40 permits since 2000 (architect on 40 permits): 21 completed, 10 in progress, 8 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 21, 2026 | In progress filed Aug 2026, not yet issued | 2400 19th Av | revision to 2024-1017-3150: add structural built-up posts at low wall partitions and additional blocking at floor joist for the support of tcr equipment.Details
revision to 2024-1017-3150: add structural built-up posts at low wall partitions and additional blocking at floor joist for the support of tcr equipment. | $25,000 | |
| Jun 26, 2026 | In progress filed Jun 2026, not yet issued | 560 Mission St | revision to #202501027602- adding push button at restroom ada stall partition doorDetails
revision to #202501027602- adding push button at restroom ada stall partition door | $1,500 | |
| Jun 17, 2026 | Completed final sign-off Oct 2026 | 801 Market St | Gray West Construction Inc | level 2: revision to bpa#202512020738. add one additional male & one female restroom due to plumbing calc requirments. modification of layouts at boh.Details
level 2: revision to bpa#202512020738. add one additional male & one female restroom due to plumbing calc requirments. modification of layouts at boh. | $10,000 |
| Jun 17, 2026 | Completed final sign-off Oct 2026 | 801 Market St | Gray West Construction Inc | revision to bpa#202512010670. relocate sales area, mw fixtures and cove per site conditionDetails
revision to bpa#202512010670. relocate sales area, mw fixtures and cove per site condition | |
| Jun 15, 2026 | Completed final sign-off Aug 2026 | 2299 Alameda St | C C I Commercial Construction & Improv | interior t.i in an existing showroom. interior partitions, lighting and electrical, and new millwork fixtures.Details
interior t.i in an existing showroom. interior partitions, lighting and electrical, and new millwork fixtures. | $422,704 |
| Jun 4, 2026 | Completed final sign-off Sep 2026 | 350 Bay St | Tilton Pacific Const Inc. | rev to pa 202505126240: relocated meat cooler and associate meat scale, riracold units, lighting per site condition. revised dh units and mechanical units. layout at mechanical yard per m-sheets, site conditions. added mini parking kiosk (e) parking requirements. no exterior work. sprinklr sep permDetails
rev to pa 202505126240: relocated meat cooler and associate meat scale, riracold units, lighting per site condition. revised dh units and mechanical units. layout at mechanical yard per m-sheets, site conditions. added mini parking kiosk (e) parking requirements. no exterior work. sprinklr sep perm | |
| Feb 17, 2026 | Completed final sign-off Sep 2026 | 350 Bay St | Classic Refigeration Socal Inc | deferred submittal for walk-in cooler and freezer boxes. ref ti permit 202505126240Details
deferred submittal for walk-in cooler and freezer boxes. ref ti permit 202505126240 | |
| Feb 3, 2026 | In progress issued Jun 2026 | 560 Mission St | Gci, Inc | rev to pa# 202501027602, ti interior common areas within (e) 31-story business occupancy bldg. revision notated as bulletins d & e, due to (e) field conditions & rfi/submittal responses narrative included itemizing changes in detail. ref pa# 202507100540, 202507150838 & 202509195753.Details
rev to pa# 202501027602, ti interior common areas within (e) 31-story business occupancy bldg. revision notated as bulletins d & e, due to (e) field conditions & rfi/submittal responses narrative included itemizing changes in detail. ref pa# 202507100540, 202507150838 & 202509195753. | $50,000 |
| Jan 14, 2026 | Completed final sign-off Sep 2026 | 350 Bay St | Tilton Pacific Const Inc. | revision to pa#202505126240. convert electric heat to gas heat. updated grab & go specfications. shifted meat, fish bunkers, and berry bin bse. suite 113 store # 610 for storefront frontwall location per field condition. updated sanitation certification per latest specs added conrete house keeping.Details
revision to pa#202505126240. convert electric heat to gas heat. updated grab & go specfications. shifted meat, fish bunkers, and berry bin bse. suite 113 store # 610 for storefront frontwall location per field condition. updated sanitation certification per latest specs added conrete house keeping. | |
| Dec 2, 2025 | Completed final sign-off Oct 2026 | 801 Market St | Gray West Construction Inc | 2nd fl ti new partitons, finishes, fixtures, mepDetails
2nd fl ti new partitons, finishes, fixtures, mep | $1,872,077 |
| Dec 1, 2025 | Completed final sign-off Sep 2026 | 801 Market St | Gray West Construction Inc | 1st fl - ti (n) partitions, finishes, fixtures, mepDetails
1st fl - ti (n) partitions, finishes, fixtures, mep | $1,872,077 |
| Oct 22, 2025 | In progress issued Jul 2026 | 3251 20th Av | Singular Builders | tenant improvement with roof-top mounted hvac equipment.Details
tenant improvement with roof-top mounted hvac equipment. | $400,000 |
| Jul 30, 2025 | In progress issued Sep 2025 | 1155 Battery St | Interior Systems Contracting Inc. | revision to pa 202503263121 updates to add dropped ceiling soffit to enclose mechanical unitsDetails
revision to pa 202503263121 updates to add dropped ceiling soffit to enclose mechanical units | $4,951 |
| Jul 15, 2025 | In progress issued Oct 2025 | 560 Mission St | Gci, Inc | revision to permit 202501027602. completed structural details for stone veneer attachment at ground floor level.Details
revision to permit 202501027602. completed structural details for stone veneer attachment at ground floor level. | |
| Jul 10, 2025 | In progress issued Sep 2025 | 560 Mission St | Gci, Inc | revision to pa #2025-0102-7602 to document various field/construction changes, general detailing and clarification per rfi responses at ground floor cafe, back of house area and 2nd level.Details
revision to pa #2025-0102-7602 to document various field/construction changes, general detailing and clarification per rfi responses at ground floor cafe, back of house area and 2nd level. | $14,000 |
| May 27, 2025 | Completed final sign-off Sep 2026 | 350 Bay St | Tilton Pacific Const Inc. | interior alteration of (e) building for a new grocery store, no change of use, prior use of building was a grocery store. no exterior work proposed under this permit.Details
interior alteration of (e) building for a new grocery store, no change of use, prior use of building was a grocery store. no exterior work proposed under this permit. | $950,000 |
| Apr 10, 2025 | Expired or cancelled withdrawn Jun 2026 | 560 Mission St | 1/fl- interior non structural demo to include removal of floor wall and ceiling finishes as indicated. interior partitions and door and lighting and fixtures floor boxesDetails
1/fl- interior non structural demo to include removal of floor wall and ceiling finishes as indicated. interior partitions and door and lighting and fixtures floor boxes | $5,000 | |
| Mar 26, 2025 | In progress issued Jul 2025 | 1155 Battery St | Interior Systems Contracting Inc. | ground fl - interior tenant fit-out adjacent to existing public plaza. work includes interior partitions, wall fixture, light fixsture, electrical outlets. convert portion of office to accessory retail. resttroom and drinking fountain under bpa# 202501178624. electrical deferred.Details
ground fl - interior tenant fit-out adjacent to existing public plaza. work includes interior partitions, wall fixture, light fixsture, electrical outlets. convert portion of office to accessory retail. resttroom and drinking fountain under bpa# 202501178624. electrical deferred. | $900,000 |
| Jan 17, 2025 | In progress issued May 2025 | 560 Mission St | Gci, Inc | basement parking garage includes new finishes and lighting at elevator lobby and entry area.g/f: new cafe area, new seating areas throughout, new restrooms and phone rooms, new entry doors and new finishes throughout. 2/f: new seating areas, new training room, new gym area with lockers and showersDetails
basement parking garage includes new finishes and lighting at elevator lobby and entry area.g/f: new cafe area, new seating areas throughout, new restrooms and phone rooms, new entry doors and new finishes throughout. 2/f: new seating areas, new training room, new gym area with lockers and showers | $15,000,000 |
| Dec 12, 2024 | Completed final sign-off Dec 2025 | 300 Post St | Bates Construction Company | replace exterior doors, finishes, walk off matt and hardwareDetails
replace exterior doors, finishes, walk off matt and hardware | $985,000 |
| Oct 17, 2024 | In progress issued Mar 2026 | 2400 19th Av | Deb Construction Llc | citibank: teller counters. voluntary accessibility remediation intended to remove barriers to branch access.Details
citibank: teller counters. voluntary accessibility remediation intended to remove barriers to branch access. | $164,000 |
| May 22, 2024 | Completed final sign-off Aug 2024 | 3251 20th Av | Pacific Wide Builders Inc. | revision to 2024-0319-8185: update dimmers, wall display junction boxes and keynote #10. update keynote #2 to not used. update keynote #8. added ceiling junction boxes for wall display drivers. removed 1 quad and 1 data receptacle in storage area. update panel schedule for wall displays.Details
revision to 2024-0319-8185: update dimmers, wall display junction boxes and keynote #10. update keynote #2 to not used. update keynote #8. added ceiling junction boxes for wall display drivers. removed 1 quad and 1 data receptacle in storage area. update panel schedule for wall displays. | |
| Mar 19, 2024 | Completed final sign-off Aug 2024 | 3251 20th Av | Pacific Wide Builders Inc. | suite 116 pop mart - interior tenant fit out within existing space; work includes partitions/walls, wall fixtures, flooring, ceiling, light fixtures, mechanical & electricalDetails
suite 116 pop mart - interior tenant fit out within existing space; work includes partitions/walls, wall fixtures, flooring, ceiling, light fixtures, mechanical & electrical | $300,000 |
| Sep 29, 2023 | Completed final sign-off Jan 2024 | 815 Market St | Horizon Retail Construction Inc | add new security grill @ storefrontDetails
add new security grill @ storefront | $2,000 |
| Sep 13, 2023 | Completed final sign-off Nov 2023 | 170 Maiden Ln | Sajo, Inc. | revision to bpa# 202212218908: additional door in elevator vestible for (e) purposes. exit signage, emergency lighting in unoccupied space.Details
revision to bpa# 202212218908: additional door in elevator vestible for (e) purposes. exit signage, emergency lighting in unoccupied space. | |
| Sep 11, 2023 | Completed final sign-off Sep 2023 | 360 Post St | Sajo, Inc. | revision to 202306281101: demo of all tenant partitions, doors, as well as removal of furniture, millwork & quipments. no work to sprinkler or fire alarm system. work do not included removal of ceilings, lighting fixtures & mech deffusersDetails
revision to 202306281101: demo of all tenant partitions, doors, as well as removal of furniture, millwork & quipments. no work to sprinkler or fire alarm system. work do not included removal of ceilings, lighting fixtures & mech deffusers | |
| Jul 5, 2023 | Never finaled issued Jul 2023, no final | 170 Maiden Ln | Sajo, Inc. | 4/f: partial remodel hvac design, of existing multi tenant bldg, work includes an additional fan coil unit and relocation of energy recovery ventilator. work also included relocation of electrical & mechanical equipment in the electrical room, minor flr plan and equipment rev per pa# 202212218908.Details
4/f: partial remodel hvac design, of existing multi tenant bldg, work includes an additional fan coil unit and relocation of energy recovery ventilator. work also included relocation of electrical & mechanical equipment in the electrical room, minor flr plan and equipment rev per pa# 202212218908. | $8,000 |
| Jul 5, 2023 | Completed final sign-off Aug 2023 | 2000 Irving St | Wilson Delang Construction Group | atm vestibule storefront glazing door replacement. all scope of work located in interiorDetails
atm vestibule storefront glazing door replacement. all scope of work located in interior | $90,000 |
| Jun 28, 2023 | Never finaled issued Aug 2023, no final | 360 Post St | Sajo, Inc. | 7/f ste 701: work includes demolition of all tenant patitions, door and ceilings as well as furniture, millwork and equipment. work also includes removal of supply & return grills thru and associated ducting and wiring. hvac system to remainDetails
7/f ste 701: work includes demolition of all tenant patitions, door and ceilings as well as furniture, millwork and equipment. work also includes removal of supply & return grills thru and associated ducting and wiring. hvac system to remain | $10,000 |
| Jan 30, 2023 | Completed final sign-off Aug 2024 | 3251 20th Av | Plant Construction Co, Lp | new remote back of house, break area, inclues new partions furniture, kitchnette with no stove or oven. remodeled restroom. no structural work.Details
new remote back of house, break area, inclues new partions furniture, kitchnette with no stove or oven. remodeled restroom. no structural work. | $100,000 |
| Dec 21, 2022 | Never finaled issued May 2023, no final | 170 Maiden Ln | Sajo, Inc. | partial 4th fl remodel: non structural partitions, ceilings, furniture, finishes, related hvac, electrical, & plumbingDetails
partial 4th fl remodel: non structural partitions, ceilings, furniture, finishes, related hvac, electrical, & plumbing | $80,000 |
| Dec 20, 2022 | Completed final sign-off Nov 2023 | 1690 Folsom St | W. L. Butler Construction Inc | installation of interior overhead security grilles on (e) storefront windows along perimeter of store, minor facade modification to accommodate new hollow metal emergency egress/employee entry door to (e) parking lot.Details
installation of interior overhead security grilles on (e) storefront windows along perimeter of store, minor facade modification to accommodate new hollow metal emergency egress/employee entry door to (e) parking lot. | $275,000 |
| Nov 28, 2022 | Completed final sign-off May 2023 | 88 Kearny St | Wilson Delang Construction Group | replace 2 atm machines and associated non load bearing wall. no work to the hvac and sprinkler systemDetails
replace 2 atm machines and associated non load bearing wall. no work to the hvac and sprinkler system | $100,000 |
| Nov 7, 2022 | Never finaled issued Jul 2023, no final | 1528 Pine St | Gray West Construction Inc | 2/f: t.i., new partitions, doors, ceiling, lighting, millwork, finishes, & mep. on the second floor, existing car lifts to be replaced with new lifts, weight to match existing equipment weight. structural work at second floor only.Details
2/f: t.i., new partitions, doors, ceiling, lighting, millwork, finishes, & mep. on the second floor, existing car lifts to be replaced with new lifts, weight to match existing equipment weight. structural work at second floor only. | $350,000 |
| Nov 7, 2022 | Never finaled issued Jul 2023, no final | 1528 Pine St | Gray West Construction Inc | 1/f & mezzanine - tenant improvement including new partitions, doors, ceilings, lighting, millwork, finishes & mep.Details
1/f & mezzanine - tenant improvement including new partitions, doors, ceilings, lighting, millwork, finishes & mep. | $500,000 |
| Nov 7, 2022 | Never finaled issued Jul 2023, no final | 1528 Pine St | Gray West Construction Inc | basement t.i., new floor finishes, new interior wall finishes, electrical system, mechanical & plumbingDetails
basement t.i., new floor finishes, new interior wall finishes, electrical system, mechanical & plumbing | $150,000 |
| Nov 7, 2022 | Never finaled issued Jul 2023, no final | 1528 Pine St | Gray West Construction Inc | roof - tenant improvement including new electrical & mechanical systems.Details
roof - tenant improvement including new electrical & mechanical systems. | $100,000 |
| Sep 20, 2022 | Never finaled issued Oct 2022, no final | 300 Post St | Sajo, Inc., Shawmut Woodworking & Supply Inc | 2/f: remodel of existing center. work includes non structural partitions, ceiling, furniture, finishes and related hvac, electrical and plumbing work. remodel of 3/f existing tenant open work area, including voluntary ada restroom. upgrade, storage, furniture and related hvac, elec. and plumbing.Details
2/f: remodel of existing center. work includes non structural partitions, ceiling, furniture, finishes and related hvac, electrical and plumbing work. remodel of 3/f existing tenant open work area, including voluntary ada restroom. upgrade, storage, furniture and related hvac, elec. and plumbing. | $104,180 |
| Aug 19, 2022 | Completed final sign-off Apr 2024 | 789 Mission St | W. L. Butler Construction Inc | remodel of (e) retail store to the g/f interior improvements only. this permit is for mep fixtures and seismic shelving fixtures. t.i. pa202206307535.Details
remodel of (e) retail store to the g/f interior improvements only. this permit is for mep fixtures and seismic shelving fixtures. t.i. pa202206307535. | $350,000 |
| Jun 30, 2022 | Completed final sign-off Apr 2024 | 789 Mission St | W. L. Butler Construction Inc | remodel to the ground floor with exterior and interior improvements including the (e) starbucks exterior pick-up window & remodel. tenant to convert retail sales to storage for mobile order pick-up. sprinklers/fire alarm under separate permits.Details
remodel to the ground floor with exterior and interior improvements including the (e) starbucks exterior pick-up window & remodel. tenant to convert retail sales to storage for mobile order pick-up. sprinklers/fire alarm under separate permits. | $575,000 |