13 permits since 2000 (engineer on 13 permits): 4 completed, 9 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 13, 2026 | In progress issued Jun 2026 | 1800 Owens St | Dome Construction Corp | floor 4 to 7: upgrading the finishes to existing elevator lobbies. 1st floor: replacing floor finished and installing new shower glass doors in existing restrooms. for general building accessible upgrades. ref#2202406255203Details
floor 4 to 7: upgrading the finishes to existing elevator lobbies. 1st floor: replacing floor finished and installing new shower glass doors in existing restrooms. for general building accessible upgrades. ref#2202406255203 | $300,000 |
| Mar 16, 2026 | In progress issued Jul 2026 | 1800 Owens St | Dome Construction Corp | sector 1, level 1; t.i. to develop a pilates studio. work out area with (12) reformers machines, reception area with merchandise. propose new exterior entrance. approx 100 sqft. of the slab in new entry way to be demo and sloped (1.5% max) for accessiblity.Details
sector 1, level 1; t.i. to develop a pilates studio. work out area with (12) reformers machines, reception area with merchandise. propose new exterior entrance. approx 100 sqft. of the slab in new entry way to be demo and sloped (1.5% max) for accessiblity. | $255,000 |
| Nov 24, 2025 | In progress filed Nov 2025, not yet issued | 123 Ofarrell St | elevator modernization of 3 traction elevtors 1,2&3.upgrademew machines, new microprocessor based controllers, digital landing equipment, new guide rollers, new wiring at machine room. 2 way emergency interactive video/text based communication system.Details
elevator modernization of 3 traction elevtors 1,2&3.upgrademew machines, new microprocessor based controllers, digital landing equipment, new guide rollers, new wiring at machine room. 2 way emergency interactive video/text based communication system. | $1,065,000 | |
| Oct 22, 2025 | In progress filed Oct 2025, not yet issued | 433 Kearny St | elevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc.Details
elevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc. | $2,300,000 | |
| Oct 14, 2025 | In progress issued Feb 2026 | 500 Terry A Francois Bl | Novo Construction Inc | ground floor ti work includes refresh of tenant spaces north and main lobby and full ti to suite soth main lobby. partitions, fixtures and finishes and associated mepDetails
ground floor ti work includes refresh of tenant spaces north and main lobby and full ti to suite soth main lobby. partitions, fixtures and finishes and associated mep | $5,263,755 |
| Oct 14, 2025 | In progress issued Jan 2026 | 500 Terry A Francois Bl | Novo Construction Inc | deferred electrical work, ref 2/f t.i. pa 202506269604.Details
deferred electrical work, ref 2/f t.i. pa 202506269604. | |
| Sep 30, 2025 | Completed final sign-off Jun 2026 | 100 California St | West Coast Build Aka Fairway Constructio | basement: remodel of existing amenity gym. new non-structural partitions, lighting, power, millwork and finishesDetails
basement: remodel of existing amenity gym. new non-structural partitions, lighting, power, millwork and finishes | $1,160,414 |
| Jul 2, 2025 | In progress issued Aug 2025 | 500 Terry A Francois Bl | Novo Construction Inc | 3rd floor: interior alteration of existing tenant space, including light touch alterations, including finishes, fixture and equipment. mep included.Details
3rd floor: interior alteration of existing tenant space, including light touch alterations, including finishes, fixture and equipment. mep included. | $4,790,589 |
| Jul 1, 2025 | In progress issued Oct 2025 | 500 Terry A Francois Bl | Novo Construction Inc | 4th fl: interior alteration at existing tenant space including light touch alterations, including finishes, fixtures, equipment. mep included.Details
4th fl: interior alteration at existing tenant space including light touch alterations, including finishes, fixtures, equipment. mep included. | $4,322,847 |
| Jun 26, 2025 | In progress issued Aug 2025 | 500 Terry A Francois Bl | Novo Construction Inc | 2/fl: interior alteration of existing tenant spaces\. light touch alteration includes finishes, fixtures, equipment.Details
2/fl: interior alteration of existing tenant spaces\. light touch alteration includes finishes, fixtures, equipment. | $4,203,710 |
| Apr 9, 2025 | Completed final sign-off Sep 2026 | 100 California St | Turner Construction Co | alterations to the two-story facade fronting the plaza & remedial waterproofing of the (e) planter. installation of curtain wall, all work within the property line, no alteration or impact to the public right of way.Details
alterations to the two-story facade fronting the plaza & remedial waterproofing of the (e) planter. installation of curtain wall, all work within the property line, no alteration or impact to the public right of way. | $1,300,000 |
| Oct 4, 2023 | Completed final sign-off Dec 2025 | 1 Bush St | Bcci Construction Company | 3rd fl demo and construction of interior partitoins, open work space and conference rooms. mep included.Details
3rd fl demo and construction of interior partitoins, open work space and conference rooms. mep included. | $400,000 |
| Dec 15, 2022 | Completed final sign-off Mar 2025 | 140 New Montgomery St | Bcci Construction Company | 10th fl: demo and construction of new office. new work areas, officds, meeting rooms, all gender restrooms, lactation room and break rooms. mep included.Details
10th fl: demo and construction of new office. new work areas, officds, meeting rooms, all gender restrooms, lactation room and break rooms. mep included. | $1,200,000 |