Block 0312, lot 009
49 Geary St
- City’s use
- Commercial Office
- Built
- 1912
- Stories
- 5
- Rooms
- 27 bathrooms
- Building
- 151,546 sq ft
- Lot
- 25,530 sq ft
- Zoning
- C3R
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
The 200 most recent permits filed for this property.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 3, 2024 | In progress filed Jul 2024, not yet issued | 49 Geary St | Bilcor Inc | rev 202406124265- wrong fire sequenceDetails
rev 202406124265- wrong fire sequence | |
| Jun 12, 2024 | Completed final sign-off Aug 2024 | 49 Geary St | Bilcor Inc | revision to pa# 202309227177 (ste 550): install (1) duct detector. install (2) control relay.Details
revision to pa# 202309227177 (ste 550): install (1) duct detector. install (2) control relay. | $1,998 |
| Dec 20, 2023 | In progress issued May 2024 | 49 Geary St | Western Roofing Service | existing roofing membrane removal and full replacement of the membrane system. removal and disposal of existing wood curbs of mechanical units, and replacement with new. new roofing system to be installed shall be 2-ply sbs modified bituman roofing over tapered polyiso insulationDetails
existing roofing membrane removal and full replacement of the membrane system. removal and disposal of existing wood curbs of mechanical units, and replacement with new. new roofing system to be installed shall be 2-ply sbs modified bituman roofing over tapered polyiso insulation | $1,200,000 |
| Nov 30, 2023 | Completed final sign-off May 2024 | 55 Geary St | Durkin Signs & Graphics Inc | install (2) non-electric double faced flag signs on existing projecting pole: "theory". to comply with planning dept complaint # 2022-012879enfDetails
install (2) non-electric double faced flag signs on existing projecting pole: "theory". to comply with planning dept complaint # 2022-012879enf | $100 |
| Nov 20, 2023 | Completed final sign-off Dec 2023 | 740 Market St | Bilcor Inc | revision to pa# 202311090489. instlal 1 booster panel. install 11 wall mount speaker-strobes approved on 2023-1109-0489;remove 3 duct detector and 3 control relay. as builtDetails
revision to pa# 202311090489. instlal 1 booster panel. install 11 wall mount speaker-strobes approved on 2023-1109-0489;remove 3 duct detector and 3 control relay. as built | |
| Nov 9, 2023 | Completed final sign-off Dec 2023 | 740 Market St | Bilcor Inc | 1/f: install 1 booster panel, 11 wall mount speaker-strobes, 3 duct detector, 3 control relay. ref permits 202304045053 (phase 1), and 202307172334 (phase 2)Details
1/f: install 1 booster panel, 11 wall mount speaker-strobes, 3 duct detector, 3 control relay. ref permits 202304045053 (phase 1), and 202307172334 (phase 2) | $11,988 |
| Oct 10, 2023 | Completed final sign-off Nov 2023 | 49 Geary St | Golden Gate Fire Protection Inc | replace pump with the same size pumpDetails
replace pump with the same size pump | $8,000 |
| Sep 22, 2023 | Completed final sign-off Aug 2024 | 49 Geary St | Bilcor Inc | ste #550: install (18) wall mount speaker-strobes. install (1) smoke detector. install (2) duct detector. install (3) control relays. arch ti# 202304175872 - mech ti #202308184764Details
ste #550: install (18) wall mount speaker-strobes. install (1) smoke detector. install (2) duct detector. install (3) control relays. arch ti# 202304175872 - mech ti #202308184764 | $15,984 |
| Sep 15, 2023 | Completed final sign-off Jun 2024 | 740 Market St | Anderson, Rowe & Buckley, Inc. | 1/f: revision to pa#202306079424, add 2 upright & 1 pendent fire sprinklers, ref ti pa# 202304045053.Details
1/f: revision to pa#202306079424, add 2 upright & 1 pendent fire sprinklers, ref ti pa# 202304045053. | $2,000 |
| Aug 18, 2023 | Completed final sign-off Oct 2024 | 49 Geary St | M C S Construction Services | 5th fl: mech & electrical work. ref arch pa#202304175872. deferred permit int t.i). no ext workDetails
5th fl: mech & electrical work. ref arch pa#202304175872. deferred permit int t.i). no ext work | $182,000 |
| Jul 17, 2023 | Completed final sign-off Jul 2024 | 740 Market St | Gci, Inc | phase 1: permit revision. phase 2a soft demo of unused mep and landlord build out including construction of rated partitions, speculative tenant space to receive aesthetic improvements including general partch nd reapirs, finises, paint and lighting, new entry doors and store front windowsDetails
phase 1: permit revision. phase 2a soft demo of unused mep and landlord build out including construction of rated partitions, speculative tenant space to receive aesthetic improvements including general partch nd reapirs, finises, paint and lighting, new entry doors and store front windows | $225,000 |
| Jun 7, 2023 | Completed final sign-off Jun 2024 | 740 Market St | Anderson, Rowe & Buckley, Inc. | 1/f: t.i. to (e) fire sprinkler system. relocate 7 and add 5 fire sprinklers. maher n/a. ref to 202304045053Details
1/f: t.i. to (e) fire sprinkler system. relocate 7 and add 5 fire sprinklers. maher n/a. ref to 202304045053 | $7,500 |
| Apr 17, 2023 | Completed final sign-off Oct 2024 | 49 Geary St | M C S Construction Services | 5th flr tenant improvement to suite 550. minor demolition, construction of new non-loading bearing partition walls to create new office space. space types included are open office, conference rooms, phone rooms, pantry, mother's room, server room, elecrical closet, copy room, model room andDetails
5th flr tenant improvement to suite 550. minor demolition, construction of new non-loading bearing partition walls to create new office space. space types included are open office, conference rooms, phone rooms, pantry, mother's room, server room, elecrical closet, copy room, model room and | $482,530 |
| Apr 4, 2023 | Completed final sign-off Jul 2024 | 740 Market St | Gci, Inc | building out of retail space including construction of rated and non rated partitions, restrooms, break room, office walls, door, storage room, finishes and lightingDetails
building out of retail space including construction of rated and non rated partitions, restrooms, break room, office walls, door, storage room, finishes and lighting | $450,000 |
| Oct 4, 2022 | Completed final sign-off Nov 2022 | 740 Market St | Ayoob & Peery Plumbing Co Inc | 1st floor: changeout (29) fire sprinklers per t.i. ref # 202209061930. job #22-670.Details
1st floor: changeout (29) fire sprinklers per t.i. ref # 202209061930. job #22-670. | $38,100 |
| Sep 23, 2022 | Completed final sign-off Jun 2023 | 49 Geary St | 5/f suite 540 and 550: demolition of non-load bearing partitons, ceiling, light fixtures millwork, plumbing and finishesDetails
5/f suite 540 and 550: demolition of non-load bearing partitons, ceiling, light fixtures millwork, plumbing and finishes | $85,000 | |
| Sep 6, 2022 | Never finaled issued Sep 2022, no final | 740 Market St | Anning-Johnson Company | demo interior @ ground fl & roof top eqiuipment only of non structural partitions, ceiling, finishes & associated mep.Details
demo interior @ ground fl & roof top eqiuipment only of non structural partitions, ceiling, finishes & associated mep. | $90,000 |
| Aug 27, 2020 | Completed final sign-off Nov 2020 | 49 Geary St | Bilcor Inc | fire life safety: install 6 smoke detectors with baseDetails
fire life safety: install 6 smoke detectors with base | $3,960 |
| Aug 5, 2020 | Never finaled issued Aug 2020, no final | 49 Geary St | Bilcor Inc | 5th floor: fire life safety: remove and relocate 2 wall mount speaker strobes. remove 1 wall mount speaker strobe. relocate 2 wall mount speaker strobe. install 2 new wall mount speaker strobe. ref app#202003046110Details
5th floor: fire life safety: remove and relocate 2 wall mount speaker strobes. remove 1 wall mount speaker strobe. relocate 2 wall mount speaker strobe. install 2 new wall mount speaker strobe. ref app#202003046110 | $1,320 |
| Mar 4, 2020 | Completed final sign-off Sep 2020 | 49 Geary St | Johnstone - Mc Auliffe Const. Inc. | #530: t.i. includes construction of non load bearing partitions, new office doors and painting. mep deffered under separate permitDetails
#530: t.i. includes construction of non load bearing partitions, new office doors and painting. mep deffered under separate permit | $165,000 |
| Sep 27, 2019 | Completed final sign-off Dec 2019 | 65 Geary St | Martin Sign Co Inc. | installation of illuminated channel letters to exterior metal facade.Details
installation of illuminated channel letters to exterior metal facade. | $1,000 |
| Jul 23, 2019 | Completed final sign-off Jul 2019 | 49 Geary St | Bilcor Inc | unit 238: as builts for lost issued plans - to obtain final ionspection for work under approves pa# 201403251608. all work is completeDetails
unit 238: as builts for lost issued plans - to obtain final ionspection for work under approves pa# 201403251608. all work is complete | |
| Jul 5, 2019 | Completed final sign-off Jul 2019 | 49 Geary St | Bilcor Inc | 2/f suite 200: fire alarm ti: install 5 ceiling speaker strobes, remove 13 wall speaker strobes. ref t.i. 201905241644. maher n/a.Details
2/f suite 200: fire alarm ti: install 5 ceiling speaker strobes, remove 13 wall speaker strobes. ref t.i. 201905241644. maher n/a. | $3,300 |
| Jul 3, 2019 | Never finaled issued Jul 2019, no final | 49 Geary St | street spaceDetails
street space | ||
| Jun 26, 2019 | Completed final sign-off Aug 2019 | 49 Geary St | Peacock Construction | 2nd flr. t-24 mechanical and electrical for work for pa 201905241644. n/a for maherDetails
2nd flr. t-24 mechanical and electrical for work for pa 201905241644. n/a for maher | |
| Jun 5, 2019 | Completed final sign-off Jun 2019 | 49 Geary St | Bilcor Inc | ste 67 - fls ti install 4 ceiling mount speaker-strobes, 2 wall mount speaker-strobes, remove 1 wall mount speaker strobe. ref pa 2019-0211-2571Details
ste 67 - fls ti install 4 ceiling mount speaker-strobes, 2 wall mount speaker-strobes, remove 1 wall mount speaker strobe. ref pa 2019-0211-2571 | $4,620 |
| Jun 3, 2019 | Expired or cancelled withdrawn Sep 2019 | 65 Geary St | Martin Sign Co Inc. | sign, "mephisto m". electric, wall-mounted, single-facedDetails
sign, "mephisto m". electric, wall-mounted, single-faced | $3,030 |
| May 24, 2019 | Completed final sign-off Jul 2019 | 49 Geary St | Peacock Construction | 2nd floor tenant improvement: selective demo of non-structural partitions, new non-structural partitions, light fixtures, glazing, doors, frames, millwork, (e) sink and finishesDetails
2nd floor tenant improvement: selective demo of non-structural partitions, new non-structural partitions, light fixtures, glazing, doors, frames, millwork, (e) sink and finishes | $250,000 |
| May 21, 2019 | Completed final sign-off Jan 2020 | 65 Geary St | Olson Construction | revision to pa #201903256092. install (2) mobile shelving units: (1) 6'-0" x 14'-7" x 8'-0" h. (1) 6'-0" x 16'-1" x 8'-0" h.Details
revision to pa #201903256092. install (2) mobile shelving units: (1) 6'-0" x 14'-7" x 8'-0" h. (1) 6'-0" x 16'-1" x 8'-0" h. | $9,000 |
| May 20, 2019 | Completed final sign-off May 2019 | 65 Geary St | Bilcor Inc | install 2 ceiling mount speaker strobesDetails
install 2 ceiling mount speaker strobes | $1,320 |
| Apr 22, 2019 | Completed final sign-off May 2019 | 49 Geary St | Bay Area Fire Protection Llc | suite 67: adding/relocating 16 pendent sprinklers to an (e) wet-pipe fire sprinkler system. ref t.i. pa#201902112571. maher n/a.Details
suite 67: adding/relocating 16 pendent sprinklers to an (e) wet-pipe fire sprinkler system. ref t.i. pa#201902112571. maher n/a. | $6,000 |
| Apr 3, 2019 | Completed final sign-off May 2019 | 65 Geary St | Ayoob & Peery Plumbing Co Inc | ground floor add (4), relocate (9) and plug (1) sprinklers to conform with the new wall/ceiling layout of the tenant improvement. .Details
ground floor add (4), relocate (9) and plug (1) sprinklers to conform with the new wall/ceiling layout of the tenant improvement. . | $3,125 |
| Apr 1, 2019 | Completed final sign-off Jun 2019 | 55 Geary St | Bilcor Inc | fire alarm ti - install 10 ceiling speaker strobes, install 2 ceiling strobes, install 2 walls speaker strobes. ref pa 2019-0125-1284. n/a for maher.Details
fire alarm ti - install 10 ceiling speaker strobes, install 2 ceiling strobes, install 2 walls speaker strobes. ref pa 2019-0125-1284. n/a for maher. | $8,400 |
| Mar 25, 2019 | Completed final sign-off Jan 2020 | 65 Geary St | Olson Construction | non-structural interior demolition, new drywall partitions, new drywall ceilings, new finishes, doors frames and harware, lighting, powder, and hvac duct alteration. fire alarm/fire sprinklers on deferred submittals. no plumbing on this project. n/a for maher.Details
non-structural interior demolition, new drywall partitions, new drywall ceilings, new finishes, doors frames and harware, lighting, powder, and hvac duct alteration. fire alarm/fire sprinklers on deferred submittals. no plumbing on this project. n/a for maher. | $202,799 |
| Mar 21, 2019 | Completed final sign-off Mar 2019 | 55 Geary St | Ayoob & Peery Plumbing Co Inc | ref pa# 201901251284; add relocate and remove fire sprinkler per t.i. 12 +1 (13) adds, 24 relocates, 1 remove 1st fl.Details
ref pa# 201901251284; add relocate and remove fire sprinkler per t.i. 12 +1 (13) adds, 24 relocates, 1 remove 1st fl. | $11,700 |
| Mar 14, 2019 | Never finaled issued Mar 2019, no final | 49 Geary St | street spaceDetails
street space | ||
| Mar 14, 2019 | Never finaled issued Mar 2019, no final | 65 Geary St | per request from owner, add two commercial addresses at block 0312, lot 009 as; 65, 67 geary streetDetails
per request from owner, add two commercial addresses at block 0312, lot 009 as; 65, 67 geary street | ||
| Feb 21, 2019 | Completed final sign-off Mar 2019 | 47 Geary St | Eco Fire Sprinklers Inc | nfpa 13 fire sprinkler installation add 2 sprinklers, relocate 8, remove 2 sprinklers in area 06 tenant improvementDetails
nfpa 13 fire sprinkler installation add 2 sprinklers, relocate 8, remove 2 sprinklers in area 06 tenant improvement | $5,540 |
| Feb 19, 2019 | Completed final sign-off Feb 2019 | 47 Geary St | Bilcor Inc | as-built to correct errors. ref ti #201901291466.Details
as-built to correct errors. ref ti #201901291466. | |
| Feb 11, 2019 | Completed final sign-off Jun 2019 | 49 Geary St | Jrm Construction Management | suite 67 - tenant improvement. minor interior demo, relocation of restroom, new walls for fitting room, (n) drop ceiling, plumb, mech, electrical, (n) flooring and fixturesDetails
suite 67 - tenant improvement. minor interior demo, relocation of restroom, new walls for fitting room, (n) drop ceiling, plumb, mech, electrical, (n) flooring and fixtures | $133,837 |
| Feb 4, 2019 | Never finaled issued Feb 2019, no final | 47 Geary St | Michilli Inc | anchorage of fixed and/or mobile retail shelving units at back of house.Details
anchorage of fixed and/or mobile retail shelving units at back of house. | $4,500 |
| Jan 29, 2019 | Completed final sign-off Feb 2019 | 49 Geary St | Bilcor Inc | fire alarm ti - install 6 wall mount speaker strobes, install 2 duct detetors with relay control. install 2 control relays, install 3 pull stations. ref pa 2018-1101-4745 and 2018-1211-8041Details
fire alarm ti - install 6 wall mount speaker strobes, install 2 duct detetors with relay control. install 2 control relays, install 3 pull stations. ref pa 2018-1101-4745 and 2018-1211-8041 | $6,500 |
| Jan 29, 2019 | Completed final sign-off Feb 2019 | 47 Geary St | Bilcor Inc | ground fl - fire alarm ti install 2 wall mount speaker strobes, install 1 pull station, install 2 duct detectors with control relay. ref pa 2018-1101-4746 and 2018-1130-7165Details
ground fl - fire alarm ti install 2 wall mount speaker strobes, install 1 pull station, install 2 duct detectors with control relay. ref pa 2018-1101-4746 and 2018-1130-7165 | $2,500 |
| Jan 25, 2019 | Completed final sign-off Jun 2019 | 55 Geary St | Dickinson Cameron Construction Company I | 1/f: t.i. of (e) retail space - work includes fixtures, partitions, millwork, changing rooms, etc. change of occupancy from a-3 to m. maher n/a.Details
1/f: t.i. of (e) retail space - work includes fixtures, partitions, millwork, changing rooms, etc. change of occupancy from a-3 to m. maher n/a. | $28,000 |
| Jan 24, 2019 | Never finaled issued Jan 2019, no final | 47 Geary St | street space onlyDetails
street space only | ||
| Jan 24, 2019 | Never finaled issued Jan 2019, no final | 49 Geary St | street space onlyDetails
street space only | ||
| Jan 23, 2019 | Never finaled issued Feb 2019, no final | 47 Geary St | Michilli Inc | revision to 201811135650 to include misc electrical and minor interior changesDetails
revision to 201811135650 to include misc electrical and minor interior changes | |
| Jan 14, 2019 | Completed final sign-off May 2019 | 47 Geary St | Golden Gate Sign Company Inc. | sign 3:to erect non electric 2 sided double face projecting sign (zadig + voltaire)Details
sign 3:to erect non electric 2 sided double face projecting sign (zadig + voltaire) | $3,000 |
| Jan 14, 2019 | Never finaled issued Feb 2019, no final | 47 Geary St | Golden Gate Sign Company Inc. | sign 2: store front window sign. non structural. (vadig + voltaire)Details
sign 2: store front window sign. non structural. (vadig + voltaire) | $1,000 |
| Jan 14, 2019 | Completed final sign-off May 2019 | 47 Geary St | Golden Gate Sign Company Inc. | sign 1:to erect non electric single wall sign (zadig + voltaire)Details
sign 1:to erect non electric single wall sign (zadig + voltaire) | $2,000 |
| Jan 4, 2019 | Completed final sign-off Aug 2019 | 55 Geary St | Dickinson Cameron Construction Company I | interior non structural demo of fixtures and finishes, no ext work. no work to rated construction. ab-017. n/a for maher.Details
interior non structural demo of fixtures and finishes, no ext work. no work to rated construction. ab-017. n/a for maher. | $20,000 |
| Dec 11, 2018 | Completed final sign-off Apr 2019 | 49 Geary St | Swinerton Builders | mechanical and electrical work only see pa 2018-1101-4745 for architectureDetails
mechanical and electrical work only see pa 2018-1101-4745 for architecture | $8,000 |
| Nov 30, 2018 | Completed final sign-off Apr 2019 | 47 Geary St | Swinerton Builders | mechanical and electrical only. see app#201811014746 and 201504214187. install hvac system to provide ventilation and space heating and cooling. install exhaust fan in new restroom.Details
mechanical and electrical only. see app#201811014746 and 201504214187. install hvac system to provide ventilation and space heating and cooling. install exhaust fan in new restroom. | $20,000 |
| Nov 13, 2018 | Completed final sign-off Feb 2020 | 47 Geary St | Michilli Inc | ground floor: interior renovation of extg dimised retail space: new fixtures, nw finishes, nw lighting, nw ceiling, nw electrical panels, nw ductwork. no exterior work. n/a for maherDetails
ground floor: interior renovation of extg dimised retail space: new fixtures, nw finishes, nw lighting, nw ceiling, nw electrical panels, nw ductwork. no exterior work. n/a for maher | $300,000 |
| Nov 1, 2018 | Completed final sign-off Mar 2019 | 47 Geary St | Swinerton Builders | ground level. construct 1 single occupant restroom incl non-load bearing partitions, ceiling, light fixture, new ddor & frame, plumbing fixtures and (n) finishes. maher n/aDetails
ground level. construct 1 single occupant restroom incl non-load bearing partitions, ceiling, light fixture, new ddor & frame, plumbing fixtures and (n) finishes. maher n/a | $45,000 |
| Nov 1, 2018 | Completed final sign-off Apr 2019 | 49 Geary St | Swinerton Builders | suites 65/67. construct of 2 single occupancy restrooms incl non-load bearing partitions, ceiling, light fixture, new doors & frames, plumbing fixtures and new finishes. maher n/aDetails
suites 65/67. construct of 2 single occupancy restrooms incl non-load bearing partitions, ceiling, light fixture, new doors & frames, plumbing fixtures and new finishes. maher n/a | $45,000 |
| Oct 19, 2018 | Never finaled issued Oct 2018, no final | 49 Geary St | street spaceDetails
street space | ||
| Sep 28, 2018 | Never finaled issued Sep 2018, no final | 47 Geary St | street spaceDetails
street space | ||
| Sep 28, 2018 | Never finaled issued Sep 2018, no final | 49 Geary St | street space.Details
street space. | ||
| Aug 22, 2018 | Completed final sign-off Sep 2018 | 49 Geary St | Bilcor Inc | 4/f suite 411: fire alarm ti - install 2 ceiling speaker-strobes ref pa 2018-0706-3961. maher n/a.Details
4/f suite 411: fire alarm ti - install 2 ceiling speaker-strobes ref pa 2018-0706-3961. maher n/a. | $1,000 |
| Jul 6, 2018 | Completed final sign-off Sep 2018 | 49 Geary St | Commercial Interior Builders Inc | ste 411 - modification of (e) ti to include construction of non-load bearing partitions, re-purposed office door & frame, salvage & re-use of existing materials if practicable. n/a for maher.Details
ste 411 - modification of (e) ti to include construction of non-load bearing partitions, re-purposed office door & frame, salvage & re-use of existing materials if practicable. n/a for maher. | $20,000 |
| Jun 29, 2018 | Never finaled issued Jul 2018, no final | 49 Geary St | Swinerton Builders | mezzanine: revision to 201803022704 relocating electrical card reader, intercom, telephone, biometric card reader and emergency door release.Details
mezzanine: revision to 201803022704 relocating electrical card reader, intercom, telephone, biometric card reader and emergency door release. | |
| May 31, 2018 | Completed final sign-off Apr 2019 | 49 Geary St | Swinerton Builders | revisionto 201504214189 revision provided structural shop drawings for bld storefront connections and loads maher naDetails
revisionto 201504214189 revision provided structural shop drawings for bld storefront connections and loads maher na | |
| May 16, 2018 | Completed final sign-off Sep 2018 | 49 Geary St | Bilcor Inc | fire alarm as built- adding card readers with a mushroom button. see sequence of operations- rev pa# 201805028013; install (1) control relay moduleDetails
fire alarm as built- adding card readers with a mushroom button. see sequence of operations- rev pa# 201805028013; install (1) control relay module | |
| May 2, 2018 | Completed final sign-off May 2018 | 49 Geary St | Bilcor Inc | fire alarm ti, install (3) ceiling mount speakers ref #201803022704Details
fire alarm ti, install (3) ceiling mount speakers ref #201803022704 | $1,500 |
| Mar 29, 2018 | Never finaled issued Mar 2018, no final | 47 Geary St | street space permit and mtaDetails
street space permit and mta | ||
| Mar 29, 2018 | Never finaled issued Mar 2018, no final | 49 Geary St | street space permit and mta - renewal of permit # m844527Details
street space permit and mta - renewal of permit # m844527 | ||
| Mar 16, 2018 | Completed final sign-off May 2018 | 49 Geary St | Swinerton Builders | revision of pa#201507232305, modify demo of 2nd level mezzanine slab removalDetails
revision of pa#201507232305, modify demo of 2nd level mezzanine slab removal | $5,000 |
| Mar 2, 2018 | Completed final sign-off Oct 2018 | 49 Geary St | Ayoob & Peery Plumbing Co Inc | 1/f: fire sprinklers: add (10), relocate (4), and plug (5) sprinklers in order to conform with the new walls and ceilings of the ti. ref #201712045411. maher naDetails
1/f: fire sprinklers: add (10), relocate (4), and plug (5) sprinklers in order to conform with the new walls and ceilings of the ti. ref #201712045411. maher na | $2,954 |
| Mar 2, 2018 | Completed final sign-off Sep 2018 | 49 Geary St | Swinerton Builders | modification of (e) ti to include selective demo and construction of non-load bearing partitions, light fixture relocation and re-switching. new office doors and frames, salvage and new finishes. proposed construction at the it/data room in this project does create an info tech roomDetails
modification of (e) ti to include selective demo and construction of non-load bearing partitions, light fixture relocation and re-switching. new office doors and frames, salvage and new finishes. proposed construction at the it/data room in this project does create an info tech room | $190,000 |
| Mar 2, 2018 | Completed final sign-off Jul 2019 | 47 Geary St | Ayoob & Peery Plumbing Co Inc | fire sprinklers: relocate (2) and change out (6) sprinklers. tie in second floor system to 1st fl in order to conform with the new wall and ceiling layout of the ti. ref #201712045409. maher naDetails
fire sprinklers: relocate (2) and change out (6) sprinklers. tie in second floor system to 1st fl in order to conform with the new wall and ceiling layout of the ti. ref #201712045409. maher na | $1,688 |
| Jan 31, 2018 | Completed final sign-off May 2018 | 49 Geary St | Bilcor Inc | suite #402: fire alarm t.i. to install 11 ceiling mount speaker strobe. install 3 duct detectors. install 3 control relay modules. ref app#201709198939. n/a for maherDetails
suite #402: fire alarm t.i. to install 11 ceiling mount speaker strobe. install 3 duct detectors. install 3 control relay modules. ref app#201709198939. n/a for maher | $7,500 |
| Jan 22, 2018 | Completed final sign-off Jun 2018 | 49 Geary St | San Francisco Commercial Builders Inc | #402. revision to current permitted office under pa 2017-0919-8939. finishes, full height (non load bearing) wallsDetails
#402. revision to current permitted office under pa 2017-0919-8939. finishes, full height (non load bearing) walls | $15,000 |
| Dec 7, 2017 | Never finaled issued Dec 2017, no final | 49 Geary St | C B F Inc | suite #402 -provide new lighting/branch circuiting to existing panel. maintain some of existing power and signal outlets and provided additional new ppower branch circuiting and raceways systems as required to new power and signal outlets. ref# 2017-0919-8939. n/a maherDetails
suite #402 -provide new lighting/branch circuiting to existing panel. maintain some of existing power and signal outlets and provided additional new ppower branch circuiting and raceways systems as required to new power and signal outlets. ref# 2017-0919-8939. n/a maher | $25,000 |
| Dec 4, 2017 | Completed final sign-off May 2018 | 47 Geary St | Swinerton Builders | commencement of work not started under 201507232306Details
commencement of work not started under 201507232306 | $10,000 |
| Dec 4, 2017 | Completed final sign-off May 2018 | 49 Geary St | Swinerton Builders | commencement of work not started under previously approved permit 201507232305Details
commencement of work not started under previously approved permit 201507232305 | $20,000 |
| Dec 1, 2017 | Completed final sign-off Jun 2018 | 49 Geary St | City Mechanical Inc | 4th fl hvac improvements - install fan coil & heat pump units as located to provide area with cooling & heating. install outside air fan for ventilation ref pa 2017-0919-8939Details
4th fl hvac improvements - install fan coil & heat pump units as located to provide area with cooling & heating. install outside air fan for ventilation ref pa 2017-0919-8939 | $95,000 |
| Nov 21, 2017 | Completed final sign-off May 2018 | 55 Geary St | Swinerton Builders | selective demo of non-load bearing partitions, ceilings, light fixtures, millwork, plumbing and finishesDetails
selective demo of non-load bearing partitions, ceilings, light fixtures, millwork, plumbing and finishes | $20,000 |
| Oct 16, 2017 | Never finaled issued Oct 2017, no final | 47 Geary St | street spaceDetails
street space | ||
| Oct 16, 2017 | Never finaled issued Oct 2017, no final | 49 Geary St | street spaceDetails
street space | ||
| Sep 19, 2017 | Completed final sign-off Jun 2018 | 49 Geary St | San Francisco Commercial Builders Inc | #402- modification & expansion of an (e) office to include selective demo & construct of non-load bearing partitions, modify (e) light fixtures & new including re-switching, new office doors & frames, salvage & reuse of (e) selected materials & new finishesDetails
#402- modification & expansion of an (e) office to include selective demo & construct of non-load bearing partitions, modify (e) light fixtures & new including re-switching, new office doors & frames, salvage & reuse of (e) selected materials & new finishes | $250,000 |
| Mar 29, 2017 | Completed final sign-off Mar 2017 | 49 Geary St | Bilcor Inc | fire alarm ti remove and replace 3 wall mount speaker strobes, 1 wall mount speaker strobeDetails
fire alarm ti remove and replace 3 wall mount speaker strobes, 1 wall mount speaker strobe | $1,600 |
| Mar 29, 2017 | Completed final sign-off Apr 2017 | 730 Market St | Golden Gate Fire Protection Inc | 1st floor: fire sprinkler only - relocate 2 heads in vestibule. ref 201706170313 maher naDetails
1st floor: fire sprinkler only - relocate 2 heads in vestibule. ref 201706170313 maher na | $500 |
| Mar 22, 2017 | Completed final sign-off Jun 2017 | 730 Market St | Peacock Construction | ground floor - t-24 electrical for work done under pa #201606170313.Details
ground floor - t-24 electrical for work done under pa #201606170313. | $18,000 |
| Jun 17, 2016 | Completed final sign-off Jun 2017 | 730 Market St | Peacock Construction | barrier removal - the walgreens employee break room is currently located on the upper level which is 42" higher than rest of store. disabled employees currently required to use gated lift for break room access. this application relocates break room to the lower levelDetails
barrier removal - the walgreens employee break room is currently located on the upper level which is 42" higher than rest of store. disabled employees currently required to use gated lift for break room access. this application relocates break room to the lower level | $50,000 |
| Feb 26, 2016 | Completed final sign-off Apr 2016 | 49 Geary St | Bayside Interiors Inc. | #411: demolition and drywall patching.Details
#411: demolition and drywall patching. | $4,800 |
| Dec 23, 2015 | Completed final sign-off Feb 2016 | 49 Geary St | Peacock Construction | mechanical for work done under pa# 201510079158.Details
mechanical for work done under pa# 201510079158. | $57,000 |
| Dec 14, 2015 | Expired or cancelled cancelled Aug 2023 | 49 Geary St | Bilcor Inc | 3rd floor fire alarm as-built ref to pa #201510079158 & #201510210407 - install 1 ceiling mount speaker/strobe.Details
3rd floor fire alarm as-built ref to pa #201510079158 & #201510210407 - install 1 ceiling mount speaker/strobe. | $500 |
| Dec 9, 2015 | Completed final sign-off Dec 2015 | 49 Geary St | Commercial Interior Builders Inc | suite #300: renovation of brown bag lunch area with associated electrical and plumbing work. non structural partitioning of storage space.Details
suite #300: renovation of brown bag lunch area with associated electrical and plumbing work. non structural partitioning of storage space. | $92,825 |
| Nov 6, 2015 | Completed final sign-off Feb 2016 | 49 Geary St | Peacock Construction | electrical for work done under pa#201510079158Details
electrical for work done under pa#201510079158 | $102,000 |
| Oct 21, 2015 | Completed final sign-off Jan 2016 | 49 Geary St | Bilcor Inc | 3/f: fire alarm ti install 10 ceiling mount speaker-strobes. revision to pa 2015-0921-7542, ti 2015-1007-9158Details
3/f: fire alarm ti install 10 ceiling mount speaker-strobes. revision to pa 2015-0921-7542, ti 2015-1007-9158 | $4,000 |
| Oct 7, 2015 | Completed final sign-off Feb 2016 | 49 Geary St | Peacock Construction | 3rd floor: includes selective construction of non-structural partitions, perimeter furring, new door and frame.Details
3rd floor: includes selective construction of non-structural partitions, perimeter furring, new door and frame. | $132,000 |
| Oct 7, 2015 | Completed final sign-off Feb 2016 | 49 Geary St | Peacock Construction | 3rd floor: construct new non-structural partitions, new light fixtures, new doors and frames, new millwork, sink and finishes. m & e and lifesafty under seperate permit.Details
3rd floor: construct new non-structural partitions, new light fixtures, new doors and frames, new millwork, sink and finishes. m & e and lifesafty under seperate permit. | $321,000 |
| Sep 21, 2015 | Completed final sign-off Dec 2015 | 49 Geary St | Bilcor Inc | 3rd flr: fire alarm - install 1 booster panelDetails
3rd flr: fire alarm - install 1 booster panel | $1,000 |
| Jul 30, 2015 | Completed final sign-off Aug 2015 | 49 Geary St | San Francisco Commercial Builders Inc | modification of extg t.i. to include construction of non-load bearing partitions, relocate and reswitch one light fixture, one new office door, frame & sidellight, new countertop and new sink at extg location, and new finishes. suite # 500Details
modification of extg t.i. to include construction of non-load bearing partitions, relocate and reswitch one light fixture, one new office door, frame & sidellight, new countertop and new sink at extg location, and new finishes. suite # 500 | $51,273 |
| Jul 23, 2015 | Expired or cancelled cancelled Apr 2019 | 49 Geary St | Swinerton Builders | interior demo of non load bearing partitions, ceiling, lighting, doors, and partial 2nd floor slab and framing. scope also includes new structural floor framing around area of slab removal. will comply with ab-017Details
interior demo of non load bearing partitions, ceiling, lighting, doors, and partial 2nd floor slab and framing. scope also includes new structural floor framing around area of slab removal. will comply with ab-017 | $250,000 |
| Jul 23, 2015 | Expired or cancelled cancelled Apr 2019 | 47 Geary St | Swinerton Builders | interior demo of non load bearing partitions, ceiling, lighting, doors, and partial 2nd floor slab and framing. scope also includes new structural floor framing around area of slab removal. will comply with ab-017Details
interior demo of non load bearing partitions, ceiling, lighting, doors, and partial 2nd floor slab and framing. scope also includes new structural floor framing around area of slab removal. will comply with ab-017 | $10,000 |
| Apr 21, 2015 | Completed final sign-off Apr 2019 | 49 Geary St | Swinerton Builders | demo and redesign of (e) storefront along geary street. demo inlcudes ground and second level. restoration of (e) stone pilasters, to be repaired with patching mortar. structural framing & details for storefront / curtainwall under separate permit.Details
demo and redesign of (e) storefront along geary street. demo inlcudes ground and second level. restoration of (e) stone pilasters, to be repaired with patching mortar. structural framing & details for storefront / curtainwall under separate permit. | $1,100,000 |
| Apr 21, 2015 | Completed final sign-off Mar 2019 | 47 Geary St | Swinerton Builders | demo and redesign of (e) storefront along geary street. demo inlcudes ground and level 2, storefront, partial floor slab and framing. mep under seperate permit.Details
demo and redesign of (e) storefront along geary street. demo inlcudes ground and level 2, storefront, partial floor slab and framing. mep under seperate permit. | $700,000 |
| Oct 22, 2014 | Completed final sign-off Jun 2015 | 49 Geary St | San Francisco Commercial Builders Inc | #350: interior t.i. demolition, non bearing partition wall, doors, flooring, millwork, ceilings, lighting.Details
#350: interior t.i. demolition, non bearing partition wall, doors, flooring, millwork, ceilings, lighting. | $41,000 |
| May 23, 2014 | Completed final sign-off Aug 2014 | 730 Market St | G P Fire Protection | relocate 3 sprinkler heads for new consulting room. seismically upgrade 2" branch line that work is being done off if needed. n/a maher ordinance 155-13Details
relocate 3 sprinkler heads for new consulting room. seismically upgrade 2" branch line that work is being done off if needed. n/a maher ordinance 155-13 | $3,260 |
| Apr 9, 2014 | Completed final sign-off Sep 2014 | 730 Market St | Walgreen Company | remodel existing walgreens, work includes adding a consult room in existing pharmacy and related work associated with this modification. new sink. no cooler/refrigerated cases- no sprinklers or fire alarm work required-Details
remodel existing walgreens, work includes adding a consult room in existing pharmacy and related work associated with this modification. new sink. no cooler/refrigerated cases- no sprinklers or fire alarm work required- | $40,000 |
| Mar 25, 2014 | Completed final sign-off Jul 2019 | 49 Geary St | Bilcor Inc | install 3 ceiling mount speakers-strobes. remove 2 wall mount speaker-strobes. t.i. app#201402259256Details
install 3 ceiling mount speakers-strobes. remove 2 wall mount speaker-strobes. t.i. app#201402259256 | $1,200 |
| Feb 25, 2014 | Completed final sign-off Aug 2014 | 49 Geary St | Rylko Builders Inc. | 2nd floor #238- interior t.i. to an (e) commercial class -a office space. improvements include (n) partitions casework & finishes, elec, lighting & plumbing. perform restroom improvements per disabled access 20% rule including relocation of toilet stall partition.Details
2nd floor #238- interior t.i. to an (e) commercial class -a office space. improvements include (n) partitions casework & finishes, elec, lighting & plumbing. perform restroom improvements per disabled access 20% rule including relocation of toilet stall partition. | $75,000 |
| Oct 2, 2013 | Never finaled issued Oct 2013, no final | 49 Geary St | street sapceDetails
street sapce | ||
| Jun 21, 2013 | Completed final sign-off Aug 2013 | 49 Geary St | Bilcor Inc | install 1 wall mount speaker strobeDetails
install 1 wall mount speaker strobe | $300 |
| May 8, 2013 | Completed final sign-off Sep 2013 | 49 Geary St | Michael Glynn Construction Services Inc, Principal Builders Inc. | suite 418 - building two new partitions & installing breakroom ocunter w/sink.Details
suite 418 - building two new partitions & installing breakroom ocunter w/sink. | $8,000 |
| Apr 16, 2013 | Completed final sign-off Apr 2013 | 49 Geary St | Bilcor Inc | 5th floor suite 530 - install 1 ceiling speaker/strobe & 6 wall speaker/strobes, replace 1 wall strobe, ref t.i. #2013.03.21.2777.Details
5th floor suite 530 - install 1 ceiling speaker/strobe & 6 wall speaker/strobes, replace 1 wall strobe, ref t.i. #2013.03.21.2777. | $4,000 |
| Mar 21, 2013 | Completed final sign-off Apr 2013 | 49 Geary St | Commercial Interior Builders Inc | 5th floor-add huddle room in (e) office space-work involves new wall, door, frame, glazing & track light relocation. no plumbing, electrical to be design build. mech, hvac also design buildDetails
5th floor-add huddle room in (e) office space-work involves new wall, door, frame, glazing & track light relocation. no plumbing, electrical to be design build. mech, hvac also design build | $8,000 |
| Dec 19, 2012 | Completed final sign-off Jul 2013 | 726 Market St | Mcm Construction Co | interior remodel (e) fedex office, no exterior.Details
interior remodel (e) fedex office, no exterior. | $75,000 |
| Oct 19, 2012 | Never finaled issued Oct 2012, no final | 49 Geary St | 2nd floor-shelving for t.i pa# 2012-0913-9707. no other workDetails
2nd floor-shelving for t.i pa# 2012-0913-9707. no other work | $10,000 | |
| Oct 9, 2012 | Completed final sign-off Jan 2013 | 49 Geary St | Shawmut Woodworking & Supply Inc | 2nd floor:revision to approved app#201209139707. scope is to clarify room 214 as storage and remove exhaust fan to comply and also addition of new sink in room 212,change to single wide door in room 201, and minor lighting and plumbing changes.Details
2nd floor:revision to approved app#201209139707. scope is to clarify room 214 as storage and remove exhaust fan to comply and also addition of new sink in room 212,change to single wide door in room 201, and minor lighting and plumbing changes. | $3,000 |
| Sep 13, 2012 | Completed final sign-off Jan 2013 | 49 Geary St | t.i for office on 2nd floor (mezz) work includes (n) partitions, doors, lockers, (n) chain link enclosure, (n) millwork, (n) lighting, mep & fire protection under separate permits.Details
t.i for office on 2nd floor (mezz) work includes (n) partitions, doors, lockers, (n) chain link enclosure, (n) millwork, (n) lighting, mep & fire protection under separate permits. | $35,000 | |
| Aug 15, 2012 | Completed final sign-off Feb 2013 | 722 Market St | Golden Gate Sign Company Inc. | erect electric, wall, single-faced, direct illuminated new sign.Details
erect electric, wall, single-faced, direct illuminated new sign. | $5,000 |
| May 13, 2011 | Completed final sign-off Jun 2011 | 49 Geary St | Commercial Interior Builders Inc | lighting updates/title 24 compliance. refer to app#201104284950 for additional work.Details
lighting updates/title 24 compliance. refer to app#201104284950 for additional work. | |
| Apr 28, 2011 | Completed final sign-off Jun 2011 | 49 Geary St | Commercial Interior Builders Inc | demolition of existing non bearing parition, doo, finishes, light fixtures. new non load bearing partition, finish flooring, light fixtures, elec/data, ceiling fans, lights, and ceiling, fans to be suspended from exposed concrete deckDetails
demolition of existing non bearing parition, doo, finishes, light fixtures. new non load bearing partition, finish flooring, light fixtures, elec/data, ceiling fans, lights, and ceiling, fans to be suspended from exposed concrete deck | $50,681 |
| Mar 31, 2011 | Completed final sign-off Nov 2011 | 730 Market St | Walgreen Company | sunscreen addition, beverage center addition, produce refrigeration, 3 comp sink, hand sinkDetails
sunscreen addition, beverage center addition, produce refrigeration, 3 comp sink, hand sink | $50,000 |
| Mar 2, 2011 | Expired or cancelled cancelled Jan 2026 | 730 Market St | v o i dDetails
v o i d | $2,000 | |
| Mar 2, 2011 | Never finaled issued Aug 2011, no final | 730 Market St | to erect electric, wall, single faced sign. install one new illuminated wall sign reading "pharmacy" for walgreensDetails
to erect electric, wall, single faced sign. install one new illuminated wall sign reading "pharmacy" for walgreens | $2,000 | |
| Dec 3, 2010 | Completed final sign-off Jan 2011 | 730 Market St | G P Fire Protection | 1/f - relocate 10 sprinkler headsDetails
1/f - relocate 10 sprinkler heads | $3,800 |
| Nov 30, 2010 | Completed final sign-off Jan 2011 | 730 Market St | Walgreen Company | minor remodel of pharmacy, waiting area, managers office and sales area and existing storage roomDetails
minor remodel of pharmacy, waiting area, managers office and sales area and existing storage room | $75,000 |
| Jun 2, 2010 | Never finaled issued Jun 2010, no final | 55 Geary St | R L H Fire Protection Inc | relocate 9 sprinkler heads and add 1 head to an existing system on the first floorDetails
relocate 9 sprinkler heads and add 1 head to an existing system on the first floor | $3,000 |
| May 14, 2010 | Completed final sign-off Jun 2010 | 55 Geary St | Pankow Special Projects Lp | interior remodel only - (n) partitions & doors, (n) wet bar, minor reconfiguration of (e) lighting & electrical @ ground flr.Details
interior remodel only - (n) partitions & doors, (n) wet bar, minor reconfiguration of (e) lighting & electrical @ ground flr. | $40,000 |
| Apr 26, 2010 | Completed final sign-off Jul 2010 | 49 Geary St | Russell Hinton Company | office ti on thr 5th fl. suite # 500. new non bearing partitions, new finishes, new electrical, new lightingDetails
office ti on thr 5th fl. suite # 500. new non bearing partitions, new finishes, new electrical, new lighting | $111,000 |
| Sep 2, 2009 | Never finaled issued Sep 2009, no final | 726 Market St | Mina-Tree Signs, Inc | install (1) set of illuminated channel letters on wall for "fedex office".Details
install (1) set of illuminated channel letters on wall for "fedex office". | $2,000 |
| Aug 24, 2009 | Completed final sign-off Oct 2009 | 49 Geary St | remove existing non load bearing partitions and cabinetry. construct new non load bearing parittions, paint, patch, minor electric. upgrade exisitng bath to meet current accessibility standards. no new lighting under this permitDetails
remove existing non load bearing partitions and cabinetry. construct new non load bearing parittions, paint, patch, minor electric. upgrade exisitng bath to meet current accessibility standards. no new lighting under this permit | $30,000 | |
| Apr 20, 2009 | Completed final sign-off Jul 2009 | 730 Market St | Golden Gate Sign Company Inc. | renew pa# 2008/01/29/3457 to obtain final inspection. all work has been completed.Details
renew pa# 2008/01/29/3457 to obtain final inspection. all work has been completed. | |
| Aug 21, 2008 | Never finaled issued Aug 2008, no final | 49 Geary St | street spaceDetails
street space | ||
| Aug 12, 2008 | Expired or cancelled expired Jun 2011 | 49 Geary St | demolition of interior non structural wall, interior door and misc. built in storage installation of new 1hr non bearing interior wall and 20 min rated double doorDetails
demolition of interior non structural wall, interior door and misc. built in storage installation of new 1hr non bearing interior wall and 20 min rated double door | $8,000 | |
| Jul 22, 2008 | Expired or cancelled expired Jun 2011 | 49 Geary St | #509- 1)demo 3 extg walls (non bearing). 2)install door to adjoining space. 3) build 2 walls. 4) sheetrock 1 extg wall. 5) move 1 lightswitch.Details
#509- 1)demo 3 extg walls (non bearing). 2)install door to adjoining space. 3) build 2 walls. 4) sheetrock 1 extg wall. 5) move 1 lightswitch. | $8,000 | |
| May 7, 2008 | Never finaled issued May 2008, no final | 49 Geary St | street spaceDetails
street space | ||
| Apr 30, 2008 | Completed final sign-off Jun 2009 | 49 Geary St | revision to 200703297622. lower 3 stories of steel braced frame at gl.e.1 is revised to concrete shear wall w/openings. new wall opening added to the concrete shear wall at gl.e on the lower basement level. length of 2 concrete shear wall piers at gl.e on basement is revised.Details
revision to 200703297622. lower 3 stories of steel braced frame at gl.e.1 is revised to concrete shear wall w/openings. new wall opening added to the concrete shear wall at gl.e on the lower basement level. length of 2 concrete shear wall piers at gl.e on basement is revised. | $10,000 | |
| Feb 27, 2008 | Never finaled issued Feb 2008, no final | 49 Geary St | street space permit.Details
street space permit. | ||
| Jan 29, 2008 | Expired or cancelled expired Jul 2009 | 730 Market St | Golden Gate Sign Company Inc. | replace existing "pharmacy" sign with new sign "food mart". same location.Details
replace existing "pharmacy" sign with new sign "food mart". same location. | $5,001 |
| Nov 8, 2007 | Never finaled issued Nov 2007, no final | 47 Geary St | street spaceDetails
street space | ||
| Oct 5, 2007 | Never finaled issued Oct 2007, no final | 49 Geary St | sidewalk onlyDetails
sidewalk only | ||
| Aug 14, 2007 | Never finaled issued Aug 2007, no final | 730 Market St | street space permitDetails
street space permit | ||
| Jul 20, 2007 | Completed final sign-off Feb 2008 | 49 Geary St | modification to exist bldg lobby including n store front entry door, glazing, new finishes. all work in full compliance w/all applicable fed,state,local codes. e hvac,power and life safety comply fully and will not be modified. n storefront double door and sidelights replaced in kindDetails
modification to exist bldg lobby including n store front entry door, glazing, new finishes. all work in full compliance w/all applicable fed,state,local codes. e hvac,power and life safety comply fully and will not be modified. n storefront double door and sidelights replaced in kind | $153,712 | |
| Mar 29, 2007 | Completed final sign-off Jun 2009 | 49 Geary St | provide voluntary seismic upgrade. not in full compliance with sec. 3403.6, sfbc, 2001.Details
provide voluntary seismic upgrade. not in full compliance with sec. 3403.6, sfbc, 2001. | $5,000,000 | |
| Jan 25, 2007 | Expired or cancelled expired Apr 2009 | 49 Geary St | Sabah International Incorporated | install & final one novec 1230 fire suppression system to protect the photo storage room. application is total flooding. method of detection: smoke detectors.Details
install & final one novec 1230 fire suppression system to protect the photo storage room. application is total flooding. method of detection: smoke detectors. | $32,922 |
| Oct 18, 2006 | Completed final sign-off Nov 2006 | 726 Market St | Rcm Fire Protection Inc. | relocate 18 existing spkr. drops to new locatin w/ new spkr hds @ 1st floor only.Details
relocate 18 existing spkr. drops to new locatin w/ new spkr hds @ 1st floor only. | $3,500 |
| Sep 15, 2006 | Never finaled issued Sep 2006, no final | 726 Market St | Signs Of All Kinds | to erect a single faced electrical wall signDetails
to erect a single faced electrical wall sign | |
| Sep 6, 2006 | Completed final sign-off Nov 2006 | 726 Market St | non-structural interior demolition and construction including new partitions, fixtures and finishes. 1 hc accessible rr is extg to remainDetails
non-structural interior demolition and construction including new partitions, fixtures and finishes. 1 hc accessible rr is extg to remain | $70,000 | |
| Jun 14, 2006 | Expired or cancelled expired Jan 2007 | 49 Geary St | Sabah International Incorporated | renew 200406237202.Details
renew 200406237202. | $11,500 |
| May 12, 2006 | Completed final sign-off Aug 2006 | 49 Geary St | San Francisco Commercial Builders Inc | 2 partition walls and outlets on 2nd floorDetails
2 partition walls and outlets on 2nd floor | $5,400 |
| Nov 18, 2005 | Never finaled issued Nov 2005, no final | 49 Geary St | Bcci Construction Company | mechanical work on floor 2Details
mechanical work on floor 2 | $10,000 |
| Nov 16, 2005 | Completed final sign-off Jan 2006 | 49 Geary St | Bcci Construction Company | electrical work on the 2nd fl,suite 218.Details
electrical work on the 2nd fl,suite 218. | $8,000 |
| Nov 15, 2005 | Completed final sign-off Jan 2006 | 49 Geary St | Simplex Grinnell | 2nd floor, suite 218 - add one smoke detector (conventional), 5 speaker/storbe (ceiling mont).Details
2nd floor, suite 218 - add one smoke detector (conventional), 5 speaker/storbe (ceiling mont). | $5,000 |
| Nov 10, 2005 | Completed final sign-off Feb 2006 | 49 Geary St | Bcci Construction Company | electrical work on 3rd floor.Details
electrical work on 3rd floor. | $15,000 |
| Nov 1, 2005 | Completed final sign-off Feb 2006 | 49 Geary St | Simplex Grinnell | addition of: (conventional) 5 smoke detectors 3rd floor, 1 nac cocntroller, 16 ceil. mnt. speaker/strobes, 2 door holdersDetails
addition of: (conventional) 5 smoke detectors 3rd floor, 1 nac cocntroller, 16 ceil. mnt. speaker/strobes, 2 door holders | $7,000 |
| Oct 17, 2005 | Completed final sign-off Jan 2006 | 49 Geary St | t.i.for architectural office including (n)partitions, (n) finishes, (n) casework, (n) lighting. mechanical under seperate permit.Details
t.i.for architectural office including (n)partitions, (n) finishes, (n) casework, (n) lighting. mechanical under seperate permit. | $55,000 | |
| Oct 11, 2005 | Completed final sign-off Jan 2006 | 49 Geary St | interior non--structural 'soft' 2nd floor demo in advange of tenant improvement under separate permit.Details
interior non--structural 'soft' 2nd floor demo in advange of tenant improvement under separate permit. | $3,750 | |
| Oct 7, 2005 | Completed final sign-off Aug 2006 | 49 Geary St | oti-1 3rd floor el, me, l/sDetails
oti-1 3rd floor el, me, l/s | $75,000 | |
| Sep 14, 2005 | Expired or cancelled expired Jan 2007 | 49 Geary St | C B F Inc | add / installing 1 speaker / strobe @ 49 geary street.Details
add / installing 1 speaker / strobe @ 49 geary street. | $800 |
| Sep 9, 2005 | Never finaled issued Sep 2005, no final | 49 Geary St | street spaceDetails
street space | ||
| Aug 30, 2005 | Completed final sign-off Feb 2006 | 49 Geary St | oti-1, 3rd floor, el, me, ls, sp.Details
oti-1, 3rd floor, el, me, ls, sp. | $450,000 | |
| Jul 29, 2005 | Completed final sign-off Dec 2005 | 49 Geary St | construct interior partitions to create two enclosed office and a breakroom. replace (e) sink +Details
construct interior partitions to create two enclosed office and a breakroom. replace (e) sink + | $10,600 | |
| Jul 1, 2005 | Never finaled issued Jul 2005, no final | 730 Market St | street spaceDetails
street space | ||
| May 16, 2005 | Completed final sign-off Apr 2006 | 49 Geary St | exterior facade repairs.repair holes & open seams in (e)sheet metal cornice,remove (e) paint/sealantDetails
exterior facade repairs.repair holes & open seams in (e)sheet metal cornice,remove (e) paint/sealant | $350,000 | |
| Apr 27, 2005 | Completed final sign-off Jun 2005 | 49 Geary St | San Francisco Commercial Builders Inc | mezzanine(between 1 & 2) -demo walls,add glass walls.alter restrm, add elec outlets.relocate lights.Details
mezzanine(between 1 & 2) -demo walls,add glass walls.alter restrm, add elec outlets.relocate lights. | $26,000 |
| Apr 14, 2005 | Completed final sign-off Jul 2005 | 49 Geary St | San Francisco Commercial Builders Inc | suite 411-build 19' long wall 9'9" h1, patch sheetrock on columns. reverse door swing-interior door.Details
suite 411-build 19' long wall 9'9" h1, patch sheetrock on columns. reverse door swing-interior door. | $2,000 |
| Dec 10, 2004 | Never finaled issued Dec 2004, no final | 49 Geary St | interior demo of tenant improvements on floors 3,2, & basementDetails
interior demo of tenant improvements on floors 3,2, & basement | $50,000 | |
| Jun 23, 2004 | Expired or cancelled expired Jan 2007 | 49 Geary St | Sabah International Incorporated | provide & install one fm200 system/final & test. 1 control panel, abort, horn/strobe, strobe, cyclinDetails
provide & install one fm200 system/final & test. 1 control panel, abort, horn/strobe, strobe, cyclin | $23,000 |
| Nov 18, 2003 | Expired or cancelled expired Jul 2006 | 49 Geary St | Turner Construction Co | soft demo: bsmnt, 2nd-3rd floor line diagrram of elect. demo; roof elec. mechDetails
soft demo: bsmnt, 2nd-3rd floor line diagrram of elect. demo; roof elec. mech | $180,000 |
| Oct 7, 2003 | Completed final sign-off Nov 2003 | 49 Geary St | 5/f- project include but not limit to selective demolition, new construction, finishes, lighting,Details
5/f- project include but not limit to selective demolition, new construction, finishes, lighting, | $15,000 | |
| Aug 14, 2003 | Completed final sign-off Oct 2003 | 49 Geary St | Rudolph Commercial Interiors Inc, Rci | minor demo carpentry door work and glass sheetrk finishes & minor elec. @ 2/f onlyDetails
minor demo carpentry door work and glass sheetrk finishes & minor elec. @ 2/f only | $45,229 |
| Aug 1, 2003 | Completed final sign-off Sep 2003 | 49 Geary St | new storage closet in existing gallery space-minor revisions to lighting- no increase in wattageDetails
new storage closet in existing gallery space-minor revisions to lighting- no increase in wattage | $6,000 | |
| Jul 24, 2003 | Completed final sign-off Aug 2003 | 49 Geary St | Charles M Prescott Electr | to renew app#2001/08/22/6636,2000/05/26/1144 &2001/01/05/9294 for final inspection.Details
to renew app#2001/08/22/6636,2000/05/26/1144 &2001/01/05/9294 for final inspection. | |
| Apr 3, 2003 | Expired or cancelled withdrawn Apr 2003 | 49 Geary St | oti-1 5th fl. lsDetails
oti-1 5th fl. ls | $13,000 | |
| Mar 11, 2003 | Expired or cancelled expired Dec 2004 | 49 Geary St | Rudolph Commercial Interiors Inc, Rci | oti-1, 7th fl, el, me, ls, sp.Details
oti-1, 7th fl, el, me, ls, sp. | $65,800 |
| Jul 24, 2002 | Never finaled issued Jul 2002, no final | 740 Market St | street space permitDetails
street space permit | ||
| Jul 3, 2002 | Completed final sign-off Dec 2002 | 730 Market St | provide exterior facade repair per plans repair all holes and open seams in (e) sheet metal cornlcesDetails
provide exterior facade repair per plans repair all holes and open seams in (e) sheet metal cornlces | $200,000 | |
| Jul 2, 2002 | Completed final sign-off Oct 2002 | 49 Geary St | tenant improvement to existing tenant spaces: partitions, doors, lighting, finishesDetails
tenant improvement to existing tenant spaces: partitions, doors, lighting, finishes | $55,000 | |
| Mar 22, 2002 | Expired or cancelled expired Jul 2002 | 49 Geary St | C B F Inc | modification to fire alarm system @ 49 geary st#525 (2) had open & (2) smoke detectorsDetails
modification to fire alarm system @ 49 geary st#525 (2) had open & (2) smoke detectors | $1,200 |
| Mar 14, 2002 | Completed final sign-off Apr 2002 | 49 Geary St | Dpr Construction Inc | oti-2, 5th floor, el, meDetails
oti-2, 5th floor, el, me | $15,000 |
| Mar 7, 2002 | Expired or cancelled expired Apr 2004 | 740 Market St | Plant Construction | to renew app#9919171,2000/04/20/7717,2000/07/06/4412 for final inspection.Details
to renew app#9919171,2000/04/20/7717,2000/07/06/4412 for final inspection. | |
| Feb 26, 2002 | Completed final sign-off Apr 2002 | 49 Geary St | Dpr Construction Inc | oti-1 5th flr ltg, mech ls, sprDetails
oti-1 5th flr ltg, mech ls, spr | $40,000 |
| Feb 15, 2002 | Completed final sign-off Apr 2002 | 49 Geary St | new partitions, lighting, floors, space has no heating or cooling, no hvac under this permitDetails
new partitions, lighting, floors, space has no heating or cooling, no hvac under this permit | $8,000 | |
| Feb 13, 2002 | Expired or cancelled expired Jun 2002 | 49 Geary St | street spaceDetails
street space | ||
| Feb 8, 2002 | Expired or cancelled expired Aug 2002 | 740 Market St | street spaceDetails
street space | ||
| Nov 5, 2001 | Completed final sign-off Dec 2001 | 49 Geary St | M.A. Mortenson Companies, Inc. | revision 200010274292 add 1 smoke detector above preaction panels 2 panels total change sequenceDetails
revision 200010274292 add 1 smoke detector above preaction panels 2 panels total change sequence | |
| Oct 3, 2001 | Expired or cancelled cancelled Nov 2024 | 49 Geary St | revise 2000/10/27/4292.add 1 smoke detector above preactors on 2 panels.Details
revise 2000/10/27/4292.add 1 smoke detector above preactors on 2 panels. | ||
| Aug 22, 2001 | Expired or cancelled expired Aug 2003 | 49 Geary St | Charles M Prescott Electr | reroute duct between 2nd floor and 3rd floorDetails
reroute duct between 2nd floor and 3rd floor | |
| May 18, 2001 | Completed final sign-off Jun 2001 | 49 Geary St | C B F Inc | life safety modefication relocate strokes basement onlyDetails
life safety modefication relocate strokes basement only | $400 |
| May 8, 2001 | Completed final sign-off Jul 2001 | 55 Geary St | Sullivan & Brampton | to erect non electrical signDetails
to erect non electrical sign | |
| Apr 12, 2001 | Expired or cancelled expired Oct 2001 | 726 Market St | C B F Inc | life safety modifications on 1st floorDetails
life safety modifications on 1st floor | $1,500 |
| Mar 1, 2001 | Completed final sign-off Jul 2001 | 726 Market St | provide sprinkler protector for new floor planDetails
provide sprinkler protector for new floor plan | $1,800 | |
| Feb 28, 2001 | Completed final sign-off Jul 2001 | 726 Market St | Cbc Construction | tidf-tenant improvement-partitions,ceiling,Details
tidf-tenant improvement-partitions,ceiling, | $142,000 |
| Feb 8, 2001 | Completed final sign-off Dec 2001 | 49 Geary St | Cosco Fire Protection Inc. | install pump and new preaction systems for protection of two areas on the third floor only.Details
install pump and new preaction systems for protection of two areas on the third floor only. | $99,000 |
| Jan 5, 2001 | Expired or cancelled expired Mar 2002 | 49 Geary St | revision to pa#2000005261144Details
revision to pa#2000005261144 | $50,000 | |
| Jan 3, 2001 | Completed final sign-off Sep 2001 | 726 Market St | demolish existing stair and infill hole in slab 1st floorDetails
demolish existing stair and infill hole in slab 1st floor | $75,000 | |
| Nov 13, 2000 | Completed final sign-off Dec 2000 | 55 Geary St | Sullivan & Brampton | non structural signDetails
non structural sign | $400 |
| Nov 13, 2000 | Completed final sign-off Dec 2000 | 55 Geary St | Sullivan & Brampton | 2 awnings at 1st floor store frontDetails
2 awnings at 1st floor store front | $6,000 |
| Oct 31, 2000 | Completed final sign-off Dec 2000 | 55 Geary St | C B F Inc | life safety modifcation to (e) system in tenant space waterworks first floorDetails
life safety modifcation to (e) system in tenant space waterworks first floor | $4,000 |
| Oct 27, 2000 | Completed final sign-off Dec 2001 | 49 Geary St | fire alarm/sprinkler under separate permitDetails
fire alarm/sprinkler under separate permit | $160,000 | |
| Oct 26, 2000 | Expired or cancelled expired Jul 2001 | 55 Geary St | revise to app #200007135030 provide auto door opener provide new tile finish at window sill new tracDetails
revise to app #200007135030 provide auto door opener provide new tile finish at window sill new trac | ||
| Oct 12, 2000 | Expired or cancelled expired Sep 2002 | 49 Geary St | Turner Construction**See 210639**** | oti-2, 2nd floor, el, meDetails
oti-2, 2nd floor, el, me | $30,000 |
| Sep 14, 2000 | Completed final sign-off May 2022 | 722 Market St | R & D Porter Company Inc | rework landing at front door, install power door operation per ab 012 handship. notice of violation#Details
rework landing at front door, install power door operation per ab 012 handship. notice of violation# | $7,500 |
| Aug 31, 2000 | Completed final sign-off Dec 2000 | 55 Geary St | fire sprklrsDetails
fire sprklrs | $13,500 | |
| Jul 13, 2000 | Completed final sign-off Dec 2000 | 55 Geary St | facade and exgterior comply with adaDetails
facade and exgterior comply with ada | $25,000 |