On San Francisco permits
Jul 2011 to May 2025

17 permits since 2000 (engineer on 16 permits, architect on 1 permit): 12 completed, 5 never finaled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Emcor Services/Mesa Energy Systems Inc (13), Northshore Build Llc (2), Adam Lewis Construction Company, Svb Construction Co. Inc.
Architects
Paul Vincent Gonzaga, Richard Sambucetti
Engineers
Juan A. Aranjo (2), Michael Orosco (2), Antonio Jacksalem, Edward Rivera, Jeffrey Taner, Juan Arajuo, William Bevier, William Norberg
Authorized agents
Daniel Johnston

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
May 13, 2025Completed
final sign-off Jul 2026
780 Mission StEmcor Services/Mesa Energy Systems Inclike for like replacement of 2 cooling tower and vfd on 3rd floor. 3 condensor water pumps and vfd 2nd floor.
Details
Permit
202505136329
Permit issued
May 21, 2025
Final sign-off
Jul 16, 2026

like for like replacement of 2 cooling tower and vfd on 3rd floor. 3 condensor water pumps and vfd 2nd floor.

Open the permit page

$448,000
Jul 14, 2023Completed
final sign-off Jul 2023
1275 Market StEmcor Services/Mesa Energy Systems Increvision to pa# 202305016789, changing path of travel coming out of shaft on 17th in a different location. alternate beam attachment for pipe support.
Details
Permit
202307142155
Permit issued
Jul 14, 2023
Final sign-off
Jul 27, 2023

revision to pa# 202305016789, changing path of travel coming out of shaft on 17th in a different location. alternate beam attachment for pipe support.

Open the permit page

$5,000
Jun 22, 2023Completed
final sign-off Sep 2024
365 Main StNorthshore Build Llcreplace 12 existing cooling units with 12 new units (interior)
Details
Permit
202306220656
Permit issued
Jul 28, 2023
Final sign-off
Sep 4, 2024

replace 12 existing cooling units with 12 new units (interior)

Open the permit page

$900,000
Jun 22, 2023Completed
final sign-off Sep 2024
365 Main StNorthshore Build Llcreplace 3 existing cooling units with 3 new ones (interior)
Details
Permit
202306220660
Permit issued
Jul 28, 2023
Final sign-off
Sep 4, 2024

replace 3 existing cooling units with 3 new ones (interior)

Open the permit page

$300,000
May 11, 2023Completed
final sign-off Nov 2024
55 04th StEmcor Services/Mesa Energy Systems Incdeferred mep; work 4th flr, 9th flr, 19th flr 38th flr elevator equipment room add one new 3.5 ton condensing unit/ahu with new electrical and new conducting. 4th flr add new 3.5 ton condensing unit/ahu, 9th flr remove and replace one fan coil, 19th flr remove and replace two fan coil,
Details
Permit
202305117580
Permit issued
Jun 22, 2023
Final sign-off
Nov 13, 2024

deferred mep; work 4th flr, 9th flr, 19th flr 38th flr elevator equipment room add one new 3.5 ton condensing unit/ahu with new electrical and new conducting. 4th flr add new 3.5 ton condensing unit/ahu, 9th flr remove and replace one fan coil, 19th flr remove and replace two fan coil,

Open the permit page

$235,000
May 1, 2023Completed
final sign-off Jul 2023
1275 Market StEmcor Services/Mesa Energy Systems Incinstall new 6" generator exhause from 2/f basement to the roof. new exhaust will be located in an existing shaft. the piping will be supported per the detailed indicated in drawings and insulated with 2" fiberglass, then wrapped with a 0.016 thick aluminum jacket. the exhaust will terminate at...
Details
Permit
202305016789
Permit issued
May 3, 2023
Final sign-off
Jul 27, 2023

install new 6" generator exhause from 2/f basement to the roof. new exhaust will be located in an existing shaft. the piping will be supported per the detailed indicated in drawings and insulated with 2" fiberglass, then wrapped with a 0.016 thick aluminum jacket. the exhaust will terminate at...

Open the permit page

$460,000
Aug 8, 2022Completed
final sign-off Mar 2024
1 Dr Carlton B Goodlett PlEmcor Services/Mesa Energy Systems Incroof - demo (2) ct demo ocp piping removal, (2) new cooling towers, extend/add vfd to electrical
Details
Permit
202208080054
Permit issued
Aug 23, 2022
Final sign-off
Mar 19, 2024

roof - demo (2) ct demo ocp piping removal, (2) new cooling towers, extend/add vfd to electrical

Open the permit page

$300,000
Nov 29, 2021Completed
final sign-off Nov 2025
560 Mission StEmcor Services/Mesa Energy Systems Incbasement: remove and replace 1 extg chiller and 2 extg pumps with 1 new high effeciency chiller and 2 new pumps. use extg electrical. extend equipment pad.
Details
Permit
202111293201
Permit issued
Mar 3, 2022
Final sign-off
Nov 26, 2025

basement: remove and replace 1 extg chiller and 2 extg pumps with 1 new high effeciency chiller and 2 new pumps. use extg electrical. extend equipment pad.

Open the permit page

$240,000
Mar 9, 2021Completed
final sign-off Sep 2021
111 Sutter StEmcor Services/Mesa Energy Systems Increplace high + low domestic booster pumps located in a subbasement. replace low + high gravity fed systems with 2 packaged skid pressure booster system. electrical - reuse & extend conduit & feeder to panelboard.
Details
Permit
202103096199
Permit issued
Jun 17, 2021
Final sign-off
Sep 30, 2021

replace high + low domestic booster pumps located in a subbasement. replace low + high gravity fed systems with 2 packaged skid pressure booster system. electrical - reuse & extend conduit & feeder to panelboard.

Open the permit page

$350,000
Dec 23, 2020Never finaled
issued Mar 2021, no final
901 Mission StEmcor Services/Mesa Energy Systems Incremove existing water chilled cooler and replace with new. modify existing support for new footprint.
Details
Permit
202012231589
Permit issued
Mar 25, 2021

remove existing water chilled cooler and replace with new. modify existing support for new footprint.

Open the permit page

$350,000
Dec 21, 2017Completed
final sign-off Sep 2023
75 Industrial StAdam Lewis Construction Companyrevision to pa #201612144986. remove (e) interior partitions. remove (e) concrete stair-on-grade & replace with (n) metal stair. add walls and doors. add (n) lighting. add (n) mechanical system, (n) electrical outlets and lighting. (n) liquid co2 storage and distribution system.
Details
Permit
201712217098
Permit issued
Oct 19, 2018
Final sign-off
Sep 20, 2023

revision to pa #201612144986. remove (e) interior partitions. remove (e) concrete stair-on-grade & replace with (n) metal stair. add walls and doors. add (n) lighting. add (n) mechanical system, (n) electrical outlets and lighting. (n) liquid co2 storage and distribution system.

Open the permit page

Aug 3, 2017Completed
final sign-off Oct 2018
81 Jefferson StSvb Construction Co. Inc.t.i. to existing restaurant space. n/a ordinance #155-13
Details
Permit
201708033804
Permit issued
Dec 18, 2017
Final sign-off
Oct 31, 2018

t.i. to existing restaurant space. n/a ordinance #155-13

Open the permit page

$350,000
Mar 9, 2015Never finaled
issued Mar 2015, no final
30 Van Ness AvEmcor Services/Mesa Energy Systems Incthe project consists of: replace 3 (e) chillers with two (n) chillers. (n) equip will match the (e) equip cooling capacities & ele capacities. the 2 (e) chillers installed on the (e) steel platform weigh less than the (e) chillers. maher - not req'd
Details
Permit
201503090278
Permit issued
Mar 9, 2015

the project consists of: replace 3 (e) chillers with two (n) chillers. (n) equip will match the (e) equip cooling capacities & ele capacities. the 2 (e) chillers installed on the (e) steel platform weigh less than the (e) chillers. maher - not req'd

Open the permit page

$180,000
Jun 3, 2013Never finaled
issued Jun 2013, no final
850 Bryant StEmcor Services/Mesa Energy Systems Incbasemt/ground level -replace (e) 535 "worthington" r-11 chilles. provide a refrigeration machine rom enclosure with correct exiting, rating & ventilation. provide refrigerant exhaust purge sys along w/monitoring & all code required alarms. upgrade all mechanical controls w/new ddc sys.
Details
Permit
201306038451
Permit issued
Jun 11, 2013

basemt/ground level -replace (e) 535 "worthington" r-11 chilles. provide a refrigeration machine rom enclosure with correct exiting, rating & ventilation. provide refrigerant exhaust purge sys along w/monitoring & all code required alarms. upgrade all mechanical controls w/new ddc sys.

Open the permit page

$906,015
Mar 21, 2013Never finaled
issued Mar 2013, no final
1200 15th StEmcor Services/Mesa Energy Systems Increpl air handlers ahu-1 & install variable air boxes for 2nd floor offices. repl ahu-2 & ahu-3, repl heating water boilers with a new near condensing boilers. upgrade energy management & control system for ahu's & boilers. repl domestic water boilers, storage tank circulating pumps & flues
Details
Permit
201303212724
Permit issued
Mar 29, 2013

repl air handlers ahu-1 & install variable air boxes for 2nd floor offices. repl ahu-2 & ahu-3, repl heating water boilers with a new near condensing boilers. upgrade energy management & control system for ahu's & boilers. repl domestic water boilers, storage tank circulating pumps & flues

Open the permit page

$370,000
Nov 1, 2011Completed
final sign-off Jul 2013
1660 Mission StEmcor Services/Mesa Energy Systems Incsuite 500 - install premium efficiency motors, ahu-1 control upgrades. vfd on garage fans, boiler replacement & related equipment. separate fa permit is required by sffd for fan shut down upon smoke detection
Details
Permit
201111018046
Permit issued
Nov 18, 2011
Final sign-off
Jul 23, 2013

suite 500 - install premium efficiency motors, ahu-1 control upgrades. vfd on garage fans, boiler replacement & related equipment. separate fa permit is required by sffd for fan shut down upon smoke detection

Open the permit page

$170,000
Jul 13, 2011Never finaled
issued Jul 2011, no final
930 Bryant StEmcor Services/Mesa Energy Systems Incboiler replacement and water heater addition @ ground floor. to replace existing.
Details
Permit
201107130111
Permit issued
Jul 18, 2011

boiler replacement and water heater addition @ ground floor. to replace existing.

Open the permit page

$48,000