Apr 2022 to Mar 2026

10 permits since 2000 (engineer on 10 permits): 8 completed, 2 in progress.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Mar 16, 2026In progress
issued Jul 2026
1800 Owens StDome Construction Corpsector 1, level 1; t.i. to develop a pilates studio. work out area with (12) reformers machines, reception area with merchandise. propose new exterior entrance. approx 100 sqft. of the slab in new entry way to be demo and sloped (1.5% max) for accessiblity.
Details
Permit
202603167623
Status
issued
Filed
Mar 16, 2026
Permit issued
Jul 29, 2026
Declared cost
$255,000
Address
1800 Owens St

sector 1, level 1; t.i. to develop a pilates studio. work out area with (12) reformers machines, reception area with merchandise. propose new exterior entrance. approx 100 sqft. of the slab in new entry way to be demo and sloped (1.5% max) for accessiblity.

Open the permit page

$255,000
Oct 22, 2025In progress
filed Oct 2025, not yet issued
433 Kearny Stelevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc.
Details
Permit
202510227929
Status
filed
Filed
Oct 22, 2025
Declared cost
$2,300,000
Address
433 Kearny St

elevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc.

Open the permit page

$2,300,000
Feb 5, 2025Completed
final sign-off May 2025
3533 California StTurner Construction Cointerior soft demo of (e) vacant space. ada upgrades will be provide on subsequent ti permit ab-017. level 1 consists of demo (e) interior non-structural paritions, doors, millwork, floor finishes, furnitures, atm, ceiling systems, light fixtures, ceiling accesories, electrical outlets, mechanical
Details
Permit
202502059696
Status
complete
Filed
Feb 5, 2025
Permit issued
Feb 21, 2025
Final sign-off
May 30, 2025
Declared cost
$100,000
Address
3533 California St

interior soft demo of (e) vacant space. ada upgrades will be provide on subsequent ti permit ab-017. level 1 consists of demo (e) interior non-structural paritions, doors, millwork, floor finishes, furnitures, atm, ceiling systems, light fixtures, ceiling accesories, electrical outlets, mechanical

Open the permit page

$100,000
Dec 17, 2024Completed
final sign-off Apr 2025
111 Pine StTurner Construction Corevision to pa# 202406275356: 2/f mechanical update to add dedicated backup exhaust serving idf room.
Details
Permit
202412177001
Status
complete
Filed
Dec 17, 2024
Permit issued
Jan 14, 2025
Final sign-off
Apr 11, 2025
Declared cost
$20,000
Address
111 Pine St

revision to pa# 202406275356: 2/f mechanical update to add dedicated backup exhaust serving idf room.

Open the permit page

$20,000
Sep 25, 2024Completed
final sign-off Apr 2025
111 Pine StTurner Construction Co2/f- revision to permit# 202406275356: there is a new corridor/hallway and idf room updates.
Details
Permit
202409251567
Status
complete
Filed
Sep 25, 2024
Permit issued
Oct 2, 2024
Final sign-off
Apr 11, 2025
Declared cost
$50,000
Address
111 Pine St

2/f- revision to permit# 202406275356: there is a new corridor/hallway and idf room updates.

Open the permit page

$50,000
Aug 9, 2024Completed
final sign-off Feb 2025
111 Pine StTurner Construction Corevision to pa# 202402075406: updating mechanical drawing m-201 to show correct as-built conditions and (e) fsd locations. scope is limited to mechanical only.
Details
Permit
202408098331
Status
complete
Filed
Aug 9, 2024
Permit issued
Aug 21, 2024
Final sign-off
Feb 26, 2025
Address
111 Pine St

revision to pa# 202402075406: updating mechanical drawing m-201 to show correct as-built conditions and (e) fsd locations. scope is limited to mechanical only.

Open the permit page

Nov 13, 2023Completed
final sign-off Aug 2024
180 Montgomery StBcci Construction Company13/f: new office ti to include new non-structural partitions, ceilings, finishes, and associated mep work. ref demo permit 202310108327
Details
Permit
202311130699
Status
complete
Filed
Nov 13, 2023
Permit issued
Dec 15, 2023
Final sign-off
Aug 30, 2024
Declared cost
$1,912,802
Address
180 Montgomery St

13/f: new office ti to include new non-structural partitions, ceilings, finishes, and associated mep work. ref demo permit 202310108327

Open the permit page

$1,912,802
Oct 11, 2023Completed
final sign-off Aug 2024
180 Montgomery StBcci Construction Company25th floor: demo only permit per ab-017, demo without full access compliance for interior demo only. mep demo included. tenant improvement permit deferred.
Details
Permit
202310118389
Status
complete
Filed
Oct 11, 2023
Permit issued
Nov 6, 2023
Final sign-off
Aug 30, 2024
Declared cost
$100,000
Address
180 Montgomery St

25th floor: demo only permit per ab-017, demo without full access compliance for interior demo only. mep demo included. tenant improvement permit deferred.

Open the permit page

$100,000
Mar 21, 2023Completed
final sign-off Nov 2023
1 Bush StBcci Construction Company18th/f office t.i. demo (e) partition & ceiling. new partitions and finishes, mep included
Details
Permit
202303214057
Status
complete
Filed
Mar 21, 2023
Permit issued
Apr 18, 2023
Final sign-off
Nov 20, 2023
Declared cost
$1,100,000
Address
1 Bush St

18th/f office t.i. demo (e) partition & ceiling. new partitions and finishes, mep included

Open the permit page

$1,100,000
Apr 7, 2022Completed
final sign-off Oct 2022
222 Sansome StCw Horton General Contractorrevision to pa# 201907186324. to document change in designated accessible mobility guestrooms.
Details
Permit
202204071785
Status
complete
Filed
Apr 7, 2022
Permit issued
Jun 28, 2022
Final sign-off
Oct 17, 2022
Address
222 Sansome St

revision to pa# 201907186324. to document change in designated accessible mobility guestrooms.

Open the permit page