- Apr 2005 to Oct 2026
130 permits since 2000 (engineer on 111 permits, architect on 15 permits, designer on 2 permits, attorney on 1 permit, authorized agent-others on 1 permit): 88 completed, 11 in progress, 12 never finaled, 19 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 130.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 2, 2026 | In progress filed Oct 2026, not yet issued | 519 Arkansas St | convert 538 sq of storage/garage area to conditioned live space. new all electric hvac. replace front windows in kind. replace front windows in kind. replace rear windows. interior stair rebuild. kitchen and bath remodel. minor structural work. no work outside (e) foot print. no change to use.Details
convert 538 sq of storage/garage area to conditioned live space. new all electric hvac. replace front windows in kind. replace front windows in kind. replace rear windows. interior stair rebuild. kitchen and bath remodel. minor structural work. no work outside (e) foot print. no change to use. | $125,000 | |
| Jul 24, 2026 | In progress issued Jul 2026 | 1638 Lake St | Bannside Construction Inc. | revision 202606082765- adjustment to permits to add steel beam, footings, adjust framing.Details
revision 202606082765- adjustment to permits to add steel beam, footings, adjust framing. | $5,000 |
| Jun 8, 2026 | In progress issued Jun 2026 | 1638 Lake St | Bannside Construction Inc. | remodel of (e) kitchen, family room, dining room and primary bath.Details
remodel of (e) kitchen, family room, dining room and primary bath. | $150,000 |
| May 28, 2026 | In progress filed May 2026, not yet issued | 1030 Jackson St | comply with nov# 202546782: divide unauthorized merged unit to allowed use of two units on 3rd floor. restore dividing wall and kitchen. no structural work.Details
comply with nov# 202546782: divide unauthorized merged unit to allowed use of two units on 3rd floor. restore dividing wall and kitchen. no structural work. | $10,000 | |
| Apr 14, 2026 | In progress issued Apr 2026 | 4645 Anza St | Leafair Construction | minor revision to risidential interior remodeling#20251006973. 1st floor: remove one interior wall in the garage, replace one (e) window w/ & (n) outdoor door. 2nd floor: add 3 skylight above the kitchen area, replace one (e) window.Details
minor revision to risidential interior remodeling#20251006973. 1st floor: remove one interior wall in the garage, replace one (e) window w/ & (n) outdoor door. 2nd floor: add 3 skylight above the kitchen area, replace one (e) window. | |
| Mar 16, 2026 | Completed final sign-off May 2026 | 835 Union St | L O D Construction | revision to bpa 202202238554: remove bathroom skylight from scope of work.Details
revision to bpa 202202238554: remove bathroom skylight from scope of work. | |
| Feb 10, 2026 | Completed final sign-off Aug 2026 | 30 Bernard St | revision to 202512171976- to include all 6 units for bathroom and kitchen remodel layout changes. installing new shower pans.Details
revision to 202512171976- to include all 6 units for bathroom and kitchen remodel layout changes. installing new shower pans. | $180,000 | |
| Dec 17, 2025 | Completed final sign-off Aug 2026 | 30 Bernard St | interior alteration of 3 units in a 6 unit building: 30 1/2, 34, 38. relocate kitchen, add bathDetails
interior alteration of 3 units in a 6 unit building: 30 1/2, 34, 38. relocate kitchen, add bath | $180,000 | |
| Dec 10, 2025 | In progress filed Dec 2025, not yet issued | 81 Rosewood Dr | Spectrum Development Co. | exterior modifications include new skylight,roof in kind, 2 new windows at rear, 3 new windows in kind at the front, remove garage door, replace with 3 windows to match existing at front, deck expansion on west side. remodel bath storage space 1st fl, kitchen, new stair 1st to 2nd fl, bath/bdrm 3rdDetails
exterior modifications include new skylight,roof in kind, 2 new windows at rear, 3 new windows in kind at the front, remove garage door, replace with 3 windows to match existing at front, deck expansion on west side. remodel bath storage space 1st fl, kitchen, new stair 1st to 2nd fl, bath/bdrm 3rd | $550,000 |
| Oct 8, 2025 | In progress issued Oct 2025 | 4645 Anza St | Leafair Construction | interior remodeling: e) kitchen & e) bathrooms by changing layout, new interior stairs, replacing e) windows in-kindDetails
interior remodeling: e) kitchen & e) bathrooms by changing layout, new interior stairs, replacing e) windows in-kind | $300,000 |
| May 21, 2025 | In progress issued Jan 2026 | 249 Mississippi St | Wing On Construction Inc | erect a four-story, type 5, residential building with two units.Details
erect a four-story, type 5, residential building with two units. | $750,000 |
| May 19, 2025 | In progress issued Jan 2026 | 249 Mississippi St | Wing On Construction Inc | demolish a two-story, type 5, single family building.Details
demolish a two-story, type 5, single family building. | $12,150 |
| Apr 14, 2025 | In progress issued Apr 2025 | 331 Elsie St | J R Home Remodeling Inc | revision to pa #202309146550 for existing foundation. revision to detail at longitudal exterior walls.Details
revision to pa #202309146550 for existing foundation. revision to detail at longitudal exterior walls. | |
| Mar 24, 2025 | Completed final sign-off Aug 2026 | 1851 40th Av | F C Company | remodel 1st and 2nd floors. addition of 299 sf at first floor within (e) envelope. (n) bedroom,bathroom, and laundry room. install (n) sliding glass door and windows at rear facade. install (n) siding at rear facade. upgrade main panel and remove interior (e) fireplaceDetails
remodel 1st and 2nd floors. addition of 299 sf at first floor within (e) envelope. (n) bedroom,bathroom, and laundry room. install (n) sliding glass door and windows at rear facade. install (n) siding at rear facade. upgrade main panel and remove interior (e) fireplace | $180,000 |
| Nov 6, 2023 | Completed final sign-off Sep 2025 | 66 Mirabel Av | Jose Martinez | remodel 2 units including replacement of mechanical, plumbing & electrical system. replacement of all windows & installation of insulation throughout. ground floor addition of 404 ft of heated space within garage envelope. infill (e) lightwell. replace stucco facade with new painted wood siding.Details
remodel 2 units including replacement of mechanical, plumbing & electrical system. replacement of all windows & installation of insulation throughout. ground floor addition of 404 ft of heated space within garage envelope. infill (e) lightwell. replace stucco facade with new painted wood siding. | $460,000 |
| Sep 14, 2023 | Completed final sign-off Jul 2026 | 331 Elsie St | J R Home Remodeling Inc, Spectrum Development Co. | partial foundation replacment to create habitable space/legal bedroom @ heated front of house,gr lvl. minor exterior work to depress entry patio, replace (e)window in-kind to meet egress requirementsDetails
partial foundation replacment to create habitable space/legal bedroom @ heated front of house,gr lvl. minor exterior work to depress entry patio, replace (e)window in-kind to meet egress requirements | $75,000 |
| Aug 9, 2023 | Never finaled filed Aug 2023, never issued | 1527 Jerrold Av | replace (e) foundation; replace all 1/f vinyl wndws w/new clad wndws; n clad door at south elev; n clad wndw at west elev; n clad french door at east elev. unit 1: 1/f remodel w/new living rm, secondary kitchen, bathrm, laundry, bedrm. unit 2: rehab w/new kitchen, living area, bathrm, bedrm.Details
replace (e) foundation; replace all 1/f vinyl wndws w/new clad wndws; n clad door at south elev; n clad wndw at west elev; n clad french door at east elev. unit 1: 1/f remodel w/new living rm, secondary kitchen, bathrm, laundry, bedrm. unit 2: rehab w/new kitchen, living area, bathrm, bedrm. | $400,000 | |
| Feb 21, 2023 | Completed final sign-off Aug 2025 | 1113 Hampshire St | R De Leon Construction | construct grd flr in-fill addition @ rear beneath (e) deck w/ steps & privacy screen firewall extend into reqd rear yard. convert (e) storage & laundry rm into primaty bedrm w/ full bath & laundry rm. construct interior stais to 2nd flr. remove rear bathrm & create bedrm. cp variance#2022000591varDetails
construct grd flr in-fill addition @ rear beneath (e) deck w/ steps & privacy screen firewall extend into reqd rear yard. convert (e) storage & laundry rm into primaty bedrm w/ full bath & laundry rm. construct interior stais to 2nd flr. remove rear bathrm & create bedrm. cp variance#2022000591var | $200,000 |
| Jan 13, 2023 | Completed final sign-off Jan 2024 | 226 Coleridge St | Spectrum Development Co. | interior alterations at first floor, partial foundation retrofit, lower slab, bathroom addition at first floor.Details
interior alterations at first floor, partial foundation retrofit, lower slab, bathroom addition at first floor. | $75,000 |
| Jun 23, 2022 | Completed final sign-off Feb 2023 | 935 Shotwell St | revision to original pa 202011038080, 202012211457 and 202112013482 original deck was built in-kind (202011038080) then large deck w/stair (202012211457) then small deck no stair (202112013482). current permit adds 2'-6" in width to permit 202112013482 and a large triangular deck, spiral stair andDetails
revision to original pa 202011038080, 202012211457 and 202112013482 original deck was built in-kind (202011038080) then large deck w/stair (202012211457) then small deck no stair (202112013482). current permit adds 2'-6" in width to permit 202112013482 and a large triangular deck, spiral stair and | $30,000 | |
| Mar 4, 2022 | Completed final sign-off Jun 2022 | 17 Lansdale Av | Joseph Francis Lockary | kitchen renovation including removal of post and installation of steel beam.Details
kitchen renovation including removal of post and installation of steel beam. | $50,000 |
| Feb 23, 2022 | Expired or cancelled expired May 2026 | 835 Union St | L O D Construction | interior remodel of single unit. remodel kitchen and bath. new living room with open floor plan to kitchen.Details
interior remodel of single unit. remodel kitchen and bath. new living room with open floor plan to kitchen. | $50,000 |
| Jan 27, 2022 | Never finaled filed Jan 2022, never issued | 57 Manchester St | Spectrum Development Co. | to comply with complaint# 202178234. legalize (e) finished storage in basement. no structural work.Details
to comply with complaint# 202178234. legalize (e) finished storage in basement. no structural work. | $2,000 |
| Oct 8, 2021 | Never finaled issued Jun 2022, no final | 344 South Van Ness Av | Leafair Construction | additions & alteration to dubplex.1st floor: new gym area & home office area in part of the garage. 2nd & 3rd floor, extension to (e) lightwell; partially lower garage to convert into habitable spaceDetails
additions & alteration to dubplex.1st floor: new gym area & home office area in part of the garage. 2nd & 3rd floor, extension to (e) lightwell; partially lower garage to convert into habitable space | $400,000 |
| Apr 23, 2021 | Completed final sign-off Dec 2021 | 1551 24th Av | (e) bathroom remodeling add 1 (n) bathroom, no additional square footage, proposed work is within (e) building footprint, no change to building envelope and yard is proposedDetails
(e) bathroom remodeling add 1 (n) bathroom, no additional square footage, proposed work is within (e) building footprint, no change to building envelope and yard is proposed | $50,000 | |
| Apr 14, 2021 | Completed final sign-off Feb 2022 | 4030 22nd St | Sarris Construction | revision to pa# 201910285680. 1st & 3rd fl bathroom layout change. rear wall door/window change. minor framing & foundation change. ab005 change. adding 1-hr passageway substituting for sprinklers to be omitted.Details
revision to pa# 201910285680. 1st & 3rd fl bathroom layout change. rear wall door/window change. minor framing & foundation change. ab005 change. adding 1-hr passageway substituting for sprinklers to be omitted. | $1,000 |
| Feb 25, 2021 | In progress issued Jan 2024 | 19 Norwich St | Redoak Construction | 1st floor remodel bedroom & bathroom. add 63 sqft extension in the projection to building rear end under the 2nd floor. add 1 new bathroom. 2nd floor remodel interior with no added sqft. new rear deck. top floor new roof deck.Details
1st floor remodel bedroom & bathroom. add 63 sqft extension in the projection to building rear end under the 2nd floor. add 1 new bathroom. 2nd floor remodel interior with no added sqft. new rear deck. top floor new roof deck. | $300,000 |
| Feb 23, 2021 | Completed final sign-off May 2022 | 1567 Leavenworth St | add bathroom and closet at residential unit. change fireplace. small interior glazing windows.Details
add bathroom and closet at residential unit. change fireplace. small interior glazing windows. | $25,000 | |
| Nov 3, 2020 | Completed final sign-off Feb 2023 | 935 Shotwell St | remodel (e) 2nd flr, (n) interior well layout, relocate kitchen-2 bedrooms-2 bathrooms. replace (e) rear 2nd story deck in-kind as required for structural stability. replace (e) water heater and furnace.Details
remodel (e) 2nd flr, (n) interior well layout, relocate kitchen-2 bedrooms-2 bathrooms. replace (e) rear 2nd story deck in-kind as required for structural stability. replace (e) water heater and furnace. | $85,000 | |
| Sep 10, 2020 | Completed final sign-off Feb 2021 | 319 Prentiss St | Next Generation Concrete Construction | replacement of front stairs in kindDetails
replacement of front stairs in kind | $10,000 |
| Feb 11, 2020 | Expired or cancelled cancelled Apr 2022 | 1028 Sanchez St | Sarris Construction | partial interior upgrade to rear wall at 1st fl unit, no change to layout or elevation.Details
partial interior upgrade to rear wall at 1st fl unit, no change to layout or elevation. | $15,000 |
| Oct 28, 2019 | Completed final sign-off Feb 2022 | 4030 22nd St | Sarris Construction | site permit: horizontal addition at 3rd floor. (bedroom and bathroom) construct workshop behind garage at 1st floor.Details
site permit: horizontal addition at 3rd floor. (bedroom and bathroom) construct workshop behind garage at 1st floor. | $150,000 |
| Aug 22, 2019 | Completed final sign-off Jul 2021 | 719 Noe St | partial interior remodeling of bathroom. no exterior work.Details
partial interior remodeling of bathroom. no exterior work. | $30,000 | |
| Jun 11, 2019 | Completed final sign-off Dec 2019 | 65 Lupine Av | Kalix Inc Dbalara Construction | revision to soft story pa #201709137915, revision to selected shearwalls, alignment & connection details.Details
revision to soft story pa #201709137915, revision to selected shearwalls, alignment & connection details. | $800 |
| Apr 2, 2019 | Completed final sign-off Apr 2019 | 1306 Mcallister St | D E F Co | install support columns in garage.Details
install support columns in garage. | $8,500 |
| Mar 22, 2019 | Completed final sign-off Mar 2021 | 164 Eastwood Dr | Rhodes Construction Inc. | remodel (e) 2 story sfd. 1/f: add bedroom #2, bath #2, playroom, laundry, lounge, bath #3 & storage. 2/f: remodel kitchen & bath #1, add master bath & closet. new stairwell to 1st fl. new water heater & furnace relocted. new windows & exterior doors.Details
remodel (e) 2 story sfd. 1/f: add bedroom #2, bath #2, playroom, laundry, lounge, bath #3 & storage. 2/f: remodel kitchen & bath #1, add master bath & closet. new stairwell to 1st fl. new water heater & furnace relocted. new windows & exterior doors. | $195,000 |
| Dec 28, 2018 | Completed final sign-off Oct 2019 | 1362 Sacramento St | remodel (e) bath, add new full bath, replace 4 windows w/ new which are not street visible at (e) openings. replace 1 window w/ 3 new, replace rafters.Details
remodel (e) bath, add new full bath, replace 4 windows w/ new which are not street visible at (e) openings. replace 1 window w/ 3 new, replace rafters. | $40,000 | |
| Dec 3, 2018 | Completed final sign-off May 2021 | 591 Guerrero St | Nabi Construction & Engineering Inc | accessible business entrance alterations. soft story not included under this permit. door actuators to be installed at storefronts. small step to be changed to ramp at 2 stores, tile to be restored.Details
accessible business entrance alterations. soft story not included under this permit. door actuators to be installed at storefronts. small step to be changed to ramp at 2 stores, tile to be restored. | $20,000 |
| Dec 3, 2018 | Completed final sign-off May 2021 | 591 Guerrero St | Nabi Construction & Engineering Inc | mandatory soft story retrofit - residential floor. 2016 cebc appendix a-12037.Details
mandatory soft story retrofit - residential floor. 2016 cebc appendix a-12037. | $30,000 |
| Dec 3, 2018 | Completed final sign-off May 2021 | 591 Guerrero St | Nabi Construction & Engineering Inc | mandatory soft story retrofit - commercial floor. 2016 cebc appendix a-4Details
mandatory soft story retrofit - commercial floor. 2016 cebc appendix a-4 | $50,000 |
| Nov 1, 2018 | Never finaled issued Mar 2021, no final | 862 Pacheco St | Rhodes Construction Inc. | expansion of existing bathroom at middle fl into existing crawl space, bathroom remodel. all work inside existing envelope, not visible from outsideDetails
expansion of existing bathroom at middle fl into existing crawl space, bathroom remodel. all work inside existing envelope, not visible from outside | $50,000 |
| Jun 6, 2018 | Completed final sign-off Aug 2021 | 1519 Polk St | Sweitzer Inc. | build out of new wine and cheese barDetails
build out of new wine and cheese bar | $95,000 |
| May 16, 2018 | Expired or cancelled expired Nov 2023 | 2509 Pacific Av | Mrcc | (n) horizontal addition @ rear yard under (e) deck @ garage (no change in perceived building envelope), interior renovations throughout. no cfc shall be issued until easement is approved, notarized & recorded.Details
(n) horizontal addition @ rear yard under (e) deck @ garage (no change in perceived building envelope), interior renovations throughout. no cfc shall be issued until easement is approved, notarized & recorded. | $300,000 |
| Dec 27, 2017 | Completed final sign-off Feb 2021 | 1235 Waller St | mandatory seismic retrofit per cebc 2016 appendix a-4Details
mandatory seismic retrofit per cebc 2016 appendix a-4 | $35,000 | |
| Dec 21, 2017 | Completed final sign-off Aug 2018 | 1723 29th Av | Art Of Construction Inc | revision to app#201711164119. revised south footing details.Details
revision to app#201711164119. revised south footing details. | |
| Oct 2, 2017 | Completed final sign-off Mar 2020 | 2605 Market St | Nabi Construction & Engineering Inc | soft story retrofit per sfebc chapter 4d, engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d, engineering criteria 2016 cebc appendix a-4. | $40,000 |
| Oct 2, 2017 | Expired or cancelled cancelled Dec 2020 | 710 25th Av | soft story retrofit per sfebc chapter 4d, engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d, engineering criteria 2016 cebc appendix a-4. | $35,000 | |
| Oct 2, 2017 | Expired or cancelled cancelled Oct 2022 | 2605 Market St | add unit per ordinance# 162-16 in basement. studio unit.Details
add unit per ordinance# 162-16 in basement. studio unit. | $35,000 | |
| Aug 30, 2017 | Completed final sign-off Aug 2018 | 1723 29th Av | Art Of Construction Inc | interior renovation to include new bedroom, bathroom, media room and laundry area in garage level, relocate internal stair, minor alteration around entry area. no alter facade or bldg envelope. no alteration of facade/building envelopeDetails
interior renovation to include new bedroom, bathroom, media room and laundry area in garage level, relocate internal stair, minor alteration around entry area. no alter facade or bldg envelope. no alteration of facade/building envelope | $80,000 |
| Aug 28, 2017 | Completed final sign-off Jan 2018 | 178 Albion St | Sft Construction Corp | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $30,000 |
| Aug 28, 2017 | Completed final sign-off Feb 2022 | 445 Ashbury St | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $40,000 | |
| Aug 16, 2017 | Expired or cancelled cancelled Aug 2022 | 559 Minna St | add unit @ 1st floor of 3-story buildingDetails
add unit @ 1st floor of 3-story building | $50,000 | |
| Jul 18, 2017 | Never finaled issued Jul 2018, no final | 2415 47th Av | 363 sq.ft. ground floor rear addition of 1 bedroom & 1 bathroom. 9e) ground floor bedroom to shift into addition to accommodate the new bathroom. new 310 sq.ft. 2nd floor deck on top of addition with new sprial stair to rear yard.Details
363 sq.ft. ground floor rear addition of 1 bedroom & 1 bathroom. 9e) ground floor bedroom to shift into addition to accommodate the new bathroom. new 310 sq.ft. 2nd floor deck on top of addition with new sprial stair to rear yard. | $80,000 | |
| May 25, 2017 | Completed final sign-off Sep 2025 | 725 Grove St | Nabi Construction & Engineering Inc | per adu ordinance# 162-16. addition of 2 units on ground floor. reference pa# 2017/05/25/7616 for soft story. 1 bedroom & 1 bath each.Details
per adu ordinance# 162-16. addition of 2 units on ground floor. reference pa# 2017/05/25/7616 for soft story. 1 bedroom & 1 bath each. | $60,000 |
| May 25, 2017 | Completed final sign-off Oct 2021 | 725 Grove St | Nabi Construction & Engineering Inc | mandatory soft story retrofit of 1st floor 2016 cebc appendix a-4.Details
mandatory soft story retrofit of 1st floor 2016 cebc appendix a-4. | $60,000 |
| Apr 17, 2017 | Expired or cancelled cancelled Oct 2022 | 646 Corbett Av | adu per ordinance #162-16, addition of four units on 1st floor. soft story under pa #201611213230.Details
adu per ordinance #162-16, addition of four units on 1st floor. soft story under pa #201611213230. | $50,000 | |
| Dec 22, 2016 | Completed final sign-off May 2020 | 492 Grove St | Joseph Francis Lockary | (residential) soft story retrofit to follow iebc 2012 appendix 4 at ground floor + basement.Details
(residential) soft story retrofit to follow iebc 2012 appendix 4 at ground floor + basement. | $50,000 |
| Dec 22, 2016 | Completed final sign-off May 2020 | 492 Grove St | Joseph Francis Lockary | (retail / commercial) soft story retrofit to follow iebc 2012 appendix 4 at ground floor + basement.Details
(retail / commercial) soft story retrofit to follow iebc 2012 appendix 4 at ground floor + basement. | $10,000 |
| Nov 21, 2016 | Expired or cancelled cancelled Feb 2020 | 646 Corbett Av | soft story mandatory retrofit per 2012 iebc appendix 4Details
soft story mandatory retrofit per 2012 iebc appendix 4 | $50,000 | |
| Oct 18, 2016 | Completed final sign-off Jun 2018 | 255 Dolores St | Glen Canyon Properties Inc | soft story seismic retrofit as shown on plans per iebc 2012 appx a4Details
soft story seismic retrofit as shown on plans per iebc 2012 appx a4 | $50,000 |
| Oct 18, 2016 | Completed final sign-off Apr 2018 | 255 Dolores St | Glen Canyon Properties Inc | replace rear (2)new windows/ (2) new doors due to soft story - not visible from streetDetails
replace rear (2)new windows/ (2) new doors due to soft story - not visible from street | $6,000 |
| Aug 29, 2016 | Completed final sign-off Feb 2020 | 331 27th Av | addition of studio unit on 1st floorDetails
addition of studio unit on 1st floor | $40,000 | |
| Aug 25, 2016 | Never finaled issued Aug 2016, no final | 1535 40th Av | interior remodel including new kitchen, baths, lightwell, rear windows, interior stairs. 1/f to include 2 bedrooms & 1 bathroom.Details
interior remodel including new kitchen, baths, lightwell, rear windows, interior stairs. 1/f to include 2 bedrooms & 1 bathroom. | $40,000 | |
| Aug 16, 2016 | Completed final sign-off Jan 2017 | 642 Oak St | Pederson Construction | construction of 10' tall screen wall at rear property line, existing r2, new u; maher ord 155-13 na.Details
construction of 10' tall screen wall at rear property line, existing r2, new u; maher ord 155-13 na. | $30,000 |
| Aug 3, 2016 | Completed final sign-off Oct 2016 | 239 Shipley St | revise 201605107054, move sink from rear to front of office, install 1-hr glass blocks at office entrance, move sink location in bathrm; maher n/aDetails
revise 201605107054, move sink from rear to front of office, install 1-hr glass blocks at office entrance, move sink location in bathrm; maher n/a | $900 | |
| Jul 1, 2016 | Completed final sign-off Nov 2016 | 900 Haight St | David Van Oosbree | repair exterior deck and footingDetails
repair exterior deck and footing | $2,000 |
| Jul 1, 2016 | Completed final sign-off Jul 2017 | 1960 Fulton St | Forum Renovation Co. Inc | soft story retrofit per 2012 iebc appendix 4. n/a ordinance #155-13Details
soft story retrofit per 2012 iebc appendix 4. n/a ordinance #155-13 | $40,000 |
| May 26, 2016 | Completed final sign-off Mar 2020 | 245 11th Av | Dave Mason Building | per ordinance# 30-15. addition of 2 studio units at 1st floor. soft story under pa# 2016/05/26/8524. ** maher: n/a **Details
per ordinance# 30-15. addition of 2 studio units at 1st floor. soft story under pa# 2016/05/26/8524. ** maher: n/a ** | $60,000 |
| May 26, 2016 | Completed final sign-off Dec 2019 | 245 11th Av | Dave Mason Building | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. ** maher: n/a **Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. ** maher: n/a ** | $50,000 |
| May 10, 2016 | Completed final sign-off Oct 2016 | 239 Shipley St | revision to pa# 201505146346. change in partitions & bathroom layout, no structural changes, no exterior or use changes.Details
revision to pa# 201505146346. change in partitions & bathroom layout, no structural changes, no exterior or use changes. | ||
| May 3, 2016 | Completed final sign-off Jul 2016 | 620 29th St | front building renovation of existing house, addition of bathroom. kitchen & bath remodel. change one window on east elevation. revision to 2016/04/05/3986Details
front building renovation of existing house, addition of bathroom. kitchen & bath remodel. change one window on east elevation. revision to 2016/04/05/3986 | $25,000 | |
| Mar 21, 2016 | Completed final sign-off Jul 2016 | 1525 Chestnut St | Lordan Construction | provide door from foyer to garage. maher naDetails
provide door from foyer to garage. maher na | $900 |
| Mar 16, 2016 | Completed final sign-off Sep 2016 | 399 Steiner St | Glen Canyon Properties Inc | legalize existing non-permited unit per ordinance 43-14, replaced cabinets & extures; replace plumbing & wiring, utilities under separate permit. soft story permit #201507151527.Details
legalize existing non-permited unit per ordinance 43-14, replaced cabinets & extures; replace plumbing & wiring, utilities under separate permit. soft story permit #201507151527. | $18,000 |
| Mar 3, 2016 | Completed final sign-off Jul 2016 | 1525 Chestnut St | Lordan Construction | soft story retrofit and new door from foyer to garage. per 2012 iebc appendix a-4. n/a for maherDetails
soft story retrofit and new door from foyer to garage. per 2012 iebc appendix a-4. n/a for maher | $50,000 |
| Feb 26, 2016 | Expired or cancelled expired Jan 2025 | 2886 Folsom St | add dwelling unit. one bedroom on first floor part of soft story retrofit per add unit ordinance 30-15. p/a#201602260598.Details
add dwelling unit. one bedroom on first floor part of soft story retrofit per add unit ordinance 30-15. p/a#201602260598. | $5,000 | |
| Feb 26, 2016 | Expired or cancelled expired Dec 2022 | 2886 Folsom St | Roberto De Leon | soft story retrofit. removal of selected post & new beam, posts, footings. 2012 iebc appendix a-4.Details
soft story retrofit. removal of selected post & new beam, posts, footings. 2012 iebc appendix a-4. | $90,000 |
| Dec 15, 2015 | Expired or cancelled expired Sep 2019 | 1900 Green St | North South Construction Inc | construct stairway from 1st to 2nd floor. interior only. n/a for maherDetails
construct stairway from 1st to 2nd floor. interior only. n/a for maher | $15,000 |
| Oct 29, 2015 | Completed final sign-off Mar 2017 | 710 Clayton St | Roberts Hardware | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4.Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. | $40,000 |
| Oct 13, 2015 | Completed final sign-off Mar 2016 | 2960 California St | S Hall Builders Inc | soft story seismic retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. maher naDetails
soft story seismic retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. maher na | $45,000 |
| Sep 22, 2015 | Expired or cancelled withdrawn Mar 2016 | 399 Steiner St | Glen Canyon Properties Inc | addition of new studio apartment in soft story space. per ordinance no. 30-15, includes bathroom & kitchen.Details
addition of new studio apartment in soft story space. per ordinance no. 30-15, includes bathroom & kitchen. | $25,000 |
| May 14, 2015 | Completed final sign-off Oct 2016 | 239 Shipley St | site permit, conversion of rear of garage to new light court, new laundry, 1 bathroom 6 biclcle parking spaces. conversion from residential garage to new commercial office on 1st floor.Details
site permit, conversion of rear of garage to new light court, new laundry, 1 bathroom 6 biclcle parking spaces. conversion from residential garage to new commercial office on 1st floor. | $40,000 | |
| Feb 4, 2015 | Completed final sign-off Mar 2016 | 399 Steiner St | Glen Canyon Properties Inc | #20 - voluntary structural upgrade. foundation & seismic retrofit of one unit in apartment bldg - partial selective upgrade at ground level (1st floor), interior only.Details
#20 - voluntary structural upgrade. foundation & seismic retrofit of one unit in apartment bldg - partial selective upgrade at ground level (1st floor), interior only. | $35,000 |
| Jan 12, 2015 | Completed final sign-off Apr 2016 | 2470 Clay St | 2nd fl unit #1: alternation to one unit on in four unit bldg. kitchen and bathroom remodel, partial wall opening. new stair from deck to yard. tempered glass adjacent to stairs.Details
2nd fl unit #1: alternation to one unit on in four unit bldg. kitchen and bathroom remodel, partial wall opening. new stair from deck to yard. tempered glass adjacent to stairs. | $35,000 | |
| Jun 27, 2014 | Never finaled issued Jun 2014, no final | 57 Manchester St | Spectrum Development Co. | volunteer foundation retrofit in basement. interior alterations on 2nd fl east unit. no change to exterior or living area boundries. kitchen remodelDetails
volunteer foundation retrofit in basement. interior alterations on 2nd fl east unit. no change to exterior or living area boundries. kitchen remodel | $60,000 |
| May 27, 2014 | Never finaled issued May 2014, no final | 944 Hampshire St | Cardea Bldg Dba Dimension Design Group | revision to appl #201403130688 - replace door & window at 1st floor rear wall.Details
revision to appl #201403130688 - replace door & window at 1st floor rear wall. | $2,000 |
| Apr 15, 2014 | Completed final sign-off Aug 2014 | 95 Mercedes Wy | Pederson Construction | footing retrofit at detached garage. dry rot repairs in kind of wood framing.Details
footing retrofit at detached garage. dry rot repairs in kind of wood framing. | $10,000 |
| Apr 15, 2014 | Completed final sign-off Jul 2014 | 1567 Leavenworth St | Bay Build Design Inc | convert extg disassembled laundry to office. add bathroom. no structural work . within extg envelope.Details
convert extg disassembled laundry to office. add bathroom. no structural work . within extg envelope. | $83,894 |
| Apr 4, 2014 | Completed final sign-off Oct 2021 | 800 El Camino Del Mar | Gelling & Judd Inc. | remodel of (e) residence & vertical addition over portion of (e) residence creation new 3rd floor. variance needed for small side yard encroachment at north / east corner. addition to include 4 new bedrooms & 3 new baths.Details
remodel of (e) residence & vertical addition over portion of (e) residence creation new 3rd floor. variance needed for small side yard encroachment at north / east corner. addition to include 4 new bedrooms & 3 new baths. | $600,000 |
| Dec 6, 2013 | Completed final sign-off Mar 2014 | 2 18th Av | Transbay Design Build | repair extg rear deck in kind within extg extents approx. 50 % as possible. elements remaining. not visible from street.Details
repair extg rear deck in kind within extg extents approx. 50 % as possible. elements remaining. not visible from street. | $8,000 |
| Nov 26, 2013 | Never finaled issued Dec 2013, no final | 1026 Masonic Av | Cal Custom Remodel & Construction | replace selected areas of doundations and associated elements as shown on plans, repair/replace windows, not visable from street.Details
replace selected areas of doundations and associated elements as shown on plans, repair/replace windows, not visable from street. | $10,000 |
| Jul 3, 2013 | Completed final sign-off Dec 2013 | 225 Grand View Av | Michael Hayes Construction | rev. to pa#201306048604. replace existing sliding glass doors & windows at east elevation 1/f & 2/f. remove existing bay window at 2nd story east elevation, remove (e) wall at kitchen/living room. add new skylight in living room, not visable from street.Details
rev. to pa#201306048604. replace existing sliding glass doors & windows at east elevation 1/f & 2/f. remove existing bay window at 2nd story east elevation, remove (e) wall at kitchen/living room. add new skylight in living room, not visable from street. | $50,000 |
| May 30, 2013 | Completed final sign-off Jul 2013 | 1960 Fulton St | Forum Renovation Co. Inc | provide selective capping of basement well and curb at rear yard. work is limited to 2nd floor west 2 units.Details
provide selective capping of basement well and curb at rear yard. work is limited to 2nd floor west 2 units. | $10,000 |
| Feb 19, 2013 | Completed final sign-off Jan 2016 | 871 Lawton St | Royal Lyon Construction | remodel including: new 1/f coat closet, 376 sq. ft. 2/f rear addition & deck, new interior stairway wall openings, 2/f kitchen remodel, remodel 2/f powder room. new pocket doors at 2nd floor storage room; replace (e) windows & sliding glass doors at 2nd & 3rd floor, 142 sq.ft. 3rd floor front additnDetails
remodel including: new 1/f coat closet, 376 sq. ft. 2/f rear addition & deck, new interior stairway wall openings, 2/f kitchen remodel, remodel 2/f powder room. new pocket doors at 2nd floor storage room; replace (e) windows & sliding glass doors at 2nd & 3rd floor, 142 sq.ft. 3rd floor front additn | $125,000 |
| Nov 9, 2012 | Completed final sign-off Dec 2014 | 114 Broderick St | 225 Shipley Inc | enlarge garage depth (area) by 159 sq ft. reconfigure level one unit including relocation of kitchen and 2 bathrooms. remodel kitchen at level 2 and bathroom at level 3. new clad wood slider located at rear of residence. new furnace at garage location.Details
enlarge garage depth (area) by 159 sq ft. reconfigure level one unit including relocation of kitchen and 2 bathrooms. remodel kitchen at level 2 and bathroom at level 3. new clad wood slider located at rear of residence. new furnace at garage location. | $85,000 |
| Sep 7, 2012 | Completed final sign-off Aug 2013 | 2060 Vallejo St | Cedar House Construction/Brian White | partial selective voluntary retrofit of existing walkway framing and footing within 50 % of structural framingDetails
partial selective voluntary retrofit of existing walkway framing and footing within 50 % of structural framing | $7,000 |
| Mar 30, 2012 | Completed final sign-off Oct 2012 | 975 14th St | revision to pa #201108263370: change in structural support for post removalDetails
revision to pa #201108263370: change in structural support for post removal | $800 | |
| Feb 29, 2012 | Completed final sign-off Sep 2013 | 2506 Bush St | side addition at existing kitchen-2nd floor and existing bedroom 3rd floor at rear of the house.Details
side addition at existing kitchen-2nd floor and existing bedroom 3rd floor at rear of the house. | $25,000 | |
| Dec 20, 2011 | Completed final sign-off Feb 2012 | 4144 23rd St | Custom Construction Enterprises | remove existing post and beam construction and replace with new beams and footings. selective strengthening of floor joists and other bracing per planDetails
remove existing post and beam construction and replace with new beams and footings. selective strengthening of floor joists and other bracing per plan | $15,000 |
| Sep 12, 2011 | Completed final sign-off Feb 2012 | 4144 23rd St | Custom Construction Enterprises | partial voluntary foundation retrofitDetails
partial voluntary foundation retrofit | $40,000 |
| Jun 16, 2011 | Completed final sign-off Dec 2012 | 711 Shotwell St | Robert J Chorak | revision to 200803046213: changes to layout and change windows to sliding doors, relocate skylight at rear carriage houseDetails
revision to 200803046213: changes to layout and change windows to sliding doors, relocate skylight at rear carriage house | $5,000 |