Michael Schulte
- Listed as
- architect, authorized agent-others, engineer
- Based in
- San Francisco
- On San Francisco permits
- May 2004 to Sep 2026
86 permits since 2000 (architect on 82 permits, authorized agent-others on 2 permits, engineer on 2 permits): 65 completed, 9 in progress, 3 never finaled, 9 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 16, 2026 | In progress issued Sep 2026 | 348 Hazelwood Av | Gil Construction & Assoc Inc. | convert a portion of crawl space and storage space into a den w/ closet. add 1 window facing the street.Details
convert a portion of crawl space and storage space into a den w/ closet. add 1 window facing the street. | $30,000 |
| Aug 27, 2026 | In progress filed Aug 2026, not yet issued | 3324 Scott St | convert storage space at gr lvel into a bedroom, bath, laundry. install new stair between 1st and 2nd fl. remodel kitchen, bath and bedroom at 2nd fl.Details
convert storage space at gr lvel into a bedroom, bath, laundry. install new stair between 1st and 2nd fl. remodel kitchen, bath and bedroom at 2nd fl. | $850,000 | |
| Aug 10, 2026 | In progress filed Aug 2026, not yet issued | 140 Tingley St | comply w/nov 202544648 - legalize construction of ground fl for new water closet w/lavatory; new shower in laundry room; new bedroom and workshop/storage; replace window in kind @ rear not visible from streetDetails
comply w/nov 202544648 - legalize construction of ground fl for new water closet w/lavatory; new shower in laundry room; new bedroom and workshop/storage; replace window in kind @ rear not visible from street | $20,000 | |
| Jun 26, 2026 | In progress issued Aug 2026 | 3324 Scott St | Gil Construction & Assoc Inc. | at rear elevation: replace (e) window with sliding door, replace (e) window in kind within the same opening. install 1 (n) window. not visible from street.Details
at rear elevation: replace (e) window with sliding door, replace (e) window in kind within the same opening. install 1 (n) window. not visible from street. | $12,000 |
| Mar 23, 2026 | Completed final sign-off Jun 2026 | 838 York St | Building Alchemy | kitchen remodel with new cabinet. relocate sink from pantry to kitchen.Details
kitchen remodel with new cabinet. relocate sink from pantry to kitchen. | $18,000 |
| Mar 23, 2026 | Completed final sign-off Jun 2026 | 834 York St | Building Alchemy | relocate kitchen sink from pantry to kitchen. add sink cabinet.Details
relocate kitchen sink from pantry to kitchen. add sink cabinet. | $2,500 |
| Feb 24, 2026 | In progress issued Feb 2026 | 601 04th St | Building Alchemy | unit 315 - bathroom remodelDetails
unit 315 - bathroom remodel | $35,000 |
| Dec 2, 2025 | In progress issued Dec 2025 | 23 Mirabel Av | Gil Construction & Assoc Inc. | reduce size of decks at 1-3 floors. replace (e) stair run from 3rd floor to 2nd floor with (n) stair run. replace all (n) guardrails with (n). replace (e) decking with (n)Details
reduce size of decks at 1-3 floors. replace (e) stair run from 3rd floor to 2nd floor with (n) stair run. replace all (n) guardrails with (n). replace (e) decking with (n) | $45,000 |
| Nov 4, 2025 | In progress filed Nov 2025, not yet issued | 62 Vista Verde Ct | replace existing wood deck @ rear of houseDetails
replace existing wood deck @ rear of house | $28,000 | |
| Sep 5, 2025 | In progress issued Sep 2025 | 6 Elsie St | Db General Construction | install 4 skylights, remove dropped celiing at living room , remove fireplace, remove 4 windows on north elevation and repalce with 3 new windows. not visible from street.Details
install 4 skylights, remove dropped celiing at living room , remove fireplace, remove 4 windows on north elevation and repalce with 3 new windows. not visible from street. | $43,000 |
| Mar 4, 2025 | Completed final sign-off Oct 2025 | 122 Parker Av | Gil Construction & Assoc Inc. | revision to pa#2025-0109-8003. remove elevator between floor 1st and second floors and all associated structural work. reverting space back to storage remaining scope to stay as is.Details
revision to pa#2025-0109-8003. remove elevator between floor 1st and second floors and all associated structural work. reverting space back to storage remaining scope to stay as is. | |
| Feb 25, 2025 | Completed final sign-off Apr 2025 | 1746 48th Av | Norwood Construction | replace 57' of fence at south side. 25' of fence at 75" height matching with existing and 32' of fence at 98" height.Details
replace 57' of fence at south side. 25' of fence at 75" height matching with existing and 32' of fence at 98" height. | $6,000 |
| Jan 9, 2025 | Completed final sign-off Oct 2025 | 122 Parker Av | Gil Construction & Assoc Inc. | install new elevator btw 1st & 2nd fls. add new bathroom at 1st fl. relocate & remodel e) water closet & laundry at 1st/f. replace 1 window at 2nd/f at rear & 2 window at side in e) openings. not visible from stDetails
install new elevator btw 1st & 2nd fls. add new bathroom at 1st fl. relocate & remodel e) water closet & laundry at 1st/f. replace 1 window at 2nd/f at rear & 2 window at side in e) openings. not visible from st | $165,000 |
| Nov 7, 2024 | Completed final sign-off Apr 2025 | 1746 48th Av | Norwood Construction | to abate nov 202419103- (n) garden shed in rear yard (100sf) varience aproved for heightDetails
to abate nov 202419103- (n) garden shed in rear yard (100sf) varience aproved for height | $12,000 |
| Jul 12, 2024 | Completed final sign-off Apr 2025 | 1242 Pierce St | Bay Build Design Inc | to abate 202173254 for rev 202105200698- revise framing for roof deckDetails
to abate 202173254 for rev 202105200698- revise framing for roof deck | |
| Jul 11, 2024 | Expired or cancelled withdrawn Jul 2024 | 2538 Great Hy | Knab Builder | revision to pa# 202203018927. omit sprinklkering requirement per info sheet ps-12 & ca govt code 65852.2Details
revision to pa# 202203018927. omit sprinklkering requirement per info sheet ps-12 & ca govt code 65852.2 | |
| Jun 25, 2024 | Completed final sign-off Jul 2025 | 1746 48th Av | Norwood Construction | on 1st floor: convert closet to tv room, add closets to primary bedroom, enclose laundry. on 2nd floor: kitchen and dining room remodel. remove unpermitted convienience stair and low roof deck per eg-03Details
on 1st floor: convert closet to tv room, add closets to primary bedroom, enclose laundry. on 2nd floor: kitchen and dining room remodel. remove unpermitted convienience stair and low roof deck per eg-03 | $55,000 |
| Jun 10, 2024 | Completed final sign-off Oct 2024 | 1325 Holloway Av | Luxury Construction Llc | revision to #202403298934: add kitchen remodel.Details
revision to #202403298934: add kitchen remodel. | $60,000 |
| Mar 29, 2024 | Completed final sign-off Oct 2024 | 1325 Holloway Av | Luxury Construction Llc | new bathroom on 2/f with window (not visible from street), remodel 2 closets.Details
new bathroom on 2/f with window (not visible from street), remodel 2 closets. | $37,000 |
| Dec 5, 2023 | In progress filed Dec 2023, not yet issued | 1512 York St | response to nov# 2022-96947.remove existing deck built without a permit and replace with a new.reduced sized deck with a property line firewall.Details
response to nov# 2022-96947.remove existing deck built without a permit and replace with a new.reduced sized deck with a property line firewall. | $3,500 | |
| Aug 31, 2023 | Expired or cancelled withdrawn Feb 2024 | 1746 48th Av | horizontal addition at 2nd floor. adding 425 sf.Details
horizontal addition at 2nd floor. adding 425 sf. | $300,000 | |
| Aug 9, 2023 | Never finaled filed Aug 2023, never issued | 1527 Jerrold Av | replace (e) foundation; replace all 1/f vinyl wndws w/new clad wndws; n clad door at south elev; n clad wndw at west elev; n clad french door at east elev. unit 1: 1/f remodel w/new living rm, secondary kitchen, bathrm, laundry, bedrm. unit 2: rehab w/new kitchen, living area, bathrm, bedrm.Details
replace (e) foundation; replace all 1/f vinyl wndws w/new clad wndws; n clad door at south elev; n clad wndw at west elev; n clad french door at east elev. unit 1: 1/f remodel w/new living rm, secondary kitchen, bathrm, laundry, bedrm. unit 2: rehab w/new kitchen, living area, bathrm, bedrm. | $400,000 | |
| Jan 30, 2023 | Completed final sign-off Jun 2023 | 918 Union St | Elisha Mayost | remodel (e) kitchen. add sink & exhaust fan in w.c. add light and exhaust fan to (e) bath. raise header in 4 locations.Details
remodel (e) kitchen. add sink & exhaust fan in w.c. add light and exhaust fan to (e) bath. raise header in 4 locations. | $58,000 |
| Dec 2, 2022 | Completed final sign-off Mar 2023 | 323 Vienna St | Automatic Gate Master & Garage Doors Inc | revision to pa#202210184529. revise gate weight and depth of post footing.Details
revision to pa#202210184529. revise gate weight and depth of post footing. | |
| Nov 10, 2022 | Completed final sign-off May 2024 | 1118 Broadway | Gil Construction & Assoc Inc. | revision to pa 2022-0302-9038 revise beam sizeDetails
revision to pa 2022-0302-9038 revise beam size | |
| Oct 18, 2022 | Completed final sign-off Mar 2023 | 323 Vienna St | install new pedestrian and automobile gate at front and side of propertyDetails
install new pedestrian and automobile gate at front and side of property | $5,000 | |
| Jul 7, 2022 | Completed final sign-off Aug 2023 | 18 Manzanita Av | Gil Construction & Assoc Inc. | convert laundry area to new office, convert extg closet to laundry, replace bathroom fixtures at 1st floor, remodel kitchen, enlarge primary bedroom's closet.Details
convert laundry area to new office, convert extg closet to laundry, replace bathroom fixtures at 1st floor, remodel kitchen, enlarge primary bedroom's closet. | $150,000 |
| Mar 9, 2022 | Completed final sign-off Apr 2022 | 41 Chenery St | Grabher Construction | revision to bpa#202202157972. revise scale of drawing from 1/4"=1'-0" to 1/2"=1'-0", add dimension of stair widthsDetails
revision to bpa#202202157972. revise scale of drawing from 1/4"=1'-0" to 1/2"=1'-0", add dimension of stair widths | |
| Mar 2, 2022 | Completed final sign-off May 2024 | 1118 Broadway | Gil Construction & Assoc Inc. | rehabilitate (e) unit from fire. install new plumbing, electrical, cabinetry, heating, insulation, and windows in kind. construct a new roof access stair to roof with sliding hatch in lieu of penthouse per ab-057. new 30" high parapet for 1 hr protection for access only. no roofdeck.Details
rehabilitate (e) unit from fire. install new plumbing, electrical, cabinetry, heating, insulation, and windows in kind. construct a new roof access stair to roof with sliding hatch in lieu of penthouse per ab-057. new 30" high parapet for 1 hr protection for access only. no roofdeck. | $300,000 |
| Mar 1, 2022 | Completed final sign-off Apr 2023 | 2212 Castro St | Better Built Contractor Inc | 1st fl: convert sauna into closet & remodel bathroom. 2nd fl: remove (e) fireplace & remodel powder room. 3rd fl: remodel bathroom & primary closet.Details
1st fl: convert sauna into closet & remodel bathroom. 2nd fl: remove (e) fireplace & remodel powder room. 3rd fl: remodel bathroom & primary closet. | $60,000 |
| Feb 15, 2022 | Completed final sign-off Apr 2022 | 41 Chenery St | Grabher Construction | remove & replace (e) non-complying stairs in-kind per 22019 sfbc 1011.12.3 stairway replacement. stair not visible from street.Details
remove & replace (e) non-complying stairs in-kind per 22019 sfbc 1011.12.3 stairway replacement. stair not visible from street. | $10,000 |
| Jan 25, 2022 | Completed final sign-off Feb 2023 | 827 33rd Av | Lopez Quality Construction, Mela Construction Co | convert extg powder room to a bathroom at ground floor with a new window. at rear elevation, replace 3 extg windows with a french door unit.Details
convert extg powder room to a bathroom at ground floor with a new window. at rear elevation, replace 3 extg windows with a french door unit. | $25,000 |
| Dec 30, 2021 | Completed final sign-off Mar 2023 | 1763 47th Av | convert (e) storage on ground fl to habitable space with new kitche,dining,laundry powder room. at 2nd floor:convert (e) dining room & kitchen into a bedroom & bathroom. enclose (e)exterior with new roof with skylights.Details
convert (e) storage on ground fl to habitable space with new kitche,dining,laundry powder room. at 2nd floor:convert (e) dining room & kitchen into a bedroom & bathroom. enclose (e)exterior with new roof with skylights. | $75,000 | |
| Nov 29, 2021 | Completed final sign-off Jan 2026 | 2538 Great Hy | Knab Builder | renovate w/facade changes front/rear of house; gr/f: add bedrm, bath & laundry; build 1-hr rated corridor; 2/f: (n) primary bedrm & bath; relocated (e) kitch to 3/f; 3/f relocate kitch, convert (e) bedrm to fam rm; (n) deck @ 2/f & 3/f w/spiral stair to gradeDetails
renovate w/facade changes front/rear of house; gr/f: add bedrm, bath & laundry; build 1-hr rated corridor; 2/f: (n) primary bedrm & bath; relocated (e) kitch to 3/f; 3/f relocate kitch, convert (e) bedrm to fam rm; (n) deck @ 2/f & 3/f w/spiral stair to grade | $300,000 |
| Nov 1, 2021 | Completed final sign-off Aug 2022 | 17 Elsie St | A J O Group Build Inc | remodel (e) bathroom @ 2nd fl; add a hallway bathroom @ 2nd fl; replace (e) windows and door @ rear elevationDetails
remodel (e) bathroom @ 2nd fl; add a hallway bathroom @ 2nd fl; replace (e) windows and door @ rear elevation | $55,000 |
| Oct 14, 2021 | Completed final sign-off Nov 2021 | 570 Diamond St | Gil Construction & Assoc Inc. | remove existing spiral stairway from 2nd floor deck and infill with new framing and decking.Details
remove existing spiral stairway from 2nd floor deck and infill with new framing and decking. | $15,000 |
| May 20, 2021 | Completed final sign-off Apr 2025 | 1242 Pierce St | in response to notice of violation# 2021-73225. legalize existing rear roof deck. approximately 114 sq ft.Details
in response to notice of violation# 2021-73225. legalize existing rear roof deck. approximately 114 sq ft. | $8,000 | |
| Mar 5, 2021 | Completed final sign-off Mar 2022 | 323 Vienna St | Lau Construction Llc | revision to app#202003137088. replace existing deteriorate foundation at rear of building approx 10-12 lin. feet.Details
revision to app#202003137088. replace existing deteriorate foundation at rear of building approx 10-12 lin. feet. | $5,000 |
| Feb 17, 2021 | Expired or cancelled withdrawn Nov 2021 | 17 Elsie St | excavate for a new garage, laundry, and workshop/storage. excavate at (e) 1st flr for new dedrooms and patio addition. horizontal addition at 2nd flr. relocate bathroom at 2nd flr.Details
excavate for a new garage, laundry, and workshop/storage. excavate at (e) 1st flr for new dedrooms and patio addition. horizontal addition at 2nd flr. relocate bathroom at 2nd flr. | $650,000 | |
| Feb 10, 2021 | Completed final sign-off Oct 2021 | 2518 17th Av | Gil Construction & Assoc Inc. | remodel hall bathroom. (n) french doors to replace (e) window at rear with (n) wood deck, less than 30" above grade. replace 2 windows at light well in kind.Details
remodel hall bathroom. (n) french doors to replace (e) window at rear with (n) wood deck, less than 30" above grade. replace 2 windows at light well in kind. | $22,500 |
| Jan 11, 2021 | Completed final sign-off May 2021 | 326 Hearst Av | Kieran Collins Construction | revision to pa 202002063680. omit kitchen renovation from scope of work including skylight and wall removal.Details
revision to pa 202002063680. omit kitchen renovation from scope of work including skylight and wall removal. | |
| Jan 7, 2021 | Completed final sign-off Nov 2021 | 45 26th Av | Gil Construction & Assoc Inc. | revision to app#202007019458: 1) revise 2nd floor framing per as built conditions. 2)relocate shear walls at 3rd floor framing plan. 2)remodel master bathroom.Details
revision to app#202007019458: 1) revise 2nd floor framing per as built conditions. 2)relocate shear walls at 3rd floor framing plan. 2)remodel master bathroom. | $17,000 |
| Dec 31, 2020 | Completed final sign-off Aug 2021 | 267 23rd Av | Gil Construction & Assoc Inc. | convert (e) closet to powder roomDetails
convert (e) closet to powder room | $13,000 |
| Sep 29, 2020 | Never finaled issued Oct 2020, no final | 45 26th Av | Gil Construction & Assoc Inc. | infill (e) window at side of house. not visible from street.Details
infill (e) window at side of house. not visible from street. | $1,000 |
| Jul 1, 2020 | Completed final sign-off Nov 2021 | 45 26th Av | Gil Construction & Assoc Inc. | remodel e kitchen, change e bedroom and bath at 1st fl into a family rm. add a bath at 2nd fl. remodel existing bath at 2nd fl, relocate laundry to 2nd flDetails
remodel e kitchen, change e bedroom and bath at 1st fl into a family rm. add a bath at 2nd fl. remodel existing bath at 2nd fl, relocate laundry to 2nd fl | $95,000 |
| Jun 26, 2020 | Completed final sign-off Feb 2021 | 1716 Quesada Av | Transbay Design Build Llc | remodel bathroom at 2nd flr, convert (e) laundry to bathroom w/ (n) skylight at 2nd flr, relocate (e) laundry to garage.Details
remodel bathroom at 2nd flr, convert (e) laundry to bathroom w/ (n) skylight at 2nd flr, relocate (e) laundry to garage. | $48,000 |
| Feb 6, 2020 | Completed final sign-off May 2021 | 326 Hearst Av | Kieran Collins Construction | 75 sf addition at gr fl at rear of bldg with remodeled laundry and bath. master bath remodel. hall bath remodel, kitchen remodel, window replacement at front and rearDetails
75 sf addition at gr fl at rear of bldg with remodeled laundry and bath. master bath remodel. hall bath remodel, kitchen remodel, window replacement at front and rear | $135,000 |
| Sep 9, 2019 | Expired or cancelled cancelled May 2021 | 1242 Pierce St | revision to 201710050554 replace exterior stair, not omit per prior permit 201608034113Details
revision to 201710050554 replace exterior stair, not omit per prior permit 201608034113 | ||
| Jul 11, 2019 | Completed final sign-off Oct 2020 | 99 San Anselmo Av | Gil Construction & Assoc Inc. | remodel of (e) office and bathroom at ground floorDetails
remodel of (e) office and bathroom at ground floor | $15,000 |
| Apr 16, 2019 | Never finaled issued Jul 2019, no final | 1340 Sloat Bl | B. Uniacke Construction, Chen & Wong Construction Inc | (74 sf) horizontal additon @ kitchen with wood deck to rear yard. new sliding glass door @ 1st fl media. new window @ 2nd fl bedroom. new powder room.Details
(74 sf) horizontal additon @ kitchen with wood deck to rear yard. new sliding glass door @ 1st fl media. new window @ 2nd fl bedroom. new powder room. | $55,000 |
| Jan 4, 2019 | Completed final sign-off Aug 2019 | 1010 Silliman St | Knab Builder | convert existing storage on grund floor to habitable space to include 2 bedroom, 1 full bathroom, media room and laundry room. new sliding doors @ rear of buidling, new windows on the east side of property.Details
convert existing storage on grund floor to habitable space to include 2 bedroom, 1 full bathroom, media room and laundry room. new sliding doors @ rear of buidling, new windows on the east side of property. | $65,000 |
| Mar 5, 2018 | Completed final sign-off Dec 2018 | 24 Elsie St | Elisha Mayost | relocate entry door and 1st floor. master bedroom and bathroom addition and remodel. new sliding glass door at 2nd floor with new wood deck.Details
relocate entry door and 1st floor. master bedroom and bathroom addition and remodel. new sliding glass door at 2nd floor with new wood deck. | $75,000 |
| Feb 2, 2018 | Completed final sign-off Jul 2018 | 1010 Silliman St | Kanler Inc | remodel kitchen with new skylight. replace 3 windows in existing openingsDetails
remodel kitchen with new skylight. replace 3 windows in existing openings | $35,000 |
| Nov 22, 2017 | Expired or cancelled cancelled Jul 2024 | 1779 46th Av | horizontal addition @ rear of 1st @ rear of bldg w/ roof deckDetails
horizontal addition @ rear of 1st @ rear of bldg w/ roof deck | $185,000 | |
| Nov 10, 2017 | Completed final sign-off Mar 2018 | 3912 Folsom St | Elisha Mayost | master bathroom remodel. relocate 2 windows at back wallDetails
master bathroom remodel. relocate 2 windows at back wall | $25,000 |
| Aug 10, 2017 | Completed final sign-off Jan 2018 | 1010 Silliman St | Kanler Inc | 2nd fl: add master bathroom, remodel (e) bathroom, replace (4) existing windows at rear.Details
2nd fl: add master bathroom, remodel (e) bathroom, replace (4) existing windows at rear. | $35,000 |
| Jun 14, 2017 | Completed final sign-off Mar 2018 | 8 Marion Pl | Lung Fung Const & Elec Co | convert storage room to a closet. kitchen remodel. bathroom remodel w/window replacement. all in kindDetails
convert storage room to a closet. kitchen remodel. bathroom remodel w/window replacement. all in kind | $45,000 |
| Dec 13, 2016 | Completed final sign-off Dec 2017 | 99 San Anselmo Av | Gil Construction & Assoc Inc. | replace 1 bathroom window replace master bathroom window with a new larger size-match existing detailDetails
replace 1 bathroom window replace master bathroom window with a new larger size-match existing detail | $3,000 |
| Oct 13, 2016 | Completed final sign-off Jan 2017 | 267 Anderson St | Altamira Construction Co | revision to pa #201609147635 - install new beam with 2 posts & a new pier foundation.Details
revision to pa #201609147635 - install new beam with 2 posts & a new pier foundation. | $750 |
| Oct 3, 2016 | Completed final sign-off Dec 2017 | 99 San Anselmo Av | Gil Construction & Assoc Inc. | remodel master bathroom and hall bathroom on 2/fDetails
remodel master bathroom and hall bathroom on 2/f | $30,000 |
| Sep 14, 2016 | Completed final sign-off Nov 2016 | 267 Anderson St | Altamira Construction Co | kitchen remodel, master bath remodel, hall bath remodelDetails
kitchen remodel, master bath remodel, hall bath remodel | $70,000 |
| Jan 26, 2016 | Completed final sign-off Jan 2017 | 267 Anderson St | Altamira Construction Co | 22 sq ft closet addition at existing light well (partial infill) on 2nd floor.Details
22 sq ft closet addition at existing light well (partial infill) on 2nd floor. | $2,200 |
| Nov 17, 2015 | Completed final sign-off May 2016 | 633 Kirkham St | revision to pa #201510220570 to clarify on this permit that 3'x9' wood deck is more than 30" above grade (4'-4") & adjacent to firewall. other area of deck in rear yard is less than 30" above grade per pa #201505085740.Details
revision to pa #201510220570 to clarify on this permit that 3'x9' wood deck is more than 30" above grade (4'-4") & adjacent to firewall. other area of deck in rear yard is less than 30" above grade per pa #201505085740. | ||
| Oct 8, 2015 | Completed final sign-off Sep 2016 | 152 Cervantes Bl | (n) 315 sq ft ground floor addition with deck above.Details
(n) 315 sq ft ground floor addition with deck above. | $120,000 | |
| Jul 14, 2015 | Completed final sign-off Jan 2016 | 2114 Divisadero St | Elisha Mayost | kitchen remodel, 1/2 bath remodel, new master bath, new laundry.Details
kitchen remodel, 1/2 bath remodel, new master bath, new laundry. | $85,000 |
| Jul 7, 2015 | Completed final sign-off Nov 2016 | 669 Shrader St | Gil Construction & Assoc Inc. | legalize existing basement by increasing head height. add new bath, bddroom, laundry/tv room at baseement at 1st fl, remodel kitchen and bathDetails
legalize existing basement by increasing head height. add new bath, bddroom, laundry/tv room at baseement at 1st fl, remodel kitchen and bath | $150,000 |
| May 15, 2015 | Completed final sign-off May 2016 | 633 Kirkham St | Joe Leo Loeser | infill lightwell at 2nd floor powder room. (8 sq)Details
infill lightwell at 2nd floor powder room. (8 sq) | $2,400 |
| May 8, 2015 | Completed final sign-off May 2016 | 633 Kirkham St | Joe Leo Loeser | remodel of (e) kitchen & nook, remodel of master bathroom & hall bath, new powder room, new wood deck @ grade less than 30".Details
remodel of (e) kitchen & nook, remodel of master bathroom & hall bath, new powder room, new wood deck @ grade less than 30". | $70,000 |
| Sep 18, 2014 | Completed final sign-off Feb 2016 | 1960 Jefferson St | Gil Construction & Assoc Inc. | kitchen remodel, bathroom remodel on 2nd floor, added master bathroom, new stair connecting 1st floor and 2nd floors, create new bedroom and laundry at 1st floor, remodel 1st floor bathroom. n/a for the maher ordinance #155-13Details
kitchen remodel, bathroom remodel on 2nd floor, added master bathroom, new stair connecting 1st floor and 2nd floors, create new bedroom and laundry at 1st floor, remodel 1st floor bathroom. n/a for the maher ordinance #155-13 | $135,000 |
| Jan 31, 2014 | Completed final sign-off Apr 2015 | 1424 10th Av | remodel (e) kitchen & bathroom. convert (e) sunroom into a (n) master bathroom. (no change to any exterior features).Details
remodel (e) kitchen & bathroom. convert (e) sunroom into a (n) master bathroom. (no change to any exterior features). | $45,000 | |
| Nov 18, 2013 | Completed final sign-off Nov 2013 | 515 Masonic Av | Gil Construction & Assoc Inc. | divide existing ground floor storage area into (5) five smaller storage areas with non-structural wood partitions per plans.Details
divide existing ground floor storage area into (5) five smaller storage areas with non-structural wood partitions per plans. | $1,000 |
| Oct 17, 2013 | Completed final sign-off Apr 2015 | 1424 10th Av | replace existing brick foundation as shown on drawings. install new patio door at ground fl. playroom, remove existing bath and shower and kitchen on gr flDetails
replace existing brick foundation as shown on drawings. install new patio door at ground fl. playroom, remove existing bath and shower and kitchen on gr fl | $60,000 | |
| Mar 7, 2013 | Expired or cancelled expired Mar 2017 | 12 Elsie St | new dormer & interior remodeling including 2 new bathrooms & a kitchen remodel. dormer is at rear of house.Details
new dormer & interior remodeling including 2 new bathrooms & a kitchen remodel. dormer is at rear of house. | $75,000 | |
| Dec 7, 2012 | Expired or cancelled cancelled Jan 2020 | 219 Eureka St | remove (e) 2 story deck & stair & replace with new 2 story wood deck & metal spiral stair.Details
remove (e) 2 story deck & stair & replace with new 2 story wood deck & metal spiral stair. | $20,000 | |
| Jun 24, 2011 | Completed final sign-off Jan 2012 | 44 Macondray Ln | Elisha Mayost | remove portion of non structural wall. appliance relocation. no new light. no change to window & doors.Details
remove portion of non structural wall. appliance relocation. no new light. no change to window & doors. | $2,500 |
| Nov 16, 2010 | Expired or cancelled expired Aug 2012 | 922 Union St | Elisha Mayost | new 500 sq ft rooftop deck w/ access 2 gates for emergency access and egress (sffd).Details
new 500 sq ft rooftop deck w/ access 2 gates for emergency access and egress (sffd). | $10,000 |
| Oct 28, 2010 | Completed final sign-off Mar 2011 | 922 Union St | Elisha Mayost | revision to appl #201006164600: reduction in scope - omit bathroom addition, omit wall removal & therefore structural work, add shower at existing bath.Details
revision to appl #201006164600: reduction in scope - omit bathroom addition, omit wall removal & therefore structural work, add shower at existing bath. | |
| Jun 4, 2010 | Completed final sign-off Jul 2011 | 1716 Quesada Av | J C Construction Co | remove 1 skylight and install 3 skylights, not visible from street. remove wall between kitchen & breakfast room.Details
remove 1 skylight and install 3 skylights, not visible from street. remove wall between kitchen & breakfast room. | $3,000 |
| Mar 26, 2010 | Completed final sign-off Aug 2010 | 920 Union St | remodel of water closet. remodel of bathroom; conversion of closet to shower. work on unti #920 only.Details
remodel of water closet. remodel of bathroom; conversion of closet to shower. work on unti #920 only. | $10,000 | |
| Sep 23, 2009 | Completed final sign-off May 2021 | 128 Elsie St | R & D Construction Co Inc | to erect 4 stories, no basement, single family dwelling.Details
to erect 4 stories, no basement, single family dwelling. | $500,000 |
| Jun 10, 2008 | Completed final sign-off Jul 2009 | 1025 Clayton St | infill existing lightwell, add a bathroom and stair reversal w/general remodel: (n) laundry room, (n) wine closet, (n) office, closets & bar.Details
infill existing lightwell, add a bathroom and stair reversal w/general remodel: (n) laundry room, (n) wine closet, (n) office, closets & bar. | $45,000 | |
| Apr 28, 2006 | Completed final sign-off Feb 2008 | 2746 Buchanan St | 3rd floor horizontal extension and relocated garage door opening and bay window.Details
3rd floor horizontal extension and relocated garage door opening and bay window. | $80,000 | |
| Oct 26, 2005 | Expired or cancelled expired Jan 2007 | 2746 Buchanan St | new skylight & raised parapet.Details
new skylight & raised parapet. | $6,000 | |
| Aug 9, 2005 | Completed final sign-off Jan 2007 | 152 Cervantes Bl | Ming Wah Construction Co. | 2 story addition at rear of property, legalize room at rear of garage.Details
2 story addition at rear of property, legalize room at rear of garage. | $18,000 |
| Dec 31, 2004 | Completed final sign-off Mar 2005 | 425 Battery St | Chow's Construction Co. | build out of current retail space to accomodate a barber shop.Details
build out of current retail space to accomodate a barber shop. | $81,900 |
| May 14, 2004 | Completed final sign-off Sep 2004 | 3 Elsie St | remodel kitchen, new windows in (e) openings,remove load bearing wall & replace w/(n)beamDetails
remodel kitchen, new windows in (e) openings,remove load bearing wall & replace w/(n)beam | $16,000 |