Built
1965
Stories
4
Units
30
Rooms
27 bathrooms
Building
14,365 sq ft
Lot
5,998 sq ft
Zoning
RH2
Construction type
D

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

20 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Aug 14, 2024Completed
final sign-off Nov 2024
1234 10th AvDouble E D Construction Incconvert (e) storage on the 1/f into employee changing room/bathroom.
Details
Permit
202408148630
Permit issued
Sep 5, 2024
Final sign-off
Nov 7, 2024

convert (e) storage on the 1/f into employee changing room/bathroom.

Open the permit page

$50,000
May 18, 2020Never finaled
issued May 2020, no final
1234 10th Avstreet space
Details
Permit
M1206307
Permit issued
May 19, 2020

street space

Open the permit page

Feb 4, 2020Never finaled
issued Feb 2020, no final
1234 10th Avstreet space
Details
Permit
M1190268
Permit issued
Feb 4, 2020

street space

Open the permit page

Jan 10, 2020Completed
final sign-off Jun 2020
1234 10th AvDouble E D Construction Incremove and replace existing dryrot backyard stairs in kind. repair in kind.
Details
Permit
202001101623
Permit issued
Feb 4, 2020
Final sign-off
Jun 4, 2020

remove and replace existing dryrot backyard stairs in kind. repair in kind.

Open the permit page

$45,000
Jun 5, 2018Completed
final sign-off Jul 2018
1234 10th AvStronger Building Servicesre-roofing
Details
Permit
201806051025
Permit issued
Jun 5, 2018
Final sign-off
Jul 20, 2018

re-roofing

Open the permit page

$15,000
Apr 16, 2018Completed
final sign-off Jul 2018
1234 10th AvCary Wing Plumbing & Fire Protection Inct.i. to add 12 heads. ref app#201801168640
Details
Permit
201804166443
Permit issued
Apr 16, 2018
Final sign-off
Jul 9, 2018

t.i. to add 12 heads. ref app#201801168640

Open the permit page

$5,000
Jan 16, 2018Completed
final sign-off Jun 2018
1234 10th AvDouble E D Construction Increvision to app#201711214474. revision scope for 3 new bathrooms.
Details
Permit
201801168640
Permit issued
Jan 19, 2018
Final sign-off
Jun 6, 2018

revision to app#201711214474. revision scope for 3 new bathrooms.

Open the permit page

$90,000
Nov 21, 2017Completed
final sign-off Jun 2018
1234 10th AvDouble E D Construction Increvision to 201705176773. 3 new non accessible bathrooms
Details
Permit
201711214474
Permit issued
Nov 22, 2017
Final sign-off
Jun 6, 2018

revision to 201705176773. 3 new non accessible bathrooms

Open the permit page

$45,000
Nov 8, 2017Never finaled
issued Nov 2017, no final
1234 10th Avstreet space permit
Details
Permit
M853987
Permit issued
Nov 8, 2017

street space permit

Open the permit page

May 17, 2017Completed
final sign-off Jun 2018
1234 10th AvDouble E D Construction Incaccessibility upgrades to comply with cbc 11b. renovation of office and manager's unit, 6 new non-accessible bathrooms. landscape changes.
Details
Permit
201705176773
Permit issued
Oct 24, 2017
Final sign-off
Jun 6, 2018

accessibility upgrades to comply with cbc 11b. renovation of office and manager's unit, 6 new non-accessible bathrooms. landscape changes.

Open the permit page

$155,000
Apr 22, 2015Completed
final sign-off Jul 2016
1234 10th AvDouble E D Construction Incvoluntary seismic retrofit upgrade of soft story wood framed building,work entails adding wood framed shear walls & their accessory structural components; per sfbc chapter 34b, 2012 iebc appendix a-4
Details
Permit
201504224287
Permit issued
Jun 6, 2016
Final sign-off
Jul 15, 2016

voluntary seismic retrofit upgrade of soft story wood framed building,work entails adding wood framed shear walls & their accessory structural components; per sfbc chapter 34b, 2012 iebc appendix a-4

Open the permit page

$75,000
Jun 4, 2013Never finaled
issued Jun 2013, no final
1234 10th AvNibbi Bros Assoc Inc.comply with ordinance 029-13 only-installation of grab bars in sro at the following locations; levels 2,3,4 behind all common toilets, 9 toilets total. using bobrick #5806 or #6806 1 1/4 round or 1 1/2 round grab bars meeting 250lbs rating with wingits attachment where wall assemblies meet test requ
Details
Permit
201306048652
Permit issued
Jun 4, 2013

comply with ordinance 029-13 only-installation of grab bars in sro at the following locations; levels 2,3,4 behind all common toilets, 9 toilets total. using bobrick #5806 or #6806 1 1/4 round or 1 1/2 round grab bars meeting 250lbs rating with wingits attachment where wall assemblies meet test requ

Open the permit page

$1,800
May 6, 2013Completed
final sign-off Dec 2013
1234 10th AvGoodlife Kitchensreplace cabinets & counter tops- exactly like for like, re-connect sink, garb disp & dishwasher, 3 kitchens, 1 at each living level (3 small kit @ 100 sq.ft. approx)
Details
Permit
201305066181
Permit issued
May 6, 2013
Final sign-off
Dec 31, 2013

replace cabinets & counter tops- exactly like for like, re-connect sink, garb disp & dishwasher, 3 kitchens, 1 at each living level (3 small kit @ 100 sq.ft. approx)

Open the permit page

$11,000
Dec 13, 2005Never finaled
issued Dec 2005, no final
1234 10th Avsidewalk permit
Details
Permit
M35669
Permit issued
Dec 13, 2005

sidewalk permit

Open the permit page

Oct 15, 2002Completed
final sign-off Dec 2002
1234 10th AvNibbi Brothers Constructionrenew permit 946670 ( 2002/02/26/2973).
Details
Permit
200210158931
Permit issued
Oct 15, 2002
Final sign-off
Dec 30, 2002

renew permit 946670 ( 2002/02/26/2973).

Open the permit page

Oct 15, 2002Completed
final sign-off Dec 2002
1234 10th AvNibbi Brothers Constructionrenew permit 961920 ( 2002/01/18/7310).
Details
Permit
200210158925
Permit issued
Oct 15, 2002
Final sign-off
Dec 30, 2002

renew permit 961920 ( 2002/01/18/7310).

Open the permit page

Jul 26, 2002Completed
final sign-off Dec 2002
1234 10th AvPaganini Electric Corp(See Signatories)fire alarm @ 1, 2, 3 & 4th floor
Details
Permit
200207262433
Permit issued
Aug 5, 2002
Final sign-off
Dec 30, 2002

fire alarm @ 1, 2, 3 & 4th floor

Open the permit page

$10,000
Jul 16, 2002Never finaled
issued Jul 2002, no final
1234 10th Avside walk repair
Details
Permit
M21155
Permit issued
Jul 16, 2002

side walk repair

Open the permit page

Jan 18, 2002Expired or cancelled
expired Dec 2002
1234 10th Avreducing scope of remodel/reducing extending of demo/adding 1 door in mngrs apt on 1st flr
Details
Permit
200201187310
Permit issued
Mar 20, 2002

reducing scope of remodel/reducing extending of demo/adding 1 door in mngrs apt on 1st flr

Open the permit page

Feb 26, 2001Expired or cancelled
expired Dec 2002
1234 10th Av1st floor remodel extg managers office and unitreconfigure extg group kchn/dng area add toilet
Details
Permit
200102262973
Permit issued
Aug 20, 2001

1st floor remodel extg managers office and unitreconfigure extg group kchn/dng area add toilet

Open the permit page

$120,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Double E D Construction Inc (6), Nibbi Brothers Construction (2), Cary Wing Plumbing & Fire Protection Inc, Goodlife Kitchens, Nibbi Bros Assoc Inc., Paganini Electric Corp(See Signatories), Stronger Building Services
Architects
John Hulett Jones (2), Paul Haydu
Engineers
Sunic Gupta
Authorized agents
Wally Macmillan
Designers
Eduardo Diao

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.