Permit GraphShortlistSan Francisco building permits since 2000

Block 3776, lot 005

550 03rd St

City’s use
Commercial Office
Built
1921
Stories
2
Rooms
2 bathrooms
Building
19,997 sq ft
Lot
11,733 sq ft
Zoning
SLI
Construction type
NA

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

23 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Feb 13, 2025Completed
final sign-off Feb 2025
550 03rd StSan Francisco Fire Protectionas builts to 202405142101. change matrix to show global shutdown for hvac system per fire inspector request during inspection
Details
Permit
202502130287
Status
complete
Filed
Feb 13, 2025
Permit issued
Feb 13, 2025
Final sign-off
Feb 26, 2025
Address
550 03rd St

as builts to 202405142101. change matrix to show global shutdown for hvac system per fire inspector request during inspection

Open the permit page

Jan 16, 2025Completed
final sign-off Feb 2025
550 03rd StSan Francisco Fire Protectionas-built to 202405142101. removed 8 duct deterors w/ monitor & relay modules from fl plan, leqeud riser& cases, due to deferred mep t.i. 202501108126
Details
Permit
202501168486
Status
complete
Filed
Jan 16, 2025
Permit issued
Jan 16, 2025
Final sign-off
Feb 26, 2025
Address
550 03rd St

as-built to 202405142101. removed 8 duct deterors w/ monitor & relay modules from fl plan, leqeud riser& cases, due to deferred mep t.i. 202501108126

Open the permit page

Jan 10, 2025Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Incinterior work offices 1st and 2nd floor. mechanical and electrical. mep deferred portion for ref app # 202412136809.
Details
Permit
202501108126
Status
complete
Filed
Jan 10, 2025
Permit issued
Jan 14, 2025
Final sign-off
Feb 25, 2025
Declared cost
$10,000
Address
550 03rd St

interior work offices 1st and 2nd floor. mechanical and electrical. mep deferred portion for ref app # 202412136809.

Open the permit page

$10,000
Dec 17, 2024Completed
final sign-off Feb 2025
550 03rd StSan Francisco Fire Protectionas builts 202405142101 due to ti on 1st & 2nd floors adding new offices, new 8 strobes will be installed and tied-in to existing notification circuits. ref pa 202412136809
Details
Permit
202412176985
Status
complete
Filed
Dec 17, 2024
Permit issued
Dec 17, 2024
Final sign-off
Feb 25, 2025
Declared cost
$4,000
Address
550 03rd St

as builts 202405142101 due to ti on 1st & 2nd floors adding new offices, new 8 strobes will be installed and tied-in to existing notification circuits. ref pa 202412136809

Open the permit page

$4,000
Dec 13, 2024Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Incinterior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred.
Details
Permit
202412136809
Status
complete
Filed
Dec 13, 2024
Permit issued
Dec 13, 2024
Final sign-off
Feb 25, 2025
Declared cost
$38,000
Address
550 03rd St

interior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred.

Open the permit page

$38,000
Nov 12, 2024Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Incelectrical lighting title - 24. ref pa#202302061449
Details
Permit
202411124830
Status
complete
Filed
Nov 12, 2024
Permit issued
Nov 19, 2024
Final sign-off
Feb 25, 2025
Declared cost
$60,000
Address
550 03rd St

electrical lighting title - 24. ref pa#202302061449

Open the permit page

$60,000
May 21, 2024Completed
final sign-off Feb 2025
550 03rd StSchmitt Heating Co Increplace extg roof mount package units and ducting wit 4 new roof mount heat pumps, ducting and 1-4 zone ductless heat pump. ref pa 2023-0206-1449
Details
Permit
202405212549
Status
complete
Filed
May 21, 2024
Permit issued
Jul 15, 2024
Final sign-off
Feb 25, 2025
Declared cost
$100,000
Address
550 03rd St

replace extg roof mount package units and ducting wit 4 new roof mount heat pumps, ducting and 1-4 zone ductless heat pump. ref pa 2023-0206-1449

Open the permit page

$100,000
May 14, 2024Completed
final sign-off Feb 2025
550 03rd StSan Francisco Fire Protectioninstallation of new fire system w/new panel, radio, smoke detectors & pull station in fully sprinklered building. install monitor modules to tie in flow & tamper switch relay modules for elevator recall & notification devices throughout. ref pa# 2023-0614-0080 & 2023-0206-1449
Details
Permit
202405142101
Status
complete
Filed
May 14, 2024
Permit issued
Aug 8, 2024
Final sign-off
Feb 25, 2025
Declared cost
$30,000
Address
550 03rd St

installation of new fire system w/new panel, radio, smoke detectors & pull station in fully sprinklered building. install monitor modules to tie in flow & tamper switch relay modules for elevator recall & notification devices throughout. ref pa# 2023-0614-0080 & 2023-0206-1449

Open the permit page

$30,000
Nov 9, 2023Completed
final sign-off Aug 2026
550 03rd StO'connor Plumbing & Fire Protectiontenant improvement. add new fire sprinkler heads per new layout.
Details
Permit
202311090491
Status
complete
Filed
Nov 9, 2023
Permit issued
Nov 9, 2023
Final sign-off
Aug 3, 2026
Declared cost
$25,000
Address
550 03rd St

tenant improvement. add new fire sprinkler heads per new layout.

Open the permit page

$25,000
Jun 14, 2023Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Increplace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only)
Details
Permit
202306140080
Status
complete
Filed
Jun 14, 2023
Permit issued
Jul 27, 2023
Final sign-off
Feb 25, 2025
Declared cost
$87,000
Address
550 03rd St

replace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only)

Open the permit page

$87,000
Mar 24, 2023Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Increplace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spaces
Details
Permit
202303244396
Status
complete
Filed
Mar 24, 2023
Permit issued
Jun 6, 2023
Final sign-off
Feb 25, 2025
Declared cost
$133,000
Address
550 03rd St

replace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spaces

Open the permit page

$133,000
Mar 10, 2023Completed
final sign-off Dec 2024
550 03rd StAlsterlind Construction Inc.rev to pa # 202210214929 - modifications to proposed interior work; minor layout changes.
Details
Permit
202303103480
Status
complete
Filed
Mar 10, 2023
Permit issued
Mar 10, 2023
Final sign-off
Dec 16, 2024
Declared cost
$16,000
Address
550 03rd St

rev to pa # 202210214929 - modifications to proposed interior work; minor layout changes.

Open the permit page

$16,000
Feb 6, 2023Completed
final sign-off Feb 2025
550 03rd StWalls Construction And Contracting Incnew elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows.
Details
Permit
202302061449
Status
complete
Filed
Feb 6, 2023
Permit issued
Nov 1, 2023
Final sign-off
Feb 25, 2025
Declared cost
$177,000
Address
550 03rd St

new elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows.

Open the permit page

$177,000
Oct 21, 2022Completed
final sign-off Feb 2025
550 03rd StAlsterlind Construction Inc.removal of (e) non-bearing walls, new accessible kitchenette, unisex restrooms & shower.
Details
Permit
202210214929
Status
complete
Filed
Oct 21, 2022
Permit issued
Oct 28, 2022
Final sign-off
Feb 25, 2025
Declared cost
$93,000
Address
550 03rd St

removal of (e) non-bearing walls, new accessible kitchenette, unisex restrooms & shower.

Open the permit page

$93,000
Apr 11, 2017Never finaled
issued Apr 2017, no final
550 03rd StCentimark Corporationre-roofing.
Details
Permit
201704113732
Status
issued
Filed
Apr 11, 2017
Permit issued
Apr 11, 2017
Declared cost
$11,600
Address
550 03rd St

re-roofing.

Open the permit page

$11,600
Apr 7, 2017Never finaled
issued Apr 2017, no final
550 03rd Ststreet space & mta parking meter
Details
Permit
M775867
Status
issued
Filed
Apr 7, 2017
Permit issued
Apr 7, 2017
Address
550 03rd St

street space & mta parking meter

Open the permit page

Jun 29, 2015Expired or cancelled
cancelled Mar 2023
550 03rd StGci, Incnew lighting in restroom power in breakroom. ref app#201505085783. n/a for maher.
Details
Permit
201506290227
Status
cancelled
Filed
Jun 29, 2015
Permit issued
Jun 29, 2015
Declared cost
$12,000
Address
550 03rd St

new lighting in restroom power in breakroom. ref app#201505085783. n/a for maher.

Open the permit page

$12,000
Jun 18, 2015Completed
final sign-off Aug 2015
550 03rd StGci, Inc1st floor:install bathroom exhaust. ref. to t.i. pa#201505085783. n/a ordinance #155-13
Details
Permit
201506189268
Status
complete
Filed
Jun 18, 2015
Permit issued
Jun 23, 2015
Final sign-off
Aug 17, 2015
Declared cost
$3,000
Address
550 03rd St

1st floor:install bathroom exhaust. ref. to t.i. pa#201505085783. n/a ordinance #155-13

Open the permit page

$3,000
Jun 5, 2015Completed
final sign-off Jul 2015
550 03rd StPioneer Fire Inc.relocate one recessed pendent and add 1 recessed pendent. fire sprinklers. ref app#201505085783. n/a for maher
Details
Permit
201506058258
Status
complete
Filed
Jun 5, 2015
Permit issued
Jun 5, 2015
Final sign-off
Jul 9, 2015
Declared cost
$4,400
Address
550 03rd St

relocate one recessed pendent and add 1 recessed pendent. fire sprinklers. ref app#201505085783. n/a for maher

Open the permit page

$4,400
May 8, 2015Completed
final sign-off Aug 2015
550 03rd StGci, Incvoluntary barrier removal, construct 2 new accessible restrooms, make kitchen millwork accessible
Details
Permit
201505085783
Status
complete
Filed
May 8, 2015
Permit issued
May 22, 2015
Final sign-off
Aug 17, 2015
Declared cost
$35,000
Address
550 03rd St

voluntary barrier removal, construct 2 new accessible restrooms, make kitchen millwork accessible

Open the permit page

$35,000
May 19, 2000Completed
final sign-off Sep 2000
550 03rd StSascomonitoring flow, tamper, and hvac units
Details
Permit
200005190484
Status
complete
Filed
May 19, 2000
Permit issued
May 19, 2000
Final sign-off
Sep 19, 2000
Declared cost
$4,500
Address
550 03rd St

monitoring flow, tamper, and hvac units

Open the permit page

$4,500
Apr 27, 2000Expired or cancelled
expired Aug 2000
550 03rd Ststreet space
Details
Permit
M12462
Status
expired
Filed
Apr 27, 2000
Permit issued
Apr 27, 2000
Address
550 03rd St

street space

Open the permit page

Mar 3, 2000Completed
final sign-off Sep 2000
550 03rd Stcomplete tenant improvement/structural strengthening of strc
Details
Permit
9918537
Status
complete
Filed
Mar 3, 2000
Permit issued
Mar 6, 2000
Final sign-off
Sep 19, 2000
Declared cost
$1,500,000
Address
550 03rd St

complete tenant improvement/structural strengthening of strc

Open the permit page

$1,500,000

Find contractors for work like this