Block 3706, lot 062
731 Market St
- City’s use
- Commercial Office
- Built
- 1908
- Stories
- 6
- Rooms
- 10 bathrooms
- Building
- 92,951 sq ft
- Lot
- 14,496 sq ft
- Zoning
- C3R
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
124 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 17, 2026 | In progress filed Aug 2026, not yet issued | 731 Market St | Skyline Construction | ste 200, tenant improvement to include selective demolition on non-structural partitions, ceilings, lighting and finishes. construction of non-structural partitions, ceiling, lighting, millwork finishes and mepDetails
ste 200, tenant improvement to include selective demolition on non-structural partitions, ceilings, lighting and finishes. construction of non-structural partitions, ceiling, lighting, millwork finishes and mep | $1,225,000 |
| Dec 16, 2020 | Completed final sign-off Feb 2021 | 731 Market St | Bilcor Inc | bsmnt & 1st fl. fire life safety: install (2) wall mount horn-strobes, (1) smoke detector w/base, (2) control relays. passenger elevator modernization.Details
bsmnt & 1st fl. fire life safety: install (2) wall mount horn-strobes, (1) smoke detector w/base, (2) control relays. passenger elevator modernization. | $3,300 |
| Nov 12, 2020 | Completed final sign-off Jun 2021 | 731 Market St | R L H Fire Protection Inc | fire sprinkler: voluntary elevator modernization. remove fire sprinklers, pipe, fitting, and hangers from elevator shaft and machine rooms per sffd approved letter dated 09.21.2020Details
fire sprinkler: voluntary elevator modernization. remove fire sprinklers, pipe, fitting, and hangers from elevator shaft and machine rooms per sffd approved letter dated 09.21.2020 | $2,500 |
| Sep 30, 2020 | Expired or cancelled withdrawn Dec 2020 | 731 Market St | exterior facade maintenance & repair at rear (stevenson st):removal of (e) non-original painted cement plaster.brick masonry repair/restoration.sheet metal repir & restoration.flashing & waterproofing.new sealants at windows.new paint & breathable coatings.Details
exterior facade maintenance & repair at rear (stevenson st):removal of (e) non-original painted cement plaster.brick masonry repair/restoration.sheet metal repir & restoration.flashing & waterproofing.new sealants at windows.new paint & breathable coatings. | $500,000 | |
| Oct 10, 2019 | Never finaled issued Oct 2019, no final | 731 Market St | street spaceDetails
street space | ||
| Aug 28, 2019 | Never finaled issued Aug 2019, no final | 731 Market St | C B F Inc | suite 200: lighting control system - title 24. retrofit 14 down lights, demo 30 light fixtures, install 23 new light fixtures. electrical work only.Details
suite 200: lighting control system - title 24. retrofit 14 down lights, demo 30 light fixtures, install 23 new light fixtures. electrical work only. | $80,000 |
| May 22, 2019 | Never finaled issued May 2019, no final | 731 Market St | Bilcor Inc | 5th & 6th fl fire alarm ti: install 2 control relays, install 2 smoke detectors.Details
5th & 6th fl fire alarm ti: install 2 control relays, install 2 smoke detectors. | $2,640 |
| Apr 18, 2019 | Expired or cancelled cancelled Jan 2026 | 731 Market St | installation of card readers at it room, elevator lobby and freight elevator at 5th and 6th fl onlyDetails
installation of card readers at it room, elevator lobby and freight elevator at 5th and 6th fl only | $8,000 | |
| Apr 18, 2019 | Expired or cancelled cancelled Jan 2026 | 731 Market St | installation of card readers at it room, elevator lobby and freight elevator at 6th fl onlyDetails
installation of card readers at it room, elevator lobby and freight elevator at 6th fl only | $8,000 | |
| Jan 29, 2019 | Completed final sign-off Feb 2019 | 731 Market St | Bilcor Inc | fire alarm voluntary tenant improvement install 2 pull stationsDetails
fire alarm voluntary tenant improvement install 2 pull stations | $800 |
| Nov 21, 2018 | Never finaled issued Nov 2018, no final | 731 Market St | street spaceDetails
street space | ||
| Oct 23, 2018 | Never finaled issued Oct 2018, no final | 731 Market St | Bilcor Inc | fire alarm ti install 1 control relay. 3rd & 4th fl.Details
fire alarm ti install 1 control relay. 3rd & 4th fl. | $600 |
| Aug 14, 2018 | Never finaled issued Aug 2018, no final | 731 Market St | street spaceDetails
street space | ||
| May 23, 2017 | Completed final sign-off Nov 2017 | 731 Market St | Legacy Mechanical & Energy Services, Inc | roof top- like for like replacement of (1) 60 tons capacity air cooled chiller & expansion tank.Details
roof top- like for like replacement of (1) 60 tons capacity air cooled chiller & expansion tank. | $90,000 |
| May 3, 2017 | Completed final sign-off May 2017 | 731 Market St | Bilcor Inc | install (1) smoke detector with base as built to pa 2016-0526-8520Details
install (1) smoke detector with base as built to pa 2016-0526-8520 | $500 |
| Jul 22, 2016 | Completed final sign-off Aug 2016 | 731 Market St | Bilcor Inc | basement: fire alarm ti - install 1 wall mount horn-strobeDetails
basement: fire alarm ti - install 1 wall mount horn-strobe | $400 |
| Jul 21, 2016 | Never finaled issued Jul 2016, no final | 731 Market St | Golden Gate Fire Protection Inc | fire sprinklers: add 1 pendent sprinkler head in new bathroom at basement level. ti ref pa 2016-0525-8325Details
fire sprinklers: add 1 pendent sprinkler head in new bathroom at basement level. ti ref pa 2016-0525-8325 | $1,000 |
| Jun 3, 2016 | Completed final sign-off Dec 2016 | 731 Market St | Gidel & Kocal Construction Co Inc | gr flr - new pharmacy counter upgrades, new drinking fountain, relocate bath fixtures, barrier removalDetails
gr flr - new pharmacy counter upgrades, new drinking fountain, relocate bath fixtures, barrier removal | $40,000 |
| May 26, 2016 | Completed final sign-off Jun 2017 | 731 Market St | Bilcor Inc | grnd flr: fire alarm tenant improvement, install (1) control relay module.Details
grnd flr: fire alarm tenant improvement, install (1) control relay module. | $400 |
| May 25, 2016 | Completed final sign-off Sep 2016 | 731 Market St | Dome Construction Corp | modification of existing trashroom to inlcude selective demo and construction of non load bearing partitions, new ceiling, new light fixtures and accessible restroom. all work is within the (e) trashroom. no change of use under this permit. no work visible from street.Details
modification of existing trashroom to inlcude selective demo and construction of non load bearing partitions, new ceiling, new light fixtures and accessible restroom. all work is within the (e) trashroom. no change of use under this permit. no work visible from street. | $40,000 |
| May 24, 2016 | Completed final sign-off Jun 2016 | 731 Market St | 4th floor - 3 evacuation signs per plansDetails
4th floor - 3 evacuation signs per plans | $1,350 | |
| Apr 15, 2016 | Completed final sign-off Jun 2016 | 731 Market St | Bilcor Inc | 4th floor: fire alarm t.i. to install 1 booster panel, install 1 signal module, install 2 pull stations, install 1 ceiling mount strobe, install 2 hall mount strobes, install 12 ceiling mount horn-strobes, install 2 wall mount horn-strobes, install 3 smoke det. with bases, install 8 duct detec.Details
4th floor: fire alarm t.i. to install 1 booster panel, install 1 signal module, install 2 pull stations, install 1 ceiling mount strobe, install 2 hall mount strobes, install 12 ceiling mount horn-strobes, install 2 wall mount horn-strobes, install 3 smoke det. with bases, install 8 duct detec. | $13,200 |
| Mar 24, 2016 | Completed final sign-off Jun 2016 | 731 Market St | City Mechanical Inc | 4th floor hvac, ti: provide & install nine fan coils, condensate piping, supply & return air duct work, two new transfer exahust systems, one outside air fan system. ref pa 2016-0217-9764Details
4th floor hvac, ti: provide & install nine fan coils, condensate piping, supply & return air duct work, two new transfer exahust systems, one outside air fan system. ref pa 2016-0217-9764 | $230,000 |
| Mar 16, 2016 | Completed final sign-off May 2016 | 731 Market St | Golden Gate Fire Protection Inc | fire sprinklers; relocated 95 upright sprinklers on the 4th floor. relocate 19 pendent sprinklers, ti 206-0217-9764Details
fire sprinklers; relocated 95 upright sprinklers on the 4th floor. relocate 19 pendent sprinklers, ti 206-0217-9764 | $58,710 |
| Mar 15, 2016 | Completed final sign-off Jun 2016 | 731 Market St | Mc Millan Electric | work is based off of the electrically engineered drawings ref pa 2016-0217-9764. partial scope office tenant retrofit lighting, power and signal, wiring, lighting & receptacle controls.Details
work is based off of the electrically engineered drawings ref pa 2016-0217-9764. partial scope office tenant retrofit lighting, power and signal, wiring, lighting & receptacle controls. | $195,000 |
| Feb 17, 2016 | Completed final sign-off Jun 2016 | 731 Market St | Dome Construction Corp | ste 400: selective demolition of partitions, new ceiling, light fixtures, doors and frames, millworks, sinks, finishes and accessible restrooms. mep/life safety deferred.Details
ste 400: selective demolition of partitions, new ceiling, light fixtures, doors and frames, millworks, sinks, finishes and accessible restrooms. mep/life safety deferred. | $544,000 |
| Jun 15, 2015 | Never finaled issued Jun 2015, no final | 731 Market St | Jeffco Roofing Co | reroofingDetails
reroofing | $106,000 |
| Feb 26, 2015 | Completed final sign-off Mar 2015 | 731 Market St | Peacock Construction | revision appl. 2014.0716.1376 & 2014.0605.7611. add doucumention for ejector pump pit for record. maher n/a.Details
revision appl. 2014.0716.1376 & 2014.0605.7611. add doucumention for ejector pump pit for record. maher n/a. | |
| Feb 12, 2015 | Never finaled issued Feb 2015, no final | 731 Market St | street spaceDetails
street space | ||
| Dec 15, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Bilcor Inc | fire alarm tenant improvement, install 7 smoke detectors, install 2 control relay modules. t.i. pa#201405014666Details
fire alarm tenant improvement, install 7 smoke detectors, install 2 control relay modules. t.i. pa#201405014666 | $3,600 |
| Nov 4, 2014 | Never finaled issued Nov 2014, no final | 731 Market St | Bilcor Inc | 5th floor: install 1 booster panel, install 17 ceiling mount horn-strobes, 2 smoke detectors with base, 2 pull stations, 2 control relay modules and 1 signal module. ref. appl. 2014.0627.9804. maher n/a.Details
5th floor: install 1 booster panel, install 17 ceiling mount horn-strobes, 2 smoke detectors with base, 2 pull stations, 2 control relay modules and 1 signal module. ref. appl. 2014.0627.9804. maher n/a. | $20,000 |
| Oct 29, 2014 | Completed final sign-off Nov 2014 | 731 Market St | Golden Gate Fire Protection Inc | 5th flr: relocate 27 pendant sprinklers on the 5th flr, relocate 66 upright heads, t.i. #201406279804; maher n/aDetails
5th flr: relocate 27 pendant sprinklers on the 5th flr, relocate 66 upright heads, t.i. #201406279804; maher n/a | $47,895 |
| Oct 14, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Bilcor Inc | as built revision to 201409237080. 1 duct detector relocated, 1 duct detector deleted, fire alarm ti for basementDetails
as built revision to 201409237080. 1 duct detector relocated, 1 duct detector deleted, fire alarm ti for basement | |
| Oct 8, 2014 | Expired or cancelled cancelled Jan 2026 | 731 Market St | as built revision to pa 201409237080. fire alarm work: 2 fsd and 1 control relay modul were not installed.Details
as built revision to pa 201409237080. fire alarm work: 2 fsd and 1 control relay modul were not installed. | ||
| Sep 26, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Peacock Construction | modification ot existing building lobby to include construction of non structural partition, modification to ceiling, moulding, light fixture.(sprinklers under separate permit)Details
modification ot existing building lobby to include construction of non structural partition, modification to ceiling, moulding, light fixture.(sprinklers under separate permit) | $27,000 |
| Sep 25, 2014 | Expired or cancelled cancelled Mar 2017 | 250 Stevenson St | Gigabyte Graphics Inc. Dba Fastsigns | erect a non electric single faced sign (sign "a"0Details
erect a non electric single faced sign (sign "a"0 | $1,000 |
| Sep 25, 2014 | Never finaled issued Oct 2016, no final | 250 Stevenson St | Gigabyte Graphics Inc. Dba Fastsigns | erect a non electric single faced sign (side of the bldg) sign "b"Details
erect a non electric single faced sign (side of the bldg) sign "b" | $5,000 |
| Sep 23, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Bilcor Inc | install 18 wall mount horn strobes, install 3 wall mount strobes, install 1 wall mount horn, install 1 signal module, install 9 control relay modules, install 4 pull stations, install 9 duct detectors with housing, install 8 smoke detectors with base, install 1 booster panel.Details
install 18 wall mount horn strobes, install 3 wall mount strobes, install 1 wall mount horn, install 1 signal module, install 9 control relay modules, install 4 pull stations, install 9 duct detectors with housing, install 8 smoke detectors with base, install 1 booster panel. | $21,600 |
| Sep 11, 2014 | Completed final sign-off Dec 2014 | 731 Market St | Matrix Hg Inc | revision to previously submitted mechanical dwgs, orig permit no. 201406279804.Details
revision to previously submitted mechanical dwgs, orig permit no. 201406279804. | $65,000 |
| Sep 9, 2014 | Completed final sign-off Sep 2014 | 731 Market St | Golden Gate Fire Protection Inc | relocate 31 pendent sprinklers on the basement level. relocate 7 uppright sprinklers, upgrade end of bracing. ref ti #2014-0605-7611Details
relocate 31 pendent sprinklers on the basement level. relocate 7 uppright sprinklers, upgrade end of bracing. ref ti #2014-0605-7611 | $19,570 |
| Sep 3, 2014 | Completed final sign-off Aug 2015 | 731 Market St | Peacock Construction | structural improvement limited to infill of existing clearstory openings into basement at 731 marketDetails
structural improvement limited to infill of existing clearstory openings into basement at 731 market | $38,000 |
| Aug 21, 2014 | Never finaled issued Aug 2014, no final | 731 Market St | street space permitDetails
street space permit | ||
| Jul 24, 2014 | Never finaled issued Jul 2014, no final | 250 Stevenson St | per pa #201406057611, to create address for office in church as; 250 stevenson st at block 3706, lot 062.Details
per pa #201406057611, to create address for office in church as; 250 stevenson st at block 3706, lot 062. | ||
| Jul 16, 2014 | Completed final sign-off Mar 2015 | 731 Market St | Peacock Construction | revision to appl #2014.0605.7611 - five columns to be removed at basement level of structure. the steel beams that frame into the (e) columns will be re-supported by new beams, span between new columns. new foundation work is required to accomodate new load.Details
revision to appl #2014.0605.7611 - five columns to be removed at basement level of structure. the steel beams that frame into the (e) columns will be re-supported by new beams, span between new columns. new foundation work is required to accomodate new load. | $193,000 |
| Jul 8, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Bilcor Inc | install 2 ceiling mount horn-strobe. relocate 1 ceiling mount horn-strobe. remove 1 ceiling mount horn-strobe. ref. t.i. appl. 201405216392. maher n/a.Details
install 2 ceiling mount horn-strobe. relocate 1 ceiling mount horn-strobe. remove 1 ceiling mount horn-strobe. ref. t.i. appl. 201405216392. maher n/a. | $1,600 |
| Jul 2, 2014 | Never finaled issued Jul 2014, no final | 731 Market St | street spaceDetails
street space | ||
| Jun 27, 2014 | Completed final sign-off Aug 2015 | 731 Market St | Peacock Construction | 5/f: modification and expansion of existing space, improvements to include selective demo, and construction of non-structual partitions, new ceiling grid and tiel, light fixtures, office doors and frames, millwork sinks and finishes inlcuding t-24, mech, elec.Details
5/f: modification and expansion of existing space, improvements to include selective demo, and construction of non-structual partitions, new ceiling grid and tiel, light fixtures, office doors and frames, millwork sinks and finishes inlcuding t-24, mech, elec. | $1,250,000 |
| Jun 26, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Peacock Construction Inc | m.e.p. for pa#201406057611Details
m.e.p. for pa#201406057611 | $225,000 |
| Jun 6, 2014 | Completed final sign-off Jul 2014 | 731 Market St | Aquamatic Fire Protection | 3rd floor suite 300 sprinkler renovations , 8 new heads, 5 relocates. ref #201405216392.Details
3rd floor suite 300 sprinkler renovations , 8 new heads, 5 relocates. ref #201405216392. | $3,400 |
| Jun 5, 2014 | Completed final sign-off Mar 2015 | 731 Market St | Peacock Construction Inc | change of use to church from office. construct new non-structural partitions, ceiling grid and tile, new lighting fixtures, new doors and frames, millwork, sinks and finishes, add hvac unit on roof. mep, sprinkler and fire alram under separate permit. maher n/a.Details
change of use to church from office. construct new non-structural partitions, ceiling grid and tile, new lighting fixtures, new doors and frames, millwork, sinks and finishes, add hvac unit on roof. mep, sprinkler and fire alram under separate permit. maher n/a. | $700,000 |
| May 23, 2014 | Completed final sign-off Jun 2014 | 731 Market St | Golden Gate Fire Protection Inc | 1st through 6th flrs: add 4 upright sprinkler and delete 1 on basement level. add one sidewall sprinkler on the 1st flr. add 1 upright sprinkler on the 2nd flr & delete one sprinkler. relocate 1 upright sprinkler on the 3rd flr. add 1 updright sprnkl ont he 4th flr & lower 4 spr. add 1 on 6th flDetails
1st through 6th flrs: add 4 upright sprinkler and delete 1 on basement level. add one sidewall sprinkler on the 1st flr. add 1 upright sprinkler on the 2nd flr & delete one sprinkler. relocate 1 upright sprinkler on the 3rd flr. add 1 updright sprnkl ont he 4th flr & lower 4 spr. add 1 on 6th fl | $5,150 |
| May 21, 2014 | Completed final sign-off Aug 2015 | 731 Market St | Peacock Construction Inc | selective demo and construction of non structural partitons, modify existing ceiling gid. new doors and frames, millwork, rework lighting. sprinkler, life safety, mep under sep permitDetails
selective demo and construction of non structural partitons, modify existing ceiling gid. new doors and frames, millwork, rework lighting. sprinkler, life safety, mep under sep permit | $81,000 |
| May 1, 2014 | Completed final sign-off Jan 2015 | 731 Market St | Peacock Construction Inc | basement:this work is limitted to cold shell modifications including the construction of a trash room, janitor's room, engineering office, and the addition of an elevator vestibule and connecting corridors. t.i. under seperate permit. ab-017; ada deferred to future t.i.Details
basement:this work is limitted to cold shell modifications including the construction of a trash room, janitor's room, engineering office, and the addition of an elevator vestibule and connecting corridors. t.i. under seperate permit. ab-017; ada deferred to future t.i. | $75,000 |
| Jan 24, 2014 | Completed final sign-off Feb 2014 | 731 Market St | Golden Gate Fire Protection Inc | basement:add 5 upright sprinkler and 3 pendents at new stairs in the basement. ref app#201307222423Details
basement:add 5 upright sprinkler and 3 pendents at new stairs in the basement. ref app#201307222423 | $4,120 |
| Dec 19, 2013 | Completed final sign-off May 2014 | 731 Market St | Bilcor Inc | install 1 ceiling horn-strobes, install 1 smoke detector with base, install 11 dual monitor modules and install 1 control relay module.Details
install 1 ceiling horn-strobes, install 1 smoke detector with base, install 11 dual monitor modules and install 1 control relay module. | $5,600 |
| Dec 17, 2013 | Completed final sign-off Jul 2014 | 731 Market St | Peacock Construction Inc | this work is limited to the addition of one maintenance room including new partitions, doors, and lighting.this work introduces new bldg service space part of the cold shell build out of the basement level.electrical work is defffered submittal.Details
this work is limited to the addition of one maintenance room including new partitions, doors, and lighting.this work introduces new bldg service space part of the cold shell build out of the basement level.electrical work is defffered submittal. | $15,000 |
| Dec 13, 2013 | Completed final sign-off Apr 2014 | 731 Market St | Peacock Construction Inc | revision to appl #2013.1105.1118 - rating of (e) elevation machine room & structure.Details
revision to appl #2013.1105.1118 - rating of (e) elevation machine room & structure. | $2,000 |
| Nov 15, 2013 | Never finaled issued Nov 2013, no final | 731 Market St | Golden Gate Fire Protection Inc | add new sprinkler system on the 4th floor, add 98 pendent sprinkler heads, new end of line bracing. ref. pa#201309277896.Details
add new sprinkler system on the 4th floor, add 98 pendent sprinkler heads, new end of line bracing. ref. pa#201309277896. | $50,470 |
| Nov 5, 2013 | Never finaled issued Nov 2013, no final | 731 Market St | Golden Gate Fire Protection Inc | add new sprinkler system on 5th floor, add 98 pendent sprinkler heads, ref to pa#201309277896 (6th floor) . new end of line bracing and earthquake bracing.Details
add new sprinkler system on 5th floor, add 98 pendent sprinkler heads, ref to pa#201309277896 (6th floor) . new end of line bracing and earthquake bracing. | $50,372 |
| Nov 5, 2013 | Completed final sign-off Jan 2015 | 731 Market St | Peacock Construction Inc | revision 1: modification to structural framing per as-built conditions; set-back of ground level storefront, revisiotn to 201307222423Details
revision 1: modification to structural framing per as-built conditions; set-back of ground level storefront, revisiotn to 201307222423 | $2,500 |
| Sep 27, 2013 | Completed final sign-off May 2014 | 731 Market St | Golden Gate Fire Protection Inc | 6th floor-add new sprinkler system on 6th floor. add 144 upright sprinklers & add 22 pendent sprinklers. new end of line & e.q bracing. install new fire pump in the basement. hydraulic calculation included.Details
6th floor-add new sprinkler system on 6th floor. add 144 upright sprinklers & add 22 pendent sprinklers. new end of line & e.q bracing. install new fire pump in the basement. hydraulic calculation included. | $90,640 |
| Aug 20, 2013 | Never finaled issued Aug 2013, no final | 731 Market St | street space permitDetails
street space permit | ||
| Jul 22, 2013 | Completed final sign-off May 2014 | 731 Market St | Peacock Construction Inc | new 1-hr fire rated enclosure at future pump room (part of sprinkler retrofit), includes new 60 min. entry door in basement level. core and shell work. t.i. work under separate permit.Details
new 1-hr fire rated enclosure at future pump room (part of sprinkler retrofit), includes new 60 min. entry door in basement level. core and shell work. t.i. work under separate permit. | $3,500 |
| Jul 22, 2013 | Completed final sign-off Jan 2015 | 731 Market St | Peacock Construction Inc | new stevenson street entry with new lobby and canopy; storefront, interior entry stair into basement, and enclosure of 1 existing exit stair. core and shell per ab-017. ti under separate permit.Details
new stevenson street entry with new lobby and canopy; storefront, interior entry stair into basement, and enclosure of 1 existing exit stair. core and shell per ab-017. ti under separate permit. | $324,425 |
| May 20, 2013 | Completed final sign-off May 2014 | 731 Market St | Golden Gate Fire Protection Inc | 2nd floor - add new sprinkler system - add 71 new uprights & add 17 pendent sprinklers, new end of line & earthquake bracing. ref pa #2013.02.15.0305Details
2nd floor - add new sprinkler system - add 71 new uprights & add 17 pendent sprinklers, new end of line & earthquake bracing. ref pa #2013.02.15.0305 | $45,320 |
| May 9, 2013 | Never finaled issued May 2013, no final | 731 Market St | Matrix Hg Inc | 2nd floor-installation of 8 air handling units with heating & chilled meter coils, hot & chilled water piping. installation of duct work, installation of fresh air fanDetails
2nd floor-installation of 8 air handling units with heating & chilled meter coils, hot & chilled water piping. installation of duct work, installation of fresh air fan | $180,000 |
| Apr 25, 2013 | Completed final sign-off Jun 2013 | 731 Market St | Bilcor Inc | 2nd floor-install 9 ceiling horn strobes, 1 ceiling strobe, 5 wall horn strobes, 3 wall strobes, 2 smoke detectors with base, 3 pull stations, 8 control relay modules, 1 booster panel & 1 signal moduleDetails
2nd floor-install 9 ceiling horn strobes, 1 ceiling strobe, 5 wall horn strobes, 3 wall strobes, 2 smoke detectors with base, 3 pull stations, 8 control relay modules, 1 booster panel & 1 signal module | $13,200 |
| Apr 19, 2013 | Never finaled issued Apr 2013, no final | 731 Market St | 2nd floor-install 3 evacuation signsDetails
2nd floor-install 3 evacuation signs | $1,050 | |
| Mar 22, 2013 | Completed final sign-off Apr 2013 | 731 Market St | Peacock Construction Inc | mechanical only - new distribution of air per new layout. other work done under pa #201209270827.Details
mechanical only - new distribution of air per new layout. other work done under pa #201209270827. | $45,000 |
| Feb 15, 2013 | Completed final sign-off Jul 2013 | 731 Market St | Peacock Construction Inc | 2nd floor:demo of non structural partition, new non structural partitions, suspended, ceilings, new light fixtures, doors and frames, millwork and finishes. barrier removal in restrooms. mep, sprinkler and fire alarm under seperate permit.Details
2nd floor:demo of non structural partition, new non structural partitions, suspended, ceilings, new light fixtures, doors and frames, millwork and finishes. barrier removal in restrooms. mep, sprinkler and fire alarm under seperate permit. | $638,000 |
| Feb 8, 2013 | Completed final sign-off Mar 2013 | 731 Market St | evacuation map 6th flDetails
evacuation map 6th fl | $1,200 | |
| Jan 18, 2013 | Completed final sign-off Jan 2013 | 731 Market St | C B F Inc | ti pa#2012-09-27-0827 install 14 ceiling horn-strobes, 1 wall horn-strobe, 2 wll strobes, 3 smoke detector w/ base, 2 pull stations, 2 control relay modules, 1 booster panel, 1 signal module, connect new notification devices to new booster panel, connect addressable smoke, pull stations&modules f/aDetails
ti pa#2012-09-27-0827 install 14 ceiling horn-strobes, 1 wall horn-strobe, 2 wll strobes, 3 smoke detector w/ base, 2 pull stations, 2 control relay modules, 1 booster panel, 1 signal module, connect new notification devices to new booster panel, connect addressable smoke, pull stations&modules f/a | $11,200 |
| Sep 27, 2012 | Completed final sign-off Apr 2013 | 731 Market St | Peacock Construction Inc | 6th floor-demolition & construction of non structural partitions, new suspended ceilings, new light fixtures, doors, frames, millwork & finishes. barrier removal in restrooms. sprinklers, life safety, electrical & mechanical under seperate permitsDetails
6th floor-demolition & construction of non structural partitions, new suspended ceilings, new light fixtures, doors, frames, millwork & finishes. barrier removal in restrooms. sprinklers, life safety, electrical & mechanical under seperate permits | $350,000 |
| Mar 9, 2012 | Completed final sign-off Mar 2012 | 731 Market St | Red Hawk Fire & Security Ca Llc | 3rd floor - add strobes, add horn/strobes.Details
3rd floor - add strobes, add horn/strobes. | $5,000 |
| Feb 2, 2012 | Completed final sign-off Mar 2012 | 731 Market St | Dome Construction Corp | 3rd floor: demolition of extg const. within a 13,633 sq ft suite, in extg 6 story bldg. tenant imp. to be completed under seprate permit. extg interior partitions and partial extg suspended ceiling and tiles to be demolished.Details
3rd floor: demolition of extg const. within a 13,633 sq ft suite, in extg 6 story bldg. tenant imp. to be completed under seprate permit. extg interior partitions and partial extg suspended ceiling and tiles to be demolished. | $6,000 |
| Feb 1, 2012 | Completed final sign-off Mar 2012 | 731 Market St | Golden Gate Fire Protection Inc | fire sprinkler system upgrade. relocate 11 pendant sprinkler heads on the 3rd floor.Details
fire sprinkler system upgrade. relocate 11 pendant sprinkler heads on the 3rd floor. | $5,665 |
| Jan 20, 2012 | Never finaled issued Jan 2012, no final | 731 Market St | Red Hawk Fire & Security Ca Llc | renew for final 200810144111. all work is completeDetails
renew for final 200810144111. all work is complete | |
| Jan 19, 2012 | Completed final sign-off Mar 2012 | 731 Market St | Dome Construction Corp | 3rd floor tenant improvement to modify offices, conference room, storage on 3rd floor - new partition wall will be constructed.Details
3rd floor tenant improvement to modify offices, conference room, storage on 3rd floor - new partition wall will be constructed. | $352,100 |
| May 26, 2011 | Completed final sign-off Aug 2011 | 731 Market St | Peacock Construction Inc | 4th floor-build wall & door, new carpet & paint. mep including lighting under separate permit.Details
4th floor-build wall & door, new carpet & paint. mep including lighting under separate permit. | $95,500 |
| May 18, 2011 | Completed final sign-off Nov 2011 | 731 Market St | Peacock Construction Inc | 4th floor- demo walls, ceiling & lighting in 2 suites, per ab-017Details
4th floor- demo walls, ceiling & lighting in 2 suites, per ab-017 | $9,850 |
| Nov 12, 2010 | Completed final sign-off Feb 2011 | 731 Market St | R 3 Builders Inc. | to erect electric, projecting, double faced sign. install one 24"x24" projecting sign on front facade.Details
to erect electric, projecting, double faced sign. install one 24"x24" projecting sign on front facade. | $1,500 |
| Oct 14, 2010 | Expired or cancelled withdrawn Apr 2011 | 731 Market St | R 3 Builders Inc. | to erect electric, wall, single faced sign. revision to pa# 2010/08/10/8507.Details
to erect electric, wall, single faced sign. revision to pa# 2010/08/10/8507. | $2,500 |
| Oct 1, 2010 | Completed final sign-off Nov 2010 | 731 Market St | Anderson, Rowe & Buckley, Inc. | tenant improvements: existing fire sprinkler system; remove -5; add-98; relocate-24; 1st flrDetails
tenant improvements: existing fire sprinkler system; remove -5; add-98; relocate-24; 1st flr | $24,400 |
| Sep 24, 2010 | Completed final sign-off Apr 2011 | 731 Market St | Bcci Construction Company | install cooling tower on roof to replace extg.Details
install cooling tower on roof to replace extg. | $138,000 |
| Aug 23, 2010 | Completed final sign-off Jan 2011 | 731 Market St | Red Hawk Fire & Security Ca Llc | 1st fl -horn/strobes & strobes added to retail area, pharmacy and other areas. smoke detector provided in receiving area for stroke power supply. duct detectors and relay modules added to havac units for shutdown monitor module added for water flow and tamer, manual pulls at exits, 6 ducts, 2 pulls,Details
1st fl -horn/strobes & strobes added to retail area, pharmacy and other areas. smoke detector provided in receiving area for stroke power supply. duct detectors and relay modules added to havac units for shutdown monitor module added for water flow and tamer, manual pulls at exits, 6 ducts, 2 pulls, | $8,000 |
| Aug 10, 2010 | Expired or cancelled cancelled Jul 2016 | 731 Market St | install 1 projecting sign (24" x 22")Details
install 1 projecting sign (24" x 22") | $2,000 | |
| Aug 10, 2010 | Completed final sign-off Mar 2011 | 731 Market St | R 3 Builders Inc. | install 3 wall signs as follows: 2 at 18"x54" ( 7 sf ea) and 1 36" x 25'1" ( 75 ft)Details
install 3 wall signs as follows: 2 at 18"x54" ( 7 sf ea) and 1 36" x 25'1" ( 75 ft) | $4,500 |
| Aug 5, 2010 | Completed final sign-off Jan 2011 | 731 Market St | R 3 Builders Inc. | install new shelving in retail space approved under 201003259000Details
install new shelving in retail space approved under 201003259000 | $15,000 |
| Mar 25, 2010 | Completed final sign-off Jan 2011 | 731 Market St | R 3 Builders Inc. | interior ground floor t.i. to install new partitons, flooring & ceiling, new casework, equipment & finiahes. new lighting & mechanical. no change in occupancy, no exterior alteration. fire protection uhder seperate permit.Details
interior ground floor t.i. to install new partitons, flooring & ceiling, new casework, equipment & finiahes. new lighting & mechanical. no change in occupancy, no exterior alteration. fire protection uhder seperate permit. | $840,000 |
| Oct 14, 2008 | Never finaled issued Oct 2008, no final | 731 Market St | Red Hawk Fire & Security Ca Llc | elevator recall system for frieght elevator. add new smoke detectors to extg spnkler monitoring system- dedicated system. 9 smoke detectors, 2 relay modulesDetails
elevator recall system for frieght elevator. add new smoke detectors to extg spnkler monitoring system- dedicated system. 9 smoke detectors, 2 relay modules | $5,000 |
| Jun 26, 2008 | Completed final sign-off Sep 2008 | 731 Market St | Rudolph Commercial Interiors Inc, Rci | 6th floor: barrier removal, relocate plumbing fixtures. repair automatic door opener.Details
6th floor: barrier removal, relocate plumbing fixtures. repair automatic door opener. | $30,000 |
| Jun 26, 2008 | Completed final sign-off Sep 2008 | 731 Market St | Rudolph Commercial Interiors Inc, Rci | 5th floor: barrier removal - create new unisex restroom, add door frame + hardware & plumbing fixtures.Details
5th floor: barrier removal - create new unisex restroom, add door frame + hardware & plumbing fixtures. | $25,000 |
| Jun 26, 2008 | Completed final sign-off Sep 2008 | 731 Market St | Rudolph Commercial Interiors Inc, Rci | 4th floor: barrier removal, restrooms- new gyp board partition door, frame, hardware, relocate plumbing fixtures.Details
4th floor: barrier removal, restrooms- new gyp board partition door, frame, hardware, relocate plumbing fixtures. | $30,000 |
| Jun 26, 2008 | Completed final sign-off Oct 2008 | 731 Market St | Rudolph Commercial Interiors Inc, Rci | 2nd floor: tenant improvement, barrier removal - restrooms new gyp borad partition, door, frame, hardware. relocate (e) toilet accessories.Details
2nd floor: tenant improvement, barrier removal - restrooms new gyp borad partition, door, frame, hardware. relocate (e) toilet accessories. | $10,000 |
| Aug 9, 2007 | Completed final sign-off Aug 2007 | 731 Market St | Red Hawk Fire & Security Ca Llc | resubmit as built for appl#200706154031Details
resubmit as built for appl#200706154031 | |
| Jul 6, 2007 | Completed final sign-off Aug 2007 | 731 Market St | R L H Fire Protection Inc | 3rd floor-t.i. upgrade of sprinkler system; relocate 32 pendend sprinkler heads. relocate upright coverage 42 relocates in all.Details
3rd floor-t.i. upgrade of sprinkler system; relocate 32 pendend sprinkler heads. relocate upright coverage 42 relocates in all. | $6,000 |
| Jun 15, 2007 | Completed final sign-off Aug 2007 | 731 Market St | Red Hawk Fire & Security Ca Llc | fire sprinkler control monitoring system, basement, 1,2,3rd flfoorsDetails
fire sprinkler control monitoring system, basement, 1,2,3rd flfoors | $2,500 |
| Jun 4, 2007 | Completed final sign-off Aug 2007 | 731 Market St | 3rd floor-demo with interior build deck. new walls, partitions, doors-3rd floor. electrical, hvac & life safety, sprinkler to be on seperate permitDetails
3rd floor-demo with interior build deck. new walls, partitions, doors-3rd floor. electrical, hvac & life safety, sprinkler to be on seperate permit | $300,000 | |
| Apr 6, 2007 | Completed final sign-off Aug 2007 | 731 Market St | R L H Fire Protection Inc | install new fire sprinkler system on 3rd floor of building. 181added heads.Details
install new fire sprinkler system on 3rd floor of building. 181added heads. | $22,000 |
| Jan 24, 2007 | Completed final sign-off Aug 2007 | 731 Market St | 3rd floor - demo (soft interior) doors & wall, install (n) 1 hour rated full height walls, (n) m & w restrooms.Details
3rd floor - demo (soft interior) doors & wall, install (n) 1 hour rated full height walls, (n) m & w restrooms. | $190,000 | |
| Aug 14, 2006 | Never finaled issued Aug 2006, no final | 731 Market St | street space permitDetails
street space permit | ||
| Feb 10, 2006 | Completed final sign-off Apr 2006 | 731 Market St | Weather Masters Inc. | oti-2 2/f me modify (e) duct system for new office configuration.no mechanical equipment to be installed, zone controls per mechanical plans.Details
oti-2 2/f me modify (e) duct system for new office configuration.no mechanical equipment to be installed, zone controls per mechanical plans. | $37,000 |
| Oct 12, 2005 | Completed final sign-off May 2006 | 731 Market St | oti-1 2/f el, meDetails
oti-1 2/f el, me | $102,000 | |
| Mar 14, 2005 | Completed final sign-off Jun 2005 | 731 Market St | new flooring main lobby upgrades, new flooring & wall finishes, new accessible entry door and store-Details
new flooring main lobby upgrades, new flooring & wall finishes, new accessible entry door and store- | $70,000 | |
| Mar 7, 2005 | Expired or cancelled expired May 2006 | 731 Market St | remove existing rooftop air handling unit supports &replc w/ new steel platforms.repair exist chilleDetails
remove existing rooftop air handling unit supports &replc w/ new steel platforms.repair exist chille | $15,000 | |
| Mar 4, 2005 | Never finaled issued Mar 2005, no final | 731 Market St | street spaceDetails
street space | ||
| Nov 22, 2004 | Never finaled issued Nov 2004, no final | 731 Market St | street space permitDetails
street space permit | ||
| Jan 30, 2002 | Completed final sign-off Mar 2002 | 731 Market St | Mc Sal Commercial | oti-1,4th floor, el,meDetails
oti-1,4th floor, el,me | $15,000 |
| Oct 29, 2001 | Expired or cancelled expired Feb 2002 | 731 Market St | street spaceDetails
street space | ||
| Aug 20, 2001 | Expired or cancelled expired Jan 2002 | 731 Market St | Vahdani Construction Co Inc | revision to pa#99712284/Details
revision to pa#99712284/ | |
| May 22, 2001 | Completed final sign-off Jul 2001 | 731 Market St | repair brick, mortar joints & broken terra cotta on exterior of bldg. paint finish, repair in kindDetails
repair brick, mortar joints & broken terra cotta on exterior of bldg. paint finish, repair in kind | $95,000 | |
| Jan 23, 2001 | Expired or cancelled expired Mar 2004 | 731 Market St | Gci, Inc | new crosswalls for seismic upgrade/1 partition replacement/paint new carpet on 5th floor no mech ligDetails
new crosswalls for seismic upgrade/1 partition replacement/paint new carpet on 5th floor no mech lig | $30,000 |
| Nov 10, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | demolish storage rm walls in bsement install new door levers on all basement doors no structural worDetails
demolish storage rm walls in bsement install new door levers on all basement doors no structural wor | $8,000 | |
| Nov 10, 2000 | Completed final sign-off Jan 2001 | 731 Market St | Rossi Builders Inc. | oti-1 (4th floor)Details
oti-1 (4th floor) | $65,000 |
| Oct 13, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | revision to restroom partitionDetails
revision to restroom partition | ||
| Aug 30, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | Gci, Inc | ti build out of 5th flr space install new walls,new bar ceilingsDetails
ti build out of 5th flr space install new walls,new bar ceilings | $300,000 |
| Aug 23, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | Gci, Inc | structural revision to pa#200007114750 install walls per structal plans/detailsDetails
structural revision to pa#200007114750 install walls per structal plans/details | $5,000 |
| Aug 10, 2000 | Completed final sign-off Dec 2000 | 731 Market St | Gci, Inc | remove non-structural partitions @ 5th floorDetails
remove non-structural partitions @ 5th floor | $15,000 |
| Jul 26, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | Gci, Inc | oti-2 4/f lighting mechanicalDetails
oti-2 4/f lighting mechanical | $10,000 |
| Jul 26, 2000 | Completed final sign-off Dec 2000 | 731 Market St | Gci, Inc | oti-1 4/fDetails
oti-1 4/f | $20,000 |
| Jul 11, 2000 | Expired or cancelled expired Mar 2004 | 731 Market St | Gci, Inc | oti-1= el & me. 4th fl. onlyDetails
oti-1= el & me. 4th fl. only | $70,000 |
| Mar 29, 2000 | Expired or cancelled expired Jul 2000 | 731 Market St | Gci, Inc | renewal of pa 9815885Details
renewal of pa 9815885 | |
| Mar 16, 2000 | Completed final sign-off Jun 2000 | 731 Market St | oti 1 4th floor, el, meDetails
oti 1 4th floor, el, me | $65,000 | |
| Mar 16, 2000 | Expired or cancelled expired Sep 2000 | 731 Market St | new walls, relocate lights/fixtures,install elect outlet,1 supply grille,3return grille,minor ductDetails
new walls, relocate lights/fixtures,install elect outlet,1 supply grille,3return grille,minor duct | $15,000 |
Find contractors for work like this