Otis Elevator Co
- Based in
- San Francisco
- On San Francisco permits
- Jun 2007 to Dec 2012
- Last 24 months
- 0 permits filed
14 permits since 2000: 8 completed, 5 never finaled, 1 expired or cancelled.
Of the 5 never-finaled permits, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 12, 2012 | Completed final sign-off Mar 2014 | 22 04th St | lobby, installation of destination based controls & fixts for the 4 elevators of the main passenger grap. this installation of fixts to be compliant to ab-090 in (e) lobbies. f/a recall under separate permit.Details
lobby, installation of destination based controls & fixts for the 4 elevators of the main passenger grap. this installation of fixts to be compliant to ab-090 in (e) lobbies. f/a recall under separate permit. | $143,872 |
| May 15, 2012 | Completed final sign-off Oct 2012 | 475 Sansome St | to obtain final inspection for work approved under pa #2007.10.25.6493. all work is complete.Details
to obtain final inspection for work approved under pa #2007.10.25.6493. all work is complete. | |
| May 14, 2012 | Never finaled issued Aug 2012, no final | 1275 Market St | elevator modernization with destination base controlers on the low rise and high rise (7) cabs consistent with ab-90. barrier removal only and fire inspection under a seperate permit. work done in (e) elevator shaft on all floorsDetails
elevator modernization with destination base controlers on the low rise and high rise (7) cabs consistent with ab-90. barrier removal only and fire inspection under a seperate permit. work done in (e) elevator shaft on all floors | $118,470 |
| Mar 8, 2012 | Completed final sign-off May 2012 | 407 Sansome St | minor renovation to elevator interior car for "barrier removal" scope of work includes replacing existing with new: car operating panel, car position indicator, handrail, hall lantern, call button and car fan. change of elevator door at basement landing. ada upgrades to elevator controlsDetails
minor renovation to elevator interior car for "barrier removal" scope of work includes replacing existing with new: car operating panel, car position indicator, handrail, hall lantern, call button and car fan. change of elevator door at basement landing. ada upgrades to elevator controls | $40,000 |
| Nov 30, 2011 | Never finaled issued Dec 2011, no final | 50 Fremont St | elevator modernization with destination based controllers for low rise, mid rise, and high rise. this modernization will be consistant with ab-090. barrier removal only.Details
elevator modernization with destination based controllers for low rise, mid rise, and high rise. this modernization will be consistant with ab-090. barrier removal only. | $339,118 |
| Feb 18, 2010 | Completed final sign-off May 2012 | 525 Market St | install only new destination based elevator controls on all floors. new technology that will provide equivalent facilitation for path of travel not correctly defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing.Details
install only new destination based elevator controls on all floors. new technology that will provide equivalent facilitation for path of travel not correctly defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing. | $302,035 |
| Dec 3, 2009 | Never finaled issued Feb 2012, no final | 335 Powell St | st francis hotel. install (n) elev. controls on all flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing for 15 elevators.Details
st francis hotel. install (n) elev. controls on all flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing for 15 elevators. | $317,855 |
| Mar 4, 2009 | Completed final sign-off Aug 2012 | 100 Pine St | install new elevator on all floors. new technology will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing.Details
install new elevator on all floors. new technology will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing. | $163,179 |
| Mar 4, 2009 | Never finaled issued Feb 2011, no final | 206 Sansome St | install new elevator controls on all floor. new technology that will provide equivalent facilitaton for path of travel not currently defined by ca title 24. provide new hall stations and announcement in place of traditional call fixtures in lobbies and each landingDetails
install new elevator controls on all floor. new technology that will provide equivalent facilitaton for path of travel not currently defined by ca title 24. provide new hall stations and announcement in place of traditional call fixtures in lobbies and each landing | $31,136 |
| Jan 14, 2009 | Completed final sign-off Jan 2013 | 50 Beale St | install (n) elevator controls on all flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide (n) hall stations & announcements in place of traditional call fixtures in lobbies & ea. landing.Details
install (n) elevator controls on all flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide (n) hall stations & announcements in place of traditional call fixtures in lobbies & ea. landing. | $162,514 |
| Jan 14, 2009 | Completed final sign-off Dec 2012 | 1 Front St | install (n) elevator controls on the flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide (n) hall stations & annoucements in place of traditional call fixture in lobbies & ea. landing.Details
install (n) elevator controls on the flrs. (n) technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide (n) hall stations & annoucements in place of traditional call fixture in lobbies & ea. landing. | $185,730 |
| Nov 21, 2008 | Never finaled issued Apr 2011, no final | 45 Fremont St | install new elevator controls on all floors. new technology that will provede equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcments in place of tradtional call fixtures in lobbies and each landing.Details
install new elevator controls on all floors. new technology that will provede equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcments in place of tradtional call fixtures in lobbies and each landing. | $173,607 |
| Oct 25, 2007 | Expired or cancelled expired Aug 2012 | 475 Sansome St | install new elevator control on all floors. new technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing.Details
install new elevator control on all floors. new technology that will provide equivalent facilitation for path of travel not currently defined by ca title 24. provide new hall stations and announcements in place of traditional call fixtures in lobbies and each landing. | $116,838 |
| Jun 26, 2007 | Completed final sign-off Apr 2008 | 111 Pine St | destination based elevator controls for cars #1 through #5.Details
destination based elevator controls for cars #1 through #5. | $62,000 |