the permit page

$50,000
Dec 18, 2025Completed
final sign-off Mar 2026
100 01st StNovo Construction Inc14th floor: 1063 sf interior t.i. consisting of demolition of non-structural partitions finishes upgrades and addition of lighting. mechanical work included.
Details
Permit
202512182178
Permit issued
Dec 22, 2025
Final sign-off
Mar 26, 2026

14th floor: 1063 sf interior t.i. consisting of demolition of non-structural partitions finishes upgrades and addition of lighting. mechanical work included.

Open the permit page

$199,000
Dec 18, 2025Completed
final sign-off Mar 2026
100 01st StNovo Construction Inc15th floor: 1000 sf interior t.i. at office suite to include demolition of non-structural partitions replacement of finishes and fixtures in kind.
Details
Permit
202512182174
Permit issued
Dec 23, 2025
Final sign-off
Mar 26, 2026

15th floor: 1000 sf interior t.i. at office suite to include demolition of non-structural partitions replacement of finishes and fixtures in kind.

Open the permit page

$145,000
Nov 24, 2025Completed
final sign-off Dec 2025
100 01st StCodesign Llcinstall (4) anchored phone booths - ref pa# 202509115108 - 25th floor
Details
Permit
202511240351
Permit issued
Nov 25, 2025
Final sign-off
Dec 2, 2025

install (4) anchored phone booths - ref pa# 202509115108 - 25th floor

Open the permit page

$3,500
Oct 16, 2025Completed
final sign-off Oct 2025
100 01st StBilcor Inc25th fl - relocate (2) ceiling mount speaker strobes. arch ref#: 202509115108.
Details
Permit
202510167475
Permit issued
Oct 16, 2025
Final sign-off
Oct 24, 2025

25th fl - relocate (2) ceiling mount speaker strobes. arch ref#: 202509115108.

Open the permit page

$1,332
Oct 1, 2025In progress
issued Oct 2025
100 01st StFire Stop Sprinkler Company25/fl- relocate 3 pendent heads
Details
Permit
202510016460
Permit issued
Oct 1, 2025

25/fl- relocate 3 pendent heads

Open the permit page

$7,672
Sep 11, 2025Completed
final sign-off Oct 2025
100 01st StCodesign Llc25/fl-interior renovation to (e) office suite to include (n) office, expand pantry area and update finishes. no change to occupancy, use, or egress. no structural or remodel of exterior
Details
Permit
202509115108
Permit issued
Sep 15, 2025
Final sign-off
Oct 31, 2025

25/fl-interior renovation to (e) office suite to include (n) office, expand pantry area and update finishes. no change to occupancy, use, or egress. no structural or remodel of exterior

Open the permit page

$391,853
Jul 21, 2025Completed
final sign-off Jun 2026
100 01st StEmcor Services/Mesa Energy Systems Incproject consists of the replacement of 1 chiller, chilled waterpump and condenser water pump in the basement. mechanical and electrical capacity will match the existing equipment. weight of the new equipmet are equal or less in weight than the existing equipment.
Details
Permit
202507211251
Permit issued
Aug 12, 2025
Final sign-off
Jun 23, 2026

project consists of the replacement of 1 chiller, chilled waterpump and condenser water pump in the basement. mechanical and electrical capacity will match the existing equipment. weight of the new equipmet are equal or less in weight than the existing equipment.

Open the permit page

$856,000
Aug 13, 2024Completed
final sign-off Aug 2024
100 01st StBilcor Incinstall 1 duct detector, install 1 control relay ref pa 202403208233
Details
Permit
202408138499
Permit issued
Aug 13, 2024
Final sign-off
Aug 29, 2024

install 1 duct detector, install 1 control relay ref pa 202403208233

Open the permit page

$1,332
Mar 20, 2024Completed
final sign-off Sep 2024
100 01st StRichlen Constructionrestaurant tenant improvement. take out restaurant includes new prep & dishwashing, new electrical and plumbing, mechanical systems, finishes & equipment. no exterior changes
Details
Permit
202403208233
Permit issued
Jun 21, 2024
Final sign-off
Sep 17, 2024

restaurant tenant improvement. take out restaurant includes new prep & dishwashing, new electrical and plumbing, mechanical systems, finishes & equipment. no exterior changes

Open the permit page

$75,000
Jan 30, 2024In progress
filed Jan 2024, not yet issued
100 01st StNovo Construction Inc14/f: installation of (2) phone booths and (2) double phone booths. 13/f: installation of (1) phone booth and (1) nook.
Details
Permit
202401304891

14/f: installation of (2) phone booths and (2) double phone booths. 13/f: installation of (1) phone booth and (1) nook.

Open the permit page

$50,000
Nov 2, 2023Completed
final sign-off Dec 2023
100 01st StTrue North Signs & Graphic Servicesinstall (5) evacuation plans for the 13th fl. all work is indoors.
Details
Permit
202311020055
Permit issued
Nov 6, 2023
Final sign-off
Dec 11, 2023

install (5) evacuation plans for the 13th fl. all work is indoors.

Open the permit page

$2,000
Aug 22, 2023Completed
final sign-off Sep 2023
100 01st StSabah International Incorporated14/f: f/a t.i., ref bpa#202306139924
Details
Permit
202308224902
Permit issued
Aug 22, 2023
Final sign-off
Sep 29, 2023

14/f: f/a t.i., ref bpa#202306139924

Open the permit page

$18,999
Aug 11, 2023Completed
final sign-off Dec 2024
100 01st StPioneer Fire Inc.14/f: relocate (11) sprinkler heads. ref ti permit 202306139924
Details
Permit
202308114196
Permit issued
Aug 11, 2023
Final sign-off
Dec 11, 2024

14/f: relocate (11) sprinkler heads. ref ti permit 202306139924

Open the permit page

$1,527
Jul 21, 2023Completed
final sign-off Oct 2023
100 01st StPioneer Fire Inc.13/f: relocate (52) pendent heads, add (2) pendent heads, (5) upgrights, convert (78) heads to upright. ref bpa#202305308779
Details
Permit
202307212668
Permit issued
Jul 25, 2023
Final sign-off
Oct 23, 2023

13/f: relocate (52) pendent heads, add (2) pendent heads, (5) upgrights, convert (78) heads to upright. ref bpa#202305308779

Open the permit page

$19,200
Jun 13, 2023Completed
final sign-off Nov 2023
100 01st StNovo Construction Inc14/f: t.i., open office area, meeting rooms, storage area. sprinkler & f/a deferred
Details
Permit
202306139924
Permit issued
Jun 23, 2023
Final sign-off
Nov 27, 2023

14/f: t.i., open office area, meeting rooms, storage area. sprinkler & f/a deferred

Open the permit page

$400,000
May 30, 2023Completed
final sign-off Dec 2023
100 01st StNovo Construction Inc13/f: interior t.i., open office area, meeting rooms, break area and training room. mep included. fire alarm/sprinklers deferred.
Details
Permit
202305308779
Permit issued
Jun 26, 2023
Final sign-off
Dec 13, 2023

13/f: interior t.i., open office area, meeting rooms, break area and training room. mep included. fire alarm/sprinklers deferred.

Open the permit page

$2,500,000
Oct 18, 2022Completed
final sign-off Feb 2023
100 01st StPioneer Fire Inc.26th fl: relocate (46) pendents, (7) uprights, add (4) pendents, (16) uprights, convert (11) uprights, (13) pendents, remove (6) pendents, (1) upright gfci# 202208251245. install (n) pre-action for it rm#2643.
Details
Permit
202210184530
Permit issued
Oct 18, 2022
Final sign-off
Feb 21, 2023

26th fl: relocate (46) pendents, (7) uprights, add (4) pendents, (16) uprights, convert (11) uprights, (13) pendents, remove (6) pendents, (1) upright gfci# 202208251245. install (n) pre-action for it rm#2643.

Open the permit page

$55,545
Aug 25, 2022Completed
final sign-off Apr 2023
100 01st StField Construction Inc.26/f: interior demo of partitions, doors, finishes, ceilings, lighting, mechanical/electrical. new constr of partitions, lighting, ceilings, mechanical/electrical, plumbing & finishes. life safety/sprinkler permits deferred.
Details
Permit
202208251245
Permit issued
Sep 15, 2022
Final sign-off
Apr 17, 2023

26/f: interior demo of partitions, doors, finishes, ceilings, lighting, mechanical/electrical. new constr of partitions, lighting, ceilings, mechanical/electrical, plumbing & finishes. life safety/sprinkler permits deferred.

Open the permit page

$2,217,200
Aug 19, 2022Never finaled
issued Aug 2022, no final
100 01st StPioneer Fire Inc.13/f: relocate 47 (e) pendent sprinlker using 1in outlet due to new wall & ceiling configuration. reloc 81 to uprights. total 128 heads. ref t.i. pa 202205124064.
Details
Permit
202208190875
Permit issued
Aug 23, 2022

13/f: relocate 47 (e) pendent sprinlker using 1in outlet due to new wall & ceiling configuration. reloc 81 to uprights. total 128 heads. ref t.i. pa 202205124064.

Open the permit page

$9,400
May 12, 2022Never finaled
issued Jun 2022, no final
100 01st StNovo Construction Incdemo of (e) partitions, ceilings, mech and elec. construction of new partitons, ceilings, mechanical and elec life saety fire sprinkler under sep permit
Details
Permit
202205124064
Permit issued
Jun 3, 2022

demo of (e) partitions, ceilings, mech and elec. construction of new partitons, ceilings, mechanical and elec life saety fire sprinkler under sep permit

Open the permit page

$2,100,000
Feb 28, 2022Completed
final sign-off May 2023
100 01st StMsr Mechanical Llcbasement level: in-kind chiller replacement
Details
Permit
202202288820
Permit issued
Mar 8, 2022
Final sign-off
May 25, 2023

basement level: in-kind chiller replacement

Open the permit page

$168,000
Sep 29, 2020Completed
final sign-off Dec 2020
100 01st StTrue North Signs & Graphic Servicesevacuation plaques interior to the building(not visible from exterior)
Details
Permit
202009295471
Permit issued
Nov 13, 2020
Final sign-off
Dec 14, 2020

evacuation plaques interior to the building(not visible from exterior)

Open the permit page

$1,400
Sep 28, 2020Completed
final sign-off Oct 2020
100 01st StAyoob & Peery Plumbing Co Inc16th flr add 7 and change out 146 sprinklers to conform with the new wall/ceiling layout of the ti. job #20-603
Details
Permit
202009285334
Permit issued
Oct 14, 2020
Final sign-off
Oct 27, 2020

16th flr add 7 and change out 146 sprinklers to conform with the new wall/ceiling layout of the ti. job #20-603

Open the permit page

$36,525
Aug 5, 2020Completed
final sign-off Oct 2020
100 01st StArrow Sign Companyinstall new bracket at sign connection as extg bracket interferes with window washing equipment. ref app#201804206963
Details
Permit
202008051184
Permit issued
Aug 11, 2020
Final sign-off
Oct 2, 2020

install new bracket at sign connection as extg bracket interferes with window washing equipment. ref app#201804206963

Open the permit page

$4,800
Mar 10, 2020Completed
final sign-off Aug 2020
100 01st StTrue North Signs & Graphic Services24th fl: (4) evacuation signs - all work indoors.
Details
Permit
202003106631
Permit issued
Mar 10, 2020
Final sign-off
Aug 11, 2020

24th fl: (4) evacuation signs - all work indoors.

Open the permit page

$1,400
Feb 10, 2020Completed
final sign-off Aug 2020
100 01st StAyoob & Peery Plumbing Co Inc17th fl add 87, relocate 36, plug 6 sprinklers to conform with the new wall ceiling layout of ti ref 201912230293
Details
Permit
202002104013
Permit issued
Feb 14, 2020
Final sign-off
Aug 10, 2020

17th fl add 87, relocate 36, plug 6 sprinklers to conform with the new wall ceiling layout of ti ref 201912230293

Open the permit page

$53,775
Feb 10, 2020Never finaled
issued Feb 2020, no final
100 01st StAyoob & Peery Plumbing Co Inc16th fl relocate add remove sprinklers per ti. 86 relocates, 74 adds, 29 removes
Details
Permit
202002104014
Permit issued
Feb 14, 2020

16th fl relocate add remove sprinklers per ti. 86 relocates, 74 adds, 29 removes

Open the permit page

$58,200
Feb 10, 2020Completed
final sign-off Oct 2020
100 01st StAyoob & Peery Plumbing Co Inc12th floor: add relocate, plug, change out sprinklers per tenant improvement. 1 add, 35 change outs, 3 relocates, 10 plugs, ref 202002053557
Details
Permit
202002104012
Permit issued
Feb 14, 2020
Final sign-off
Oct 15, 2020

12th floor: add relocate, plug, change out sprinklers per tenant improvement. 1 add, 35 change outs, 3 relocates, 10 plugs, ref 202002053557

Open the permit page

$9,079
Feb 6, 2020Completed
final sign-off Apr 2020
100 01st StPioneer Fire Inc.fire sprinkler for 24th fl: relocate 13 pendents, 2 uprights, add 1 pendent. ti 201912169599
Details
Permit
202002063724
Permit issued
Feb 6, 2020
Final sign-off
Apr 30, 2020

fire sprinkler for 24th fl: relocate 13 pendents, 2 uprights, add 1 pendent. ti 201912169599

Open the permit page

$8,000
Feb 5, 2020Completed
final sign-off Oct 2020
100 01st StNovo Construction Incpartial floor interior demo 12th fl ab-017
Details
Permit
202002053557
Permit issued
Feb 20, 2020
Final sign-off
Oct 1, 2020

partial floor interior demo 12th fl ab-017

Open the permit page

$22,000
Feb 5, 2020Completed
final sign-off Oct 2020
100 01st StNovo Construction Increv to pa# 201912230290; revision to demo
Details
Permit
202002053564
Permit issued
Feb 6, 2020
Final sign-off
Oct 22, 2020

rev to pa# 201912230290; revision to demo

Open the permit page

Dec 23, 2019Never finaled
issued Feb 2020, no final
100 01st StNovo Construction Incpartial floor ti on the 12th fl - to include new partitions, ceiling, lighting, finishes. mep included.
Details
Permit
201912230297
Permit issued
Feb 25, 2020

partial floor ti on the 12th fl - to include new partitions, ceiling, lighting, finishes. mep included.

Open the permit page

$1,755,675
Dec 23, 2019Completed
final sign-off Sep 2020
100 01st StNovo Construction Incfull floor tenant improvement on the 17th fl to oinclude new partitions, ceiling, lighting, finishes. new caferteria w no prep mep inc
Details
Permit
201912230293
Permit issued
Feb 6, 2020
Final sign-off
Sep 23, 2020

full floor tenant improvement on the 17th fl to oinclude new partitions, ceiling, lighting, finishes. new caferteria w no prep mep inc

Open the permit page

$1,755,675
Dec 23, 2019Never finaled
issued Jan 2020, no final
100 01st StNovo Construction Incfull fl ti on 16th fl to include partitions, ceiling, lighting and finishes. new mothers room, new cafeteria w/no prep. mep included.
Details
Permit
201912230290
Permit issued
Jan 30, 2020

full fl ti on 16th fl to include partitions, ceiling, lighting and finishes. new mothers room, new cafeteria w/no prep. mep included.

Open the permit page

$1,755,675
Dec 16, 2019Completed
final sign-off Aug 2020
100 01st StNovo Construction Inct.i. improvement to include finishes, ligthing furniture power/data
Details
Permit
201912169599
Permit issued
Dec 31, 2019
Final sign-off
Aug 28, 2020

t.i. improvement to include finishes, ligthing furniture power/data

Open the permit page

$150,000
Nov 26, 2019Never finaled
issued Dec 2019, no final
100 01st StMc Millan Security Systems Incproposed installation of delayed egress hardware on new card reader door
Details
Permit
201911268214
Permit issued
Dec 16, 2019

proposed installation of delayed egress hardware on new card reader door

Open the permit page

$5,500
Oct 15, 2019Never finaled
issued Oct 2019, no final
100 01st StNovo Construction Increvision to pa# 201810163342: to show new location of air transfer duct
Details
Permit
201910154415
Permit issued
Oct 16, 2019

revision to pa# 201810163342: to show new location of air transfer duct

Open the permit page

Aug 5, 2019Completed
final sign-off Mar 2020
100 01st StSabah International Incorporated6th & 8th flr - as built for 201811216526 show (e) in duct smk det at (e) fsd not shown on original package
Details
Permit
201908057861
Permit issued
Oct 29, 2019
Final sign-off
Mar 10, 2020

6th & 8th flr - as built for 201811216526 show (e) in duct smk det at (e) fsd not shown on original package

Open the permit page

Jul 18, 2019Completed
final sign-off Aug 2019
100 01st StNovo Construction Increvision to pa #201810163342 to add fsd. 6th floor
Details
Permit
201907186223
Permit issued
Jul 22, 2019
Final sign-off
Aug 28, 2019

revision to pa #201810163342 to add fsd. 6th floor

Open the permit page

Apr 19, 2019Completed
final sign-off Jun 2019
100 01st StSabah International Incorporatedfire alarm as builts for 201812178467 add 2 smoke detectors for hold-opens at elevator lobby doors.
Details
Permit
201904198512
Permit issued
Apr 19, 2019
Final sign-off
Jun 8, 2019

fire alarm as builts for 201812178467 add 2 smoke detectors for hold-opens at elevator lobby doors.

Open the permit page

Apr 19, 2019Completed
final sign-off Jun 2019
100 01st StSabah International Incorporatedfire alarm as built for 201812178468. add 2 smoke detectors for mag hold opens outside elevator lobby.
Details
Permit
201904198514
Permit issued
Apr 19, 2019
Final sign-off
Jun 8, 2019

fire alarm as built for 201812178468. add 2 smoke detectors for mag hold opens outside elevator lobby.

Open the permit page

Apr 10, 2019Completed
final sign-off Jun 2019
100 01st StSabah International Incorporatedas built submittal to 201812249061. add 2 smoke detectors at elevator lobby doors and 1 duct detector for new fsd along wi 1 dual monitor module to monitor open and closed status
Details
Permit
201904107546
Permit issued
Apr 10, 2019
Final sign-off
Jun 8, 2019

as built submittal to 201812249061. add 2 smoke detectors at elevator lobby doors and 1 duct detector for new fsd along wi 1 dual monitor module to monitor open and closed status

Open the permit page

Mar 21, 2019Completed
final sign-off Mar 2020
100 01st StSabah International Incorporatedprovide a new 2 way emergency comm system 4th fl - 2018-0807-6647, 5th - 2018-0711-4230, 6th fl - 2018-0827-8372, 7th fl - 2018-0807-6656, 8th fl - 2018-0827-8375, 9th fl - 2018-0907-9414, 10th 2018-0711-4231, 11th fl - 2018-0914-0234, 14th - 2018-0312-3385, 15th fl - 2018-0807-6649
Details
Permit
201903215856
Permit issued
Mar 21, 2019
Final sign-off
Mar 12, 2020

provide a new 2 way emergency comm system 4th fl - 2018-0807-6647, 5th - 2018-0711-4230, 6th fl - 2018-0827-8372, 7th fl - 2018-0807-6656, 8th fl - 2018-0827-8375, 9th fl - 2018-0907-9414, 10th 2018-0711-4231, 11th fl - 2018-0914-0234, 14th - 2018-0312-3385, 15th fl - 2018-0807-6649

Open the permit page

$27,000
Dec 24, 2018Completed
final sign-off Jun 2019
100 01st StSabah International Incorporatedref pa# 201808076649; modify (e) fire alarm system, add 1 booster power supply, 4 smoike detectors, 18 duct smoke detectores, 17 high power control relays, 4 single input modules, 2 synchronization modules, 56 ceiling speaker/strobes, 5 speaker, 4 fire smoke dampers
Details
Permit
201812249061
Permit issued
Dec 24, 2018
Final sign-off
Jun 8, 2019

ref pa# 201808076649; modify (e) fire alarm system, add 1 booster power supply, 4 smoike detectors, 18 duct smoke detectores, 17 high power control relays, 4 single input modules, 2 synchronization modules, 56 ceiling speaker/strobes, 5 speaker, 4 fire smoke dampers

Open the permit page

$23,693
Dec 17, 2018Completed
final sign-off Jun 2019
100 01st StSabah International Incorporated4th fl - add 1 booster power supply, 13 photo smoke duct detectors, 14 control relays, 2 sync output modules, 62 speakers/strobes, 3 speakers(repl existing). ref pa 2018-0807-6647
Details
Permit
201812178467
Permit issued
Dec 17, 2018
Final sign-off
Jun 8, 2019

4th fl - add 1 booster power supply, 13 photo smoke duct detectors, 14 control relays, 2 sync output modules, 62 speakers/strobes, 3 speakers(repl existing). ref pa 2018-0807-6647

Open the permit page

$23,693
Dec 17, 2018Completed
final sign-off Aug 2019
100 01st StSabah International Incorporated7th fl - add 1 booster power supply, 13 photo smoke duct detectors, 1 pull station, 14 control relays, 2 sync output modules, 58 speakers/strobes, 4 speakers (repl existing). ref pa 2018-0807-6656
Details
Permit
201812178468
Permit issued
Dec 17, 2018
Final sign-off
Aug 23, 2019

7th fl - add 1 booster power supply, 13 photo smoke duct detectors, 1 pull station, 14 control relays, 2 sync output modules, 58 speakers/strobes, 4 speakers (repl existing). ref pa 2018-0807-6656

Open the permit page

$23,693
Dec 5, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc4th fl - revision to pa 2018-0807-6647 to change storage to utility closet 426. ref pa 2018-0807-6647
Details
Permit
201812057473
Permit issued
Dec 5, 2018
Final sign-off
Aug 27, 2019

4th fl - revision to pa 2018-0807-6647 to change storage to utility closet 426. ref pa 2018-0807-6647

Open the permit page

Nov 26, 2018Completed
final sign-off May 2019
100 01st StNovo Construction Inc1st flr. led display wall installation incl structural supports at ground floor building lobby. no exterior work.
Details
Permit
201811266649
Permit issued
Nov 28, 2018
Final sign-off
May 2, 2019

1st flr. led display wall installation incl structural supports at ground floor building lobby. no exterior work.

Open the permit page

$24,000
Nov 21, 2018Completed
final sign-off Nov 2019
100 01st StSabah International Incorporatedmodify existing fire alarm system. add(2) booster power supplies,(10)smoke detectors,(35)duct smoke detectors,(30) high power control relays,(11)dual input modules,(4) synch medules,(113) ceiling speakers/strobes,add(7)ceiling speakes,(9) fire smoke dampers.ref #201808278372 & 201708278375
Details
Permit
201811216526
Permit issued
Dec 17, 2018
Final sign-off
Nov 1, 2019

modify existing fire alarm system. add(2) booster power supplies,(10)smoke detectors,(35)duct smoke detectors,(30) high power control relays,(11)dual input modules,(4) synch medules,(113) ceiling speakers/strobes,add(7)ceiling speakes,(9) fire smoke dampers.ref #201808278372 & 201708278375

Open the permit page

$47,625
Nov 16, 2018Never finaled
issued Nov 2018, no final
100 01st StTrue North Signs & Graphic Servicesinstall 36 evacuation maps
Details
Permit
201811166065
Permit issued
Nov 16, 2018

install 36 evacuation maps

Open the permit page

$12,600
Oct 31, 2018Completed
final sign-off Jan 2020
100 01st StNovo Construction Inc6th flr, t.i - electrical, mechanical, plumbing, ref pa#201808278372
Details
Permit
201810314575
Permit issued
Oct 31, 2018
Final sign-off
Jan 16, 2020

6th flr, t.i - electrical, mechanical, plumbing, ref pa#201808278372

Open the permit page

$250,000
Oct 29, 2018Completed
final sign-off Mar 2019
100 01st StNovo Construction Inc8th flr, fitness room. structural work for trx support ref: pa# 201808278375
Details
Permit
201810294355
Permit issued
Oct 29, 2018
Final sign-off
Mar 6, 2019

8th flr, fitness room. structural work for trx support ref: pa# 201808278375

Open the permit page

$2,000
Oct 26, 2018Completed
final sign-off Jan 2019
100 01st StGci, Inc24/f:demo of (e) partitions, ceiling, lighting, finishes, & any associated mep in a full floor unoccupied office space. per ab-017, space will remain unoccupied.f/s sep permit pa201810052403. maher n/a.
Details
Permit
201810264286
Permit issued
Oct 29, 2018
Final sign-off
Jan 3, 2019

24/f:demo of (e) partitions, ceiling, lighting, finishes, & any associated mep in a full floor unoccupied office space. per ab-017, space will remain unoccupied.f/s sep permit pa201810052403. maher n/a.

Open the permit page

$40,000
Oct 19, 2018Expired or cancelled
cancelled Jan 2026
100 01st StNovo Construction Incstructural work on the 15th fl
Details
Permit
201810193656

structural work on the 15th fl

Open the permit page

Oct 16, 2018Completed
final sign-off Feb 2019
100 01st Ststructural work only. stregthening (e) beams under 5th flr, "all hands room"
Details
Permit
201810163341
Permit issued
Oct 29, 2018
Final sign-off
Feb 14, 2019

structural work only. stregthening (e) beams under 5th flr, "all hands room"

Open the permit page

$10,000
Oct 16, 2018Completed
final sign-off Jan 2020
100 01st StNovo Construction Inc8th flr. mechanical and electrical, electrical, mechanical and plumbing for tenant improvement
Details
Permit
201810163342
Permit issued
Oct 22, 2018
Final sign-off
Jan 9, 2020

8th flr. mechanical and electrical, electrical, mechanical and plumbing for tenant improvement

Open the permit page

Oct 16, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc14th flr. elevator lobby upgrade. removal of (e) lobby doors access control devices. (n) 1-hour rated glass doors, (n) access control and emergency door release
Details
Permit
201810163340
Permit issued
Oct 29, 2018
Final sign-off
Aug 27, 2019

14th flr. elevator lobby upgrade. removal of (e) lobby doors access control devices. (n) 1-hour rated glass doors, (n) access control and emergency door release

Open the permit page

$50,000
Oct 5, 2018Completed
final sign-off Dec 2018
100 01st StAyoob & Peery Plumbing Co Inc24th fl - add 4, relocate 20, change out (43) and plug (8) sprinklers to conform with the new wall ceiling layout of ti
Details
Permit
201810052403
Permit issued
Oct 11, 2018
Final sign-off
Dec 4, 2018

24th fl - add 4, relocate 20, change out (43) and plug (8) sprinklers to conform with the new wall ceiling layout of ti

Open the permit page

$16,175
Oct 3, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incmechanical, electrical, & plumbing for tenant improvement on 5th fl. ref arch #201807114230.
Details
Permit
201810032093
Permit issued
Oct 23, 2018
Final sign-off
Aug 27, 2019

mechanical, electrical, & plumbing for tenant improvement on 5th fl. ref arch #201807114230.

Open the permit page

Oct 1, 2018Completed
final sign-off Jul 2019
100 01st StAyoob & Peery Plumbing Co Inc8th flr - add 52, relocate 119, and plug 45 sprinklers in order to conform to the new wall/ceiling layout of the ti ref 201808278375
Details
Permit
201810011889
Permit issued
Oct 5, 2018
Final sign-off
Jul 24, 2019

8th flr - add 52, relocate 119, and plug 45 sprinklers in order to conform to the new wall/ceiling layout of the ti ref 201808278375

Open the permit page

$54,075
Oct 1, 2018Completed
final sign-off Dec 2018
100 01st StAyoob & Peery Plumbing Co Inc6th flr - add 98, relocate 106, and plug 20 sprinklers. install 2 new fhu's in order to conform to the new wall/ceiling layout of the ti ref 201808278372
Details
Permit
201810011887
Permit issued
Oct 5, 2018
Final sign-off
Dec 4, 2018

6th flr - add 98, relocate 106, and plug 20 sprinklers. install 2 new fhu's in order to conform to the new wall/ceiling layout of the ti ref 201808278372

Open the permit page

$75,300
Sep 25, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incmechanical and electrical plumbing for tenant improvemnt 7th fl ref 201808076656
Details
Permit
201809251348
Permit issued
Sep 26, 2018
Final sign-off
Aug 27, 2019

mechanical and electrical plumbing for tenant improvemnt 7th fl ref 201808076656

Open the permit page

Sep 25, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incmechanical and electrical plumbing for tenant improvemnt 15th fl ref 201808076649
Details
Permit
201809251349
Permit issued
Nov 28, 2018
Final sign-off
Aug 27, 2019

mechanical and electrical plumbing for tenant improvemnt 15th fl ref 201808076649

Open the permit page

Sep 24, 2018Completed
final sign-off Dec 2018
100 01st StAyoob & Peery Plumbing Co Inc7th flr. add 120, relocate 120 and plug 54 sprinklers to conform w/ new wall / ceiling layout of t.i
Details
Permit
201809241251
Permit issued
Sep 27, 2018
Final sign-off
Dec 4, 2018

7th flr. add 120, relocate 120 and plug 54 sprinklers to conform w/ new wall / ceiling layout of t.i

Open the permit page

$90,000
Sep 24, 2018Completed
final sign-off Mar 2019
100 01st StNovo Construction Inctenant improvement of existing interstitial stairs between floors 14th and 15th. to include new guard rails, handrails finishes. structural work to support of new glass guardrail.
Details
Permit
201809241195
Permit issued
Oct 23, 2018
Final sign-off
Mar 6, 2019

tenant improvement of existing interstitial stairs between floors 14th and 15th. to include new guard rails, handrails finishes. structural work to support of new glass guardrail.

Open the permit page

$147,952
Sep 24, 2018Completed
final sign-off Nov 2018
100 01st StAyoob & Peery Plumbing Co Inc4th flr. add 124, relocate 199 and plug 50 sprinklers to conform w/ new wall / ceiling layout of t.i
Details
Permit
201809241248
Permit issued
Sep 27, 2018
Final sign-off
Nov 7, 2018

4th flr. add 124, relocate 199 and plug 50 sprinklers to conform w/ new wall / ceiling layout of t.i

Open the permit page

$91,775
Sep 24, 2018Completed
final sign-off Mar 2019
100 01st StNovo Construction Inctenant improvement of existing interstitial stairs between floors 5th and 6th. to include new guard rails, handrails finishes. structural scope is limited to support of new glass guardrail.
Details
Permit
201809241197
Permit issued
Oct 4, 2018
Final sign-off
Mar 6, 2019

tenant improvement of existing interstitial stairs between floors 5th and 6th. to include new guard rails, handrails finishes. structural scope is limited to support of new glass guardrail.

Open the permit page

$47,952
Sep 24, 2018Completed
final sign-off Dec 2018
100 01st StAyoob & Peery Plumbing Co Inc15th flr. add 99, relocate 100 and plug 59 sprinklers to conform w/ new wall / ceiling layout of t.i.
Details
Permit
201809241253
Permit issued
Oct 5, 2018
Final sign-off
Dec 4, 2018

15th flr. add 99, relocate 100 and plug 59 sprinklers to conform w/ new wall / ceiling layout of t.i.

Open the permit page

$74,500
Sep 14, 2018Completed
final sign-off Oct 2018
100 01st StAyoob & Peery Plumbing Co Inc11th fl - add 89, relocate 117, and plug 9 sprinklers to conform with the new wall/ceiling layout of the ti ref pa 2018-0711-4231 #18-671
Details
Permit
201809140234
Permit issued
Sep 21, 2018
Final sign-off
Oct 26, 2018

11th fl - add 89, relocate 117, and plug 9 sprinklers to conform with the new wall/ceiling layout of the ti ref pa 2018-0711-4231 #18-671

Open the permit page

$73,050
Sep 14, 2018Completed
final sign-off Jul 2019
100 01st StAyoob & Peery Plumbing Co Inc5th fl - add 104, relocate 114 and plug 16 sprinklers. tie in 2 new fhv into the existing standpipes in order to conform with the new wall/ceiling layout of the ti ref pa 2018-0711-4231 #18-671
Details
Permit
201809140232
Permit issued
Sep 21, 2018
Final sign-off
Jul 24, 2019

5th fl - add 104, relocate 114 and plug 16 sprinklers. tie in 2 new fhv into the existing standpipes in order to conform with the new wall/ceiling layout of the ti ref pa 2018-0711-4231 #18-671

Open the permit page

$80,250
Sep 14, 2018Completed
final sign-off Oct 2018
100 01st StAyoob & Peery Plumbing Co Inc10th fl - add 105, relocate 106 and 24 sprinklers in order to conform with the new wall/ceiling layout of the ti. ref pa 2018-0711-4231 #18-671
Details
Permit
201809140227
Permit issued
Sep 21, 2018
Final sign-off
Oct 24, 2018

10th fl - add 105, relocate 106 and 24 sprinklers in order to conform with the new wall/ceiling layout of the ti. ref pa 2018-0711-4231 #18-671

Open the permit page

$78,975
Sep 7, 2018Completed
final sign-off Dec 2018
100 01st StAyoob & Peery Plumbing Co Inc9th fl - add 105, relocate 109 and plug 16 sprinklers in order to conform with new wall/ceiling layout of the ti. ref pa 2018-0711-4234 #18-671
Details
Permit
201809079414
Permit issued
Sep 26, 2018
Final sign-off
Dec 4, 2018

9th fl - add 105, relocate 109 and plug 16 sprinklers in order to conform with new wall/ceiling layout of the ti. ref pa 2018-0711-4234 #18-671

Open the permit page

$79,650
Aug 27, 2018Completed
final sign-off Jan 2020
100 01st StNovo Construction Inc6th flr -full flr ti: new partitions, ceiling and finishes, new gender neutral restroom, new 2-hr fire rated horizontal exit. mep/fire/life safety under sep permit add a-2 occupancy dining area
Details
Permit
201808278372
Permit issued
Oct 16, 2018
Final sign-off
Jan 16, 2020

6th flr -full flr ti: new partitions, ceiling and finishes, new gender neutral restroom, new 2-hr fire rated horizontal exit. mep/fire/life safety under sep permit add a-2 occupancy dining area

Open the permit page

$1,734,534
Aug 27, 2018Completed
final sign-off Jan 2020
100 01st StNovo Construction Inc8th flr -full flr ti: new partitions, ceiling and finishes, new gender neutral restroom, new 2-hr fire rated horizontal exit for egress compliance. mep/fire/life safety under sep permit
Details
Permit
201808278375
Permit issued
Oct 1, 2018
Final sign-off
Jan 16, 2020

8th flr -full flr ti: new partitions, ceiling and finishes, new gender neutral restroom, new 2-hr fire rated horizontal exit for egress compliance. mep/fire/life safety under sep permit

Open the permit page

$1,448,928
Aug 22, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc9th fl - mechanical, electrical & plumbing. ref pa 2018-0711-4234
Details
Permit
201808228002
Permit issued
Aug 23, 2018
Final sign-off
Aug 27, 2019

9th fl - mechanical, electrical & plumbing. ref pa 2018-0711-4234

Open the permit page

Aug 22, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc10th fl - mechanical, electrical and plumbing for tenant improvement. ref pa 2018-0711-4231
Details
Permit
201808228003
Permit issued
Aug 23, 2018
Final sign-off
Aug 27, 2019

10th fl - mechanical, electrical and plumbing for tenant improvement. ref pa 2018-0711-4231

Open the permit page

Aug 17, 2018Completed
final sign-off Sep 2018
100 01st StGolden Gate Fire Protection Inc22nd flr fire sprinkler only -relocate 16 pendent for suite 2200. ref 201807195028
Details
Permit
201808177630
Permit issued
Aug 17, 2018
Final sign-off
Sep 7, 2018

22nd flr fire sprinkler only -relocate 16 pendent for suite 2200. ref 201807195028

Open the permit page

$8,000
Aug 17, 2018Completed
final sign-off Aug 2018
100 01st StSabah International Incorporatedti# 201807194932. add 1 ceiling speaker/strobe. remove 1 ceiling speaker. remove 1 wall mount strobe. add 1 wall mount strobe
Details
Permit
201808177623
Permit issued
Aug 17, 2018
Final sign-off
Aug 27, 2018

ti# 201807194932. add 1 ceiling speaker/strobe. remove 1 ceiling speaker. remove 1 wall mount strobe. add 1 wall mount strobe

Open the permit page

$8,000
Aug 17, 2018Completed
final sign-off Aug 2018
100 01st StGolden Gate Fire Protection Inc2nd flr fire sprinkler only -relocate 1 pendent for new restroom. ref 201806071283
Details
Permit
201808177627
Permit issued
Aug 17, 2018
Final sign-off
Aug 27, 2018

2nd flr fire sprinkler only -relocate 1 pendent for new restroom. ref 201806071283

Open the permit page

$530
Aug 7, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc7th flr. full floor tenant improvement. new partitions, ceilings, lights, and finishes. mep and fire life safety under separate permit
Details
Permit
201808076656
Permit issued
Sep 25, 2018
Final sign-off
Aug 28, 2019

7th flr. full floor tenant improvement. new partitions, ceilings, lights, and finishes. mep and fire life safety under separate permit

Open the permit page

$1,250,000
Aug 7, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incfull floor tenant improvement on 15th fl, new partitions, ceiling, lighting and finishes. mep & fire life safety under sep permit.
Details
Permit
201808076649
Permit issued
Oct 2, 2018
Final sign-off
Aug 28, 2019

full floor tenant improvement on 15th fl, new partitions, ceiling, lighting and finishes. mep & fire life safety under sep permit.

Open the permit page

$1,250,000
Aug 7, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incfull floor tenant improvement on 4th fl, new partitions, ceiling, lighting and finishes. mep deferred. fire alarm and sprinklers under separate permit.
Details
Permit
201808076647
Permit issued
Aug 14, 2018
Final sign-off
Aug 28, 2019

full floor tenant improvement on 4th fl, new partitions, ceiling, lighting and finishes. mep deferred. fire alarm and sprinklers under separate permit.

Open the permit page

$1,250,000
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services5th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026201
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

5th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$19,016
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services15th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026208
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

15th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$21,525
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services11th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026207
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

11th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$18,582
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services10th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026206
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

10th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$21,016
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services7th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026203
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

7th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$18,781
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services9th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026205
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

9th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$17,702
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services8th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026204
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

8th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$19,445
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services6th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026202
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

6th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$19,105
Aug 2, 2018Completed
final sign-off Oct 2018
100 01st StM C S Construction Services4th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations
Details
Permit
201808026199
Permit issued
Aug 2, 2018
Final sign-off
Oct 31, 2018

4th flr - restroom accessibility improvement - toilet, partition modifications, reinstall (e) plm fixtures & accessories to ada compliant locations

Open the permit page

$16,502
Jul 25, 2018Completed
final sign-off Jul 2018
100 01st StGolden Gate Fire Protection Incfire sprinklers: relocate 1 pendent sprinkler and add 1 pendent sprinkler on 3rd floor. t.i. 201-07-19-4932.
Details
Permit
201807255478
Permit issued
Jul 26, 2018
Final sign-off
Jul 31, 2018

fire sprinklers: relocate 1 pendent sprinkler and add 1 pendent sprinkler on 3rd floor. t.i. 201-07-19-4932.

Open the permit page

$2,000
Jul 23, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Incmep for ti on 11th fl. relocate existing. ref pa #201807114240.
Details
Permit
201807235209
Permit issued
Aug 17, 2018
Final sign-off
Aug 27, 2019

mep for ti on 11th fl. relocate existing. ref pa #201807114240.

Open the permit page

Jul 11, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inctenant improvement on the 11th fl. improvements include new partitoins, ceiling, lighting, finishes. mep and fire ls under sep permit
Details
Permit
201807114240
Permit issued
Jul 20, 2018
Final sign-off
Aug 28, 2019

tenant improvement on the 11th fl. improvements include new partitoins, ceiling, lighting, finishes. mep and fire ls under sep permit

Open the permit page

$3,300,000
Jul 11, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc9th fl - full floor arch ti to include new partitions, ceiling, lighting and finishes. mep & fire life safety under separate permit, to include two-way communication systems, also deferred; mep & fire life safety under seperate permit
Details
Permit
201807114234
Permit issued
Aug 2, 2018
Final sign-off
Aug 28, 2019

9th fl - full floor arch ti to include new partitions, ceiling, lighting and finishes. mep & fire life safety under separate permit, to include two-way communication systems, also deferred; mep & fire life safety under seperate permit

Open the permit page

$3,300,000
Jul 11, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inc5/f: tenant improvement to include new partitions, ceilings, lighting, finishes, new gender neutral restroom, and new assembly occupancy spaces. new 2 hour rated exit provided for egress compliance. mep, fire life safety under sep permit
Details
Permit
201807114230
Permit issued
Sep 26, 2018
Final sign-off
Aug 28, 2019

5/f: tenant improvement to include new partitions, ceilings, lighting, finishes, new gender neutral restroom, and new assembly occupancy spaces. new 2 hour rated exit provided for egress compliance. mep, fire life safety under sep permit

Open the permit page

$3,000,000
Jul 11, 2018Expired or cancelled
cancelled Jan 2026
100 01st StNovo Construction Inc14th fl - partial ti to single floor tenant removal of existing elevator lobby doors, removal of access control devices and installation of new 1 hr fire rated glass doos at elevator lobby with access control device. will comply with 10.10.1.9.2
Details
Permit
201807114239

14th fl - partial ti to single floor tenant removal of existing elevator lobby doors, removal of access control devices and installation of new 1 hr fire rated glass doos at elevator lobby with access control device. will comply with 10.10.1.9.2

Open the permit page

$5,000
Jul 11, 2018Completed
final sign-off Aug 2019
100 01st StNovo Construction Inctenant improvement on the 10th fl to include new paritions, ceiling lighting,finishes. mep and fine life safety under sep permit
Details
Permit
201807114231
Permit issued
Aug 2, 2018
Final sign-off
Aug 28, 2019

tenant improvement on the 10th fl to include new paritions, ceiling lighting,finishes. mep and fine life safety under sep permit

Open the permit page

$3,300,000
Jun 4, 2018Completed
final sign-off Jul 2018
100 01st StTrue North Signs & Graphic Services(4) evacuation plaques
Details
Permit
201806040856
Permit issued
Jun 4, 2018
Final sign-off
Jul 23, 2018

(4) evacuation plaques

Open the permit page

$1,400
May 9, 2018Completed
final sign-off Jun 2018
100 01st St14th flr - fire sprinkler permit relocate 60 pendents & 26 uprights, install 40 new pendents and 20 new uprights, delete 18 pendents and 16 uprights. add 2 new 3" hose values at new horizontal exits ref 201803123385
Details
Permit
201805098639
Permit issued
May 10, 2018
Final sign-off
Jun 11, 2018

14th flr - fire sprinkler permit relocate 60 pendents & 26 uprights, install 40 new pendents and 20 new uprights, delete 18 pendents and 16 uprights. add 2 new 3" hose values at new horizontal exits ref 201803123385

Open the permit page

$48,000
Apr 20, 2018Completed
final sign-off May 2019
100 01st StArrow Sign Companyinstall 2 illminated letter sets on building exterior wall mounted single faced. "okta"
Details
Permit
201804206963
Permit issued
Aug 24, 2018
Final sign-off
May 2, 2019

install 2 illminated letter sets on building exterior wall mounted single faced. "okta"

Open the permit page

$9,000
Apr 12, 2018Completed
final sign-off Jun 2018
100 01st StPribuss Engineering Inc1st floor: fire sprinkler t.i. total relocated sprinklers = 1 at 514.00. ref app#201802121005
Details
Permit
201804126147
Permit issued
Apr 12, 2018
Final sign-off
Jun 14, 2018

1st floor: fire sprinkler t.i. total relocated sprinklers = 1 at 514.00. ref app#201802121005

Open the permit page

$514
Apr 10, 2018Completed
final sign-off Sep 2018
100 01st StNovo Construction Incmechanical & electrical for ti on the 14th fl. ref pa 2018-0312-3385
Details
Permit
201804105959
Permit issued
May 29, 2018
Final sign-off
Sep 25, 2018

mechanical & electrical for ti on the 14th fl. ref pa 2018-0312-3385

Open the permit page

Mar 12, 2018Completed
final sign-off Sep 2018
100 01st StNovo Construction Inc14th fl - ti to include 2 hour separation and horizontal existing new partitions, ceiling finishes. new gender neutral restrooms and break room. mep sep permit
Details
Permit
201803123385
Permit issued
Apr 10, 2018
Final sign-off
Sep 25, 2018

14th fl - ti to include 2 hour separation and horizontal existing new partitions, ceiling finishes. new gender neutral restrooms and break room. mep sep permit

Open the permit page

$3,300,000
Feb 26, 2018Completed
final sign-off Aug 2018
100 01st StNovo Construction Inc14/f: full floor demo excluding building core and restrooms//refer sprinkler demo permit #201611152693. per ab-017.
Details
Permit
201802262193
Permit issued
Feb 27, 2018
Final sign-off
Aug 22, 2018

14/f: full floor demo excluding building core and restrooms//refer sprinkler demo permit #201611152693. per ab-017.

Open the permit page

$10,000
Feb 12, 2018Completed
final sign-off Oct 2018
100 01st StField Construction Inc.ste 145. install new exam room in exsisting un-used space of exsisting optometry office.
Details
Permit
201802121005
Permit issued
Apr 4, 2018
Final sign-off
Oct 24, 2018

ste 145. install new exam room in exsisting un-used space of exsisting optometry office.

Open the permit page

$25,000
Dec 1, 2017Completed
final sign-off Feb 2018
100 01st StTrue North Signs & Graphic Services25th flr: 4 evac plaques
Details
Permit
201712015216
Permit issued
Dec 1, 2017
Final sign-off
Feb 6, 2018

25th flr: 4 evac plaques

Open the permit page

$1,400
Oct 11, 2017Never finaled
issued Oct 2017, no final
100 01st StCommercial Interior Builders Inc25th fl: installation of 3 new fan powered boxes with electric heat, 2 new coding only vavs and new low pressure ductwork. one new fire smoke damper. ref 201608316421 & 201706300796.
Details
Permit
201710110860
Permit issued
Oct 17, 2017

25th fl: installation of 3 new fan powered boxes with electric heat, 2 new coding only vavs and new low pressure ductwork. one new fire smoke damper. ref 201608316421 & 201706300796.

Open the permit page

$99,958
Oct 11, 2017Completed
final sign-off Dec 2017
100 01st StCommercial Interior Builders Inc25/f- elevator lobby lighting and controls. ref 201706300796
Details
Permit
201710110862
Permit issued
Oct 11, 2017
Final sign-off
Dec 22, 2017

25/f- elevator lobby lighting and controls. ref 201706300796

Open the permit page

$15,000
Jan 9, 2017Completed
final sign-off Mar 2017
100 01st StCommercial Interior Builders Inc22nd floor: lighting, power, and signal wiring, lighting and receptacle controls. modification of (e) hvac systems to match the new arch. layout. scopes includes new vav box and water source heat pump for the idf closet. new fire smoke damper. ref. arch #2016-1017-0404.
Details
Permit
201701096708
Permit issued
Jan 31, 2017
Final sign-off
Mar 20, 2017

22nd floor: lighting, power, and signal wiring, lighting and receptacle controls. modification of (e) hvac systems to match the new arch. layout. scopes includes new vav box and water source heat pump for the idf closet. new fire smoke damper. ref. arch #2016-1017-0404.

Open the permit page

$60,000
Jan 4, 2017Never finaled
issued Jan 2017, no final
100 01st StTrue North Signs & Graphic Services25th fl - 4 evac maps
Details
Permit
201701046448
Permit issued
Jan 4, 2017

25th fl - 4 evac maps

Open the permit page

$1,200
Nov 9, 2016Never finaled
issued Nov 2016, no final
100 01st StGolden Gate Fire Protection Inc25/f- fire sprinkler only, relocate 45 pendents, add 3 pendents (48 heads). t.i. pa#201608316421
Details
Permit
201611092326
Permit issued
Nov 9, 2016

25/f- fire sprinkler only, relocate 45 pendents, add 3 pendents (48 heads). t.i. pa#201608316421

Open the permit page

$14,100
Oct 17, 2016Completed
final sign-off Mar 2017
100 01st StCommercial Interior Builders Inc22nd floor suite 2250 - partition demolition & finish removal. new non-structural partitions, glazing, doors, ceiling & tiles, less than 10% lighitng additoins, millwork & finishes. mep/life safety/sprinklers deferred.
Details
Permit
201610170404
Permit issued
Nov 10, 2016
Final sign-off
Mar 20, 2017

22nd floor suite 2250 - partition demolition & finish removal. new non-structural partitions, glazing, doors, ceiling & tiles, less than 10% lighitng additoins, millwork & finishes. mep/life safety/sprinklers deferred.

Open the permit page

$200,000
Oct 12, 2016Completed
final sign-off Mar 2017
100 01st StCommercial Interior Builders Incste. #300: lighting and mechanical work per title 24 ref pa 2016-0921-8339 for architectural. no new fire smoke dampers
Details
Permit
201610120016
Permit issued
Oct 14, 2016
Final sign-off
Mar 22, 2017

ste. #300: lighting and mechanical work per title 24 ref pa 2016-0921-8339 for architectural. no new fire smoke dampers

Open the permit page

$176,748
Oct 12, 2016Completed
final sign-off Dec 2017
100 01st StCommercial Interior Builders Incelectrical work per title 24. ref pa 2016-0831-6421
Details
Permit
201610120014
Permit issued
Oct 14, 2016
Final sign-off
Dec 22, 2017

electrical work per title 24. ref pa 2016-0831-6421

Open the permit page

$120,000
Oct 5, 2016Completed
final sign-off Oct 2016
100 01st StGolden Gate Fire Protection Inc3rd floor fire srpinkler only - relocate 19 pendents, add 3 pendents for pix (3rd floor). ref pa 2016-0622-0596
Details
Permit
201610059549
Permit issued
Oct 5, 2016
Final sign-off
Oct 18, 2016

3rd floor fire srpinkler only - relocate 19 pendents, add 3 pendents for pix (3rd floor). ref pa 2016-0622-0596

Open the permit page

$11,550
Sep 21, 2016Completed
final sign-off Mar 2017
100 01st StCommercial Interior Builders Inc3rd fl #300 - re-work of demising partition between (2) suites. demo of (e) lights, ceilings, partitions, finishes. non-structural partitions, glazing, doors, ceilings, lights, millwork and finishes. mep under separate permit
Details
Permit
201609218339
Permit issued
Oct 3, 2016
Final sign-off
Mar 22, 2017

3rd fl #300 - re-work of demising partition between (2) suites. demo of (e) lights, ceilings, partitions, finishes. non-structural partitions, glazing, doors, ceilings, lights, millwork and finishes. mep under separate permit

Open the permit page

$800,000
Aug 31, 2016Completed
final sign-off Dec 2017
100 01st StCommercial Interior Builders Incdemo of existing lights, ceilings, partitoins, finishes. new non structural partitions, glazing, doors, ceilings,light fixtures, millwork, finishes and new smoke guard at elevator doors complying with dbi info sheet fs-07.lobby in high rise.
Details
Permit
201608316421
Permit issued
Sep 6, 2016
Final sign-off
Dec 22, 2017

demo of existing lights, ceilings, partitoins, finishes. new non structural partitions, glazing, doors, ceilings,light fixtures, millwork, finishes and new smoke guard at elevator doors complying with dbi info sheet fs-07.lobby in high rise.

Open the permit page

$725,000
May 27, 2016Completed
final sign-off Jul 2016
100 01st StWolverine Fire Protection Corelocate 63, add 12, and delete 3 sprinklers in office ti on the 12th floor. ref pa 2016-0429-6118
Details
Permit
201605278579
Permit issued
May 31, 2016
Final sign-off
Jul 25, 2016

relocate 63, add 12, and delete 3 sprinklers in office ti on the 12th floor. ref pa 2016-0429-6118

Open the permit page

$30,000
May 9, 2016Completed
final sign-off Aug 2016
100 01st StNovo Construction Incmechanical & electrical work for ti at ste 1250
Details
Permit
201605096876
Permit issued
May 9, 2016
Final sign-off
Aug 30, 2016

mechanical & electrical work for ti at ste 1250

Open the permit page

$20,000
Apr 29, 2016Completed
final sign-off Aug 2016
100 01st StNovo Construction Inc12th flr, suite 1250 tenant improvement to include new partitions ceiling, path of travel upgrades and finishes, mep, life safety and fire sprinkler under separate permit.
Details
Permit
201604296118
Permit issued
May 9, 2016
Final sign-off
Aug 30, 2016

12th flr, suite 1250 tenant improvement to include new partitions ceiling, path of travel upgrades and finishes, mep, life safety and fire sprinkler under separate permit.

Open the permit page

$150,000
Mar 9, 2016Completed
final sign-off Mar 2016
100 01st StGolden Gate Fire Protection Inc22nd floor - fire sprinkler only, relocate 5 pendents for simon kucher & partners 22nd floor. ref pa 2015-1211-4852
Details
Permit
201603091541
Permit issued
Mar 9, 2016
Final sign-off
Mar 17, 2016

22nd floor - fire sprinkler only, relocate 5 pendents for simon kucher & partners 22nd floor. ref pa 2015-1211-4852

Open the permit page

$2,500
Feb 17, 2016Completed
final sign-off Apr 2016
100 01st StGolden Gate Fire Protection Incfire sprinkler ti only. relocate 24 sprinkler pendents, add 1 head total 24 heads for 3rd floor corridor
Details
Permit
201602179736
Permit issued
Feb 17, 2016
Final sign-off
Apr 5, 2016

fire sprinkler ti only. relocate 24 sprinkler pendents, add 1 head total 24 heads for 3rd floor corridor

Open the permit page

$12,500
Jan 22, 2016Never finaled
issued Jan 2016, no final
100 01st StTrue North Signs & Graphic Services4 evacuation plaques
Details
Permit
201601227683
Permit issued
Jan 22, 2016

4 evacuation plaques

Open the permit page

$1,400
Dec 3, 2015Completed
final sign-off Jan 2016
100 01st StGolden Gate Fire Protection Incfire sprinklers; relocate 5 pendent sprinklers on the 12th floor. ref ti 2014-1223-4367
Details
Permit
201512034035
Permit issued
Dec 3, 2015
Final sign-off
Jan 27, 2016

fire sprinklers; relocate 5 pendent sprinklers on the 12th floor. ref ti 2014-1223-4367

Open the permit page

$2,575
Nov 4, 2015Completed
final sign-off Nov 2015
100 01st StGolden Gate Fire Protection Incturn up sprinkler head; change pendents to uprights 64 heads total for the 25th floor. ref pa 2015-0805-3358
Details
Permit
201511041684
Permit issued
Nov 4, 2015
Final sign-off
Nov 13, 2015

turn up sprinkler head; change pendents to uprights 64 heads total for the 25th floor. ref pa 2015-0805-3358

Open the permit page

$32,000
Oct 21, 2015Never finaled
issued Oct 2015, no final
100 01st StGolden Gate Fire Protection Incfire sprinkers, relocate 28 pendents sprinklers on the 3rd fl. relocate 32 upright sprinklers
Details
Permit
201510210337
Permit issued
Oct 21, 2015

fire sprinkers, relocate 28 pendents sprinklers on the 3rd fl. relocate 32 upright sprinklers

Open the permit page

$30,900
Mar 24, 2015Never finaled
issued Mar 2015, no final
100 01st StTrue North Signs & Graphic Services(4) evauation signs for 12th floor.
Details
Permit
201503241711
Permit issued
Mar 24, 2015

(4) evauation signs for 12th floor.

Open the permit page

$1,500
Mar 4, 2015Completed
final sign-off Mar 2015
100 01st StGolden Gate Fire Protection Incfire sprinkler only. relocate 27 sprinkler pendents, add 4, [plug off 10. total 31 sprinkler pendents for the 12th fl
Details
Permit
201503049901
Permit issued
Mar 4, 2015
Final sign-off
Mar 19, 2015

fire sprinkler only. relocate 27 sprinkler pendents, add 4, [plug off 10. total 31 sprinkler pendents for the 12th fl

Open the permit page

$15,500
Jan 9, 2015Completed
final sign-off Mar 2015
100 01st Strevision appl. 2014.1210.3484. provide one additional sign.
Details
Permit
201501095345
Permit issued
Jan 9, 2015
Final sign-off
Mar 5, 2015

revision appl. 2014.1210.3484. provide one additional sign.

Open the permit page

$345
Dec 10, 2014Never finaled
issued Dec 2014, no final
100 01st St26th floor - to create & produce evacuation maps.
Details
Permit
201412103484
Permit issued
Dec 10, 2014

26th floor - to create & produce evacuation maps.

Open the permit page

$1,100
Nov 3, 2014Completed
final sign-off Mar 2015
100 01st StTrue North Signs & Graphic Servicesprovide 8 evacuation signs (4 ea on 5th and 7th floor)
Details
Permit
201411030473
Permit issued
Nov 3, 2014
Final sign-off
Mar 20, 2015

provide 8 evacuation signs (4 ea on 5th and 7th floor)

Open the permit page

$2,400
Oct 31, 2014Completed
final sign-off May 2015
100 01st StAura Fire Safety Incupgrade fire system for hood and duct in the kitchen area to meet ul 300 standards
Details
Permit
201410310437
Permit issued
Oct 31, 2014
Final sign-off
May 28, 2015

upgrade fire system for hood and duct in the kitchen area to meet ul 300 standards

Open the permit page

$2,000
Sep 30, 2014Completed
final sign-off Sep 2014
100 01st StSabah International Incorporated26th floor - as built per field inspester for approval appl 2014.0731.2727. revise sequence of operation to show idf room smoke detectors unlock elevator lobby doors.
Details
Permit
201409307650
Permit issued
Sep 30, 2014
Final sign-off
Sep 30, 2014

26th floor - as built per field inspester for approval appl 2014.0731.2727. revise sequence of operation to show idf room smoke detectors unlock elevator lobby doors.

Open the permit page

Sep 9, 2014Completed
final sign-off Mar 2015
100 01st StTrue North Signs & Graphic Services(4) evacuation signs for 11th flr
Details
Permit
201409095852
Permit issued
Sep 9, 2014
Final sign-off
Mar 20, 2015

(4) evacuation signs for 11th flr

Open the permit page

$710
Aug 25, 2014Never finaled
issued Nov 2014, no final
100 01st StNovo Construction Inctenant improvement on 13th flr to build new glass partition at reception area, mep on separate permit.
Details
Permit
201408254609
Permit issued
Nov 25, 2014

tenant improvement on 13th flr to build new glass partition at reception area, mep on separate permit.

Open the permit page

$10,000
Jul 31, 2014Completed
final sign-off Sep 2014
100 01st StGolden Gate Fire Protection Inc26th floor:relocate 55 pendent sprinkler heads. relocate 28 upright sprinklers. upgrade earthquake bracing. ref app#201406047444.
Details
Permit
201407312679
Permit issued
Aug 5, 2014
Final sign-off
Sep 10, 2014

26th floor:relocate 55 pendent sprinkler heads. relocate 28 upright sprinklers. upgrade earthquake bracing. ref app#201406047444.

Open the permit page

$44,805
Jul 31, 2014Never finaled
issued Sep 2014, no final
100 01st StSabah International Incorporated26th floor: provide a modification of the existing fire alarm system. add 23 new ceiling speaker/strobes. demolish 30 existing strobes. demolish 17 existing speakers. relocate 8 smoke detectors. ref. appl 2014.0604.7444.
Details
Permit
201407312727
Permit issued
Sep 23, 2014

26th floor: provide a modification of the existing fire alarm system. add 23 new ceiling speaker/strobes. demolish 30 existing strobes. demolish 17 existing speakers. relocate 8 smoke detectors. ref. appl 2014.0604.7444.

Open the permit page

$9,149
Jul 2, 2014Never finaled
issued Jul 2014, no final
100 01st StTrue North Signs & Graphic Servicesreplace 4 evacuation signs on 10th floor. compliance with ordinance no 155-13 not reuqired.
Details
Permit
201407020289
Permit issued
Jul 2, 2014

replace 4 evacuation signs on 10th floor. compliance with ordinance no 155-13 not reuqired.

Open the permit page

$710
Jun 24, 2014Never finaled
issued Jun 2014, no final
100 01st StPacific Neon Companywork in suite 110: erect an electric single faced sign on existing light trough structure.
Details
Permit
201406249216
Permit issued
Jun 24, 2014

work in suite 110: erect an electric single faced sign on existing light trough structure.

Open the permit page

$6,500
Jun 24, 2014Never finaled
issued Jun 2014, no final
100 01st StPacific Neon Companysuite 110: erect an electric double faced projecting sign.
Details
Permit
201406249218
Permit issued
Jun 24, 2014

suite 110: erect an electric double faced projecting sign.

Open the permit page

$1,800
Jun 3, 2014Completed
final sign-off Jun 2014
100 01st StGolden Gate Fire Protection Increlocate 125 pendent sprinklers on the 10th floor, upgrade end of line bracing & earthquake bracing. t.i. #2014.0408.2696
Details
Permit
201406037355
Permit issued
Jun 3, 2014
Final sign-off
Jun 11, 2014

relocate 125 pendent sprinklers on the 10th floor, upgrade end of line bracing & earthquake bracing. t.i. #2014.0408.2696

Open the permit page

$64,375
Mar 10, 2014Never finaled
issued Mar 2014, no final
100 01st StParamount Sign Contractorspainted wall sign
Details
Permit
201403100267
Permit issued
Mar 10, 2014

painted wall sign

Open the permit page

$500
Mar 5, 2014Completed
final sign-off Feb 2015
100 01st StParamount Sign Contractorserect sign - indirect electric wall sign
Details
Permit
201403059970
Permit issued
Mar 10, 2014
Final sign-off
Feb 5, 2015

erect sign - indirect electric wall sign

Open the permit page

$28,000
Jan 7, 2014Completed
final sign-off Jan 2014
100 01st StSabah International Incorporated8th floor:provide a modification of the extg fire alarm system for the 8th floor. the addition shall consist of the following: 18 speaker strobes, one control relay for door holders, 9 duct smoke detectors for fsd's, 4 new smoke detectors, 3 door holders. ref app#201310169371
Details
Permit
201401075684
Permit issued
Jan 7, 2014
Final sign-off
Jan 16, 2014

8th floor:provide a modification of the extg fire alarm system for the 8th floor. the addition shall consist of the following: 18 speaker strobes, one control relay for door holders, 9 duct smoke detectors for fsd's, 4 new smoke detectors, 3 door holders. ref app#201310169371

Open the permit page

$17,000
Dec 18, 2013Completed
final sign-off Jan 2014
100 01st StGolden Gate Fire Protection Inc8th floor - relcoate 47 pendent sprinkler heads. relocate 6 upright sprinklers, upgrade end of line bracing. t.i. #2013.10.16.9371
Details
Permit
201312184500
Permit issued
Dec 19, 2013
Final sign-off
Jan 2, 2014

8th floor - relcoate 47 pendent sprinkler heads. relocate 6 upright sprinklers, upgrade end of line bracing. t.i. #2013.10.16.9371

Open the permit page

$28,840
Jul 17, 2013Completed
final sign-off Jul 2013
100 01st StPribuss Engineering Inc1st floor-fire sprinkler t.i-relocate 12 sprinklers, plug 3
Details
Permit
201307172023
Permit issued
Jul 17, 2013
Final sign-off
Jul 24, 2013

1st floor-fire sprinkler t.i-relocate 12 sprinklers, plug 3

Open the permit page

$6,175
Apr 22, 2013Never finaled
issued Apr 2013, no final
100 01st St2nd floor suite 279 fire sprinkler permit - remove 44 pendents, add 43 pendents & 23 uprights. ref t.i. #2013.02.26.0979
Details
Permit
201304225062
Permit issued
Apr 22, 2013

2nd floor suite 279 fire sprinkler permit - remove 44 pendents, add 43 pendents & 23 uprights. ref t.i. #2013.02.26.0979

Open the permit page

$33,000
Apr 17, 2013Never finaled
issued Apr 2013, no final
100 01st StPrincipal Builders Inc.mech work for t.i on the 2nd fl to demo ducts & install new fans, diffusers, exhausts fans and thermostat. pls ref to pa# 201302260979 for t.i reference.
Details
Permit
201304174787
Permit issued
Apr 17, 2013

mech work for t.i on the 2nd fl to demo ducts & install new fans, diffusers, exhausts fans and thermostat. pls ref to pa# 201302260979 for t.i reference.

Open the permit page

$280,000
Apr 16, 2013Completed
final sign-off Sep 2013
100 01st StField Construction Inc.#145- non structural interior remodel for optometry office consisting of optical retail, exam rooms, work,contact training &pre-test areas
Details
Permit
201304164629
Permit issued
Jun 24, 2013
Final sign-off
Sep 3, 2013

#145- non structural interior remodel for optometry office consisting of optical retail, exam rooms, work,contact training &pre-test areas

Open the permit page

$68,800
Feb 26, 2013Completed
final sign-off Jun 2013
100 01st StPrincipal Builders Inc.2nd floor:demolition and construction of non load bearing partitions walls, finishes, doors and ceiling for ti on multi tennant floor. med, sprinkler, life safety on seperate permit.
Details
Permit
201302260979
Permit issued
Feb 27, 2013
Final sign-off
Jun 25, 2013

2nd floor:demolition and construction of non load bearing partitions walls, finishes, doors and ceiling for ti on multi tennant floor. med, sprinkler, life safety on seperate permit.

Open the permit page

$250,000
Nov 19, 2012Completed
final sign-off Nov 2013
100 01st StParamount Sign Contractorsto erect 3 single faced projecting signs
Details
Permit
201211194455
Permit issued
Nov 19, 2012
Final sign-off
Nov 15, 2013

to erect 3 single faced projecting signs

Open the permit page

$45,000
Nov 19, 2012Completed
final sign-off Nov 2013
100 01st StParamount Sign Contractors7 electric wall projecting signs
Details
Permit
201211194454
Permit issued
Nov 19, 2012
Final sign-off
Nov 15, 2013

7 electric wall projecting signs

Open the permit page

$95,000
Sep 21, 2012Completed
final sign-off Oct 2012
100 01st Stfire sprinkler. relocate 8 and add 2 pendent heads.
Details
Permit
201209210367
Permit issued
Sep 24, 2012
Final sign-off
Oct 18, 2012

fire sprinkler. relocate 8 and add 2 pendent heads.

Open the permit page

$7,000
Aug 23, 2012Completed
final sign-off Oct 2012
100 01st StCommercial Interior Builders Inc27th floor:provide 2 vav boxes, ductwork and grilles and electrical title 24 work. ref: app#201206293779 for arch. permit.
Details
Permit
201208238093
Permit issued
Aug 23, 2012
Final sign-off
Oct 30, 2012

27th floor:provide 2 vav boxes, ductwork and grilles and electrical title 24 work. ref: app#201206293779 for arch. permit.

Open the permit page

$35,000
Aug 23, 2012Completed
final sign-off Apr 2013
100 01st StNovo Construction Inctenant improvement to consists of demo of non load bearing partitions associated electrical power/lighting associated mechanical. fire alarm/sprinkler seperate permit.
Details
Permit
201208238099
Permit issued
Aug 28, 2012
Final sign-off
Apr 29, 2013

tenant improvement to consists of demo of non load bearing partitions associated electrical power/lighting associated mechanical. fire alarm/sprinkler seperate permit.

Open the permit page

$850,000
Aug 15, 2012Completed
final sign-off Feb 2013
100 01st StSabah International Incorporated27th floor-provide a modification of (e) f.a system for partial tenant build out-addition shall consist of providing the following:add 1 genesis strobe, 5 atlas speakers, relocate 5 (e) strobes, 1 speaker, 1 smoke detector
Details
Permit
201208157390
Permit issued
Aug 15, 2012
Final sign-off
Feb 5, 2013

27th floor-provide a modification of (e) f.a system for partial tenant build out-addition shall consist of providing the following:add 1 genesis strobe, 5 atlas speakers, relocate 5 (e) strobes, 1 speaker, 1 smoke detector

Open the permit page

$10,667
Aug 1, 2012Completed
final sign-off Sep 2012
100 01st Stground floor fire sprinkler - 11 relocated & 3 added uprights, 2 relocated & 1 added pendents. seismic calc's, adding end of line restraints.
Details
Permit
201208016245
Permit issued
Aug 1, 2012
Final sign-off
Sep 26, 2012

ground floor fire sprinkler - 11 relocated & 3 added uprights, 2 relocated & 1 added pendents. seismic calc's, adding end of line restraints.

Open the permit page

$8,500
Jul 25, 2012Completed
final sign-off Sep 2012
100 01st StSabah International Incorporatedprovide modication of the existing fa system for partial tenant build out on partial 1st fl. add 1 duct detector, 1 control relay 3 speaker strobes, remove 1 existing strobe, 1 duct det, 2 ceiling speakers
Details
Permit
201207255711
Permit issued
Jul 25, 2012
Final sign-off
Sep 17, 2012

provide modication of the existing fa system for partial tenant build out on partial 1st fl. add 1 duct detector, 1 control relay 3 speaker strobes, remove 1 existing strobe, 1 duct det, 2 ceiling speakers

Open the permit page

$6,900
Jul 10, 2012Never finaled
issued Jul 2012, no final
100 01st Stfire sprinkler only- relocate 1 sprinkler head; add a head and plug off one head, 2 heads total for adr on 27th floor.
Details
Permit
201207104435
Permit issued
Jul 10, 2012

fire sprinkler only- relocate 1 sprinkler head; add a head and plug off one head, 2 heads total for adr on 27th floor.

Open the permit page

$1,000
Jun 29, 2012Completed
final sign-off Aug 2012
100 01st StCommercial Interior Builders Incsuite #2700 -minor tenant improvement to add offices/rooms. includes partitions, framing, doors, glazing. electrical at new walls, light relocations to be design build under sep permit. mech rebalance under sep permit
Details
Permit
201206293779
Permit issued
Jun 29, 2012
Final sign-off
Aug 30, 2012

suite #2700 -minor tenant improvement to add offices/rooms. includes partitions, framing, doors, glazing. electrical at new walls, light relocations to be design build under sep permit. mech rebalance under sep permit

Open the permit page

$77,653
May 30, 2012Never finaled
issued May 2012, no final
100 01st St1st and 2nd floor floor-fire sprinkler only-relocate 7 heads, 3 delete & add 1 head-
Details
Permit
201205301440
Permit issued
May 31, 2012

1st and 2nd floor floor-fire sprinkler only-relocate 7 heads, 3 delete & add 1 head-

Open the permit page

$9,000
May 24, 2012Completed
final sign-off Nov 2012
100 01st StThe Whiting-Turner Contracting Companyoffice t.i. on the 1st floor. work to include non rated and non structural walls. new finishes, new lighting and mechanical.
Details
Permit
201205241197
Permit issued
Jun 29, 2012
Final sign-off
Nov 16, 2012

office t.i. on the 1st floor. work to include non rated and non structural walls. new finishes, new lighting and mechanical.

Open the permit page

$56,580
Mar 14, 2012Never finaled
issued Mar 2012, no final
100 01st Stground floor fire sprinkler work - relcoate the fdc's on the n.w. & s.e. corners, relcoate 1 & add 1 pendent sprinkler.
Details
Permit
201203146017
Permit issued
Mar 14, 2012

ground floor fire sprinkler work - relcoate the fdc's on the n.w. & s.e. corners, relcoate 1 & add 1 pendent sprinkler.

Open the permit page

$11,500
Mar 1, 2012Never finaled
issued Mar 2012, no final
100 01st Ststreetspace
Details
Permit
M305187
Permit issued
Mar 1, 2012

streetspace

Open the permit page

Feb 14, 2012Completed
final sign-off Feb 2013
100 01st StThe Whiting-Turner Contracting Companyexterior and interior remodel. new walk off mats, new exterior lighting, metal portal construction at mission street entrance, curtain wall entry replacemen, column base embellishment modification and planter box construction. (sep. mep.)
Details
Permit
201202144133
Permit issued
Mar 7, 2012
Final sign-off
Feb 11, 2013

exterior and interior remodel. new walk off mats, new exterior lighting, metal portal construction at mission street entrance, curtain wall entry replacemen, column base embellishment modification and planter box construction. (sep. mep.)

Open the permit page

$432,000
Feb 6, 2012Completed
final sign-off Apr 2012
100 01st StSabah International Incorporatedpartial 2nd floor provide a modification of the existing fire alarm system for partial tenant build out, add (1) new genesis strobe, relocate (1) existing strobe.
Details
Permit
201202063587
Permit issued
Feb 6, 2012
Final sign-off
Apr 4, 2012

partial 2nd floor provide a modification of the existing fire alarm system for partial tenant build out, add (1) new genesis strobe, relocate (1) existing strobe.

Open the permit page

$3,244
Jan 4, 2012Completed
final sign-off Feb 2012
100 01st StAyoob & Peery Plumbing Co Inc22nd floor - relocate and remove fire sprinkler heads per tenant improvement, 22 relocate, 6 remove
Details
Permit
201201041699
Permit issued
Jan 4, 2012
Final sign-off
Feb 7, 2012

22nd floor - relocate and remove fire sprinkler heads per tenant improvement, 22 relocate, 6 remove

Open the permit page

$11,308
Nov 10, 2011Completed
final sign-off Jan 2012
100 01st Stfire sprinkler only - relocate 61 heads, add 9 heads, remove 8 heads; total 70 heads. spec suite on the 27th floor.
Details
Permit
201111108636
Permit issued
Nov 10, 2011
Final sign-off
Jan 27, 2012

fire sprinkler only - relocate 61 heads, add 9 heads, remove 8 heads; total 70 heads. spec suite on the 27th floor.

Open the permit page

$35,000
Sep 14, 2011Completed
final sign-off Oct 2011
100 01st StSabah International Incorporatedmodify fire alarm system for partial tenant build out on partial 2nd fl. remove 1 wall mounjt stobe. install 1 new ceiling mount strobe. existing circuits will be reused. arch pa 2011-06017141
Details
Permit
201109144558
Permit issued
Sep 14, 2011
Final sign-off
Oct 20, 2011

modify fire alarm system for partial tenant build out on partial 2nd fl. remove 1 wall mounjt stobe. install 1 new ceiling mount strobe. existing circuits will be reused. arch pa 2011-06017141

Open the permit page

$6,500
Sep 12, 2011Completed
final sign-off May 2012
100 01st StThe Whiting-Turner Contracting Company5 new exterior windows on ground floor
Details
Permit
201109124316
Permit issued
Dec 15, 2011
Final sign-off
May 16, 2012

5 new exterior windows on ground floor

Open the permit page

$35,000
Aug 18, 2011Never finaled
issued Aug 2011, no final
100 01st StParamount Sign Contractorsinterior illuminated wall sign. kilroy realty corp.on mezannine btn 1st and 2nd floor
Details
Permit
201108182763
Permit issued
Aug 18, 2011

interior illuminated wall sign. kilroy realty corp.on mezannine btn 1st and 2nd floor

Open the permit page

$13,000
Aug 4, 2011Completed
final sign-off Sep 2011
100 01st StAyoob & Peery Plumbing Co Incadd, relocate and removed fire sprinkler heads on the 3rd floor. 1 add, 2 remove and 7 relocate
Details
Permit
201108041744
Permit issued
Aug 4, 2011
Final sign-off
Sep 1, 2011

add, relocate and removed fire sprinkler heads on the 3rd floor. 1 add, 2 remove and 7 relocate

Open the permit page

$2,000
Jul 25, 2011Completed
final sign-off Sep 2011
100 01st StPrincipal Builders Inc.#360:demo full height walls, paint and carpet.
Details
Permit
201107251013
Permit issued
Jul 29, 2011
Final sign-off
Sep 27, 2011

#360:demo full height walls, paint and carpet.

Open the permit page

$261,600
Jul 20, 2011Completed
final sign-off Sep 2011
100 01st StSabah International Incorporatedmodify fire alarm system for tenant buildout 2nd fl. 1 new phto smk detector, 6 new photo duct smk det, 6 new control relay, 1 manual pull station, 2 ceiling strobes, 8 ceiling speaker/strobes, relocate 1 pull station
Details
Permit
201107200608
Permit issued
Jul 20, 2011
Final sign-off
Sep 1, 2011

modify fire alarm system for tenant buildout 2nd fl. 1 new phto smk detector, 6 new photo duct smk det, 6 new control relay, 1 manual pull station, 2 ceiling strobes, 8 ceiling speaker/strobes, relocate 1 pull station

Open the permit page

$14,198
Jul 20, 2011Completed
final sign-off Sep 2011
100 01st Stadd, relocate and remove fire sprinkler heads per tenant improvements on 2nd floor. 1 add, 45 relocate, 9 remove
Details
Permit
201107200616
Permit issued
Jul 20, 2011
Final sign-off
Sep 1, 2011

add, relocate and remove fire sprinkler heads per tenant improvements on 2nd floor. 1 add, 45 relocate, 9 remove

Open the permit page

$17,000
Jun 1, 2011Completed
final sign-off Sep 2011
100 01st StPrincipal Builders Inc.tenant improvment on 2nd floor office space. build out offices, conference room
Details
Permit
201106017141
Permit issued
Jun 14, 2011
Final sign-off
Sep 2, 2011

tenant improvment on 2nd floor office space. build out offices, conference room

Open the permit page

$300,000
Mar 30, 2011Completed
final sign-off Apr 2011
100 01st StAnderson, Rowe & Buckley, Inc.23rd floor-t.i. to (e) fire sprinkler system-4 added sprinklers, 10 relocated sprinklers, 2 removed sprinklers
Details
Permit
201103303068
Permit issued
Mar 30, 2011
Final sign-off
Apr 29, 2011

23rd floor-t.i. to (e) fire sprinkler system-4 added sprinklers, 10 relocated sprinklers, 2 removed sprinklers

Open the permit page

$2,800
Mar 11, 2011Completed
final sign-off Jan 2012
100 01st StTurner Construction Coexisting ti, space 2300 construction on non load bearing partitions, new door,sidelights, new ceiling grid, new and relocate lights fixtures, mill work, new finishes, mech and elec. fire sprinkler and life safety alarm under separate permit. work to core ("core improvement") as noted on plans.
Details
Permit
201103111913
Permit issued
Mar 15, 2011
Final sign-off
Jan 24, 2012

existing ti, space 2300 construction on non load bearing partitions, new door,sidelights, new ceiling grid, new and relocate lights fixtures, mill work, new finishes, mech and elec. fire sprinkler and life safety alarm under separate permit. work to core ("core improvement") as noted on plans.

Open the permit page

$510,000
Mar 9, 2011Completed
final sign-off Jan 2012
100 01st StAyoob & Peery Plumbing Co Inc24th floor add, relcoate & removed fire sprinkler heads per tenant improvements, add 22, relcoate 68, remove 2.
Details
Permit
201103091713
Permit issued
Mar 11, 2011
Final sign-off
Jan 30, 2012

24th floor add, relcoate & removed fire sprinkler heads per tenant improvements, add 22, relcoate 68, remove 2.

Open the permit page

$34,000
Mar 9, 2011Completed
final sign-off Feb 2012
100 01st StAyoob & Peery Plumbing Co Inc23rd floor add, relocate & removed fire sprinkler heads per tenant improvements, add 19, relocate 76, remove 4.
Details
Permit
201103091712
Permit issued
Mar 11, 2011
Final sign-off
Feb 1, 2012

23rd floor add, relocate & removed fire sprinkler heads per tenant improvements, add 19, relocate 76, remove 4.

Open the permit page

$38,000
Mar 9, 2011Completed
final sign-off Feb 2012
100 01st StAyoob & Peery Plumbing Co Inc20th & 21st floor add, relcoate & remove fire sprinkler heads per tenant improvement, 20th floor: add 28, relcoate 88, remove 1. 21st floor: add 23, relocate 96, remove 8.
Details
Permit
201103091714
Permit issued
Mar 11, 2011
Final sign-off
Feb 1, 2012

20th & 21st floor add, relcoate & remove fire sprinkler heads per tenant improvement, 20th floor: add 28, relcoate 88, remove 1. 21st floor: add 23, relocate 96, remove 8.

Open the permit page

$117,500
Mar 9, 2011Completed
final sign-off Jan 2012
100 01st StAyoob & Peery Plumbing Co Inc18th & 19th floor add, relocate & remove fire sprinkler heads per tenant improvements, 18th floor: add 30, relcoate 139, remvoe 17. 19th floor: add 19, relcoate 104, remove 6.
Details
Permit
201103091715
Permit issued
Mar 9, 2011
Final sign-off
Jan 30, 2012

18th & 19th floor add, relocate & remove fire sprinkler heads per tenant improvements, 18th floor: add 30, relcoate 139, remvoe 17. 19th floor: add 19, relcoate 104, remove 6.

Open the permit page

$146,000
Mar 8, 2011Completed
final sign-off Apr 2011
100 01st StSan Francisco Commercial Builders Incfloor 3 - new office addition including new prtitions, new door & relocated lighting, patch ceiling & finishes to match existing, mep & life safety & mep to be design build under separate permit.
Details
Permit
201103081617
Permit issued
Mar 23, 2011
Final sign-off
Apr 15, 2011

floor 3 - new office addition including new prtitions, new door & relocated lighting, patch ceiling & finishes to match existing, mep & life safety & mep to be design build under separate permit.

Open the permit page

$12,000
Mar 4, 2011Never finaled
issued Apr 2011, no final
100 01st StTurner Construction Cooffice ti on the 23rd floor incl. construction of nonload bearing walls, new doors, frames, side lights , new ceiling grid and acoustical tile, new millwork and finishes. mep under separate permit.
Details
Permit
201103041445
Permit issued
Apr 13, 2011

office ti on the 23rd floor incl. construction of nonload bearing walls, new doors, frames, side lights , new ceiling grid and acoustical tile, new millwork and finishes. mep under separate permit.

Open the permit page

$53,000
Mar 4, 2011Completed
final sign-off Jan 2012
100 01st StTurner Construction Co24th floor-t.i.-construction of non load bearing partitions, new doors, relocation og light fixtures & new finishes. mechanical, electrical, fire sprinkler, life safety alarm under seperate permit
Details
Permit
201103041390
Permit issued
Mar 7, 2011
Final sign-off
Jan 24, 2012

24th floor-t.i.-construction of non load bearing partitions, new doors, relocation og light fixtures & new finishes. mechanical, electrical, fire sprinkler, life safety alarm under seperate permit

Open the permit page

$900,000
Mar 3, 2011Completed
final sign-off Jan 2012
100 01st StTurner Construction Coexisting ti, space 2100. construction of non load bearing parititons, new doors, relocation o f light fixtures and new finishes, mechanical, elec. fire sprikler and life safety alarm under sep permit
Details
Permit
201103031328
Permit issued
Mar 7, 2011
Final sign-off
Jan 24, 2012

existing ti, space 2100. construction of non load bearing parititons, new doors, relocation o f light fixtures and new finishes, mechanical, elec. fire sprikler and life safety alarm under sep permit

Open the permit page

$900,000
Mar 2, 2011Completed
final sign-off Jan 2012
100 01st StTurner Construction Coextg ti, space 2000 construction of non load bearing partitions, new doors, relocation of light fixtures and new finishes,mechanical and electrical. fire sprinkler and life safety alarm under separate permit.
Details
Permit
201103021274
Permit issued
Mar 7, 2011
Final sign-off
Jan 24, 2012

extg ti, space 2000 construction of non load bearing partitions, new doors, relocation of light fixtures and new finishes,mechanical and electrical. fire sprinkler and life safety alarm under separate permit.

Open the permit page

$900,000
Mar 1, 2011Completed
final sign-off Jan 2012
100 01st StTurner Construction Coextg t.i. space 1900 construction of non load bearing partitions, new doors, relocation of light fixtures and new finishes, mechanical and electrical fire sprinkler & life safety alarm under seperate permit.
Details
Permit
201103011165
Permit issued
Mar 7, 2011
Final sign-off
Jan 24, 2012

extg t.i. space 1900 construction of non load bearing partitions, new doors, relocation of light fixtures and new finishes, mechanical and electrical fire sprinkler & life safety alarm under seperate permit.

Open the permit page

$1,000,000
Feb 15, 2011Completed
final sign-off Mar 2011
100 01st StTurner Construction Co18th floor space 1800 existing t.i., construction of non-load bearing partitions, new office doors & side lights, new ceiling grid & tile, new & relocated light fixtures, new millwork, new finishes, mechanical & electrical. fire sprinkler & life safety under separate permit.
Details
Permit
201102150308
Permit issued
Mar 1, 2011
Final sign-off
Mar 4, 2011

18th floor space 1800 existing t.i., construction of non-load bearing partitions, new office doors & side lights, new ceiling grid & tile, new & relocated light fixtures, new millwork, new finishes, mechanical & electrical. fire sprinkler & life safety under separate permit.

Open the permit page

$1,500,000
Dec 21, 2010Completed
final sign-off Dec 2010
100 01st StAyoob & Peery Plumbing Co Inc11th floor-relocate fire sprinkler heads per tenant improvements, 2 relocated
Details
Permit
201012217110
Permit issued
Dec 21, 2010
Final sign-off
Dec 30, 2010

11th floor-relocate fire sprinkler heads per tenant improvements, 2 relocated

Open the permit page

$1,200
Jul 22, 2008Completed
final sign-off Jul 2008
100 01st Strenew pa# 2007/12/04/9542 for final inspection only.
Details
Permit
200807227268
Permit issued
Jul 22, 2008
Final sign-off
Jul 31, 2008

renew pa# 2007/12/04/9542 for final inspection only.

Open the permit page

Mar 25, 2008Completed
final sign-off Sep 2008
100 01st StPribuss Engineering Incti for fire sprinler on the 14th floor. add 66 new sprinkler heads and relocate 163 heads.
Details
Permit
200803257894
Permit issued
Mar 25, 2008
Final sign-off
Sep 23, 2008

ti for fire sprinler on the 14th floor. add 66 new sprinkler heads and relocate 163 heads.

Open the permit page

$49,100
Feb 26, 2008Completed
final sign-off Sep 2008
100 01st St14th floor: tenant improvement build new offices and support facilities. install open office workstations.
Details
Permit
200802265659
Permit issued
Feb 28, 2008
Final sign-off
Sep 23, 2008

14th floor: tenant improvement build new offices and support facilities. install open office workstations.

Open the permit page

$625,000
Jan 10, 2008Completed
final sign-off Dec 2008
100 01st StSkyline Construction16th floor-fire sprinkler work-147 relocates, 26 removed. ref pa# 200712261320
Details
Permit
200801102232
Permit issued
Jan 10, 2008
Final sign-off
Dec 24, 2008

16th floor-fire sprinkler work-147 relocates, 26 removed. ref pa# 200712261320

Open the permit page

$120,000
Dec 26, 2007Completed
final sign-off Dec 2008
100 01st Sttenant improvement on 16th floor, new partitions, architectural work only m.e.p., sprinkler, fire alarm under separate permit.
Details
Permit
200712261320
Permit issued
Jan 9, 2008
Final sign-off
Dec 24, 2008

tenant improvement on 16th floor, new partitions, architectural work only m.e.p., sprinkler, fire alarm under separate permit.

Open the permit page

$631,000
Dec 20, 2007Expired or cancelled
expired Dec 2008
100 01st Stinterior non-structural demolition of 16th floor. demo interior office partitions. ti under seperate permit.
Details
Permit
200712200928
Permit issued
Dec 20, 2007

interior non-structural demolition of 16th floor. demo interior office partitions. ti under seperate permit.

Open the permit page

$15,000
Dec 4, 2007Expired or cancelled
expired Jul 2008
100 01st Stto renew app #200408272728
Details
Permit
200712049542
Permit issued
Dec 4, 2007

to renew app #200408272728

Open the permit page

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Novo Construction Inc (47), Ayoob & Peery Plumbing Co Inc (21), Sabah International Incorporated (19), Golden Gate Fire Protection Inc (14), True North Signs & Graphic Services (12), Commercial Interior Builders Inc (10), M C S Construction Services (9), Turner Construction Co (7), Paramount Sign Contractors (5), Pioneer Fire Inc. (5), Principal Builders Inc. (4), Field Construction Inc. (3), Pribuss Engineering Inc (3), The Whiting-Turner Contracting Company (3), Arrow Sign Company (2), Bilcor Inc (2), Codesign Llc (2), Pacific Neon Company (2), Anderson, Rowe & Buckley, Inc., Aura Fire Safety Inc, Emcor Services/Mesa Energy Systems Inc, Fire Stop Sprinkler Company, Gci, Inc, Mc Millan Security Systems Inc, Msr Mechanical Llc, Richlen Construction, San Francisco Commercial Builders Inc, Skyline Construction, Wolverine Fire Protection Co
Architects
Kimberly O'dowd (6), Teresa Emery (4), David De Valeria (3), Chris Sullivan (2), Heather Sanders-Jacob (2), J. Edgar Fennies Jr (2), Nathaniel Haynes (2), Ashley Miller, Bryan Provencal, Douglas Zucker, Ken Eng, Nicholas Brereton, Roger Wong, Sashikala Murthy, Scott Brady
Engineers
Alexander Joseph Pacheco (4), Joseph Fay (4), Rodolfo Bustos (3), Chow Wong (2), Erik Elmtoft (2), Erik Elmtoft (2), Robert Nixdorf (2), Robin Paul Roderick (2), Shahla Saiidnia (2), Amit Wadhwa, Levi Abarte, Nathan Tremblay, Roger Parra
Authorized agents
Loren Sheffeld
Designers
John Walsh

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.