Debbie Grieves
- Listed as
- architect, authorized agent-others, engineer
- Firm
- Pae
- Based in
- San Francisco
- On San Francisco permits
- Mar 2005 to Jun 2025
15 permits since 2000 (engineer on 13 permits, architect on 1 permit, authorized agent-others on 1 permit): 12 completed, 1 in progress, 1 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 2, 2025 | In progress issued Jul 2026 | 880 Mcallister St | Guzman Construction Group Inc. | 100% afforable senior housing for a 104,000sf type 1, 7 story/115 unit with commerical ground floor. 81 1-bedroom and 35-2 bedroom units. 2 ground floor landscape courtyard and roof terrace.Details
100% afforable senior housing for a 104,000sf type 1, 7 story/115 unit with commerical ground floor. 81 1-bedroom and 35-2 bedroom units. 2 ground floor landscape courtyard and roof terrace. | $70,000,000 |
| Dec 20, 2022 | Completed final sign-off Feb 2025 | 555 California St | Novo Construction Inc | 46/f - ste 4646: revision to pa 2022-0706-7839 to create new ti closet, 2 private offices, lighting finishes and powerDetails
46/f - ste 4646: revision to pa 2022-0706-7839 to create new ti closet, 2 private offices, lighting finishes and power | |
| Jun 10, 2022 | Completed final sign-off Oct 2023 | 200 Paul Av | Skyline Construction | bldg f: new 1500 sq ft room within an existing data hall for new server racks.Details
bldg f: new 1500 sq ft room within an existing data hall for new server racks. | $800,000 |
| Sep 30, 2021 | Completed final sign-off Apr 2022 | 1185 Market St | Eric F Anderson Incorporated | ref pa# 202007200503. door swing clarification of existing door to convenience stair. mechanical purge system for refrigeration system associated with tenant improvement for whole foods market currently under construction. fire smoke damper matrix and kitchen exhaust smoke control memo.Details
ref pa# 202007200503. door swing clarification of existing door to convenience stair. mechanical purge system for refrigeration system associated with tenant improvement for whole foods market currently under construction. fire smoke damper matrix and kitchen exhaust smoke control memo. | |
| Sep 16, 2021 | Expired or cancelled withdrawn Nov 2021 | 1023 Mission St | Wci-Gc Inc | revision to pa 2021-0324-7162 for architectura changes including new conference room, break area, basement restrooms. first review of deferred mepDetails
revision to pa 2021-0324-7162 for architectura changes including new conference room, break area, basement restrooms. first review of deferred mep | $245,000 |
| Jul 20, 2020 | Completed final sign-off Apr 2022 | 1185 Market St | Eric F Anderson Incorporated | first time tenant improvement for a new whole foods to occupy existing shell space. walls, fixtures, mech, elec, plumbing, lighting, structural, refrigeration - reach-ins & walk-ins, restrooms, equipment support platforms, concrete topping slab.Details
first time tenant improvement for a new whole foods to occupy existing shell space. walls, fixtures, mech, elec, plumbing, lighting, structural, refrigeration - reach-ins & walk-ins, restrooms, equipment support platforms, concrete topping slab. | $12,000,000 |
| Aug 7, 2019 | Completed final sign-off Dec 2020 | 200 Paul Av | Dpr Construction | (4) new generators w/ 4000 gallon belly tanks. on pads 31, 32, 33 & 34 within the generator yard.**maher n/a**Details
(4) new generators w/ 4000 gallon belly tanks. on pads 31, 32, 33 & 34 within the generator yard.**maher n/a** | $2,500,000 |
| Aug 7, 2019 | Completed final sign-off Dec 2020 | 200 Paul Av | Dpr Construction Inc | 2nd fl, building f - new data center. supporting equipment rooms & electrical rooms. new walls, door, finishes, mep work, new chiller/ahu on rooftops. generator pods for future generators and transformersDetails
2nd fl, building f - new data center. supporting equipment rooms & electrical rooms. new walls, door, finishes, mep work, new chiller/ahu on rooftops. generator pods for future generators and transformers | $22,750,000 |
| Jul 19, 2018 | Never finaled issued Sep 2018, no final | 200 Paul Av | Dpr Construction | new generator for building d suite 360 under permit #201807174756Details
new generator for building d suite 360 under permit #201807174756 | $1,000,000 |
| Jan 22, 2018 | Completed final sign-off Apr 2019 | 241 California St | J & K Project Mgmt Consultants Llc | ti of the (e) space on ground level that includes non-structural partitions, doors, fixtures, finishes, electrical, mechanical, and plumbing. maher naDetails
ti of the (e) space on ground level that includes non-structural partitions, doors, fixtures, finishes, electrical, mechanical, and plumbing. maher na | $700,000 |
| Sep 22, 2017 | Completed final sign-off Aug 2018 | 200 Paul Av | Dpr Construction | bldg. d, #350- install new 2000 kw generator and 4000 gal fuel tank under pa#201707071280 and pa#201801108282. pad 28 n/a ordinance #155-13Details
bldg. d, #350- install new 2000 kw generator and 4000 gal fuel tank under pa#201707071280 and pa#201801108282. pad 28 n/a ordinance #155-13 | $250,000 |
| Oct 11, 2016 | Completed final sign-off May 2018 | 445 Geary St | Oliver & Company Inc. | revise pa#201602189900 sheet #e40-02 to delete heat detector. heat detector not required for lulaDetails
revise pa#201602189900 sheet #e40-02 to delete heat detector. heat detector not required for lula | |
| Mar 24, 2016 | Completed final sign-off Sep 2016 | 222 Sutter St | Field Construction Inc. | 6th & 8th floor - installation of (2) hvac units for cooling & electrical work. ref pa #201601298354 for 8th floor only. n/a maher ordinanceDetails
6th & 8th floor - installation of (2) hvac units for cooling & electrical work. ref pa #201601298354 for 8th floor only. n/a maher ordinance | $40,000 |
| Feb 18, 2016 | Completed final sign-off May 2018 | 445 Geary St | Oliver & Company Inc. | electrical permit only. reference pa# 2015/03/06/0168.Details
electrical permit only. reference pa# 2015/03/06/0168. | $50,000 |
| Mar 3, 2005 | Completed final sign-off May 2006 | 3 Embarcadero Center | oti-2, 21st floor, el, me.Details
oti-2, 21st floor, el, me. | $350,000 |