Block 0081, lot 001
1 Lombard St
- City’s use
- Commercial Office
- Built
- 1904
- Stories
- 3
- Units
- 2
- Rooms
- 2 bathrooms
- Lot
- 18,905 sq ft
- Zoning
- C2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
79 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 1, 2025 | Completed final sign-off Jan 2026 | 1 Lombard St | Metcon Ti, Inc | deferred plumbing: replace (e) drinking fountain at 1st fl and (e) drinking fountain at mezz level. replace (e) restroom fixtures at mezz including undermount (4) lavs, (3) urinals, (5) water closets. provide (h) & (c) water & drain line insulation kit, provide clean out at drain line.Details
deferred plumbing: replace (e) drinking fountain at 1st fl and (e) drinking fountain at mezz level. replace (e) restroom fixtures at mezz including undermount (4) lavs, (3) urinals, (5) water closets. provide (h) & (c) water & drain line insulation kit, provide clean out at drain line. | $30,000 |
| Sep 26, 2025 | Completed final sign-off Mar 2026 | 1 Lombard St | Matrix Hg Inc | replace rooftop unit, existing unit weight = 685lb, new unit weight = 565lb.Details
replace rooftop unit, existing unit weight = 685lb, new unit weight = 565lb. | $42,375 |
| Sep 19, 2025 | Completed final sign-off Jan 2026 | 1 Lombard St | Metcon Ti, Inc | deferred mep for pa# 202407085966: mechanical- demo (e) ductwork, registers, and fan coils where shown. relocate (e) registers to new location, install (n) registers/t-stats. comfort balance. electrical-upgrade/replace lighting throughout half of the 1/f. title-24 compliant. plumbing-provide and...Details
deferred mep for pa# 202407085966: mechanical- demo (e) ductwork, registers, and fan coils where shown. relocate (e) registers to new location, install (n) registers/t-stats. comfort balance. electrical-upgrade/replace lighting throughout half of the 1/f. title-24 compliant. plumbing-provide and... | $40,000 |
| Feb 7, 2025 | Completed final sign-off Mar 2025 | 1 Lombard St | Freedom Fire Protection Inc. | ref pa # 2024-0708-5966 revise fire sprinkler system new tenant fl plan/ceiling plan. relocating 3 heads and installing 19 new heads. 22 totalDetails
ref pa # 2024-0708-5966 revise fire sprinkler system new tenant fl plan/ceiling plan. relocating 3 heads and installing 19 new heads. 22 total | $38,850 |
| Jul 11, 2024 | Completed final sign-off Aug 2024 | 1 Lombard St | Peacock Construction | ref pa# 2024-0328-8781 safe off a reinstall (3) existing radiator thermostats. provide new lighting a branch circuiting to existing panelDetails
ref pa# 2024-0328-8781 safe off a reinstall (3) existing radiator thermostats. provide new lighting a branch circuiting to existing panel | $60,000 |
| Jul 8, 2024 | Completed final sign-off Jan 2026 | 1 Lombard St | Metcon Ti, Inc | 1/f & mezz. -new floor finishes, light fixtures, ceiling finishes, conduits, switches, wiring, outlets, typ. in selected areas. restroom accessibility upgrade. interior non load bearing partitions. tenant improvement, no exterior work. no changes to e building structure.Details
1/f & mezz. -new floor finishes, light fixtures, ceiling finishes, conduits, switches, wiring, outlets, typ. in selected areas. restroom accessibility upgrade. interior non load bearing partitions. tenant improvement, no exterior work. no changes to e building structure. | $250,000 |
| Jun 25, 2024 | Expired or cancelled cancelled Jun 2025 | 1 Lombard St | Metcon Ti, Inc | revision to pa#202310178850. mezanine no longer to be removed. no structural work. no exterior work.Details
revision to pa#202310178850. mezanine no longer to be removed. no structural work. no exterior work. | |
| Jun 20, 2024 | Completed final sign-off Jul 2024 | 1 Lombard St | R L H Fire Protection Inc | ref pa# 2024-0328-8781 remove 2 upright sprinklers for the demolition of full height partitionsDetails
ref pa# 2024-0328-8781 remove 2 upright sprinklers for the demolition of full height partitions | $1,500 |
| May 1, 2024 | Completed final sign-off Dec 2025 | 1 Lombard St | Pullman Sst Inc | repair e) masonry: clean & repair brick wall & terra cotta parapet. remove unused embeded metal anchors & patch. stablize 2 brick windows arches using frp, & repair deteriorated mortar joint w. mortar to match e). repair & paint penthouse windows & replace perimeter sealantDetails
repair e) masonry: clean & repair brick wall & terra cotta parapet. remove unused embeded metal anchors & patch. stablize 2 brick windows arches using frp, & repair deteriorated mortar joint w. mortar to match e). repair & paint penthouse windows & replace perimeter sealant | $256,419 |
| Mar 28, 2024 | Completed final sign-off Aug 2024 | 1 Lombard St | Peacock Construction | scope of work on 2nd fl shall consist of interior demo of non structural elements including but not nec limited to interior partitions, doors, finishes,ceilings, lighting, mech, elec outlets,switches. drawings 202206065640Details
scope of work on 2nd fl shall consist of interior demo of non structural elements including but not nec limited to interior partitions, doors, finishes,ceilings, lighting, mech, elec outlets,switches. drawings 202206065640 | $149,140 |
| Jan 18, 2024 | Expired or cancelled cancelled Jun 2024 | 1 Lombard St | Adam Lewis Construction Company | the scope of work includes (n) floor finishes, light fixtures, ceiling finishes, 3 (n) all gender restrooms. tenant improvement at level 1 only. area of work to be sectioned off. all exits to remain accessible. no exterior work. no changes to building structure.Details
the scope of work includes (n) floor finishes, light fixtures, ceiling finishes, 3 (n) all gender restrooms. tenant improvement at level 1 only. area of work to be sectioned off. all exits to remain accessible. no exterior work. no changes to building structure. | $250,000 |
| Jan 11, 2024 | In progress filed Jan 2024, not yet issued | 1 Lombard St | California Fire Systems Inc | plug existing feed to mezzanine and remove exsiting fire sprinkler piping below mezzanine. existing mezzanine to be removed and area to be protected from fire sprinkler system above.Details
plug existing feed to mezzanine and remove exsiting fire sprinkler piping below mezzanine. existing mezzanine to be removed and area to be protected from fire sprinkler system above. | $12,000 |
| Oct 17, 2023 | Expired or cancelled cancelled Jun 2025 | 1 Lombard St | Adam Lewis Construction Company | interior of demo project includes removal of selected rooms; interior non-load bearing partitions, ceiling, finishes, interior doors; removal of select existing hvac equipment and ductowrk, electrical wiring, light fixtures, switches, outlets and conduit as required. removal of previously addedDetails
interior of demo project includes removal of selected rooms; interior non-load bearing partitions, ceiling, finishes, interior doors; removal of select existing hvac equipment and ductowrk, electrical wiring, light fixtures, switches, outlets and conduit as required. removal of previously added | $15,000 |
| Oct 5, 2023 | Completed final sign-off Jan 2024 | 1 Lombard St | Matrix Hg Inc | boiler replacement.Details
boiler replacement. | $150,000 |
| Jan 24, 2023 | Completed final sign-off Feb 2024 | 1 Lombard St | Peacock Construction | title 24 drawings refer deck to the other 202206065640 new power and signal devices, title 24 compliant lighting and controlsDetails
title 24 drawings refer deck to the other 202206065640 new power and signal devices, title 24 compliant lighting and controls | $120,000 |
| Sep 29, 2022 | Completed final sign-off Jan 2023 | 1 Lombard St | Richlen Construction | supply and install wood support membranes for mechanical unitsDetails
supply and install wood support membranes for mechanical units | $350,000 |
| Aug 11, 2022 | Never finaled issued Aug 2022, no final | 1 Lombard St | Sabah International Incorporated | ste 300: to 202206226869, modify e fire alarm system, add 1 booster power supply, 1 sync output module, 1 smoke detector, 9 led ceiling horn/strobes, 1 led wall horn/strobe, 6 led ceiling strobesDetails
ste 300: to 202206226869, modify e fire alarm system, add 1 booster power supply, 1 sync output module, 1 smoke detector, 9 led ceiling horn/strobes, 1 led wall horn/strobe, 6 led ceiling strobes | $20,714 |
| Jul 6, 2022 | Completed final sign-off Oct 2022 | 1 Lombard St | Anderson, Rowe & Buckley, Inc. | fire sprinkler only. relocate 7 pendents for raines group on the 3rd fl 202206226869Details
fire sprinkler only. relocate 7 pendents for raines group on the 3rd fl 202206226869 | $3,500 |
| Jun 22, 2022 | Completed final sign-off Jan 2023 | 1 Lombard St | Bcci Construction Company | 3rd fl office t.i. to include new partitions & mepDetails
3rd fl office t.i. to include new partitions & mep | $1,100,000 |
| Jun 6, 2022 | Completed final sign-off Feb 2023 | 1 Lombard St | Peacock Construction | alternation to core restrooms on 2/f only: score will bring restrooms into full accessibility compliance. does not affect (e) renant suites, exit pats, egress or stairs.(n)finishes & plumbing fixtures, (e) to demo.(n) ceiling & power. sprinkler /fls under sep permit. maher n/aDetails
alternation to core restrooms on 2/f only: score will bring restrooms into full accessibility compliance. does not affect (e) renant suites, exit pats, egress or stairs.(n)finishes & plumbing fixtures, (e) to demo.(n) ceiling & power. sprinkler /fls under sep permit. maher n/a | $120,000 |
| May 10, 2022 | Completed final sign-off Feb 2023 | 1 Lombard St | The Lawson Roofing Co Inc. | reroofing. minimum sri of 75 (low-sloped, non-res)Details
reroofing. minimum sri of 75 (low-sloped, non-res) | $1,521,013 |
| Jan 12, 2022 | Never finaled issued Jan 2022, no final | 1 Lombard St | Peacock Construction | 3rd fl - new receptacles connected to existing to remain circuit; new lighting & controlsDetails
3rd fl - new receptacles connected to existing to remain circuit; new lighting & controls | |
| Jun 16, 2021 | Completed final sign-off Jun 2022 | 1 Lombard St | Peacock Construction | 3/f: interior alteration to core restrooms. bring restrooms into full accessibility compliance. does not affect (e) tenant suites. new finishes, fixtures at (e) restrooms. new ceiling lights and power. sprinkler and life safety under separate deferred submittals.Details
3/f: interior alteration to core restrooms. bring restrooms into full accessibility compliance. does not affect (e) tenant suites. new finishes, fixtures at (e) restrooms. new ceiling lights and power. sprinkler and life safety under separate deferred submittals. | $120,000 |
| Jan 28, 2021 | Completed final sign-off May 2021 | 15 Lombard St | Sabah International Incorporated | voluntary; modify existing fire alarm system. add (1) monitor module.Details
voluntary; modify existing fire alarm system. add (1) monitor module. | $14,460 |
| Nov 22, 2019 | Expired or cancelled cancelled Jan 2026 | 15 Lombard St | per previously submitted ada entry ordinance forms, project consists of barrier removal, adding auatomatic door operator actuatct at building main entry per da-004 & da-005Details
per previously submitted ada entry ordinance forms, project consists of barrier removal, adding auatomatic door operator actuatct at building main entry per da-004 & da-005 | $10 | |
| Sep 27, 2019 | Completed final sign-off Dec 2019 | 15 Lombard St | Acco Engineered Systems Inc. Dba Acco En | install new cooloing only split system fan coil to be install in ti closet. condensing unit to be installed in parking garageDetails
install new cooloing only split system fan coil to be install in ti closet. condensing unit to be installed in parking garage | $18,000 |
| Aug 15, 2019 | Completed final sign-off Sep 2019 | 1 Lombard St | Velox Construction | remodel kitchen in kind 2nd fl, suite 202 new cabinets and countertopsDetails
remodel kitchen in kind 2nd fl, suite 202 new cabinets and countertops | $10,000 |
| Jul 3, 2018 | Completed final sign-off Aug 2018 | 1 Lombard St | Victory Electric | 1st ft spec suite: indoor lighting, energy management control system, lighting control system. t-24.Details
1st ft spec suite: indoor lighting, energy management control system, lighting control system. t-24. | $40,000 |
| May 15, 2018 | Completed final sign-off Aug 2018 | 1 Lombard St | San Francisco Commercial Builders Inc | suite 120: project consist of a ti. build out consist of demo of (e) partitions, power/data, finishes, ceiling & lighting and construction of new millwork, finishes, power/data, ceiling & lighting. mep & life safety drawings to be under sep permit. maher naDetails
suite 120: project consist of a ti. build out consist of demo of (e) partitions, power/data, finishes, ceiling & lighting and construction of new millwork, finishes, power/data, ceiling & lighting. mep & life safety drawings to be under sep permit. maher na | $230,000 |
| Nov 17, 2016 | Completed final sign-off Dec 2016 | 1 Lombard St | Pioneer Fire Inc. | 3rd floor: add 3 sidewall sprinklers and add 2 upright sprinklers n/a for maher. t.i app#201609097213Details
3rd floor: add 3 sidewall sprinklers and add 2 upright sprinklers n/a for maher. t.i app#201609097213 | $9,221 |
| Oct 12, 2016 | Completed final sign-off Feb 2017 | 1 Lombard St | Skyline Construction | suite 303: modification & expansion of extg t.i. to include selective demo & construction of non-load bearing partitions, nw light fixtures including re-switching, nw storage & entry doors/fames, salvage & reuse of extg selectied materials if practicable, millwork & nw sink & finishes. n/a for maherDetails
suite 303: modification & expansion of extg t.i. to include selective demo & construction of non-load bearing partitions, nw light fixtures including re-switching, nw storage & entry doors/fames, salvage & reuse of extg selectied materials if practicable, millwork & nw sink & finishes. n/a for maher | $380,000 |
| Sep 9, 2016 | Completed final sign-off Dec 2016 | 1 Lombard St | Gci, Inc | 3rd floor: ti- include demo of non-structural partitiond and building new non structural partitions to create new office conference rooms and new breakroom. all new or revised meps; life safety will be submitted separatelyDetails
3rd floor: ti- include demo of non-structural partitiond and building new non structural partitions to create new office conference rooms and new breakroom. all new or revised meps; life safety will be submitted separately | $296,450 |
| Dec 8, 2015 | Completed final sign-off Jan 2016 | 1 Lombard St | Aegis Enterprises Inc | #200: add (4) pendent fire sprinkler to accommodate new tenant imrpovement changes. ref pa 2015-1106-1977Details
#200: add (4) pendent fire sprinkler to accommodate new tenant imrpovement changes. ref pa 2015-1106-1977 | $1,500 |
| Nov 17, 2015 | Never finaled issued Nov 2015, no final | 1 Lombard St | D A Pope Inc | ti add (5) light fixtures, seven outlets. ref pa 2015-1106-1977. n/a ordinance #155-13Details
ti add (5) light fixtures, seven outlets. ref pa 2015-1106-1977. n/a ordinance #155-13 | $15,022 |
| Nov 6, 2015 | Completed final sign-off Dec 2015 | 1 Lombard St | D A Pope Inc | 2nd flr, ste 200: this project involves modification of (e) tenant space to inclue selective demo and construction of non-load bearing partitions,new ceiling grid & tile,new light fixtures,new office doors & frames & new finishes; maher n/aDetails
2nd flr, ste 200: this project involves modification of (e) tenant space to inclue selective demo and construction of non-load bearing partitions,new ceiling grid & tile,new light fixtures,new office doors & frames & new finishes; maher n/a | $62,320 |
| May 12, 2015 | Completed final sign-off Jun 2015 | 1 Lombard St | Potter Fire Protection | demo 13 pendant sprinklers. add 1 pendant sprinkler. ref 201505115916Details
demo 13 pendant sprinklers. add 1 pendant sprinkler. ref 201505115916 | $1,200 |
| May 11, 2015 | Completed final sign-off Sep 2015 | 1 Lombard St | San Francisco Commercial Builders Inc | #200- demolition of some existing offices, rebuild some offices, existing lighting to remain. n/a ordinance #155-13Details
#200- demolition of some existing offices, rebuild some offices, existing lighting to remain. n/a ordinance #155-13 | $150,000 |
| Jan 12, 2015 | Completed final sign-off Feb 2015 | 1 Lombard St | San Francisco Commercial Builders Inc | build wood platforms for hvac equipment of existing roof. n/a ordinance #155-13. mep under separate permitDetails
build wood platforms for hvac equipment of existing roof. n/a ordinance #155-13. mep under separate permit | $2,500 |
| Jan 7, 2015 | Completed final sign-off Feb 2015 | 1 Lombard St | San Francisco Commercial Builders Inc | ste 200. miner demolition of extg t.i. to include selective demolition of non-load bearing partitions, ceiling and hvac. n/a for the maher.Details
ste 200. miner demolition of extg t.i. to include selective demolition of non-load bearing partitions, ceiling and hvac. n/a for the maher. | $10,000 |
| Oct 27, 2014 | Never finaled issued Nov 2014, no final | 1 Lombard St | Gci, Inc | interior ti of non structural, demo of existing office. new partitions, millwork, lighting electrical fixtures, telecome, plumbing and mechanical. no structural work. compliance with maher ordinance no. 155-13 not required.Details
interior ti of non structural, demo of existing office. new partitions, millwork, lighting electrical fixtures, telecome, plumbing and mechanical. no structural work. compliance with maher ordinance no. 155-13 not required. | $500,000 |
| Aug 13, 2014 | Completed final sign-off Oct 2014 | 1 Lombard St | Isidore Mahon Dba Izzy Construction | install chair lift for barrier removal for wheel chair access to mezzanine level, add blocking cut opening through guard wall on mezzanine. n/a ordinance #155-13Details
install chair lift for barrier removal for wheel chair access to mezzanine level, add blocking cut opening through guard wall on mezzanine. n/a ordinance #155-13 | $48,000 |
| Apr 16, 2014 | Never finaled issued May 2014, no final | 15 Lombard St | Bay Build Design Inc | ste #15: remove partitoin walls & add new partition walls as necessary. install 10 duplexs, (2) 4 plug outlets, install 6 date/tel cables. remove & replace sink in kitchenette for ada requirement. move fire sprinklers as necessary. compliance with ordinance #155-13 not requiredDetails
ste #15: remove partitoin walls & add new partition walls as necessary. install 10 duplexs, (2) 4 plug outlets, install 6 date/tel cables. remove & replace sink in kitchenette for ada requirement. move fire sprinklers as necessary. compliance with ordinance #155-13 not required | $65,000 |
| Jan 22, 2014 | Completed final sign-off Mar 2014 | 1 Lombard St | Jones Lang La Salle Construction Company | revision to pa#2013-10-04-8481. to project notes 'e' clarifying the mechanical or plumbing work/scope in this project & permit.Details
revision to pa#2013-10-04-8481. to project notes 'e' clarifying the mechanical or plumbing work/scope in this project & permit. | |
| Dec 4, 2013 | Completed final sign-off Mar 2014 | 1 Lombard St | Jones Lang La Salle Construction Company | 2/f -revision to pa 201310048481; to clarify hardship such that no ada work for (e) restroom to be required; requested by inspector.Details
2/f -revision to pa 201310048481; to clarify hardship such that no ada work for (e) restroom to be required; requested by inspector. | |
| Oct 24, 2013 | Completed final sign-off Dec 2013 | 1 Lombard St | Golden Gate Fire Protection Inc | 2nd floor-relocate 8 pendent sprinkler heads in common area.t.i 201310048481Details
2nd floor-relocate 8 pendent sprinkler heads in common area.t.i 201310048481 | $4,120 |
| Oct 4, 2013 | Completed final sign-off Mar 2014 | 1 Lombard St | Jones Lang La Salle Construction Company | common area improvement on 2nd fl including new ceiling, lighting, paritions, doorsDetails
common area improvement on 2nd fl including new ceiling, lighting, paritions, doors | $33,000 |
| Dec 12, 2012 | Never finaled issued Dec 2012, no final | 15 Lombard St | Specialized Graphics Inc | non-illuminated blade signDetails
non-illuminated blade sign | $1,300 |
| Dec 12, 2012 | Never finaled issued Dec 2012, no final | 15 Lombard St | Specialized Graphics Inc | #7, non-illuminated blade signDetails
#7, non-illuminated blade sign | $1,300 |
| Dec 12, 2012 | Never finaled issued Dec 2012, no final | 15 Lombard St | Specialized Graphics Inc | #9, non-illuminated blade signDetails
#9, non-illuminated blade sign | $1,300 |
| Apr 10, 2009 | Completed final sign-off Jul 2009 | 1 Lombard St | Gci, Inc | renew pa# 2005/07/21/8230 to obtain final inspection. all work has been completed.Details
renew pa# 2005/07/21/8230 to obtain final inspection. all work has been completed. | |
| Apr 10, 2009 | Completed final sign-off May 2009 | 1 Lombard St | Gci, Inc | renew pa# 2005/05/18/2784 to obtain final inspection. all work has been completed.Details
renew pa# 2005/05/18/2784 to obtain final inspection. all work has been completed. | |
| Mar 31, 2009 | Completed final sign-off Jun 2009 | 1 Lombard St | Cannon Constructors North Inc | revision to pa# 2009-0313-4074-bulletin #2, revision to permit drawings, demo 2 (e) offices to create open area. sprinkler nad fire alarm separte permitDetails
revision to pa# 2009-0313-4074-bulletin #2, revision to permit drawings, demo 2 (e) offices to create open area. sprinkler nad fire alarm separte permit | $10,000 |
| Mar 13, 2009 | Completed final sign-off Jun 2009 | 1 Lombard St | Cannon Constructors North Inc | minor remodel work of an extg fitness area. removal of a wall in order to make larger room. also demo of 2 offices and 1 wall. no new electrical work req. only relocatetion of extg fixtures.Details
minor remodel work of an extg fitness area. removal of a wall in order to make larger room. also demo of 2 offices and 1 wall. no new electrical work req. only relocatetion of extg fixtures. | $107,932 |
| Nov 8, 2006 | Expired or cancelled expired Feb 2009 | 1 Lombard St | Potter Fire Protection | relocate (2) fier sprinklers on the 3rd floor only.Details
relocate (2) fier sprinklers on the 3rd floor only. | $1,250 |
| Nov 6, 2006 | Expired or cancelled expired Jul 2008 | 1 Lombard St | Weather Masters Inc. | oti-2 3rd floor me. isntall new mechanical equipment.Details
oti-2 3rd floor me. isntall new mechanical equipment. | $45,000 |
| Jun 1, 2006 | Completed final sign-off Nov 2006 | 1 Lombard St | oti-1, 3rd floor, el, sp.Details
oti-1, 3rd floor, el, sp. | $150,000 | |
| May 25, 2006 | Completed final sign-off Sep 2006 | 1 Lombard St | Hathaway Dinwiddie Co. | oti-3, 3rd floor, me.Details
oti-3, 3rd floor, me. | $50,000 |
| May 5, 2006 | Completed final sign-off Sep 2006 | 1 Lombard St | Hathaway Dinwiddie Co. | oti 2-3rd floor, elDetails
oti 2-3rd floor, el | $51,270 |
| May 2, 2006 | Completed final sign-off Sep 2006 | 1 Lombard St | Potter Fire Protection | relocate 13 and plug 5 fire sprinklers to accomodate the new wall and ceiling construction in a 3rd floor office onlyDetails
relocate 13 and plug 5 fire sprinklers to accomodate the new wall and ceiling construction in a 3rd floor office only | $3,800 |
| Mar 14, 2006 | Completed final sign-off Sep 2006 | 1 Lombard St | oti-1 3rd fl-el, me, ls, sp.Details
oti-1 3rd fl-el, me, ls, sp. | $350,000 | |
| Jul 21, 2005 | Expired or cancelled expired Feb 2009 | 1 Lombard St | Gci, Inc | addition of deck to existing roof access to include demolition of double door and replace with storeDetails
addition of deck to existing roof access to include demolition of double door and replace with store | $30,000 |
| Jun 17, 2005 | Completed final sign-off Jan 2006 | 1 Lombard St | Gci, Inc | oti-4, 3rd floor, sp.Details
oti-4, 3rd floor, sp. | $500,000 |
| Jun 17, 2005 | Completed final sign-off Jan 2006 | 1 Lombard St | Gci, Inc | oti-3, 3rd floor, el.Details
oti-3, 3rd floor, el. | $150,000 |
| Jun 8, 2005 | Completed final sign-off Jan 2006 | 1 Lombard St | Gci, Inc | oti-2, 3rd floor, me.Details
oti-2, 3rd floor, me. | $56,365 |
| May 18, 2005 | Expired or cancelled expired Feb 2009 | 1 Lombard St | Gci, Inc | interior partitions to enclose office areas & conference room area. all structural calculationDetails
interior partitions to enclose office areas & conference room area. all structural calculation | $3,200 |
| May 18, 2005 | Completed final sign-off Jan 2006 | 1 Lombard St | Gci, Inc | oti-1, 3rd floor, el, me, ls, sp.Details
oti-1, 3rd floor, el, me, ls, sp. | $350,000 |
| Mar 18, 2003 | Expired or cancelled expired Feb 2009 | 1 Lombard St | Roberts And Sons Builders | renew#200102262919 for final inspectionDetails
renew#200102262919 for final inspection | |
| Feb 7, 2003 | Completed final sign-off Feb 2003 | 1 Lombard St | Mcm & Associates Inc. | renovation to exist fire sprklr system due to ti improvement. revision 200301225641 change layout ofDetails
renovation to exist fire sprklr system due to ti improvement. revision 200301225641 change layout of | |
| Jan 22, 2003 | Completed final sign-off Feb 2003 | 1 Lombard St | Pankow Special Projects Lp | oti-2, 2nd floor, el, spDetails
oti-2, 2nd floor, el, sp | $20,000 |
| Dec 23, 2002 | Completed final sign-off Feb 2003 | 1 Lombard St | Pankow Special Projects Lp | oti-1, 2nd flr,el,me,spDetails
oti-1, 2nd flr,el,me,sp | $43,905 |
| Sep 19, 2002 | Completed final sign-off Jan 2003 | 1 Lombard St | Cosco Fire Protection Inc. | relocate 26 new pendant at 1st floor, and 31 add 10 pendants on 2nd floorDetails
relocate 26 new pendant at 1st floor, and 31 add 10 pendants on 2nd floor | $8,500 |
| Jul 3, 2002 | Completed final sign-off Jan 2003 | 1 Lombard St | Cannon Constructors North Inc | demolition of non-brg walls & finishes in preparation of planned build out on 2nd flr -all interiorDetails
demolition of non-brg walls & finishes in preparation of planned build out on 2nd flr -all interior | $18,000 |
| Jun 18, 2002 | Completed final sign-off Jan 2003 | 1 Lombard St | Cannon Constructors North Inc | 15,000 s.f. commercial tenant improvement-on 1st, & 2nd flr, for exercise room at bay club sfDetails
15,000 s.f. commercial tenant improvement-on 1st, & 2nd flr, for exercise room at bay club sf | $620,000 |
| May 28, 2002 | Expired or cancelled expired Jan 2003 | 1 Lombard St | Daniel P Heath Inc. | add (1) fire sprinkler head into new server room-all interior workDetails
add (1) fire sprinkler head into new server room-all interior work | $800 |
| May 14, 2002 | Completed final sign-off Jul 2002 | 1 Lombard St | Plant Construction | construct metal framed drywall partitions to create new telephone room and coffee area sep fire permDetails
construct metal framed drywall partitions to create new telephone room and coffee area sep fire perm | $7,500 |
| Feb 25, 2002 | Completed final sign-off Apr 2002 | 1 Lombard St | Plant Construction | remove interior open communicating stair between floors, installed by prev tenant, and close flr opeDetails
remove interior open communicating stair between floors, installed by prev tenant, and close flr ope | $12,500 |
| Jan 25, 2002 | Completed final sign-off Apr 2002 | 1 Lombard St | Plant Construction | demolition & removal of existing non fire rated non=load bearing interior partitions @ 3rd fl onlyDetails
demolition & removal of existing non fire rated non=load bearing interior partitions @ 3rd fl only | $10,000 |
| Feb 26, 2001 | Expired or cancelled expired Jan 2003 | 1 Lombard St | oti-1 2nd fl, ltg, mech, ls, sprDetails
oti-1 2nd fl, ltg, mech, ls, spr | $35,000 | |
| Feb 14, 2000 | Expired or cancelled cancelled Jan 2026 | 1 Lombard St |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.