Permit GraphShortlistSan Francisco building permits since 2000

Reza Norouzi

License
E23380
Look the license up with the state
Listed as
engineer
Firm
Coolsys Energy Design
Based in
Fullerton
On San Francisco permits
May 2025 to Jun 2026

4 permits since 2000 (engineer on 4 permits): 3 completed, 1 in progress.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jun 22, 2026In progress
filed Jun 2026, not yet issued
2630 Bay Shore Blremodel (e) retail grocery market. scope includes installation of new and relocation of (e)retail shelving display fixtures and refrigeration equipment.
Details
Permit
202606223607
Status
filed
Filed
Jun 22, 2026
Declared cost
$94,000
Address
2630 Bay Shore Bl

remodel (e) retail grocery market. scope includes installation of new and relocation of (e)retail shelving display fixtures and refrigeration equipment.

Open the permit page

$94,000
Jun 4, 2026Completed
final sign-off Sep 2026
350 Bay StTilton Pacific Const Inc.rev to pa 202505126240: relocated meat cooler and associate meat scale, riracold units, lighting per site condition. revised dh units and mechanical units. layout at mechanical yard per m-sheets, site conditions. added mini parking kiosk (e) parking requirements. no exterior work. sprinklr sep perm
Details
Permit
202606042542
Status
complete
Filed
Jun 4, 2026
Permit issued
Jun 11, 2026
Final sign-off
Sep 25, 2026
Address
350 Bay St

rev to pa 202505126240: relocated meat cooler and associate meat scale, riracold units, lighting per site condition. revised dh units and mechanical units. layout at mechanical yard per m-sheets, site conditions. added mini parking kiosk (e) parking requirements. no exterior work. sprinklr sep perm

Open the permit page

Jan 14, 2026Completed
final sign-off Sep 2026
350 Bay StTilton Pacific Const Inc.revision to pa#202505126240. convert electric heat to gas heat. updated grab & go specfications. shifted meat, fish bunkers, and berry bin bse. suite 113 store # 610 for storefront frontwall location per field condition. updated sanitation certification per latest specs added conrete house keeping.
Details
Permit
202601143798
Status
complete
Filed
Jan 14, 2026
Permit issued
Jan 23, 2026
Final sign-off
Sep 25, 2026
Address
350 Bay St

revision to pa#202505126240. convert electric heat to gas heat. updated grab & go specfications. shifted meat, fish bunkers, and berry bin bse. suite 113 store # 610 for storefront frontwall location per field condition. updated sanitation certification per latest specs added conrete house keeping.

Open the permit page

May 27, 2025Completed
final sign-off Sep 2026
350 Bay StTilton Pacific Const Inc.interior alteration of (e) building for a new grocery store, no change of use, prior use of building was a grocery store. no exterior work proposed under this permit.
Details
Permit
202505126240
Status
complete
Filed
May 27, 2025
Permit issued
Nov 24, 2025
Final sign-off
Sep 25, 2026
Declared cost
$950,000
Address
350 Bay St

interior alteration of (e) building for a new grocery store, no change of use, prior use of building was a grocery store. no exterior work proposed under this permit.

Open the permit page

$950,000