Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Stairs permits
20 stairs permits: 15 completed, 1 never finaled, 4 expired or cancelled. Typically 12 days from filing to permit and 260 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 16, 2014 | Completed final sign-off Aug 2014 | 720 Market St | selective demo and construction of non-structural partitions, new ceiling grid, stairs and relocate light fixtures. mep, sprinkler and life safety-under separate permit.Details
selective demo and construction of non-structural partitions, new ceiling grid, stairs and relocate light fixtures. mep, sprinkler and life safety-under separate permit. | $51,500 |
| Jun 4, 2014 | Completed final sign-off Sep 2014 | 3 Embarcadero Center | construction of a non-rated partition to block stair & seperate 25/f from 26/f. n/a ordinance #155-13Details
construction of a non-rated partition to block stair & seperate 25/f from 26/f. n/a ordinance #155-13 | $50,000 |
| Jul 22, 2013 | Completed final sign-off Jan 2015 | 731 Market St | new stevenson street entry with new lobby and canopy; storefront, interior entry stair into basement, and enclosure of 1 existing exit stair. core and shell per ab-017. ti under separate permit.Details
new stevenson street entry with new lobby and canopy; storefront, interior entry stair into basement, and enclosure of 1 existing exit stair. core and shell per ab-017. ti under separate permit. | $324,425 |
| Feb 15, 2013 | Completed final sign-off May 2013 | 4 Embarcadero Center | garage level 2:barrier removal only. remove ramps encroching into passenger loading area. new flat accessible parking stairs and loading areas.Details
garage level 2:barrier removal only. remove ramps encroching into passenger loading area. new flat accessible parking stairs and loading areas. | $75,000 |
| Feb 14, 2013 | Completed final sign-off Aug 2013 | 3180 18th St | t.i. on 3 floors including (n) restrooms, offices, break room, stairs, partitions, casework, closets, dining area. mep, sprinklers under separate permit.Details
t.i. on 3 floors including (n) restrooms, offices, break room, stairs, partitions, casework, closets, dining area. mep, sprinklers under separate permit. | $920,000 |
| Nov 15, 2012 | Completed final sign-off Jan 2015 | 111 Sutter St | interior demolition of existing tenant partitions, ceilings, finishes. removal of existing mezzanine & stair approx. 2,120 sq.ft. safing off, capping/ removal of electrical & plumbing complying with ab-17Details
interior demolition of existing tenant partitions, ceilings, finishes. removal of existing mezzanine & stair approx. 2,120 sq.ft. safing off, capping/ removal of electrical & plumbing complying with ab-17 | $27,600 |
| Oct 11, 2012 | Completed final sign-off Jan 2013 | 201 Spear St | provide and install new evacuation sinage at the 11th & 17th floor elevator, lobbies and exti stairs.Details
provide and install new evacuation sinage at the 11th & 17th floor elevator, lobbies and exti stairs. | $1,800 |
| Jul 3, 2012 | Completed final sign-off Apr 2014 | 1 Embarcadero Center | removal of (e) curved stairs from str level to lobby level, removal of 2 (e) concrete tube structures from west face of bldg. construct new public stair adjacent to demolished curved stair. new stair moved 3" towards bldg ext. electrical & fire alarm/fire sprinkler will be under separate permit.Details
removal of (e) curved stairs from str level to lobby level, removal of 2 (e) concrete tube structures from west face of bldg. construct new public stair adjacent to demolished curved stair. new stair moved 3" towards bldg ext. electrical & fire alarm/fire sprinkler will be under separate permit. | $100,000 |
| Mar 15, 2012 | Completed final sign-off Sep 2013 | 4 Embarcadero Center | 22nd floor - demo (e) partition walls, ceiling, floorign & finishes. replace fixtures in (e) restrooms to be fully compliant.demo unused interconnecting stair bet 21st & 22nd flrs in tenant space & infill stair slab opening w/new struct slab. life safety on design/build under separate permit.Details
22nd floor - demo (e) partition walls, ceiling, floorign & finishes. replace fixtures in (e) restrooms to be fully compliant.demo unused interconnecting stair bet 21st & 22nd flrs in tenant space & infill stair slab opening w/new struct slab. life safety on design/build under separate permit. | $140,000 |
| Feb 10, 2012 | Completed final sign-off Sep 2013 | 4 Embarcadero Center | 9th flr-demo (e) partition walls, ceiling, flring & finishes throughout tenant space. new elevator lobby, 8th fl. repl finishes, fixts in men's restrms layout to remain the same. demo (e) women's restrms & relocate. new fixtures, finishes throughout, demo inter stairs 8th/9th flrs, infill stairDetails
9th flr-demo (e) partition walls, ceiling, flring & finishes throughout tenant space. new elevator lobby, 8th fl. repl finishes, fixts in men's restrms layout to remain the same. demo (e) women's restrms & relocate. new fixtures, finishes throughout, demo inter stairs 8th/9th flrs, infill stair | $260,000 |
| Dec 2, 2011 | Completed final sign-off May 2012 | 4 Embarcadero Center | new finishes and fixtures in extg restrooms. new ada compliant drinking fountain. demo unused interconnection, stair btwn 29th and 30th floors in the tenant space and infill the stair slab opening w/a new structural slab per structural dwgs,suspended ceiling in the bathrooms. mep & life safety sep.Details
new finishes and fixtures in extg restrooms. new ada compliant drinking fountain. demo unused interconnection, stair btwn 29th and 30th floors in the tenant space and infill the stair slab opening w/a new structural slab per structural dwgs,suspended ceiling in the bathrooms. mep & life safety sep. | $110,000 |
| Aug 3, 2011 | Completed final sign-off May 2012 | 2 Embarcadero Center | new finishes and fixtures in e floor common ada compliant restrooms and elev lobby layout and configuration shall remain as is. new ada compliant drinking fountain. dmo unused interconnecting stair btwn 21st/22ndfl, infill stair slab opening w/ struc slab.mep,sp, ls separate permitDetails
new finishes and fixtures in e floor common ada compliant restrooms and elev lobby layout and configuration shall remain as is. new ada compliant drinking fountain. dmo unused interconnecting stair btwn 21st/22ndfl, infill stair slab opening w/ struc slab.mep,sp, ls separate permit | $156,395 |
| Oct 29, 2009 | Never finaled issued Nov 2009, no final | 1050 Van Ness Av | bsmt fl. van ness entr: demo sub bsmnt stair n encl, demo dr and sidelight at facade. (n) sub bsmt & (n) bsmt stair. (n) dr and side light . myrtle entr: demo partitonss and drs. (n) partitions, (n) reused drs. geary entr: upgrade (e)strs&handrails compliant. add 2 60min f.r. doors at new stairsDetails
bsmt fl. van ness entr: demo sub bsmnt stair n encl, demo dr and sidelight at facade. (n) sub bsmt & (n) bsmt stair. (n) dr and side light . myrtle entr: demo partitonss and drs. (n) partitions, (n) reused drs. geary entr: upgrade (e)strs&handrails compliant. add 2 60min f.r. doors at new stairs | $125,000 |
| Jun 12, 2009 | Expired or cancelled expired Jul 2012 | 455 Anderson St | rebuild existing enclosed porch with largerfootprint to meet codeat 1/2 bath. rebuild deck & exterior stair.Details
rebuild existing enclosed porch with largerfootprint to meet codeat 1/2 bath. rebuild deck & exterior stair. | $22,500 |
| Jun 5, 2009 | Expired or cancelled expired Jul 2012 | 455 Anderson St | interior work. non-structural demo. non-structural walls. remodel kitchen & bath. new bathroom on upper level. (n) code compliant stair. (n) skylites. no increase in area. no change in occupancy or use. mechanical under separate permit.Details
interior work. non-structural demo. non-structural walls. remodel kitchen & bath. new bathroom on upper level. (n) code compliant stair. (n) skylites. no increase in area. no change in occupancy or use. mechanical under separate permit. | $50,000 |
| Apr 30, 2008 | Completed final sign-off May 2009 | 1725 Union St | the scope of the project for "crunch fitness" at 1725 union st in s.f. includes the following:1) demo of extg interior stair, abandoned hvac units, etc. 2) construction of new interior partitions. locker and restrooms, infill of extg opening in 2nd flr level, add of new accessible wheelchair liftDetails
the scope of the project for "crunch fitness" at 1725 union st in s.f. includes the following:1) demo of extg interior stair, abandoned hvac units, etc. 2) construction of new interior partitions. locker and restrooms, infill of extg opening in 2nd flr level, add of new accessible wheelchair lift | $2,000,000 |
| Sep 20, 2007 | Expired or cancelled expired Mar 2009 | 3 Embarcadero Center | remove and replace existing intervening stair between floor 29 & 30. install new accessible lift between 29 & 30 floor.. new handrails and finishes.Details
remove and replace existing intervening stair between floor 29 & 30. install new accessible lift between 29 & 30 floor.. new handrails and finishes. | $200,000 |
| Oct 12, 2005 | Expired or cancelled expired Feb 2009 | 345 California St | revision to permit app#200509122593. (infill additional hole in deck between 30th & 29th floors) where we're removing an internal stair.Details
revision to permit app#200509122593. (infill additional hole in deck between 30th & 29th floors) where we're removing an internal stair. | $5,000 |
| Sep 27, 2005 | Completed final sign-off Jun 2009 | 345 California St | demolition aspects only. removal of an interior communication staircase between 30th & 31st floor.Details
demolition aspects only. removal of an interior communication staircase between 30th & 31st floor. | $80,000 |
| Sep 12, 2005 | Completed final sign-off Jun 2009 | 345 California St | demolition of a interior communication staircase between 30th& 31st flrs infilling the slab on 31st floor.Details
demolition of a interior communication staircase between 30th& 31st flrs infilling the slab on 31st floor. | $80,000 |