Block 3735, lot 062
75 Hawthorne St
- City’s use
- Commercial Office
- Built
- 1987
- Stories
- 20
- Building
- 360,000 sq ft
- Lot
- 34,957 sq ft
- Zoning
- C3S
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
179 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 7, 2022 | Completed final sign-off Apr 2022 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 20th fl: as built. add 5 fire sprinklers in phone booths. ref pa# 202201266660.Details
20th fl: as built. add 5 fire sprinklers in phone booths. ref pa# 202201266660. | |
| Mar 3, 2022 | Completed final sign-off Apr 2022 | 75 Hawthorne St | R L H Fire Protection Inc | fire sprinkler elevator modernization per sffd letter dated 12/9/2021. 9 deleted sidewalls, 4 deleted pendent , 14 deleted uprights, 4 uprights installed outside roof level machine room.Details
fire sprinkler elevator modernization per sffd letter dated 12/9/2021. 9 deleted sidewalls, 4 deleted pendent , 14 deleted uprights, 4 uprights installed outside roof level machine room. | $20,162 |
| Jan 26, 2022 | Completed final sign-off Apr 2022 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 20th fl add 6 fire sprinkelrs in phone booths, per ti. ref 201709199023. job 21-678Details
20th fl add 6 fire sprinkelrs in phone booths, per ti. ref 201709199023. job 21-678 | $3,150 |
| Aug 13, 2021 | Never finaled filed Aug 2021, never issued | 75 Hawthorne St | Johnson Controls Fire | "elevator modernization" modify extg fie alarm system, remove all devices related to elevator shunt trip. all wiring to be class b. ref app#202010196846Details
"elevator modernization" modify extg fie alarm system, remove all devices related to elevator shunt trip. all wiring to be class b. ref app#202010196846 | $6,700 |
| May 5, 2021 | Completed final sign-off Jul 2021 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | as-built for #2021--0225-5413 8th floor: add (7) and relocate (25) sprinklers per t.i. #21-608Details
as-built for #2021--0225-5413 8th floor: add (7) and relocate (25) sprinklers per t.i. #21-608 | |
| Mar 18, 2021 | Completed final sign-off Mar 2022 | 75 Hawthorne St | Johnson Controls Fire | partial 8th floor fire alarm tenant improvement. (1) new smoke sensor, (1) new heat sensor, (5) new input/output modules, (7) new speaker/strobes. ref to ti# 2020.1019.6846Details
partial 8th floor fire alarm tenant improvement. (1) new smoke sensor, (1) new heat sensor, (5) new input/output modules, (7) new speaker/strobes. ref to ti# 2020.1019.6846 | $20,000 |
| Mar 18, 2021 | Completed final sign-off May 2021 | 75 Hawthorne St | Johnson Controls Fire | partial 19th floor fire alarm tenant improvement. remove and relocate existing notification appliances, (1) (n) relay module, (1) (n) elev lobby call box 2 way system back bone installed under pa 2019.0517.0917Details
partial 19th floor fire alarm tenant improvement. remove and relocate existing notification appliances, (1) (n) relay module, (1) (n) elev lobby call box 2 way system back bone installed under pa 2019.0517.0917 | $14,000 |
| Mar 11, 2021 | Completed final sign-off May 2021 | 75 Hawthorne St | Tack Eg | replace evacuation maps on 19th flr, due to addition of a 2-way communication system. 3 signs totalDetails
replace evacuation maps on 19th flr, due to addition of a 2-way communication system. 3 signs total | $1,200 |
| Feb 25, 2021 | Completed final sign-off Jun 2021 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 8th floor: add and relocate sprinklers as necessary to conform with the tenant improvement. add (6) and relocate (22) ref. #202-1019-6846Details
8th floor: add and relocate sprinklers as necessary to conform with the tenant improvement. add (6) and relocate (22) ref. #202-1019-6846 | $8,100 |
| Feb 8, 2021 | Completed final sign-off Jun 2021 | 75 Hawthorne St | Victory Electric | 19th floor: electrical-new lighting, power and signal. ref# 202007109943Details
19th floor: electrical-new lighting, power and signal. ref# 202007109943 | $30,000 |
| Feb 2, 2021 | Completed final sign-off Apr 2021 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 19th floor: change out (1) sprinkler per t.i. ref #2020-0710-9943. job # 21-601.Details
19th floor: change out (1) sprinkler per t.i. ref #2020-0710-9943. job # 21-601. | $225 |
| Oct 19, 2020 | Completed final sign-off Jun 2022 | 75 Hawthorne St | Field Construction Inc. | 8th floor: ti includes non-structural demo, construction of non-structural partitions, doors, interior glazing, ceiling, light fixtures, millwork, and finishes. no cahnge in occupancy, use, or area. lifesafety & sprinklers under separate permit.Details
8th floor: ti includes non-structural demo, construction of non-structural partitions, doors, interior glazing, ceiling, light fixtures, millwork, and finishes. no cahnge in occupancy, use, or area. lifesafety & sprinklers under separate permit. | $635,855 |
| Jul 10, 2020 | Completed final sign-off Jun 2021 | 75 Hawthorne St | Rudolph Commercial Interiors Inc, Rci | 19th flr - interior tenant improvement. scope includes demo of non structural partitions, construction of non structural partitions, doors, interior glazing, light fixtures and finishes. new two-way comm and evac signs in elev lobby under sep permit. ls/fa/sprinklers under sep permit.Details
19th flr - interior tenant improvement. scope includes demo of non structural partitions, construction of non structural partitions, doors, interior glazing, light fixtures and finishes. new two-way comm and evac signs in elev lobby under sep permit. ls/fa/sprinklers under sep permit. | $35,752 |
| Mar 2, 2020 | Completed final sign-off Sep 2020 | 75 Hawthorne St | C B 2 Builders Incorporated | revise (e) 7th fl roof tie back to conform with cal osha.Details
revise (e) 7th fl roof tie back to conform with cal osha. | $50,000 |
| Oct 2, 2019 | Never finaled issued Oct 2019, no final | 75 Hawthorne St | Novo Construction Inc | 8th flr - int ti construction of non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork and finishes. no change in occp/use/area. plm/fire/life safety under sep permitDetails
8th flr - int ti construction of non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork and finishes. no change in occp/use/area. plm/fire/life safety under sep permit | $635,855 |
| Oct 2, 2019 | Never finaled issued Oct 2019, no final | 75 Hawthorne St | Novo Construction Inc | 6th flr - int ti construction of non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork and finishes. no change in occp/use/area. plm/fire/life safety under sep permitDetails
6th flr - int ti construction of non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork and finishes. no change in occp/use/area. plm/fire/life safety under sep permit | $694,903 |
| Jul 31, 2019 | Completed final sign-off Aug 2020 | 75 Hawthorne St | Tcg Builders Inc Dba The Core Group | 4th flr, suite 400. evacuation plans in reference to t.i pa 201904127813Details
4th flr, suite 400. evacuation plans in reference to t.i pa 201904127813 | |
| May 29, 2019 | Completed final sign-off Aug 2020 | 75 Hawthorne St | Johnson Controls Fire | 4th fl - remove and replace notification devices. remove and replace 3 smoke detectors. remove and replace 21 speaker strobes, 11 strobes are being added. add 1 call box to the 2 way commuication system. call box box in elevator lobby. ref pa 201904127813Details
4th fl - remove and replace notification devices. remove and replace 3 smoke detectors. remove and replace 21 speaker strobes, 11 strobes are being added. add 1 call box to the 2 way commuication system. call box box in elevator lobby. ref pa 201904127813 | $21,017 |
| May 17, 2019 | Completed final sign-off May 2021 | 75 Hawthorne St | Johnson Controls Fire | installing 2-way communicaiton system equipment including: 1 powerstrip, 1 power supply, 3 battery racks, 1 supervision module, 1 distribution module, 1 ups monitoring module, 1 command center and 1 sub-command center. installing 2 fire alarm monitoring modules.Details
installing 2-way communicaiton system equipment including: 1 powerstrip, 1 power supply, 3 battery racks, 1 supervision module, 1 distribution module, 1 ups monitoring module, 1 command center and 1 sub-command center. installing 2 fire alarm monitoring modules. | $6,337 |
| May 16, 2019 | Completed final sign-off Aug 2019 | 75 Hawthorne St | Fire Stop Sprinkler Company | ti - relocate 74 pendent sprinkler heads for the new 4th floor layoutDetails
ti - relocate 74 pendent sprinkler heads for the new 4th floor layout | $25,000 |
| May 3, 2019 | Completed final sign-off Sep 2020 | 75 Hawthorne St | Tcg Builders Inc Dba The Core Group | 4th fl - mep for interior ti on (e) unoccupied space, reflected in pa 2019-0412-7813. maher n/a.Details
4th fl - mep for interior ti on (e) unoccupied space, reflected in pa 2019-0412-7813. maher n/a. | |
| Apr 12, 2019 | Completed final sign-off Sep 2020 | 75 Hawthorne St | Tcg Builders Inc Dba The Core Group | interior ti on e unoccupied 4th fl, scope includes construction of non structural partitoins, doors, interior glazing, ceiling, light fix, millwork, finishes. floor was rpev demolished per 201705055777. no change in occupancy,use or area. mech, elec,plumb, ls, sprinklers under sep permitDetails
interior ti on e unoccupied 4th fl, scope includes construction of non structural partitoins, doors, interior glazing, ceiling, light fix, millwork, finishes. floor was rpev demolished per 201705055777. no change in occupancy,use or area. mech, elec,plumb, ls, sprinklers under sep permit | $1,464,411 |
| Mar 7, 2019 | Completed final sign-off Apr 2019 | 75 Hawthorne St | Johnson Controls Fire | 20th flr. install new temporary 2-way elevator landing emergency communication system, provide rath call box at elevator lobby w/ appropriate signage. re pa 201807104045Details
20th flr. install new temporary 2-way elevator landing emergency communication system, provide rath call box at elevator lobby w/ appropriate signage. re pa 201807104045 | $2,000 |
| Feb 7, 2019 | Never finaled issued Feb 2019, no final | 75 Hawthorne St | Skender Construction Llc | installing 4 evac sign plaques on the 5th fl.Details
installing 4 evac sign plaques on the 5th fl. | $3,600 |
| Jan 25, 2019 | Completed final sign-off Feb 2019 | 75 Hawthorne St | Johnson Controls Fire | fire alarm as-built record drawings for p.a 2018-1120-6344. remove (2) addressable relays from scope. ref#201807104045Details
fire alarm as-built record drawings for p.a 2018-1120-6344. remove (2) addressable relays from scope. ref#201807104045 | |
| Jan 15, 2019 | Completed final sign-off Jun 2019 | 75 Hawthorne St | C B F Inc | 5th floor: mep only in ref to approved permit# 201809281701. new power and data for work stations and offices. new lighting and controls.Details
5th floor: mep only in ref to approved permit# 201809281701. new power and data for work stations and offices. new lighting and controls. | |
| Dec 14, 2018 | Completed final sign-off Feb 2019 | 75 Hawthorne St | Johnson Controls Fire | ref 201809281701; fire alarm t.i. on 5th fl. install 2 new smoke sensors, 2 new relalys, 6 new notifications appliances, relocate (e) appliancesDetails
ref 201809281701; fire alarm t.i. on 5th fl. install 2 new smoke sensors, 2 new relalys, 6 new notifications appliances, relocate (e) appliances | $5,700 |
| Nov 20, 2018 | Completed final sign-off Feb 2019 | 75 Hawthorne St | Johnson Controls Fire | 20th flr - fire alarm as builts for 201809190730. install 3 addressable relaysDetails
20th flr - fire alarm as builts for 201809190730. install 3 addressable relays | |
| Nov 14, 2018 | Completed final sign-off Feb 2019 | 75 Hawthorne St | Pioneer Fire Inc. | 5th fl - relocate 18 pendents, remove 4 pendents. ref pa 2018-0928-1701Details
5th fl - relocate 18 pendents, remove 4 pendents. ref pa 2018-0928-1701 | $3,798 |
| Sep 28, 2018 | Completed final sign-off Jun 2019 | 75 Hawthorne St | Skender Construction Llc | the scope of work is for tenant improvement on the partial 5th floor of 75 hawthorne.includes demolition & construction of non structural partitions, doors, interioe glazing, ceiling light fixtures, millwork & finishes no change in occupancy life safety mech,electrical & plumbing under seperate permDetails
the scope of work is for tenant improvement on the partial 5th floor of 75 hawthorne.includes demolition & construction of non structural partitions, doors, interioe glazing, ceiling light fixtures, millwork & finishes no change in occupancy life safety mech,electrical & plumbing under seperate perm | $818,837 |
| Sep 19, 2018 | Completed final sign-off Apr 2019 | 75 Hawthorne St | Johnson Controls Fire | fire alarm ti install 18 new speakers/strobes, 7 new strobes, demo e appliances as shown ref 201807104045Details
fire alarm ti install 18 new speakers/strobes, 7 new strobes, demo e appliances as shown ref 201807104045 | $13,300 |
| Aug 23, 2018 | Completed final sign-off Jul 2019 | 75 Hawthorne St | Pacific Coast Fire | modify 26 fire sprinkler heads for new office layout. unit 2200Details
modify 26 fire sprinkler heads for new office layout. unit 2200 | $10,500 |
| Jul 10, 2018 | Completed final sign-off Jul 2019 | 75 Hawthorne St | spec suite: ltg under sep perminterior ti on the (e) unoccupied 20th fl. scope includes demolition and construction of non-structural partitions, doors interior glazing, ceiling, light fixtures millwork and finishes. no change in occupancy use or area, life safety & sprinklers under separate permitDetails
spec suite: ltg under sep perminterior ti on the (e) unoccupied 20th fl. scope includes demolition and construction of non-structural partitions, doors interior glazing, ceiling, light fixtures millwork and finishes. no change in occupancy use or area, life safety & sprinklers under separate permit | $1,372,974 | |
| Apr 12, 2018 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | revision to pa # 201602028584. revision to return to (e) exterior exit gate, to remain unchanged, but allow for code req'd exiting w/ addition of safe dispersal area per 2010 cbc sec 1027.6 & approval for technical feasability of existing basement parking at accessible stalls. ref pa 201312204741Details
revision to pa # 201602028584. revision to return to (e) exterior exit gate, to remain unchanged, but allow for code req'd exiting w/ addition of safe dispersal area per 2010 cbc sec 1027.6 & approval for technical feasability of existing basement parking at accessible stalls. ref pa 201312204741 | ||
| Dec 20, 2017 | Completed final sign-off Jun 2018 | 75 Hawthorne St | Sierra Electric Co | 5/f: suite 500: title 24 electrical. ref t.i. pa201710242128.Details
5/f: suite 500: title 24 electrical. ref t.i. pa201710242128. | $10,000 |
| Dec 5, 2017 | Completed final sign-off Jan 2018 | 75 Hawthorne St | Johnson Controls Fire | 5th fl - ti consist of adding 12 speaker/strobes, 2 strobes & 1 speaker as shown on plans. demo existing devices as shown on plans. ref pa 2017-1024-2128Details
5th fl - ti consist of adding 12 speaker/strobes, 2 strobes & 1 speaker as shown on plans. demo existing devices as shown on plans. ref pa 2017-1024-2128 | $9,000 |
| Nov 29, 2017 | Completed final sign-off Apr 2018 | 75 Hawthorne St | C B 2 Builders Incorporated | mechanical systems hvac on the 5th fl together with t.i. permit #201710242128Details
mechanical systems hvac on the 5th fl together with t.i. permit #201710242128 | $113,000 |
| Nov 28, 2017 | Completed final sign-off Jan 2018 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 5th floor t.i. add 25, relocate 28, and plug 4 sprinklers to conform with the new wall/ceiling layout of the t.i. ref app#201710242128Details
5th floor t.i. add 25, relocate 28, and plug 4 sprinklers to conform with the new wall/ceiling layout of the t.i. ref app#201710242128 | $19,425 |
| Oct 24, 2017 | Completed final sign-off Jun 2018 | 75 Hawthorne St | C B 2 Builders Incorporated | ti on 5th fl suite (partial floor), includes demolition, construction of non-structural partitions, doors, interior glazing, ceiling lighting, millwork & finishes. no change in occupancy. mep under sep. permit.Details
ti on 5th fl suite (partial floor), includes demolition, construction of non-structural partitions, doors, interior glazing, ceiling lighting, millwork & finishes. no change in occupancy. mep under sep. permit. | $645,645 |
| Oct 18, 2017 | Completed final sign-off Jul 2019 | 75 Hawthorne St | Pacific Ridge Builders Inc | 20/f- furr out one secion of wall to relocate toilet for ada compliance; barriar removal. women's restroom to full ada compliance. (e) f/s & f/a to remain. maher n/a.Details
20/f- furr out one secion of wall to relocate toilet for ada compliance; barriar removal. women's restroom to full ada compliance. (e) f/s & f/a to remain. maher n/a. | $7,500 |
| Oct 6, 2017 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | revision to 201706230178, revised cover sheet and da checklisti to indicate no accessibility work per ab017 because floor will not be occupiedDetails
revision to 201706230178, revised cover sheet and da checklisti to indicate no accessibility work per ab017 because floor will not be occupied | ||
| Sep 22, 2017 | Completed final sign-off Nov 2017 | 75 Hawthorne St | Turner Construction Co | 20th floor- add (1) fire smoke damper in elevator lobby. t.i. pa#201706230178Details
20th floor- add (1) fire smoke damper in elevator lobby. t.i. pa#201706230178 | $10,000 |
| Sep 19, 2017 | Completed final sign-off Oct 2017 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 22/f: add 2, relocate 5, and change out 22 sprinklers to conform with the new wall/ceiling layout of the t.i. ref app#201706230178Details
22/f: add 2, relocate 5, and change out 22 sprinklers to conform with the new wall/ceiling layout of the t.i. ref app#201706230178 | $7,900 |
| Aug 18, 2017 | Completed final sign-off Nov 2017 | 75 Hawthorne St | Johnson Controls Fire | 20th floor - provide & install for tenant improvement consist of adding (4) storage & (6) speaker/strobes. ref ti #201706230178.Details
20th floor - provide & install for tenant improvement consist of adding (4) storage & (6) speaker/strobes. ref ti #201706230178. | $6,000 |
| Jun 23, 2017 | Never finaled issued Jun 2017, no final | 75 Hawthorne St | Turner Construction Co | demo and construction amep plans non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork. new finishes. no change in occupancy. fire/life safety sep permit, mep for elev lobby under sep permit.Details
demo and construction amep plans non structural partitions, doors, interior glazing, ceiling, light fixtures, millwork. new finishes. no change in occupancy. fire/life safety sep permit, mep for elev lobby under sep permit. | $604,758 |
| May 16, 2017 | Completed final sign-off May 2017 | 75 Hawthorne St | Ayoob & Peery Plumbing Co Inc | 4/f & 5/f- change out sprinkler to upright to convert system to base building for future tenant. 4/f - 117, 5/f- 49, total 166. t.i. pa#201705055777Details
4/f & 5/f- change out sprinkler to upright to convert system to base building for future tenant. 4/f - 117, 5/f- 49, total 166. t.i. pa#201705055777 | $38,000 |
| May 5, 2017 | Never finaled issued May 2017, no final | 75 Hawthorne St | C B 2 Builders Incorporated | 4/f, 5/f- non-structural demolition only, no build back, no change in occupancy, use or area, remain vacant per ab-017 deferring accessibility compliance until tenant improvement permit application.Details
4/f, 5/f- non-structural demolition only, no build back, no change in occupancy, use or area, remain vacant per ab-017 deferring accessibility compliance until tenant improvement permit application. | $195,000 |
| Mar 23, 2017 | Never finaled issued Mar 2017, no final | 75 Hawthorne St | Turner Construction Co | to obtain final inspection for work approved under pa # 201302049444. all work is complete.Details
to obtain final inspection for work approved under pa # 201302049444. all work is complete. | |
| Dec 8, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Allied Fire Protection | resubmittal for fire sprinklers. original app 201603101665Details
resubmittal for fire sprinklers. original app 201603101665 | |
| Dec 1, 2016 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | to obtain final inspection for work approved under pa#201304245329. all work is complete.Details
to obtain final inspection for work approved under pa#201304245329. all work is complete. | |
| Nov 17, 2016 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 3rd floor existing fire sprinkler system - 4 sprinklers relocated from pendent to upright. tenant improvements pa #201611021788.Details
3rd floor existing fire sprinkler system - 4 sprinklers relocated from pendent to upright. tenant improvements pa #201611021788. | $1,000 |
| Nov 2, 2016 | Never finaled issued Nov 2016, no final | 75 Hawthorne St | Turner Construction Co | revision to 3rd floor interior ti of multi-tenant floor. improvements include electrical, mechanical, ceiling, lighting & finishes. no structural scope. no change of use. ref pa 2013-1211-3943Details
revision to 3rd floor interior ti of multi-tenant floor. improvements include electrical, mechanical, ceiling, lighting & finishes. no structural scope. no change of use. ref pa 2013-1211-3943 | $30,000 |
| Nov 2, 2016 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | revised occupancy type training room to 1:20 b occupancy ref pa 2015-1231-6239Details
revised occupancy type training room to 1:20 b occupancy ref pa 2015-1231-6239 | $996 |
| Oct 20, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Johnson Controls Fire | 2/f- fire alarm t.i., 2 smoke detectors, 5 duct smoke detectors with relay, 6 speakers/strobes & 1 strobe. t.i. pa#201607011468Details
2/f- fire alarm t.i., 2 smoke detectors, 5 duct smoke detectors with relay, 6 speakers/strobes & 1 strobe. t.i. pa#201607011468 | $9,500 |
| Oct 4, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Turner Construction Co | evacuation signs for floors 2, 6, 7Details
evacuation signs for floors 2, 6, 7 | $1,500 |
| Sep 29, 2016 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 2nd floor: fire sprinklers, relocate 34, add 5Details
2nd floor: fire sprinklers, relocate 34, add 5 | $20,250 |
| Sep 28, 2016 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm tenant improvement to 2nd fitness central 7 duct smoke detectors, 5 input/output modules, 7 speakers/strobes, 9 strobes. ref pa 2015-1230-6199Details
fire alarm tenant improvement to 2nd fitness central 7 duct smoke detectors, 5 input/output modules, 7 speakers/strobes, 9 strobes. ref pa 2015-1230-6199 | $18,000 |
| Sep 28, 2016 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm tenant improvement to 2nd floor - 2 smoke detectors, 4 duct smoke detectors, 5 speaker/strobes, 1 strobe, 3 input/output modules. ref pa 2015-1230-6195Details
fire alarm tenant improvement to 2nd floor - 2 smoke detectors, 4 duct smoke detectors, 5 speaker/strobes, 1 strobe, 3 input/output modules. ref pa 2015-1230-6195 | $13,000 |
| Sep 7, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm ti 1st and 2nd fl. for childcare center. 5 area smoke detectors, 7 duct detectors, 8 monitor/relays modules, 10 speaker/strobes, 8 strobes ref 201602028584Details
fire alarm ti 1st and 2nd fl. for childcare center. 5 area smoke detectors, 7 duct detectors, 8 monitor/relays modules, 10 speaker/strobes, 8 strobes ref 201602028584 | $26,000 |
| Aug 24, 2016 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Turner Construction Co | revision t0 (e) ti permit to add interior clerestory windows at internal offices on the 9th floor. scope of work limited to gyp board demo, modification of partition framing for (n) window locations patching/finishes (no scope of structural/mep/fire life safety) rev 2013-1218-4509Details
revision t0 (e) ti permit to add interior clerestory windows at internal offices on the 9th floor. scope of work limited to gyp board demo, modification of partition framing for (n) window locations patching/finishes (no scope of structural/mep/fire life safety) rev 2013-1218-4509 | $10,000 |
| Aug 19, 2016 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | admin permit to document planning's change of use from b office use on 1329sf g/f suite 1400, 1401 & 1402 to retail/sale & service (limited restaurant) for pa 201312204741Details
admin permit to document planning's change of use from b office use on 1329sf g/f suite 1400, 1401 & 1402 to retail/sale & service (limited restaurant) for pa 201312204741 | |
| Aug 19, 2016 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | 7/f- full floor fire alarm t.i. 23 duct smoke detectors with relay, 20 speaker/strobes, 2 strobes, 5 input/output modules. arch t.i. pa# 201512316241 & mep ref pa 201602018528Details
7/f- full floor fire alarm t.i. 23 duct smoke detectors with relay, 20 speaker/strobes, 2 strobes, 5 input/output modules. arch t.i. pa# 201512316241 & mep ref pa 201602018528 | $45,000 |
| Aug 19, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Johnson Controls Fire | 6/f- full floor fire alarm t.i. 1 smoke detector, 23 duct smoke detectors with relay, 6 input/output modules, 20 speaker/strobes, 9 strobes. t.i. arch pa# 201512316239 & mep pa# 201601157250Details
6/f- full floor fire alarm t.i. 1 smoke detector, 23 duct smoke detectors with relay, 6 input/output modules, 20 speaker/strobes, 9 strobes. t.i. arch pa# 201512316239 & mep pa# 201601157250 | $45,000 |
| Aug 18, 2016 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | Turner Construction Co | 20th floor: demolition of entire tenant suite: non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limited to temp. egress lighting, new outlets and patching of extg gyp board.Details
20th floor: demolition of entire tenant suite: non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limited to temp. egress lighting, new outlets and patching of extg gyp board. | $150,000 |
| Aug 18, 2016 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | Turner Construction Co | 5th floor: demolition of partial 5th floor including non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limited to temp. egress lighting, new outlets and patching of extg gyp board.Details
5th floor: demolition of partial 5th floor including non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limited to temp. egress lighting, new outlets and patching of extg gyp board. | $75,000 |
| Aug 18, 2016 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | Turner Construction Co | 4th floor: demolition of entire t.i. : non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limitted to temp. egress lighting, new outlets and patching of extg gyp bd.Details
4th floor: demolition of entire t.i. : non structural partiitons, electrical, mechanical, plmg, ceiling, lighting and finishes. extg fire sprinkler to remain. minor new scope limitted to temp. egress lighting, new outlets and patching of extg gyp bd. | $150,000 |
| Aug 12, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Fire System Solutions Inc | 1st floor - install hood & duct fire suppression system. ref pa 201602028584.Details
1st floor - install hood & duct fire suppression system. ref pa 201602028584. | $1,000 |
| Aug 11, 2016 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 2nd floor: extg fire sprinkler system. t.i. 38 relocated sprinkler and 6 added. app# 201512306199. n/a for maherDetails
2nd floor: extg fire sprinkler system. t.i. 38 relocated sprinkler and 6 added. app# 201512306199. n/a for maher | $22,000 |
| Aug 11, 2016 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 6/f & 7/f- existing fire sprinkler system, relocate 279 sprinklers & add 18 sprinklers. 6/f t.i. pa#201512316239, 7/f t.i. pa#201512316241Details
6/f & 7/f- existing fire sprinkler system, relocate 279 sprinklers & add 18 sprinklers. 6/f t.i. pa#201512316239, 7/f t.i. pa#201512316241 | $60,000 |
| Aug 11, 2016 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 2nd floor: extg fire sprinkler system. t.i. 45 relocated sprinkler and 9 added sprinklers. app# 201512306195 n/a for maherDetails
2nd floor: extg fire sprinkler system. t.i. 45 relocated sprinkler and 9 added sprinklers. app# 201512306195 n/a for maher | $27,000 |
| Aug 11, 2016 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 1st and 2nd floor: extg fire sprinkler system. t.i. 60 relocated sprinklers. add 24 sprinklers. t.i. 201602028584Details
1st and 2nd floor: extg fire sprinkler system. t.i. 60 relocated sprinklers. add 24 sprinklers. t.i. 201602028584 | $17,000 |
| Jul 1, 2016 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | partial 2nd floor interior ti on multi-tenant floor improvements include partitions, electrical, mechanical, plumbing, ceiling, lighting, finishes, and life safety. no structural scopeDetails
partial 2nd floor interior ti on multi-tenant floor improvements include partitions, electrical, mechanical, plumbing, ceiling, lighting, finishes, and life safety. no structural scope | $894,800 |
| Apr 19, 2016 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | 1st, 2nd & 13th floors: revision to 2013 1220 4741- relocate ground floor security gates & x-ray equipment. change location of demising partitions, reconfigure ground floor vestibule.Details
1st, 2nd & 13th floors: revision to 2013 1220 4741- relocate ground floor security gates & x-ray equipment. change location of demising partitions, reconfigure ground floor vestibule. | |
| Mar 28, 2016 | Never finaled issued Mar 2016, no final | 75 Hawthorne St | Turner Construction Co | evacuation maps for floors 1 and 13Details
evacuation maps for floors 1 and 13 | $1,200 |
| Mar 28, 2016 | Never finaled issued Mar 2016, no final | 75 Hawthorne St | Turner Construction Co | evacuation maps for floors 8 and 9Details
evacuation maps for floors 8 and 9 | $1,200 |
| Mar 10, 2016 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Allied Fire Protection | garage level - replace (e) diesel fire pump with new. replace (e) fire controllers with new. replace (e) diesel fuel tank with new.Details
garage level - replace (e) diesel fire pump with new. replace (e) fire controllers with new. replace (e) diesel fuel tank with new. | $140,000 |
| Mar 8, 2016 | Completed final sign-off Aug 2016 | 75 Hawthorne St | Service West Inc | assemble and install teknion altos (glass) parition walls per floor plans on 9th and 13th floor. reference 9th floor appl# 2013-1218-4509. reference 13th floor per appl# 2013-1220-4741.Details
assemble and install teknion altos (glass) parition walls per floor plans on 9th and 13th floor. reference 9th floor appl# 2013-1218-4509. reference 13th floor per appl# 2013-1220-4741. | $128,474 |
| Feb 2, 2016 | Never finaled issued Jul 2016, no final | 75 Hawthorne St | Turner Construction Co | arch and mep plans with comm kitchen 4 new fsd's 1st and 2nd floors: partial floor t.i. conversion of office space to child care center. selective non-structural demolition, new partitons and finishes. close off and abandon 1 existing stair.Details
arch and mep plans with comm kitchen 4 new fsd's 1st and 2nd floors: partial floor t.i. conversion of office space to child care center. selective non-structural demolition, new partitons and finishes. close off and abandon 1 existing stair. | $880,000 |
| Feb 1, 2016 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | 7th/8th floor: partial floor ti, ref pa 2015-1231-6241: mep work. sep permits for fire/life safety/restrooms/elevator lobby/arch.Details
7th/8th floor: partial floor ti, ref pa 2015-1231-6241: mep work. sep permits for fire/life safety/restrooms/elevator lobby/arch. | $800,000 |
| Jan 15, 2016 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | 6th floor: partial floor t.i. for mep scope of work. seperate permit: fire sprinkler, fire, life safty, resterooms, elvator lobby, architectural t.i. ab 060 compliant, adding fsd's through rated walls.Details
6th floor: partial floor t.i. for mep scope of work. seperate permit: fire sprinkler, fire, life safty, resterooms, elvator lobby, architectural t.i. ab 060 compliant, adding fsd's through rated walls. | $800,000 |
| Dec 31, 2015 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | full floor ti: selective non-structural demolition; new partitions, finishes, minor structural bracing, ceiling, secondary restrooms. under separate permits: mep, fire sprinkler, fire life safety, core restrooms, elevator lobby. ab060 for idf room, controlled access egress and locked elevator lobbyDetails
full floor ti: selective non-structural demolition; new partitions, finishes, minor structural bracing, ceiling, secondary restrooms. under separate permits: mep, fire sprinkler, fire life safety, core restrooms, elevator lobby. ab060 for idf room, controlled access egress and locked elevator lobby | $996,000 |
| Dec 31, 2015 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | full floor ti: selective non-structural demolition; new partitions, finishes, minor structural bracing, ceiling, secondary restrooms. under separate permits: mep, fire sprinkler, fire life safety, core restrooms, elevator lobby.Details
full floor ti: selective non-structural demolition; new partitions, finishes, minor structural bracing, ceiling, secondary restrooms. under separate permits: mep, fire sprinkler, fire life safety, core restrooms, elevator lobby. | $996,000 |
| Dec 30, 2015 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | 2nd floor suite 2500: partial floor t.i. selective non-structural demo, new partitions, finishes, mep, ceilings, lighting, under seperate permits: fire sprinklers, fire life safety, restrooms,& elevator lobby.Details
2nd floor suite 2500: partial floor t.i. selective non-structural demo, new partitions, finishes, mep, ceilings, lighting, under seperate permits: fire sprinklers, fire life safety, restrooms,& elevator lobby. | $318,900 |
| Dec 30, 2015 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | 2nd floor suite 2400: partial floor t.i. selective non-structural demo, new partitions,minor structural, finishes, mep, ceilings, lighting. under seperate permits: fire sprinklers, fire life safety, restrooms,& elevator lobby.Details
2nd floor suite 2400: partial floor t.i. selective non-structural demo, new partitions,minor structural, finishes, mep, ceilings, lighting. under seperate permits: fire sprinklers, fire life safety, restrooms,& elevator lobby. | $833,400 |
| Dec 1, 2015 | Never finaled issued Dec 2015, no final | 75 Hawthorne St | street spaceDetails
street space | ||
| Nov 5, 2015 | Never finaled issued Nov 2015, no final | 75 Hawthorne St | sidewalk permitDetails
sidewalk permit | ||
| Oct 28, 2015 | Never finaled issued Oct 2015, no final | 75 Hawthorne St | street space permit - m622907Details
street space permit - m622907 | ||
| Oct 22, 2015 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | 1st, 2nd,13th fls: fire alarm t.i. 13 pull stations, 21 smoke detectors, 1 heat detector, 72 duct detectors, 17 monitor modules, 71 relay modules, 72 speaker strobes, 15 strobes. ref app#201312204741Details
1st, 2nd,13th fls: fire alarm t.i. 13 pull stations, 21 smoke detectors, 1 heat detector, 72 duct detectors, 17 monitor modules, 71 relay modules, 72 speaker strobes, 15 strobes. ref app#201312204741 | $165,000 |
| Oct 16, 2015 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm t.i. to floors 8 & 9 - 8 pull stations, 19 smoke detectors, 28 in-duct smokes, 45 duct mounted smoke, 9 monitor modules, 57 input/output modules, 4 relays, 27 isolation relays, 72 speaker/strobes, 29 strobes. t.i. pa#201312184509Details
fire alarm t.i. to floors 8 & 9 - 8 pull stations, 19 smoke detectors, 28 in-duct smokes, 45 duct mounted smoke, 9 monitor modules, 57 input/output modules, 4 relays, 27 isolation relays, 72 speaker/strobes, 29 strobes. t.i. pa#201312184509 | $86,000 |
| Oct 7, 2015 | Never finaled issued Oct 2015, no final | 75 Hawthorne St | Advanced Installation Services Llc | assemble and install teknion altos (glass) parition walls per floor plans. reference bpa# 2013-1218-4504.Details
assemble and install teknion altos (glass) parition walls per floor plans. reference bpa# 2013-1218-4504. | $528,040 |
| Sep 17, 2015 | Never finaled issued Sep 2015, no final | 75 Hawthorne St | street spaceDetails
street space | ||
| Sep 1, 2015 | Completed final sign-off Sep 2015 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | relocate (e) fire dept +/- 5' connection for new location of ada ramp ref pa 2013 0204 9444Details
relocate (e) fire dept +/- 5' connection for new location of ada ramp ref pa 2013 0204 9444 | $7,500 |
| Aug 18, 2015 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | structural strengthening of one rail supporting a bldg maintenance unit on the roof. repair in kind.Details
structural strengthening of one rail supporting a bldg maintenance unit on the roof. repair in kind. | $6,078 |
| Aug 13, 2015 | Never finaled issued Aug 2015, no final | 75 Hawthorne St | street space permitDetails
street space permit | ||
| Jul 30, 2015 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Turner Construction Co | evacuation signs for floors 17, 18, and 19Details
evacuation signs for floors 17, 18, and 19 | $8,866 |
| Apr 23, 2015 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm tenant improvement to floor 17,18,19. 9 pull stations, 21 smoke detectors, 22 in-duct detectors, 61 duct mounted detectors, 13 monitor modules, 5 relay modules, 82 speaker/strobes, 45 strobes, 40 isolation relays. ref #201312184504Details
fire alarm tenant improvement to floor 17,18,19. 9 pull stations, 21 smoke detectors, 22 in-duct detectors, 61 duct mounted detectors, 13 monitor modules, 5 relay modules, 82 speaker/strobes, 45 strobes, 40 isolation relays. ref #201312184504 | $130,000 |
| Apr 22, 2015 | Completed final sign-off Jun 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 1st/2nd/13th flrs: fire sprinkers-1st flr; relocate 174, add 19. 2nd flr; relocate 136, add 1. 13th flr; relocate 117, add 5- canopy in first floor corridoor separate permit ref pa# 2013 12204741Details
1st/2nd/13th flrs: fire sprinkers-1st flr; relocate 174, add 19. 2nd flr; relocate 136, add 1. 13th flr; relocate 117, add 5- canopy in first floor corridoor separate permit ref pa# 2013 12204741 | $232,610 |
| Apr 8, 2015 | Never finaled issued Apr 2015, no final | 75 Hawthorne St | Service West Inc | 14, 15 & 16th flrs: install of teknion altos arch wall. tenant furniture walls. ref pa # 2013 1218 4503Details
14, 15 & 16th flrs: install of teknion altos arch wall. tenant furniture walls. ref pa # 2013 1218 4503 | $600,000 |
| Mar 23, 2015 | Never finaled issued Apr 2015, no final | 75 Hawthorne St | Turner Construction Co | 14, 15 & 16th flrs: evacuation mapsDetails
14, 15 & 16th flrs: evacuation maps | $3,089 |
| Feb 18, 2015 | Expired or cancelled cancelled Sep 2023 | 75 Hawthorne St | Turner Construction Co | revision to app#201411060920. sizing of maps changed for floors 3,10,11, & 12 (evac sign)Details
revision to app#201411060920. sizing of maps changed for floors 3,10,11, & 12 (evac sign) | |
| Nov 18, 2014 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm tenant improv to 14 ,15, 16 fl. 9 pull stations,22 smokes, 22 in-duct smokes,62 duct mounted smokes, 15 monitor modules,46 relays,61 input/output modules, 87 speaker/strobes,51 strobes.Details
fire alarm tenant improv to 14 ,15, 16 fl. 9 pull stations,22 smokes, 22 in-duct smokes,62 duct mounted smokes, 15 monitor modules,46 relays,61 input/output modules, 87 speaker/strobes,51 strobes. | $165,000 |
| Nov 13, 2014 | Never finaled issued Nov 2014, no final | 75 Hawthorne St | Service West Inc | 10th floor: install 455 lft of teknion altos architectural wall. n/a for the interim. reference ti 201312113944Details
10th floor: install 455 lft of teknion altos architectural wall. n/a for the interim. reference ti 201312113944 | $175,000 |
| Nov 6, 2014 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Turner Construction Co | evacuation signs floors 3,10,11, & 12 for a total of 15 signs. n/a for interimDetails
evacuation signs floors 3,10,11, & 12 for a total of 15 signs. n/a for interim | $4,119 |
| Nov 4, 2014 | Never finaled issued Aug 2015, no final | 75 Hawthorne St | Turner Construction Co | administratie permit for the purpose of documentation of swing up grab bar installed on the 12th fl mens room. reasonable accomodation requestDetails
administratie permit for the purpose of documentation of swing up grab bar installed on the 12th fl mens room. reasonable accomodation request | |
| Oct 22, 2014 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm improvements to floors: sub cellar, cellar, 4,5,6,7,20,21, penthouse. 54 pull stations, 37 smokes, 1 heat, 21 duct detectors, 33 monitor modules, 52 relays, 66 spk/strobe.ref pa#201304245357 & 201305136719.Details
fire alarm improvements to floors: sub cellar, cellar, 4,5,6,7,20,21, penthouse. 54 pull stations, 37 smokes, 1 heat, 21 duct detectors, 33 monitor modules, 52 relays, 66 spk/strobe.ref pa#201304245357 & 201305136719. | $130,000 |
| Sep 25, 2014 | Completed final sign-off Oct 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | permit 201312194647; 4th flr-7 hds relocated, 6th flr, 7 hhds relocated, 7th 7 relocated, 20th 4 relocated, total hds 25x514.62 =12,000Details
permit 201312194647; 4th flr-7 hds relocated, 6th flr, 7 hhds relocated, 7th 7 relocated, 20th 4 relocated, total hds 25x514.62 =12,000 | $12,900 |
| Sep 16, 2014 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 8th fl: relocate 163 heads, add 10, total 173 9th fl: relocate 157 heads, add 8, total 165. ref ti permit 2013-1218-4509.Details
8th fl: relocate 163 heads, add 10, total 173 9th fl: relocate 157 heads, add 8, total 165. ref ti permit 2013-1218-4509. | $174,000 |
| Sep 3, 2014 | Completed final sign-off Sep 2015 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 17th, 18th,19th floors to (e) sprinkler t.i: 17th floor: relocated spinkler 118 and added sprinkler 6 total 124. 18th floor: relocated sprinkler 113, added sprinkler 6, total sprinkler 119. 19th floor: relocated sprinkler 114, added 4 total sprinkler 118.Details
17th, 18th,19th floors to (e) sprinkler t.i: 17th floor: relocated spinkler 118 and added sprinkler 6 total 124. 18th floor: relocated sprinkler 113, added sprinkler 6, total sprinkler 119. 19th floor: relocated sprinkler 114, added 4 total sprinkler 118. | $185,800 |
| Aug 26, 2014 | Never finaled issued Aug 2015, no final | 75 Hawthorne St | Turner Construction Co | document smoke control sequence for building. no work to be done for this application.Details
document smoke control sequence for building. no work to be done for this application. | |
| Aug 18, 2014 | Completed final sign-off Apr 2015 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | ref. 201312184503,fire sprinkler t.i. 14th flr, relocate 119 add 5, 15th flr relocate 122, add 4, 16th flr, relocate 114, add 6Details
ref. 201312184503,fire sprinkler t.i. 14th flr, relocate 119 add 5, 15th flr relocate 122, add 4, 16th flr, relocate 114, add 6 | $190,410 |
| Aug 12, 2014 | Completed final sign-off Nov 2014 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 3f/10f: 3rd (t.i. 201312113943)relocate 156, added 19, 10th flr (201312113944) relocate 93, add 24 total 117Details
3f/10f: 3rd (t.i. 201312113943)relocate 156, added 19, 10th flr (201312113944) relocate 93, add 24 total 117 | $150,300 |
| Aug 4, 2014 | Completed final sign-off Nov 2014 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | flrs: 11 & 12; (11th flr- added hds 41, relocate 129, includes pre-action suppression system in room server room 11111. ref app 201312204752 12th flr- added 33, relocated 106. ref app 201312113947Details
flrs: 11 & 12; (11th flr- added hds 41, relocate 129, includes pre-action suppression system in room server room 11111. ref app 201312204752 12th flr- added 33, relocated 106. ref app 201312113947 | $160,000 |
| Jul 29, 2014 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | fire alarm t.i. to floors 2,3,8-19 to include (172) smoke detectors, (79) pull stations, (107) monitor modules, (137) speaker strobes, (182) strobes, (12) speakers, (51) ff phone jacks, (256) duct detectors, (39) in-duc detectors, (37) relay modules, per t.i./c2 scope. ref 201312204741.Details
fire alarm t.i. to floors 2,3,8-19 to include (172) smoke detectors, (79) pull stations, (107) monitor modules, (137) speaker strobes, (182) strobes, (12) speakers, (51) ff phone jacks, (256) duct detectors, (39) in-duc detectors, (37) relay modules, per t.i./c2 scope. ref 201312204741. | $575,000 |
| Jul 24, 2014 | Completed final sign-off Nov 2014 | 75 Hawthorne St | Intelligent Technologies & Services Inc | 11th floor:provide detection and bell for 11th floor server/telecom room pre-action system. pre action panel was installed under sprinkler permit pa # 2014-08-04-2884 ref app#201312204752Details
11th floor:provide detection and bell for 11th floor server/telecom room pre-action system. pre action panel was installed under sprinkler permit pa # 2014-08-04-2884 ref app#201312204752 | $15,500 |
| Jun 2, 2014 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Johnson Controls Fire | voluntary fire alarm system upgrade:1facp w/battery cabinet 10 transponders, 22 booster panels, 1 led annunciator, 1 fan/damper panel, 170 smokes, 79 manual pull box, 90 monitor module, 137 speaker/strobe, 12 wall speakers, 51 phone jacks, 12 phone handsets.Details
voluntary fire alarm system upgrade:1facp w/battery cabinet 10 transponders, 22 booster panels, 1 led annunciator, 1 fan/damper panel, 170 smokes, 79 manual pull box, 90 monitor module, 137 speaker/strobe, 12 wall speakers, 51 phone jacks, 12 phone handsets. | $350,000 |
| Mar 14, 2014 | Completed final sign-off Apr 2014 | 75 Hawthorne St | Johnson Controls Fire | fire alarm t.i. to 2/f, 4/f, 6/f: add 8 speaker/strobes.Details
fire alarm t.i. to 2/f, 4/f, 6/f: add 8 speaker/strobes. | $5,000 |
| Feb 10, 2014 | Completed final sign-off Mar 2014 | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | 2nd floor: fire sprinkler t.i. relocate 89 sprinklers. ref app#201307302112. n/a for interim controls # 428-13Details
2nd floor: fire sprinkler t.i. relocate 89 sprinklers. ref app#201307302112. n/a for interim controls # 428-13 | $44,500 |
| Feb 10, 2014 | Never finaled issued Feb 2014, no final | 75 Hawthorne St | Anderson, Rowe & Buckley, Inc. | cellar/sub cellar 16,18,21st floor: sub cellar add 4 heads, cellar add 11 /remove 8. ref app#201307303112. interim controls market street #428-13 total 17 sprinklers under this scope of work.Details
cellar/sub cellar 16,18,21st floor: sub cellar add 4 heads, cellar add 11 /remove 8. ref app#201307303112. interim controls market street #428-13 total 17 sprinklers under this scope of work. | $8,500 |
| Dec 20, 2013 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | full 1st&13/fl ti.partial 2/fl ti. restroom fully upgraded. mep,sprinkler,fire alarm & ti on separate permit. accessory child care use on grd fl. interim controls - market street & soma: permit for structural or architectural work above ground floor.Details
full 1st&13/fl ti.partial 2/fl ti. restroom fully upgraded. mep,sprinkler,fire alarm & ti on separate permit. accessory child care use on grd fl. interim controls - market street & soma: permit for structural or architectural work above ground floor. | $9,498,301 |
| Dec 20, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | full 11th floor t.i. selective demo, partitions, mep. structural limited to server room. sprinklers & fire alarm on separate permit. interim controls - market street & soma: permit for structural or architectural work above ground floor.Details
full 11th floor t.i. selective demo, partitions, mep. structural limited to server room. sprinklers & fire alarm on separate permit. interim controls - market street & soma: permit for structural or architectural work above ground floor. | $1,898,641 |
| Dec 19, 2013 | Completed final sign-off Feb 2017 | 75 Hawthorne St | Turner Construction Co | elevator lobby and restroom modification on 4th, 5th, 7th floor. restroom modification on 20th only. mep included fire alarm and sprinkler on separate permitDetails
elevator lobby and restroom modification on 4th, 5th, 7th floor. restroom modification on 20th only. mep included fire alarm and sprinkler on separate permit | $148,108 |
| Dec 18, 2013 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | floors 1-20. stair upgrade. provide new lighting in stairwell for each floors 1-20. new striping & painting.Details
floors 1-20. stair upgrade. provide new lighting in stairwell for each floors 1-20. new striping & painting. | $416,053 |
| Dec 18, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | 17/f, 18/f & 19/f full tenant improvement, selective demo, partitions, structural & mep, remodel restroom, fire alarm & sprinklers on separate permitDetails
17/f, 18/f & 19/f full tenant improvement, selective demo, partitions, structural & mep, remodel restroom, fire alarm & sprinklers on separate permit | $5,687,824 |
| Dec 18, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | full floor tenant improvement for 14th, 15th & 16th floor. selective demo, partitions, structural, mep, restrooms to be fully upgraded. fire alarm & sprinklers under separate permit.Details
full floor tenant improvement for 14th, 15th & 16th floor. selective demo, partitions, structural, mep, restrooms to be fully upgraded. fire alarm & sprinklers under separate permit. | $5,687,824 |
| Dec 18, 2013 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | 8th & 9th tenant improvement. selective demo, partitions, structural, mep, restrooms fully upgraded. fire alarm & sprinklers under separate permit.Details
8th & 9th tenant improvement. selective demo, partitions, structural, mep, restrooms fully upgraded. fire alarm & sprinklers under separate permit. | $3,791,882 |
| Dec 11, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | 3rd floor t.i. to an existing office space. includes selective demo, new partitons, structural and mep. f/a and sprinkler under separate permit.Details
3rd floor t.i. to an existing office space. includes selective demo, new partitons, structural and mep. f/a and sprinkler under separate permit. | $1,718,719 |
| Dec 11, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | 10th floor t.i. to existing office space. work to include selective demo, new partitions, structural and mep. f/a and sprinkler under separate permit.Details
10th floor t.i. to existing office space. work to include selective demo, new partitions, structural and mep. f/a and sprinkler under separate permit. | $1,718,719 |
| Dec 11, 2013 | Completed final sign-off Jan 2017 | 75 Hawthorne St | Turner Construction Co | riser floor penetration work to include providing floor cores and openings for future building infrastructure serving tenant and base building serivces.relocation of door at fire control room for future upgrades upgrade floor restrooms.Details
riser floor penetration work to include providing floor cores and openings for future building infrastructure serving tenant and base building serivces.relocation of door at fire control room for future upgrades upgrade floor restrooms. | $164,000 |
| Dec 11, 2013 | Completed final sign-off Nov 2016 | 75 Hawthorne St | Turner Construction Co | 12th floor t.i. to an existing office space. includes selective demo, new partitons, structural and mep. f/a and sprinkler under separate permit.Details
12th floor t.i. to an existing office space. includes selective demo, new partitons, structural and mep. f/a and sprinkler under separate permit. | $1,718,719 |
| Oct 9, 2013 | Completed final sign-off Dec 2014 | 75 Hawthorne St | Turner Construction Co | interior non structural demolition on the 3rd fl. all work to comply with abo17Details
interior non structural demolition on the 3rd fl. all work to comply with abo17 | $30,000 |
| Jul 30, 2013 | Completed final sign-off Jun 2014 | 75 Hawthorne St | Turner Construction Co | 2nd/4th/6th floors-repair/refreshing of finishes, revise millwork for elective barrier removal; add card readers at elected doors.Details
2nd/4th/6th floors-repair/refreshing of finishes, revise millwork for elective barrier removal; add card readers at elected doors. | $15,000 |
| May 13, 2013 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Turner Construction Co | installation of new bms control system infastructure. install new chiller, boiler, cooling tower and associated equipment at the roof penthouse, 16th and 18th flr. structural and mep work only.Details
installation of new bms control system infastructure. install new chiller, boiler, cooling tower and associated equipment at the roof penthouse, 16th and 18th flr. structural and mep work only. | $2,994,092 |
| May 13, 2013 | Never finaled issued Nov 2013, no final | 75 Hawthorne St | Turner Construction Co | new generator on penthouse roof & new disel fuel storage tank in sib-celler rated shafts for fuel lines. provide new roof hatch with access ladder and new guard rail at penthouse roof.Details
new generator on penthouse roof & new disel fuel storage tank in sib-celler rated shafts for fuel lines. provide new roof hatch with access ladder and new guard rail at penthouse roof. | $866,716 |
| Apr 24, 2013 | Completed final sign-off Jan 2017 | 75 Hawthorne St | cellar level partial floor t.i. -selective demolition, modification of storage room, new bike storage & roll-up garage door replacement, cooling units, concrete pads & rated shaft for cooling units.Details
cellar level partial floor t.i. -selective demolition, modification of storage room, new bike storage & roll-up garage door replacement, cooling units, concrete pads & rated shaft for cooling units. | $525,000 | |
| Apr 24, 2013 | Completed final sign-off Dec 2016 | 75 Hawthorne St | Turner Construction Co | existing loading dock improvements including selective demolitoin, paritions, electrical, ceiling & finishes.Details
existing loading dock improvements including selective demolitoin, paritions, electrical, ceiling & finishes. | $60,000 |
| Apr 12, 2013 | Completed final sign-off Jul 2013 | 75 Hawthorne St | Simplexgrinnell Lp. | 5th floor: t.i. fire alarm system consist of adding one smoke detector, 9 duct detectors, 9 test switches, 24 speaker/strobes, 1 relay alarm, 9 monitor zam and 3 relays.Details
5th floor: t.i. fire alarm system consist of adding one smoke detector, 9 duct detectors, 9 test switches, 24 speaker/strobes, 1 relay alarm, 9 monitor zam and 3 relays. | $32,000 |
| Apr 2, 2013 | Never finaled issued Nov 2013, no final | 75 Hawthorne St | Turner Construction Co | structural floor strengthening for future storage and high density floor loads. restroom modifications at 3rd floor including accessible compliant layout, new plumbing fixtures, lighting and finishes. partial foor strengthening on floors-1,2,3,8,11,& 13.Details
structural floor strengthening for future storage and high density floor loads. restroom modifications at 3rd floor including accessible compliant layout, new plumbing fixtures, lighting and finishes. partial foor strengthening on floors-1,2,3,8,11,& 13. | $306,927 |
| Mar 21, 2013 | Completed final sign-off May 2013 | 75 Hawthorne St | Pribuss Engineering Inc | add 27 fire sprinklers. relocate 37 fire sprinklers. relocate & c.d 54 fire sprinklers. change out 7 fire sprinkers. t.i ref pa# 201302120052Details
add 27 fire sprinklers. relocate 37 fire sprinklers. relocate & c.d 54 fire sprinklers. change out 7 fire sprinkers. t.i ref pa# 201302120052 | $64,328 |
| Feb 28, 2013 | Never finaled issued Feb 2013, no final | 75 Hawthorne St | street spaceDetails
street space | ||
| Feb 15, 2013 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | Turner Construction Co | structural only - 6th floor, elective structural strengthening. increase shear capacity b/w girder & column at 2 locations.Details
structural only - 6th floor, elective structural strengthening. increase shear capacity b/w girder & column at 2 locations. | $3,000 |
| Feb 14, 2013 | Completed final sign-off Jul 2013 | 75 Hawthorne St | Turner Construction Co | mep for 5th fl ti for partial floor. architectural under pa#2013-02-12-0052.Details
mep for 5th fl ti for partial floor. architectural under pa#2013-02-12-0052. | $10,000 |
| Feb 12, 2013 | Completed final sign-off Jul 2013 | 75 Hawthorne St | Turner Construction Co | 5th floor-partial 5th floor tenant improvement-restroom upgrades, new partitions & finishes. minor structural work limited to server room & restrooms. new bollards in cellar level. m.e.p, sprinkler, fire alarm on seperate permitsDetails
5th floor-partial 5th floor tenant improvement-restroom upgrades, new partitions & finishes. minor structural work limited to server room & restrooms. new bollards in cellar level. m.e.p, sprinkler, fire alarm on seperate permits | $235,000 |
| Feb 4, 2013 | Never finaled issued Feb 2013, no final | 75 Hawthorne St | Turner Construction Co | assessibility improvements related to path of travel-including parking re-stripping, parking signage, elevator signage, exterior ramp. ramp & stair handrails & stair nosing. relocate fdc as needed for ramp modificationsDetails
assessibility improvements related to path of travel-including parking re-stripping, parking signage, elevator signage, exterior ramp. ramp & stair handrails & stair nosing. relocate fdc as needed for ramp modifications | $108,000 |
| Jan 23, 2013 | Completed final sign-off Apr 2013 | 75 Hawthorne St | Turner Construction Co | 5th floor-demolition of non structural interior elements for 1 tenant suite & demo of building common restrooms, comply with ab-017- mep, construction, mep, sprinklers and fire alarm, electrical separate permitDetails
5th floor-demolition of non structural interior elements for 1 tenant suite & demo of building common restrooms, comply with ab-017- mep, construction, mep, sprinklers and fire alarm, electrical separate permit | $30,000 |
| Feb 24, 2011 | Never finaled issued Dec 2011, no final | 75 Hawthorne St | Metropolitan Electrical Construction | installation of e-911 antenna as required by fcc.Details
installation of e-911 antenna as required by fcc. | $5,000 |
| Jul 6, 2010 | Completed final sign-off Aug 2010 | 75 Hawthorne St | Novo Construction Inc | interior non load bearing partition demolition at fifth floor only.Details
interior non load bearing partition demolition at fifth floor only. | $800 |
| Jun 17, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | Simplex Grinnell | 5th floor-install 13 speakers/strobes, 2 strobes and 2 duct detectorsDetails
5th floor-install 13 speakers/strobes, 2 strobes and 2 duct detectors | $20,000 |
| Apr 30, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | R L H Fire Protection Inc | t.i. on (e) fire sprinkler system. relocate 19 heads, add 20 heads.Details
t.i. on (e) fire sprinkler system. relocate 19 heads, add 20 heads. | $8,000 |
| Apr 24, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | 5th floor: m.e.p. drawings - (n) hvac piping, (n) fan, (n) a/c, (n) van boxes, (n) fire smoke dampers. ref. arch drawings 200803268020.Details
5th floor: m.e.p. drawings - (n) hvac piping, (n) fan, (n) a/c, (n) van boxes, (n) fire smoke dampers. ref. arch drawings 200803268020. | $225,000 | |
| Mar 26, 2008 | Expired or cancelled cancelled Jan 2026 | 75 Hawthorne St | 5th floor-revision to structural pa# 2008-0118-2844, 2008-0118-2842-change in the way we are connecting the bridge between the buildingsDetails
5th floor-revision to structural pa# 2008-0118-2844, 2008-0118-2842-change in the way we are connecting the bridge between the buildings | ||
| Mar 26, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | 5th floor-t.i. including building ceiling height partitions, new doors with side lights and ceiling grid, tile and lights. mep & sprinkler under seperate permitDetails
5th floor-t.i. including building ceiling height partitions, new doors with side lights and ceiling grid, tile and lights. mep & sprinkler under seperate permit | $150,000 | |
| Feb 13, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | Simplex Grinnell | add 2 new smoke detectors and 1 door holdes. all devices will be tied into existing system.Details
add 2 new smoke detectors and 1 door holdes. all devices will be tied into existing system. | $2,600 |
| Jan 18, 2008 | Completed final sign-off Jan 2009 | 75 Hawthorne St | 5th floor: create a demising wall in office tenant tenant space. add rated corridors, restroom upgrades, construction of passage way to 95 hawthorne st, 5th floor. lighting, mech 200801182842Details
5th floor: create a demising wall in office tenant tenant space. add rated corridors, restroom upgrades, construction of passage way to 95 hawthorne st, 5th floor. lighting, mech 200801182842 | $80,000 | |
| Jan 18, 2008 | Never finaled issued Jan 2008, no final | 75 Hawthorne St | R L H Fire Protection Inc | 5th floor - t.i. upgrade on the (e) fire sprinkler, for us passport office, relocate 13 heads for coverage. calc's done as a voluntery pre-caution..... double k factorDetails
5th floor - t.i. upgrade on the (e) fire sprinkler, for us passport office, relocate 13 heads for coverage. calc's done as a voluntery pre-caution..... double k factor | $2,600 |
| Dec 18, 2007 | Completed final sign-off Feb 2008 | 75 Hawthorne St | Plant Construction Company Lp | revision to pa# 2007/11/30/9344. re-construct a portion of an ex. non-structural 4-hr perimeter wall on the 3rd, 4th and 5th floors.Details
revision to pa# 2007/11/30/9344. re-construct a portion of an ex. non-structural 4-hr perimeter wall on the 3rd, 4th and 5th floors. | $30,000 |
| Oct 23, 2007 | Completed final sign-off Feb 2008 | 75 Hawthorne St | R L H Fire Protection Inc | ti upgrade on (e) fire sprinkler system for "certain software" on 3rd floor, relocate 10 heads.Details
ti upgrade on (e) fire sprinkler system for "certain software" on 3rd floor, relocate 10 heads. | $2,000 |
| Oct 12, 2007 | Completed final sign-off Feb 2008 | 75 Hawthorne St | Simplex Grinnell | fire alarm addition/ 3rd floor,13 wall strobes,8 spkr/strobes,remove and replace 1 strobeDetails
fire alarm addition/ 3rd floor,13 wall strobes,8 spkr/strobes,remove and replace 1 strobe | $6,500 |
| Oct 9, 2007 | Completed final sign-off Feb 2008 | 75 Hawthorne St | Plant Construction Company Lp | 3rd floor - t.i. to office spaces: included adding offices for demonstration, stroage, bread etc. demo. mechanical, electrical included. fire sprinkler, life safety under seperate permit. no increase in office space. no exterior modifications to building.Details
3rd floor - t.i. to office spaces: included adding offices for demonstration, stroage, bread etc. demo. mechanical, electrical included. fire sprinkler, life safety under seperate permit. no increase in office space. no exterior modifications to building. | $150,000 |
| Jul 26, 2007 | Completed final sign-off Dec 2007 | 75 Hawthorne St | oti-1 grnd fl, lsDetails
oti-1 grnd fl, ls | $9,500 | |
| Jun 21, 2007 | Completed final sign-off Dec 2007 | 75 Hawthorne St | Plant Construction Company Lp | voluntary seismic strengthening of 1st floor columns. no increase in office space, no exterior modifications to buildingDetails
voluntary seismic strengthening of 1st floor columns. no increase in office space, no exterior modifications to building | $125,000 |
| Jul 13, 2006 | Never finaled issued Aug 2006, no final | 75 Hawthorne St | Novo Construction Inc | suite #2001 - demising (e) single floor tenant space into 2 seperate spaces. creating 1 hr. fire rated corridor with new partitions, ceilings, lighting & finishes. mep under seperate permit-design/build.Details
suite #2001 - demising (e) single floor tenant space into 2 seperate spaces. creating 1 hr. fire rated corridor with new partitions, ceilings, lighting & finishes. mep under seperate permit-design/build. | $50,000 |
| Jun 20, 2006 | Completed final sign-off Aug 2006 | 75 Hawthorne St | Novo Construction Inc | imporved portion of single flr tenant space inclues enlaring conferencde room, revised kitchen, and updated finishes, oti-1, 20th fl-el, me,lsDetails
imporved portion of single flr tenant space inclues enlaring conferencde room, revised kitchen, and updated finishes, oti-1, 20th fl-el, me,ls | $85,176 |
| Apr 25, 2006 | Expired or cancelled cancelled Mar 2007 | 75 Hawthorne St | oti-1 ground floor, el, mech, ls, sp update egress and ada requirements at conference rooms. ground floorDetails
oti-1 ground floor, el, mech, ls, sp update egress and ada requirements at conference rooms. ground floor | $21,600 | |
| Jun 17, 2004 | Completed final sign-off Jul 2004 | 75 Hawthorne St | Rudolph Commercial Interiors Inc, Rci | alterations to permit removal of 1 of 2 garage doors (see ps.1) w endorsement of both architect andDetails
alterations to permit removal of 1 of 2 garage doors (see ps.1) w endorsement of both architect and | |
| Dec 16, 2003 | Never finaled issued Dec 2003, no final | 75 Hawthorne St | street spaceDetails
street space | ||
| Nov 12, 2003 | Never finaled issued Nov 2003, no final | 75 Hawthorne St | street spaceDetails
street space | ||
| Oct 29, 2003 | Completed final sign-off Jul 2004 | 75 Hawthorne St | Rudolph Commercial Interiors Inc, Rci | barrier removal-upgrade (1) men's & (1) women's restroom, upgrade entrance exit doors to currrentDetails
barrier removal-upgrade (1) men's & (1) women's restroom, upgrade entrance exit doors to currrent | $85,600 |
| Aug 6, 2002 | Completed final sign-off Aug 2002 | 75 Hawthorne St | change asphalt to concrete/revision to app #200105048417Details
change asphalt to concrete/revision to app #200105048417 | $30,367 | |
| May 4, 2001 | Completed final sign-off Aug 2002 | 75 Hawthorne St | one-stop:c.hom,installation from children's playard,removal of asphalt paving.Details
one-stop:c.hom,installation from children's playard,removal of asphalt paving. | $125,000 | |
| Apr 16, 2001 | Completed final sign-off Dec 2001 | 75 Hawthorne St | Red Top Electric Co Emeryville Inc | install speakers and strobes for life safetyDetails
install speakers and strobes for life safety | $15,000 |
| Mar 5, 2001 | Completed final sign-off Dec 2001 | 75 Hawthorne St | Acco Engineered Systems Inc. Dba Acco En | oti-3 3rd fl mechDetails
oti-3 3rd fl mech | $22,000 |
| Feb 5, 2001 | Completed final sign-off Dec 2001 | 75 Hawthorne St | oti-1, 3rd floor, el, me, l/s & spDetails
oti-1, 3rd floor, el, me, l/s & sp | $180,000 | |
| Feb 5, 2001 | Completed final sign-off Dec 2001 | 75 Hawthorne St | oti-2, 3rd floor, el, me & spDetails
oti-2, 3rd floor, el, me & sp | $70,000 | |
| Jan 16, 2001 | Expired or cancelled expired Feb 2004 | 75 Hawthorne St | Sabah International Incorporated | provide install (1) fm 200 suppression systemDetails
provide install (1) fm 200 suppression system | $17,200 |
| Jul 20, 2000 | Completed final sign-off Sep 2000 | 75 Hawthorne St | Red Top Electric Co Emeryville Inc | add life safety system for tenant work. devices: horn/strobes, smoke detectorsDetails
add life safety system for tenant work. devices: horn/strobes, smoke detectors | $14,000 |
| May 3, 2000 | Completed final sign-off Aug 2000 | 75 Hawthorne St | install special access control door realese for unlocking elevator lobby doorsDetails
install special access control door realese for unlocking elevator lobby doors | $1,590 | |
| Mar 17, 2000 | Expired or cancelled expired Sep 2000 | 75 Hawthorne St | Red Top Electric Co Emeryville Inc | addition of speakers & strobes. life safety workDetails
addition of speakers & strobes. life safety work | $15,000 |
| Feb 9, 2000 | Completed final sign-off Sep 2000 | 75 Hawthorne St | remodel ti office space on 7th fl,demo/add new partitionsDetails
remodel ti office space on 7th fl,demo/add new partitions | $150,000 | |
| Jan 20, 2000 | Expired or cancelled expired May 2000 | 75 Hawthorne St | Pacific Automatic Sprinkler | relocate and install fire sprinklersDetails
relocate and install fire sprinklers | $2,250 |
Find contractors for work like this