- Dec 2003 to Oct 2020
18 permits since 2000 (engineer on 12 permits, architect on 5 permits, authorized agent-others on 1 permit): 12 completed, 3 never finaled, 3 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 16, 2020 | Completed final sign-off May 2023 | 145 Leavenworth St | Centric Construction Inc | mayor dir 17-02. revision to pa #201804136335s1, changes include: ground floor load map updated to arch plans, shift shear walls as needed. update elevator shaft dimensions.Details
mayor dir 17-02. revision to pa #201804136335s1, changes include: ground floor load map updated to arch plans, shift shear walls as needed. update elevator shaft dimensions. | |
| Sep 29, 2020 | Completed final sign-off Nov 2022 | 145 Leavenworth St | tower crane foundation & erect tower crane. mayor ed 17-02 project.Details
tower crane foundation & erect tower crane. mayor ed 17-02 project. | $180,000 | |
| Jul 15, 2020 | Completed final sign-off Apr 2023 | 361 Turk St | Centric Construction Inc | mayor dir# 17-02. revision to pa# 201804136327-s1. work includes changes to shear walls. location of steps & depressions. dimension cleanups for coordination purposes. ** maher: n/a **Details
mayor dir# 17-02. revision to pa# 201804136327-s1. work includes changes to shear walls. location of steps & depressions. dimension cleanups for coordination purposes. ** maher: n/a ** | |
| Jan 9, 2020 | Completed final sign-off Oct 2022 | 361 Turk St | Centric Construction Inc | tower crane foundation and erect tower craneDetails
tower crane foundation and erect tower crane | $50,000 |
| Feb 17, 2016 | Completed final sign-off Oct 2019 | 210 Taylor St | Cahill Contractors Llc., Cahill Contractors Inc | erect 9 story, type 1, zero basement, 113 dwelling unit and retail building.Details
erect 9 story, type 1, zero basement, 113 dwelling unit and retail building. | $40,000,000 |
| Apr 22, 2015 | Completed final sign-off Jul 2016 | 1234 10th Av | Double E D Construction Inc | voluntary seismic retrofit upgrade of soft story wood framed building,work entails adding wood framed shear walls & their accessory structural components; per sfbc chapter 34b, 2012 iebc appendix a-4Details
voluntary seismic retrofit upgrade of soft story wood framed building,work entails adding wood framed shear walls & their accessory structural components; per sfbc chapter 34b, 2012 iebc appendix a-4 | $75,000 |
| Jul 23, 2014 | Completed final sign-off Apr 2016 | 540 Mission Bay Blvd North Bl | Nibbi Bros Assoc Inc. | indicator piles for new construction. ref pa# 2013/10/25/0271.Details
indicator piles for new construction. ref pa# 2013/10/25/0271. | $190,000 |
| Feb 15, 2012 | Never finaled issued Feb 2012, no final | 1001 Potrero Av | Rodan Builders Inc | revision to 201111229421.to add additional information for non bearing wall framing and housekeeping padDetails
revision to 201111229421.to add additional information for non bearing wall framing and housekeeping pad | |
| Nov 22, 2011 | Completed final sign-off Apr 2012 | 1001 Potrero Av | Rodan Builders Inc | barrier removal, construct 3 offices, interior finishes hvac. fire alarm revisions under separate application.Details
barrier removal, construct 3 offices, interior finishes hvac. fire alarm revisions under separate application. | $947,230 |
| Aug 12, 2009 | Completed final sign-off Aug 2009 | 555 Mission Rock St | Nibbi Bros Construction | to obtain for final inspection for app#200608028365. all work is complete.Details
to obtain for final inspection for app#200608028365. all work is complete. | |
| Aug 12, 2009 | Completed final sign-off Aug 2009 | 555 Mission Rock St | Nibbi Bros Construction | to obtain for final inspection for app#200610185373. all work is complete.Details
to obtain for final inspection for app#200610185373. all work is complete. | |
| Jun 15, 2009 | Never finaled issued Nov 2009, no final | 3150 Sacramento St | interior remodel of 1st&2nd/fl new finishes, ff & e, elec/mech sys. new public toilet facilities. correct access issues @sidewalk, curb ramp, exteiror ramps/bookdrop & elevator. refurnish perimeter book shelves&windows. restore exterior masonry, terra cotta, main stairs&entry portico ceiling.Details
interior remodel of 1st&2nd/fl new finishes, ff & e, elec/mech sys. new public toilet facilities. correct access issues @sidewalk, curb ramp, exteiror ramps/bookdrop & elevator. refurnish perimeter book shelves&windows. restore exterior masonry, terra cotta, main stairs&entry portico ceiling. | $1,560,000 | |
| Oct 23, 2007 | Expired or cancelled expired Jul 2009 | 330 Berry St | revision to approved appl. 2006 0928 3218 s: indicator pile program. fabricate and drive 8 steel h-piles.Details
revision to approved appl. 2006 0928 3218 s: indicator pile program. fabricate and drive 8 steel h-piles. | $7,000 | |
| Oct 23, 2007 | Expired or cancelled expired Jul 2009 | 335 Berry St | revision to approved appl. 2006 0925 3217: indicator pile program for 335 berry street. fabricate and drive 15 steel h-piles where and as shown on the plans.Details
revision to approved appl. 2006 0925 3217: indicator pile program for 335 berry street. fabricate and drive 15 steel h-piles where and as shown on the plans. | $15,000 | |
| Mar 30, 2007 | Never finaled issued Apr 2007, no final | 5600 03rd St | drive 8 indicator piles for soil & structural testing on vacant lot. reference site pa# 2005/09/29/4323.Details
drive 8 indicator piles for soil & structural testing on vacant lot. reference site pa# 2005/09/29/4323. | $26,000 | |
| Aug 2, 2006 | Expired or cancelled expired Aug 2009 | 555 Mission Rock St | provide indicator pile per plan.Details
provide indicator pile per plan. | $200,000 | |
| Sep 19, 2005 | Completed final sign-off Nov 2005 | 55 04th St | revision to approved pa# 2005/03/03/6642. structural slab leveling for retail spaces on 1st floor.Details
revision to approved pa# 2005/03/03/6642. structural slab leveling for retail spaces on 1st floor. | $22,000 | |
| Dec 16, 2003 | Completed final sign-off Jul 2006 | 50 Lansing St | demolish a four story commercial buildingDetails