Permit 201610130187
267 Anderson St
revision to pa #201609147635 - install new beam with 2 posts & a new pier foundation.
- Outcome
- Completed (city status: complete, Jan 23, 2017)
- Filed
- Oct 13, 2016
- Permit issued
- Oct 14, 2016
- Final sign-off
- Jan 23, 2017
- Declared cost
- $750
- Building use
- 2 family dwelling
- Neighborhood
- Bernal Heights
- Contractor
- Altamira Construction Co (license 725217)
- Property
- All permits at this address (block 5662, lot 036)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
The parties on this permit have not been loaded yet.