Block 0345, lot 002
145 Leavenworth St
- City’s use
- Commercial Misc
- Built
- 2023
- Stories
- 8
- Units
- 96
- Building
- 42,056 sq ft
- Lot
- 6,873 sq ft
- Zoning
- C3G
- Construction type
- REI
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
15 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 14, 2022 | Completed final sign-off May 2023 | 145 Leavenworth St | Centric Construction Inc | revision 201804136335 s3 to document the revised area with the mechanical room at roof levelDetails
revision 201804136335 s3 to document the revised area with the mechanical room at roof level | |
| Oct 7, 2022 | Completed final sign-off Nov 2022 | 145 Leavenworth St | Incom Mechanical Inc | as-built 90 degree underground added. revision to pa#202108065974.Details
as-built 90 degree underground added. revision to pa#202108065974. | |
| Mar 31, 2022 | Completed final sign-off Apr 2023 | 145 Leavenworth St | Centric Construction Inc | revision to pa 201804136335-s3. revised walls with unit bathrooms. revised wall layout with community laundry space.Details
revision to pa 201804136335-s3. revised walls with unit bathrooms. revised wall layout with community laundry space. | |
| Dec 29, 2021 | Completed final sign-off Mar 2023 | 145 Leavenworth St | Blue Water Projects Inc | evac signs for base building see site permit 201804136335.Details
evac signs for base building see site permit 201804136335. | $6,000 |
| Oct 18, 2021 | Never finaled issued Jan 2022, no final | 145 Leavenworth St | sign c: non illuminated 16 inch by 16 inch aluminum plaque with letters (tl145)Details
sign c: non illuminated 16 inch by 16 inch aluminum plaque with letters (tl145) | $500 | |
| Oct 18, 2021 | Never finaled issued Jan 2022, no final | 145 Leavenworth St | Blue Water Projects Inc | sign a: non illuminated 10 inch aluminum letters (tl145)Details
sign a: non illuminated 10 inch aluminum letters (tl145) | $3,000 |
| Oct 18, 2021 | Never finaled issued Jan 2022, no final | 145 Leavenworth St | Blue Water Projects Inc | sign b: non illuminated 5 inch aluminum letters (tl145)Details
sign b: non illuminated 5 inch aluminum letters (tl145) | $2,500 |
| Sep 22, 2021 | Completed final sign-off May 2023 | 145 Leavenworth St | Sun Light & Power | new roof mounted solar water heater(7) collectors total,(18.2) kwth,(4) storage tanks at (119) gal each.Details
new roof mounted solar water heater(7) collectors total,(18.2) kwth,(4) storage tanks at (119) gal each. | $79,915 |
| Aug 6, 2021 | Completed final sign-off Nov 2022 | 145 Leavenworth St | Incom Mechanical Inc | fire underground only. install new 6" underground service - 14 feet on vacant lot. see site permit 201804136335 (s). sprinkler/sprinkler monitoring under sep permits.Details
fire underground only. install new 6" underground service - 14 feet on vacant lot. see site permit 201804136335 (s). sprinkler/sprinkler monitoring under sep permits. | $15,000 |
| May 12, 2021 | Completed final sign-off May 2023 | 145 Leavenworth St | Centric Construction Inc | stormwater systempermit for future construction of building at 145 leavenworth under pa #201804136335-sDetails
stormwater systempermit for future construction of building at 145 leavenworth under pa #201804136335-s | $10,000 |
| Oct 16, 2020 | Completed final sign-off May 2023 | 145 Leavenworth St | Centric Construction Inc | mayor dir 17-02. revision to pa #201804136335s1, changes include: ground floor load map updated to arch plans, shift shear walls as needed. update elevator shaft dimensions.Details
mayor dir 17-02. revision to pa #201804136335s1, changes include: ground floor load map updated to arch plans, shift shear walls as needed. update elevator shaft dimensions. | |
| Sep 29, 2020 | Completed final sign-off Nov 2022 | 145 Leavenworth St | tower crane foundation & erect tower crane. mayor ed 17-02 project.Details
tower crane foundation & erect tower crane. mayor ed 17-02 project. | $180,000 | |
| Sep 23, 2020 | Completed final sign-off Feb 2023 | 145 Leavenworth St | Centric Construction Inc | mayor dir# 17-02. rev to pa# 201804136335-s9. 46 ri columns were added in vicenity of tower crane. these ri's are shown in plan review on attached & also highlighted in ri column section. dimension of added "c" type ri's are same as "a" type ri's but they are on a 4' spacing instead of 8'spacing.Details
mayor dir# 17-02. rev to pa# 201804136335-s9. 46 ri columns were added in vicenity of tower crane. these ri's are shown in plan review on attached & also highlighted in ri column section. dimension of added "c" type ri's are same as "a" type ri's but they are on a 4' spacing instead of 8'spacing. | |
| May 31, 2019 | Expired or cancelled withdrawn Apr 2023 | 145 Leavenworth St | Centric Construction Inc | excavation of (e) soil to sub-grade to prepare for (n) constructionDetails
excavation of (e) soil to sub-grade to prepare for (n) construction | $250,500 |
| Apr 13, 2018 | Completed final sign-off May 2023 | 145 Leavenworth St | Centric Construction Inc, Swinerton Builders | to erect 9 stories, 1 basement, type 1-b, 94 units residential covered multi family dwellings with ground floor restaurant tenant space . (r-2, a-2, a-3) ** maher: n/a **Details
to erect 9 stories, 1 basement, type 1-b, 94 units residential covered multi family dwellings with ground floor restaurant tenant space . (r-2, a-2, a-3) ** maher: n/a ** | $30,000,000 |
Find contractors for work like this