- Feb 2006 to Sep 2026
186 permits since 2000 (architect on 172 permits, authorized agent-others on 16 permits, designer on 2 permits, engineer on 2 permits): 105 completed, 32 in progress, 35 never finaled, 14 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 186.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 30, 2026 | In progress issued Sep 2026 | 1263 Mission St | add exterior steps to existing roof deck, at existing gate, add fire escape signage. ref pa# 2013-1017-9622.Details
add exterior steps to existing roof deck, at existing gate, add fire escape signage. ref pa# 2013-1017-9622. | $2,800 | |
| Sep 16, 2026 | In progress issued Sep 2026 | 461 Pacific Av | Two Bricks Design Build | revision to mep pa# 202605151362 & arch pa# 202407186789.Details
revision to mep pa# 202605151362 & arch pa# 202407186789. | |
| Sep 10, 2026 | In progress issued Sep 2026 | 144 02nd St | Walls Construction And Contracting Inc | 2&3/fl ti work to replace (e) breakroom to include (n) non bearing wall and applicances.Details
2&3/fl ti work to replace (e) breakroom to include (n) non bearing wall and applicances. | $45,500 |
| Sep 4, 2026 | In progress issued Sep 2026 | 461 Pacific Av | Two Bricks Design Build | revision 202407186789 & 202605040620- interior work only adding (n) non bearing interior wallsDetails
revision 202407186789 & 202605040620- interior work only adding (n) non bearing interior walls | $12,500 |
| Sep 4, 2026 | In progress filed Sep 2026, not yet issued | 51 Commonwealth Av | C C I Commercial Construction & Improv | after fire re-build of mid-section building to match existing (like for like) with same area and building envelopeDetails
after fire re-build of mid-section building to match existing (like for like) with same area and building envelope | $235,500 |
| Aug 31, 2026 | In progress issued Sep 2026 | 370 Townsend St | Walls Construction And Contracting Inc | tenant interior work at ground floor & basement, adding new non-bearing interior partition walls, kitchenettes, cleaned up finishes, existing restroom plumbing fixtures and finishes to be replaced in kind.Details
tenant interior work at ground floor & basement, adding new non-bearing interior partition walls, kitchenettes, cleaned up finishes, existing restroom plumbing fixtures and finishes to be replaced in kind. | $128,545 |
| Jul 10, 2026 | In progress issued Jul 2026 | 463 Pacific Av | Two Bricks Design Build | revision to pa #202407186789, minor revision to footing at 1st floor stair wall, and python fasteners as approved in permit pa #202605040620.Details
revision to pa #202407186789, minor revision to footing at 1st floor stair wall, and python fasteners as approved in permit pa #202605040620. | |
| Jun 12, 2026 | In progress issued Oct 2026 | 1125 Mission St | C C I Commercial Construction & Improv | (n) store front roll up at 1125 mission street front facade. not in public right of wayDetails
(n) store front roll up at 1125 mission street front facade. not in public right of way | $3,800 |
| May 22, 2026 | In progress issued Jun 2026 | 61 New Montgomery St | Walls Construction And Contracting Inc | ground floor/mezzanine improvements, add restrooms/kitchenette, non-bearing partions, to ground floor, add kitchenette/snack counters and non-bearing partitions to mezzanine (no catering service)Details
ground floor/mezzanine improvements, add restrooms/kitchenette, non-bearing partions, to ground floor, add kitchenette/snack counters and non-bearing partitions to mezzanine (no catering service) | $85,000 |
| May 4, 2026 | In progress issued May 2026 | 461 Pacific Av | Two Bricks Design Build | revision to permit #202511149590 to modify the exterior stair enclosure due to field conditionsDetails
revision to permit #202511149590 to modify the exterior stair enclosure due to field conditions | |
| May 4, 2026 | In progress issued Aug 2026 | 40 Gold St | B-Side Inc. | replacement of (e) front entry doors, and minor interior tenant improvement work on the ground floor.Details
replacement of (e) front entry doors, and minor interior tenant improvement work on the ground floor. | $48,300 |
| Apr 8, 2026 | Completed final sign-off Jul 2026 | 1805 Geary Bl | Swinerton Builders | extend the existing service elevator canopy within the rear alleyway to provide continue weather protection over the 2nd fl exterior landing.Details
extend the existing service elevator canopy within the rear alleyway to provide continue weather protection over the 2nd fl exterior landing. | $18,500 |
| Mar 2, 2026 | In progress issued Mar 2026 | 55 New Montgomery St | Walls Construction And Contracting Inc | remove non-compliant convenience stair 3 add non-bearing office partition @ floors 3,5,6,7 & 8. no change of use on office floorsDetails
remove non-compliant convenience stair 3 add non-bearing office partition @ floors 3,5,6,7 & 8. no change of use on office floors | $210,500 |
| Feb 20, 2026 | In progress issued Mar 2026 | 2919 Webster St | Yefa Construction Inc | revision to permit 202212289279. minor interior modifications.Details
revision to permit 202212289279. minor interior modifications. | |
| Feb 19, 2026 | In progress issued Jun 2026 | 350 Parnassus Av | Wci-Gc Inc | 7th/f ste 706: t.i. add 2 single-user restrooms. no structural modificationDetails
7th/f ste 706: t.i. add 2 single-user restrooms. no structural modification | $48,450 |
| Jan 23, 2026 | In progress issued Feb 2026 | 461 Pacific Av | Two Bricks Design Build | mep permit for t.i. 202407186789 & 202511149590Details
mep permit for t.i. 202407186789 & 202511149590 | $48,500 |
| Jan 21, 2026 | In progress issued Jan 2026 | 55 New Montgomery St | Walls Construction And Contracting Inc | floors 3,5,6,7 & 8 revision to pa #2025-1223-2562: modified restroom layoutDetails
floors 3,5,6,7 & 8 revision to pa #2025-1223-2562: modified restroom layout | |
| Dec 24, 2025 | Completed final sign-off Apr 2026 | 747 Howard St | Swinerton Builders | to comply with nov 202539626: exhibition level interior work, install prefabricated office system vender check in desk. change of use from storage to businessDetails
to comply with nov 202539626: exhibition level interior work, install prefabricated office system vender check in desk. change of use from storage to business | $48,220 |
| Dec 23, 2025 | In progress issued Jan 2026 | 55 New Montgomery St | Walls Construction And Contracting Inc | 3,5,6,7,8th/f: identical t.i. new men's/women's restrooms, kitchenette/snack for office use only. interior work onlyDetails
3,5,6,7,8th/f: identical t.i. new men's/women's restrooms, kitchenette/snack for office use only. interior work only | $210,000 |
| Dec 4, 2025 | In progress issued Jun 2026 | 123 Townsend St | C C I Commercial Construction & Improv | 5th floor tenant improvement demo of (e) non bearing walls, adding (n) interior non bearing walls and cleanup finishes. reduced scope from 12/4/2025 review.Details
5th floor tenant improvement demo of (e) non bearing walls, adding (n) interior non bearing walls and cleanup finishes. reduced scope from 12/4/2025 review. | $145,500 |
| Nov 14, 2025 | In progress issued Jan 2026 | 461 Pacific Av | Two Bricks Design Build | exteiro work updating (e) storefront at 1st floor, replacing (e) stair from 3rd to roof with reconfigured stair enclosure, replacing roof deck at (e) roof, adding (n) windows on east facade of building within the same opening. remove rear fire escape and replace vertical ladders on front w/inclineDetails
exteiro work updating (e) storefront at 1st floor, replacing (e) stair from 3rd to roof with reconfigured stair enclosure, replacing roof deck at (e) roof, adding (n) windows on east facade of building within the same opening. remove rear fire escape and replace vertical ladders on front w/incline | $204,250 |
| Sep 22, 2025 | In progress issued Jan 2026 | 51 Commonwealth Av | C C I Commercial Construction & Improv | bldg a: after fire renovation of bldg a, new elevator with domers, reconfigure e) restrooms, voluntary stengthening of e) structure new dormers on roof facing street. new ramp.Details
bldg a: after fire renovation of bldg a, new elevator with domers, reconfigure e) restrooms, voluntary stengthening of e) structure new dormers on roof facing street. new ramp. | $240,395 |
| Sep 12, 2025 | In progress filed Sep 2025, not yet issued | 428 11th St | relocate temporary city navigation center, including 60 cabin units, restrooms and shower trailers, and storage containers to new 428 11th street location. previously approved permit 2023-0501-6790.Details
relocate temporary city navigation center, including 60 cabin units, restrooms and shower trailers, and storage containers to new 428 11th street location. previously approved permit 2023-0501-6790. | $240,000 | |
| Sep 3, 2025 | Completed final sign-off Sep 2025 | 3940 Lawton St | to obtain final inspection for work approved under pa # 2019-1227-0855. all work is complete.Details
to obtain final inspection for work approved under pa # 2019-1227-0855. all work is complete. | ||
| Aug 27, 2025 | In progress issued Oct 2025 | 151 Belvedere St | Jones Real Estate Development Llc | revise pa #2021-0902-7679 attic conversion 4/f revised roof at mid house light well, due to dryrot.Details
revise pa #2021-0902-7679 attic conversion 4/f revised roof at mid house light well, due to dryrot. | |
| Aug 5, 2025 | In progress issued Aug 2025 | 51 Commonwealth Av | C C I Commercial Construction & Improv | commencement of work not started under previously aproved permit. application 2021-09-01-7568Details
commencement of work not started under previously aproved permit. application 2021-09-01-7568 | |
| May 14, 2025 | Completed final sign-off Oct 2025 | 350 Parnassus Av | Cobuild Construction Services Inc | 3rd/f: interior work only, 3rd fl new non-bearing partition & new sinkDetails
3rd/f: interior work only, 3rd fl new non-bearing partition & new sink | $12,500 |
| Apr 9, 2025 | Completed final sign-off Jan 2026 | 1805 Geary Bl | Swinerton Builders | revision to permit 202202212343 ground floor tentant 1539 fillmore st. reconfigure machine room, restroom @ ground fl; remove stair & 2nd fl lula elevator from scopeDetails
revision to permit 202202212343 ground floor tentant 1539 fillmore st. reconfigure machine room, restroom @ ground fl; remove stair & 2nd fl lula elevator from scope | |
| Dec 13, 2024 | Completed final sign-off Feb 2025 | 550 03rd St | Walls Construction And Contracting Inc | interior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred.Details
interior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred. | $38,000 |
| Oct 10, 2024 | Completed final sign-off Aug 2025 | 800 Howard St | Swinerton Builders | mechanical electrical permit. ref pa# 202409181070Details
mechanical electrical permit. ref pa# 202409181070 | $68,000 |
| Sep 18, 2024 | Completed final sign-off Sep 2025 | 800 Howard St | Swinerton Builders | voluntary plumbing fixture in kind replacement. at (e) mens/womens restrooms on 1st,2nd,3rd floor. replace (e) wall finishes. no layout changes.Details
voluntary plumbing fixture in kind replacement. at (e) mens/womens restrooms on 1st,2nd,3rd floor. replace (e) wall finishes. no layout changes. | $650,000 |
| Aug 29, 2024 | In progress filed Aug 2024, not yet issued | 2224 Union St | 1st floor interior work only- add (n) non bearing partitions and cleaned up finishes. change of use from general retail to health services.Details
1st floor interior work only- add (n) non bearing partitions and cleaned up finishes. change of use from general retail to health services. | $125,375 | |
| Jul 18, 2024 | In progress issued Nov 2025 | 461 Pacific Av | Two Bricks Design Build, Bbc Construction Inc. | interior work only. replacement of (e) non-compliant stairs. removal of (e) non-bearing interior walls. 1 hour fire rated stair enclousureDetails
interior work only. replacement of (e) non-compliant stairs. removal of (e) non-bearing interior walls. 1 hour fire rated stair enclousure | $138,000 |
| Jun 18, 2024 | Completed final sign-off Jan 2025 | 2177 Jerrold Av | C C I Commercial Construction & Improv | interior work only: 1/f - add non-bearing walls & accessible restroom. 2/f: minor change to wall layout. rev to 202310209176Details
interior work only: 1/f - add non-bearing walls & accessible restroom. 2/f: minor change to wall layout. rev to 202310209176 | $63,000 |
| May 7, 2024 | Completed final sign-off Apr 2025 | 2177 Jerrold Av | C C I Commercial Construction & Improv | install 60 pre-fab units of interim homeless housing building b scope of work: new accessible uniisex restrooms with showers, new mens and womens restrooms + showers provide parking for rv's.Details
install 60 pre-fab units of interim homeless housing building b scope of work: new accessible uniisex restrooms with showers, new mens and womens restrooms + showers provide parking for rv's. | $1,300,000 |
| Apr 25, 2024 | In progress issued Jul 2024 | 156 02nd St | Walls Construction And Contracting Inc | new observation deck at extg roof level.Details
new observation deck at extg roof level. | $63,000 |
| Apr 10, 2024 | In progress issued Apr 2024 | 185 Clara St | Walls Construction And Contracting Inc | obtain final inspection for work approved under 200708311568. all work is complete.Details
obtain final inspection for work approved under 200708311568. all work is complete. | |
| Mar 29, 2024 | In progress issued Apr 2024 | 51 Commonwealth Av | C C I Commercial Construction & Improv | new fence at front and side property lines.Details
new fence at front and side property lines. | $48,500 |
| Mar 21, 2024 | Completed final sign-off Oct 2024 | 1100 Sansome St | Two Bricks Design Build | revision to 202312273177: interior elevations & framing clarificationDetails
revision to 202312273177: interior elevations & framing clarification | |
| Mar 20, 2024 | Completed final sign-off Oct 2024 | 735 Montgomery St | M C S Construction Services | 4th/f tenant improvement. ref pa#202301200473 interior work- add (n) non bearing partitions, minor revision to restrooms & kitchenetteDetails
4th/f tenant improvement. ref pa#202301200473 interior work- add (n) non bearing partitions, minor revision to restrooms & kitchenette | $85,000 |
| Feb 8, 2024 | Completed final sign-off Aug 2024 | 1100 Sansome St | Two Bricks Design Build | 2/f tenant interior - (n) non bearing partitons, (n) office and office bathroom.Details
2/f tenant interior - (n) non bearing partitons, (n) office and office bathroom. | $138,500 |
| Feb 2, 2024 | Completed final sign-off Oct 2024 | 1100 Sansome St | Two Bricks Design Build | revision to pa# 202312273177, change to office layout, proposed walls. add 3 walls non load bearing non rated partitionsDetails
revision to pa# 202312273177, change to office layout, proposed walls. add 3 walls non load bearing non rated partitions | $4,500 |
| Dec 27, 2023 | Completed final sign-off Oct 2024 | 1100 Sansome St | Two Bricks Design Build | tenant interior (n) mens/womens's restrooms and (n) offices at 1st fl.Details
tenant interior (n) mens/womens's restrooms and (n) offices at 1st fl. | $185,000 |
| Dec 4, 2023 | In progress filed Dec 2023, not yet issued | 156 02nd St | assembly space @ ground floor & basement. no scope of workDetails
assembly space @ ground floor & basement. no scope of work | ||
| Nov 7, 2023 | Completed final sign-off Nov 2023 | 880 Harrison St | Walls Construction And Contracting Inc | revision to permit 202202158047. clarification of metal screen shape.Details
revision to permit 202202158047. clarification of metal screen shape. | |
| Oct 20, 2023 | Completed final sign-off Jan 2025 | 2177 Jerrold Av | C C I Commercial Construction & Improv | interior work, add accessible elevator connecting e 2 stories, add unisex ada restroom at 2nd fl and cleaned up finishes.Details
interior work, add accessible elevator connecting e 2 stories, add unisex ada restroom at 2nd fl and cleaned up finishes. | $155,695 |
| Oct 6, 2023 | Completed final sign-off Jul 2024 | 126 Guerrero St | renovate (e) primary bathroom replace fixturesDetails
renovate (e) primary bathroom replace fixtures | $8,500 | |
| Sep 5, 2023 | In progress issued Mar 2024 | 1067 Green St | revision to pa# 202212087894. foundation strengthening of existing building, and alterations at basement level.Details
revision to pa# 202212087894. foundation strengthening of existing building, and alterations at basement level. | $85,000 | |
| Jun 14, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | Walls Construction And Contracting Inc | replace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only)Details
replace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only) | $87,000 |
| May 5, 2023 | Completed final sign-off Oct 2023 | 350 Parnassus Av | Dome Construction Corp | revison to permit# 2022-1116-6678. remove non-bearing wall, reduction of scopeDetails
revison to permit# 2022-1116-6678. remove non-bearing wall, reduction of scope | |
| Apr 14, 2023 | Completed final sign-off Jul 2023 | 1324 Willard St | revision to pa# 2022-0607-5761; updated t-24 report, remove proposed solar water heating panels from scope of workDetails
revision to pa# 2022-0607-5761; updated t-24 report, remove proposed solar water heating panels from scope of work | ||
| Apr 11, 2023 | Completed final sign-off Aug 2024 | 350 Parnassus Av | Dome Construction Corp | mep work for 202212087889. rooftop mechanical equipment added with ductwork to floors below.Details
mep work for 202212087889. rooftop mechanical equipment added with ductwork to floors below. | $756,000 |
| Mar 24, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | Walls Construction And Contracting Inc | replace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spacesDetails
replace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spaces | $133,000 |
| Mar 22, 2023 | Expired or cancelled cancelled Jan 2026 | 1504 Bryant St | Cogent Construction & Consulting Inc | extend (e) stairs & stair cores to roof for maintenance access, add (3)new exterior windows, repair (e) entry awning. no change of useDetails
extend (e) stairs & stair cores to roof for maintenance access, add (3)new exterior windows, repair (e) entry awning. no change of use | $55,000 |
| Mar 10, 2023 | Completed final sign-off Dec 2024 | 550 03rd St | Alsterlind Construction Inc. | rev to pa # 202210214929 - modifications to proposed interior work; minor layout changes.Details
rev to pa # 202210214929 - modifications to proposed interior work; minor layout changes. | $16,000 |
| Mar 10, 2023 | Completed final sign-off Jan 2026 | 1805 Geary Bl | Swinerton Builders | voluntary replacement of (e) service lift at back of side alley.Details
voluntary replacement of (e) service lift at back of side alley. | $103,000 |
| Feb 21, 2023 | Completed final sign-off Mar 2023 | 350 Parnassus Av | Ayoob & Peery Plumbing Co Inc | 3/f: relocate 79 fire sprinkler heads per ti ref# 202202117832.Details
3/f: relocate 79 fire sprinkler heads per ti ref# 202202117832. | $49,072 |
| Feb 21, 2023 | Completed final sign-off Mar 2023 | 350 Parnassus Av | Ayoob & Peery Plumbing Co Inc | 4/f: relocate 88 fire sprinkler heads per ti ref# 202211166678.Details
4/f: relocate 88 fire sprinkler heads per ti ref# 202211166678. | $54,663 |
| Feb 21, 2023 | Completed final sign-off Jan 2026 | 1805 Geary Bl | Swinerton Builders | voluntary replacement of (e) rear fire stair #2, (n) ada lula elevator from 2nd to 3rd fl, repl concrete pad of side alley service lift.Details
voluntary replacement of (e) rear fire stair #2, (n) ada lula elevator from 2nd to 3rd fl, repl concrete pad of side alley service lift. | $176,000 |
| Feb 10, 2023 | Completed final sign-off Apr 2024 | 735 Montgomery St | M C S Construction Services | revision to permit 202205255011. 2/f: interior work only. demolition of non-bearing partitions, add new non-bearing partitions.Details
revision to permit 202205255011. 2/f: interior work only. demolition of non-bearing partitions, add new non-bearing partitions. | $35,000 |
| Feb 10, 2023 | Expired or cancelled expired Jan 2026 | 1805 Geary Bl | Swinerton Builders | voluntary replacement of (e) front fire stair in-kind and replace alleyway gate.Details
voluntary replacement of (e) front fire stair in-kind and replace alleyway gate. | $64,000 |
| Feb 6, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | Walls Construction And Contracting Inc | new elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows.Details
new elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows. | $177,000 |
| Feb 3, 2023 | Completed final sign-off Aug 2025 | 735 Montgomery St | M C S Construction Services | 4/f: to provide ada lift for acess to (e) roof deck & guardrail upgradeDetails
4/f: to provide ada lift for acess to (e) roof deck & guardrail upgrade | $45,545 |
| Jan 20, 2023 | Completed final sign-off Aug 2025 | 735 Montgomery St | M C S Construction Services | 4th fl - demolition of non-bearing partitions, add few (n) non-bearing partitions, upgrade restrooms, add kitchenetteDetails
4th fl - demolition of non-bearing partitions, add few (n) non-bearing partitions, upgrade restrooms, add kitchenette | $125,945 |
| Dec 30, 2022 | Completed final sign-off Jul 2025 | 3969 24th St | accessible business entrance checklist abe201910287470Details
accessible business entrance checklist abe201910287470 | ||
| Dec 28, 2022 | In progress issued Apr 2025 | 2919 Webster St | Yefa Construction Inc | attic conversion with (n) dormers,(n) horizontal addition & roof deck at attic level. access stair at rear. ground level remodel at (e) garage and back storage space conversion to living space.Details
attic conversion with (n) dormers,(n) horizontal addition & roof deck at attic level. access stair at rear. ground level remodel at (e) garage and back storage space conversion to living space. | $225,800 |
| Dec 8, 2022 | Never finaled issued Dec 2022, no final | 1067 Green St | voluntary foundation strengthening of e building interior work only, no changes to exteriorDetails
voluntary foundation strengthening of e building interior work only, no changes to exterior | $38,500 | |
| Dec 8, 2022 | Completed final sign-off Aug 2024 | 350 Parnassus Av | Dome Construction Corp | building infrastructure work only. rooftop mechanical equipment and duct runs to floors below via both fire-rated stairwells top to bottom for voluntary stair pressurization. not visible not historical. mep/fire life safety under sep permits.Details
building infrastructure work only. rooftop mechanical equipment and duct runs to floors below via both fire-rated stairwells top to bottom for voluntary stair pressurization. not visible not historical. mep/fire life safety under sep permits. | $165,000 |
| Dec 5, 2022 | Completed final sign-off Nov 2023 | 350 Parnassus Av | Dome Construction Corp | revision to bpa#202202117832 3/f, new interior, nonbearing partitions, new kitchenette, new restroomsDetails
revision to bpa#202202117832 3/f, new interior, nonbearing partitions, new kitchenette, new restrooms | $85,800 |
| Nov 16, 2022 | Completed final sign-off Dec 2023 | 350 Parnassus Av | Dome Construction Corp | interior work only: 4th floor demolition of non-bearing partition walls, adding new non-bearing walls and new kitchenette and restrooms.Details
interior work only: 4th floor demolition of non-bearing partition walls, adding new non-bearing walls and new kitchenette and restrooms. | $135,125 |
| Nov 2, 2022 | Never finaled issued Aug 2023, no final | 1067 Green St | new curb cut, driveway car gate, replace front fence. modification to (e) garage.Details
new curb cut, driveway car gate, replace front fence. modification to (e) garage. | $18,500 | |
| Nov 2, 2022 | Never finaled issued Nov 2022, no final | 735 Montgomery St | M C S Construction Services | to erect an exterior signage non illuminaed blade wall sign.Details
to erect an exterior signage non illuminaed blade wall sign. | $4,500 |
| Oct 28, 2022 | Completed final sign-off Jul 2023 | 3104 24th St | Saturn Construction Co | remove extg non-bearing partition between dining area and restaurant, ground floor at 3108 24th streetDetails
remove extg non-bearing partition between dining area and restaurant, ground floor at 3108 24th street | $38,000 |
| Oct 21, 2022 | Completed final sign-off Feb 2025 | 550 03rd St | Alsterlind Construction Inc. | removal of (e) non-bearing walls, new accessible kitchenette, unisex restrooms & shower.Details
removal of (e) non-bearing walls, new accessible kitchenette, unisex restrooms & shower. | $93,000 |
| Aug 23, 2022 | Expired or cancelled expired Jan 2025 | 350 Parnassus Av | C C I Commercial Construction & Improv | lobby interior work only: updating all interior finishes paint & general clean up, remove (e) soffit, patch & repair as required.Details
lobby interior work only: updating all interior finishes paint & general clean up, remove (e) soffit, patch & repair as required. | $12,500 |
| Aug 3, 2022 | Never finaled issued Jan 2023, no final | 20 Heron St | C C I Commercial Construction & Improv | change of occupancy & use from s-2 to f-1, light manufacturing.Details
change of occupancy & use from s-2 to f-1, light manufacturing. | |
| Jul 29, 2022 | Never finaled issued Sep 2022, no final | 20 Palo Alto Av | interior work only: remodel of (e) bathrooms and kitchens @ basement & 1st fl. replace main stair and remodel laundry/ bathrooms on the 2nd fl. update finishes. ref lower level adu permit 2020 0910 3866.Details
interior work only: remodel of (e) bathrooms and kitchens @ basement & 1st fl. replace main stair and remodel laundry/ bathrooms on the 2nd fl. update finishes. ref lower level adu permit 2020 0910 3866. | $235,000 | |
| Jul 15, 2022 | Completed final sign-off Dec 2022 | 1690 38th Av | Sf Gonzalez Concrete Inc. | one new curb cut at moraga street.Details
one new curb cut at moraga street. | $8,500 |
| Jul 14, 2022 | Completed final sign-off Apr 2024 | 735 Montgomery St | M C S Construction Services | 2/f: deffered mech & electrical for t.i. pa 20220525.5011.Details
2/f: deffered mech & electrical for t.i. pa 20220525.5011. | $100,000 |
| May 25, 2022 | Completed final sign-off Apr 2024 | 735 Montgomery St | M C S Construction Services | interior work only 2nd floor demolition of (e) non bearing walls (n) non-bearing paritions for open office space, upgrade restrooms and add kitchenette. mep under seperate permit. seperate permit for tenant improvement.Details
interior work only 2nd floor demolition of (e) non bearing walls (n) non-bearing paritions for open office space, upgrade restrooms and add kitchenette. mep under seperate permit. seperate permit for tenant improvement. | $154,785 |
| May 4, 2022 | Completed final sign-off Nov 2022 | 735 Montgomery St | Sc Builders, Inc | 3/f ti: department of public health review to previously approved permit 202111243152. revised layout for kitchenette/bar/pantry.Details
3/f ti: department of public health review to previously approved permit 202111243152. revised layout for kitchenette/bar/pantry. | |
| Mar 29, 2022 | Never finaled issued Apr 2022, no final | 468 09th St | C C I Commercial Construction & Improv | remove (e) non-load bearing interior partitions. remodel (e) toilet room, (n) kitchenette, and replace roll up door.Details
remove (e) non-load bearing interior partitions. remodel (e) toilet room, (n) kitchenette, and replace roll up door. | $48,000 |
| Mar 25, 2022 | Never finaled issued Apr 2022, no final | 42 Rossi Av | Baxter Construction | remove (e) structural columns in basement, remove (e) interior non bearing wall on the 1st fl. kitchen, and 2 fl. bathroomDetails
remove (e) structural columns in basement, remove (e) interior non bearing wall on the 1st fl. kitchen, and 2 fl. bathroom | $38,000 |
| Feb 11, 2022 | Expired or cancelled expired Nov 2023 | 350 Parnassus Av | Dome Construction Corp, C C I Commercial Construction & Improv | 3rd fl - interior work only non-bearing partition; demo w/n kitchenette and meeting room. accessibility per ab-017.Details
3rd fl - interior work only non-bearing partition; demo w/n kitchenette and meeting room. accessibility per ab-017. | $49,000 |
| Jan 28, 2022 | Never finaled issued Jan 2022, no final | 200 Green St | Meylan Construction | revision to permit #202106243158. install new ada automatic door opener system at suite 200 main entrance.Details
revision to permit #202106243158. install new ada automatic door opener system at suite 200 main entrance. | $1,500 |
| Dec 10, 2021 | Never finaled issued Dec 2021, no final | 350 Parnassus Av | C C I Commercial Construction & Improv | interior work only: demo permit for 6th floor. remove non-bearing interior walls.Details
interior work only: demo permit for 6th floor. remove non-bearing interior walls. | $65,000 |
| Nov 24, 2021 | Completed final sign-off Nov 2022 | 735 Montgomery St | Sc Builders, Inc | revision to permit 202107023728. 3rd floor interior tenant improvements - revised layout to relocate bathrooms & build new non bearing walls.Details
revision to permit 202107023728. 3rd floor interior tenant improvements - revised layout to relocate bathrooms & build new non bearing walls. | $84,550 |
| Oct 28, 2021 | Completed final sign-off Jul 2022 | 20 Heron St | C C I Commercial Construction & Improv | new interior wall partitions, ada shower, kitchenetts and pendant lighting on 1st to 4th floor.Details
new interior wall partitions, ada shower, kitchenetts and pendant lighting on 1st to 4th floor. | $225,000 |
| Oct 14, 2021 | Completed final sign-off Jun 2022 | 1155 Bryant St | Dome Construction Corp | interior work only: renovation @ 1st and 3rd fl. adding a few non bearing walls, mep under separate permit. fire alarm/sprinklers under sep permits, if applic.Details
interior work only: renovation @ 1st and 3rd fl. adding a few non bearing walls, mep under separate permit. fire alarm/sprinklers under sep permits, if applic. | $225,000 |
| Sep 2, 2021 | Never finaled issued Feb 2023, no final | 151 Belvedere St | Sage Construction Services, Jones Real Estate Development Llc | renovation to (e) attic including (n) shed dormers for (n) occupied space and (n) elevator w/ access to all floors. (n) balcony, add skylights. sprinklers per nfpa 13r and sprinkler montioring per nfpa 72 deferred.Details
renovation to (e) attic including (n) shed dormers for (n) occupied space and (n) elevator w/ access to all floors. (n) balcony, add skylights. sprinklers per nfpa 13r and sprinkler montioring per nfpa 72 deferred. | $170,000 |
| Sep 2, 2021 | Never finaled issued May 2023, no final | 314 Twin Peaks Bl | addition at (e) roof deck attached to (e) stair enclosure. plus replacing & extending (e) balcony at 1st flr & back yard modification to (e) exterior deck on grade w/ outdoor wet bar & pool / hot tub combination.Details
addition at (e) roof deck attached to (e) stair enclosure. plus replacing & extending (e) balcony at 1st flr & back yard modification to (e) exterior deck on grade w/ outdoor wet bar & pool / hot tub combination. | $185,000 | |
| Sep 1, 2021 | Never finaled issued Sep 2021, no final | 51 Commonwealth Av | revision to permit 2020-1005-5906 add to description of work "restore interior in-kind, to match condition prior to fire damage." repair / replace windows in-kind.Details
revision to permit 2020-1005-5906 add to description of work "restore interior in-kind, to match condition prior to fire damage." repair / replace windows in-kind. | $50,000 | |
| Aug 10, 2021 | Never finaled issued Nov 2021, no final | 314 Twin Peaks Bl | replacement of (e) exterior windows in kind with new insulated units.Details
replacement of (e) exterior windows in kind with new insulated units. | $85,000 | |
| Jul 2, 2021 | Completed final sign-off Nov 2022 | 735 Montgomery St | M C S Construction Services, Sc Builders, Inc | 3rd floor interior t.i. remove a few non-bearing partition walls, add a new kitchenette.Details
3rd floor interior t.i. remove a few non-bearing partition walls, add a new kitchenette. | $115,000 |
| Jun 24, 2021 | Completed final sign-off Feb 2022 | 200 Green St | Meylan Construction | interior work only, add interior non bearing partitoins on 1st fl and cleaned up finishesDetails
interior work only, add interior non bearing partitoins on 1st fl and cleaned up finishes | $48,000 |
| May 5, 2021 | Never finaled issued May 2021, no final | 1128 Market St | C C I Commercial Construction & Improv | 5th fl: revision to pa# 202009124049. add 1 kitchenette, remove 1 lavatory (sink) in (e) (#2) mens room with new finishes (paint and tile, as required).Details
5th fl: revision to pa# 202009124049. add 1 kitchenette, remove 1 lavatory (sink) in (e) (#2) mens room with new finishes (paint and tile, as required). | $35,000 |
| Mar 29, 2021 | Completed final sign-off Aug 2021 | 1805 Geary Bl | Swinerton Builders | voluntary floor reinforcement at existing 2nd floor music hall.Details
voluntary floor reinforcement at existing 2nd floor music hall. | $185,500 |
| Mar 24, 2021 | In progress issued Sep 2025 | 900 Sansome St | Gci, Inc | change of use and occupancy from s-2 (parking garage) to b (office) use, including: a new elevator, egress and ada bathroom upgradesDetails
change of use and occupancy from s-2 (parking garage) to b (office) use, including: a new elevator, egress and ada bathroom upgrades | $260,000 |
| Mar 17, 2021 | Never finaled issued Apr 2021, no final | 2000 Judah St | Robert B Lewis Renovations | replace & widen existing load-in roll-up door.Details
replace & widen existing load-in roll-up door. | $15,000 |
| Feb 4, 2021 | Completed final sign-off Oct 2021 | 150 Golden Gate Av | Nibbi Bros Assoc Inc. | adding 3 new unisex bathrooms & a laundry space at ground floor of existing building.Details