Paulett Taggart
- Listed as
- architect, authorized agent-others, designer, engineer
- Firm
- Paulett Taggart Architects
- Based in
- San Francisco
- On San Francisco permits
- Mar 2001 to Jul 2025
57 permits since 2000 (architect on 53 permits, authorized agent-others on 2 permits, designer on 1 permit, engineer on 1 permit): 44 completed, 2 in progress, 5 never finaled, 6 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 15, 2025 | In progress issued Jul 2026 | 401 California Av | Cahill Contractors Llc. | to erect 6 stories, no basement, type i-a & ii-a, 150 units residential units with child development center (warmshell), (r-2, b,a-3,s-1,s-2,i-4)Details
to erect 6 stories, no basement, type i-a & ii-a, 150 units residential units with child development center (warmshell), (r-2, b,a-3,s-1,s-2,i-4) | $79,391,871 |
| Apr 26, 2024 | Completed final sign-off Jul 2026 | 2601 40th Av | Argo Construction Inc | renovate (e)sf rec & parks clubhouse.exterior work includes,sewer lateral replacement/modifcation & storm drain,(n) wall paint,concrete pavement & stair replacement,earthwork to provide additional patio area,restroom entrance,roof replacement,exterior doors, lighting,interior signage.Details
renovate (e)sf rec & parks clubhouse.exterior work includes,sewer lateral replacement/modifcation & storm drain,(n) wall paint,concrete pavement & stair replacement,earthwork to provide additional patio area,restroom entrance,roof replacement,exterior doors, lighting,interior signage. | $2,650,000 |
| Oct 3, 2023 | Never finaled filed Oct 2023, never issued | 1939 Market St | Swinerton Rubecon Joint Venture, Swinerton Builders | installation of underground fire protection water service.Details
installation of underground fire protection water service. | $21,600 |
| Nov 4, 2022 | In progress issued Oct 2023 | 1939 Market St | Swinerton Builders | erect a 15 story bldg with 187 dwelling units, residential/commercial(warmshell) ,type 1a. 100% affordable housingDetails
erect a 15 story bldg with 187 dwelling units, residential/commercial(warmshell) ,type 1a. 100% affordable housing | $86,686,000 |
| Nov 14, 2019 | Completed final sign-off Dec 2025 | 78 Haight St | Guzman Construction Group Inc., Guzman - Suffolk Jv Llc, Westates Mechanical Corporation Inc | to erect 8 stories, 1 basement, type i-b, 63 residential units with child development center & office building. (r-2,e,b) 100% affordable studios & 1 bedroom apartments for low-income households and transition aged youth (tay)Details
to erect 8 stories, 1 basement, type i-b, 63 residential units with child development center & office building. (r-2,e,b) 100% affordable studios & 1 bedroom apartments for low-income households and transition aged youth (tay) | $13,500,000 |
| Jun 3, 2019 | Completed final sign-off Oct 2021 | 691 China Basin St | Cahill Contractors Llc. | crane foundation and crane erection/installation. ref pa 2018-0419-6818 (s1). **maher n/a**Details
crane foundation and crane erection/installation. ref pa 2018-0419-6818 (s1). **maher n/a** | |
| Oct 5, 2018 | Completed final sign-off Apr 2019 | 1271 Treat Av | Build Group Inc. | to demolish one story, type 5 recreation center bldg.Details
to demolish one story, type 5 recreation center bldg. | $25,000 |
| Sep 25, 2018 | Completed final sign-off Jan 2019 | 27 Edith St | repair of rear 3' deck support.Details
repair of rear 3' deck support. | $9,000 | |
| Apr 19, 2018 | Completed final sign-off Oct 2021 | 691 China Basin St | Cahill Contractors Llc. | priority processing project. erect a new r-2,e,b 7 stories with 152 dwelling unit, no basement. residential,child developement center and art activity space. type 1a,iii,vaDetails
priority processing project. erect a new r-2,e,b 7 stories with 152 dwelling unit, no basement. residential,child developement center and art activity space. type 1a,iii,va | $90,000,000 |
| Jan 25, 2018 | Completed final sign-off Oct 2018 | 666 Ellis St | D & H Construction | improvements & completion of emergency generator (existing) permitted originally in 1993.Details
improvements & completion of emergency generator (existing) permitted originally in 1993. | $10,000 |
| Dec 22, 2017 | Completed final sign-off Apr 2021 | 1271 Treat Av | renovation of (e) pool building, replacement mechanical, electical, plumbing and pool systems. a (n) lobby & clubhose will be constructed to create one integrated facility.Details
renovation of (e) pool building, replacement mechanical, electical, plumbing and pool systems. a (n) lobby & clubhose will be constructed to create one integrated facility. | $7,750,000 | |
| Dec 22, 2017 | Expired or cancelled withdrawn Mar 2018 | 1271 Treat Av | to erect a 1-story clubhouse.Details
to erect a 1-story clubhouse. | $6,000,000 | |
| Mar 22, 2017 | Completed final sign-off Dec 2017 | 146 West Point Rd | Cahill-Nibbi Joint Venture | revision to 201406279737-s2-r1. revisions pertain to interiors of childcare center at wing - b level. add door b141 at corridor, add casework to classrooms, offices, staff loughe & kitchen. second we added to classroom b103-1, bottle washing station added to classroom b10-1Details
revision to 201406279737-s2-r1. revisions pertain to interiors of childcare center at wing - b level. add door b141 at corridor, add casework to classrooms, offices, staff loughe & kitchen. second we added to classroom b103-1, bottle washing station added to classroom b10-1 | $90,000 |
| Jan 12, 2017 | Completed final sign-off Dec 2017 | 146 West Point Rd | Cahill-Nibbi Joint Venture | revision to 201406279737 s2 to include elevator hoistway smoke detection access hatch & cage.Details
revision to 201406279737 s2 to include elevator hoistway smoke detection access hatch & cage. | |
| Sep 15, 2016 | Expired or cancelled withdrawn May 2017 | 325 Lombard St | Pfautz Design And Construction | front bldg. new windows, radiant heat, roofing, lighting, finishe, landscape, interior kitchen, bath & badroom remodel.Details
front bldg. new windows, radiant heat, roofing, lighting, finishe, landscape, interior kitchen, bath & badroom remodel. | $600,000 |
| Sep 15, 2016 | Expired or cancelled withdrawn May 2017 | 329 Lombard St | Pfautz Design And Construction | rear bldg. new windows, new bedroom, & entry vestibule addition, new roofing, lighting, finishes, landscape.Details
rear bldg. new windows, new bedroom, & entry vestibule addition, new roofing, lighting, finishes, landscape. | $250,000 |
| Jan 27, 2016 | Completed final sign-off Jun 2017 | 1880 Pine St | Nibbi Bros Assoc Inc. | this is a revision to approved permit 2015-0327-2042, to clarify full scope of accessibility imiprovements required by mayor's office on disability in their enforcement o f the 2010 ada standards and the cbc. maher naDetails
this is a revision to approved permit 2015-0327-2042, to clarify full scope of accessibility imiprovements required by mayor's office on disability in their enforcement o f the 2010 ada standards and the cbc. maher na | |
| Jan 13, 2016 | Completed final sign-off Apr 2017 | 939 Eddy St | Transworld Construction | this is a revision to pa#201503261963 in order to clarify the full scope of accessibility improvement required by mayor's office on disability in their enforcement of the 2010 ada standards and the california building code.Details
this is a revision to pa#201503261963 in order to clarify the full scope of accessibility improvement required by mayor's office on disability in their enforcement of the 2010 ada standards and the california building code. | |
| Jan 13, 2016 | Never finaled issued Jan 2016, no final | 951 Eddy St | Transworld Construction | this is a revision to pa#201503261957 in order to clarify the full scope of accessibility improvement required by mayor's office on disability in their enforcement of the 2010 ada standards and the california building code.Details
this is a revision to pa#201503261957 in order to clarify the full scope of accessibility improvement required by mayor's office on disability in their enforcement of the 2010 ada standards and the california building code. | |
| Mar 31, 2015 | Completed final sign-off Feb 2018 | 666 Ellis St | D & H Construction | mohcd rad project. renovation. access upgrades, lobby reconfiguration. elevator modernization, roofing, new fire sprinkler system, new windows, apartment units upgrades: fixtures, casework, finishes. convert 1 unit used for storge into new management office. sprinklers & fire alarm separate permit.Details
mohcd rad project. renovation. access upgrades, lobby reconfiguration. elevator modernization, roofing, new fire sprinkler system, new windows, apartment units upgrades: fixtures, casework, finishes. convert 1 unit used for storge into new management office. sprinklers & fire alarm separate permit. | $8,100,000 |
| Mar 26, 2015 | Completed final sign-off May 2017 | 951 Eddy St | Transworld Construction | mohcd rad program submittal. renovation; accessibility improvements, deferred maintenance, community space upgrades, finishes, roof, mep included. elevator controller, sprinklers and fire alarm under seperate permit.Details
mohcd rad program submittal. renovation; accessibility improvements, deferred maintenance, community space upgrades, finishes, roof, mep included. elevator controller, sprinklers and fire alarm under seperate permit. | $1,964,496 |
| Mar 26, 2015 | Completed final sign-off Apr 2017 | 939 Eddy St | Transworld Construction | mohcd rad program submittal. renovation; accessibility upgrades, ufe safety upgrades, soft-story improvement, deferred maintenance, finishes, fixtures, paint, roof, mep included. sprinkler's and fire alarm under seperate permit.Details
mohcd rad program submittal. renovation; accessibility upgrades, ufe safety upgrades, soft-story improvement, deferred maintenance, finishes, fixtures, paint, roof, mep included. sprinkler's and fire alarm under seperate permit. | $3,148,459 |
| Dec 15, 2014 | Completed final sign-off Mar 2016 | 543 Howard St | Cannon Constructors North Inc | title 24- lighting for tenant improvement to pa# 201409055601. title 24- mechanical.Details
title 24- lighting for tenant improvement to pa# 201409055601. title 24- mechanical. | $273,535 |
| Jun 27, 2014 | Completed final sign-off Dec 2017 | 146 West Point Rd | Cahill-Nibbi Joint Venture | to erect 5 stories, no basement, 72 dwelling units residential multi-family, commercial, mixed use bldg.Details
to erect 5 stories, no basement, 72 dwelling units residential multi-family, commercial, mixed use bldg. | $25,073,500 |
| Dec 2, 2013 | Completed final sign-off Mar 2017 | 1500 Page St | renovation of an (e) building into 17 units of housing for developmentally disabled adults.Details
renovation of an (e) building into 17 units of housing for developmentally disabled adults. | $3,300,000 | |
| Oct 9, 2013 | Completed final sign-off Mar 2015 | 600 Columbus Av | to demolish 1 story restroom.Details
to demolish 1 story restroom. | $65,000 | |
| Aug 20, 2013 | Completed final sign-off Jun 2017 | 140 Middle Point Rd | Cahill-Nibbi Joint Venture | erect 5-story, type 3, 1 basement/garage, 50 dwelling units building.Details
erect 5-story, type 3, 1 basement/garage, 50 dwelling units building. | $11,100,000 |
| Aug 20, 2013 | Completed final sign-off Apr 2017 | 148 Middle Point Rd | Cahill-Nibbi Joint Venture | to erect 3-story, type 5, no basement, 7 dwelling units building.Details
to erect 3-story, type 5, no basement, 7 dwelling units building. | $3,000,000 |
| Aug 20, 2013 | Completed final sign-off Jun 2017 | 112 West Point Rd | Cahill-Nibbi Joint Venture | to erect 3-story, type 5, no basement, 7 dwelling units building.Details
to erect 3-story, type 5, no basement, 7 dwelling units building. | $3,000,000 |
| Aug 20, 2013 | Completed final sign-off Jun 2017 | 120 Middle Point Rd | Cahill-Nibbi Joint Venture | erect 3-story, type 5, no basement, 7 dwelling units building.Details
erect 3-story, type 5, no basement, 7 dwelling units building. | $3,000,000 |
| Aug 20, 2013 | Completed final sign-off May 2017 | 142 West Point Rd | Cahill-Nibbi Joint Venture, Convergint Technologies Llc | erect 5-story, type 3, no basement, 50 dwelling units building.Details
erect 5-story, type 3, no basement, 50 dwelling units building. | $17,600,000 |
| Aug 20, 2013 | Completed final sign-off Jun 2017 | 110 Middle Point Rd | Cahill-Nibbi Joint Venture | to erect 3-story, type 5, no basement, 8 dwelling units building.Details
to erect 3-story, type 5, no basement, 8 dwelling units building. | $3,400,000 |
| Oct 17, 2012 | Completed final sign-off Sep 2013 | 555 Minna St | James E Roberts-Obayashi Corporation | for admin purposes only.rev to (e) 2011-0919-4932.provide oshpd certificate letter for proj 2011-0919-4932. see highlighted note in pre-app notes (sheet a0.1c in 2011-0919-4932). proj is part of development of (2) properties to serve as 1 facility. see 2011-909-4257 for adjacent lot 551 minna st.Details
for admin purposes only.rev to (e) 2011-0919-4932.provide oshpd certificate letter for proj 2011-0919-4932. see highlighted note in pre-app notes (sheet a0.1c in 2011-0919-4932). proj is part of development of (2) properties to serve as 1 facility. see 2011-909-4257 for adjacent lot 551 minna st. | |
| Aug 13, 2012 | Completed final sign-off Nov 2014 | 201 Turk St | James E Roberts-Obayashi Corporation | exterior painting, new roof, new flooring at all residential levels, new painting at interior, upgrade some light fixtures, rebuild courtyard.Details
exterior painting, new roof, new flooring at all residential levels, new painting at interior, upgrade some light fixtures, rebuild courtyard. | $4,000,000 |
| Oct 12, 2011 | Completed final sign-off Aug 2012 | 1 Montague Pl | Moroso Construction Inc | revision to approved pa# 2007.01.30.2873. new guard rail at roof deckDetails
revision to approved pa# 2007.01.30.2873. new guard rail at roof deck | |
| Sep 19, 2011 | Completed final sign-off Feb 2012 | 555 Minna St | James E Roberts-Obayashi Corporation | to demolish 2 stories, office building.Details
to demolish 2 stories, office building. | $20,000 |
| Sep 19, 2011 | Completed final sign-off Aug 2013 | 555 Minna St | James E Roberts-Obayashi Corporation | to erect 1 stories, social services building.Details
to erect 1 stories, social services building. | $500,000 |
| Sep 9, 2011 | Completed final sign-off Aug 2013 | 551 Minna St | James E Roberts-Obayashi Corporation | remodeling of an (e) building, upgrade foundations, upgrade electrical, plumbing and new finishes.Details
remodeling of an (e) building, upgrade foundations, upgrade electrical, plumbing and new finishes. | $1,000,000 |
| Dec 3, 2009 | Completed final sign-off Sep 2011 | 185 06th St | Anton Kalafati | tenant improvement of 1st floor & basement fo the plaza apts for a 99-sear black-box theater with support spaces consisting of: 1st floor- lobby, office, basement-lobby, restrooms, green room, black box performance space, tech, booth, dressing room & storage. note: see fire comments below.Details
tenant improvement of 1st floor & basement fo the plaza apts for a 99-sear black-box theater with support spaces consisting of: 1st floor- lobby, office, basement-lobby, restrooms, green room, black box performance space, tech, booth, dressing room & storage. note: see fire comments below. | $347,500 |
| May 27, 2009 | Completed final sign-off Nov 2011 | 1801 Green St | renovation & small addition to an (e) san francisco library, scope of work to include seismic upgrade, accessibility access, mechanical & electrical uprgadesDetails
renovation & small addition to an (e) san francisco library, scope of work to include seismic upgrade, accessibility access, mechanical & electrical uprgades | $4,500,000 | |
| Dec 10, 2008 | Completed final sign-off Mar 2009 | 1 South Van Ness Av | Chiang C M Construction Inc. | interior demolition of partition walls, finishes, fixtures, and equipment on 6th fl, and partial basement enant space, to comply w/ ab-017. ref pa #200807146652.Details
interior demolition of partition walls, finishes, fixtures, and equipment on 6th fl, and partial basement enant space, to comply w/ ab-017. ref pa #200807146652. | $22,989 |
| Nov 7, 2008 | Completed final sign-off Dec 2010 | 165 Turk St | D.F.P.F Corp Dba Fine Line Construction | renovation & accessibility upgrade of (e) low-income apartment complex (details on cover sheet). voluntary seismic retrofit of an existing low-income apartment complex. sprinkler and fire alarm are required under separate permit.Details
renovation & accessibility upgrade of (e) low-income apartment complex (details on cover sheet). voluntary seismic retrofit of an existing low-income apartment complex. sprinkler and fire alarm are required under separate permit. | $75,000 |
| Nov 7, 2008 | Completed final sign-off Jan 2011 | 249 Eddy St | D.F.P.F Corp Dba Fine Line Construction | voluntary seismic retrofit of an existing low-income apartment complex. life safety (sprinkler and fa) under separate permit.Details
voluntary seismic retrofit of an existing low-income apartment complex. life safety (sprinkler and fa) under separate permit. | $300,000 |
| Sep 19, 2008 | Expired or cancelled expired Jun 2010 | 165 Turk St | renovation of facade at ground floorDetails
renovation of facade at ground floor | $45,000 | |
| Sep 19, 2008 | Completed final sign-off Jan 2011 | 249 Eddy St | renovation of facade at 1st & 2nd floorsDetails
renovation of facade at 1st & 2nd floors | $51,000 | |
| Jul 22, 2008 | Completed final sign-off Dec 2009 | 762 Fulton St | ground floor, 2nd & 3rd floor - barrier removal project under cb 1134b.2, exception 2j. upgrade toilets on g/f, 2nd fl & 3rd fl, upgrade accessible parking, upgrade lobby lighting & ratip, upgrade some finishes.Details
ground floor, 2nd & 3rd floor - barrier removal project under cb 1134b.2, exception 2j. upgrade toilets on g/f, 2nd fl & 3rd fl, upgrade accessible parking, upgrade lobby lighting & ratip, upgrade some finishes. | $650,000 | |
| Jul 14, 2008 | Completed final sign-off Feb 2010 | 1 South Van Ness Av | basment (partial) & 6th floor tenant improvements to 6th floor offices-new ceilings, filing systems, structural support, work stations, casework, electrical, mechanical, plumbing. demo of storage room and construction of storeroom, small office in basement.Details
basment (partial) & 6th floor tenant improvements to 6th floor offices-new ceilings, filing systems, structural support, work stations, casework, electrical, mechanical, plumbing. demo of storage room and construction of storeroom, small office in basement. | ||
| Feb 28, 2008 | Never finaled issued Feb 2008, no final | 2695 19th Av | Thompson Builders Corp | revision to application # 200509304488, addition of 1 hour wall & double doors to create boiler room.Details
revision to application # 200509304488, addition of 1 hour wall & double doors to create boiler room. | $8,500 |
| Feb 15, 2008 | Never finaled issued Feb 2008, no final | 6221 Geary Bl | J M A Construction | application is for minor revision to building pa# 200608048633, revision clarifies intent to install 1 new smoke guard and 1 local smoke detector at (e) 3rd floor elevatorDetails
application is for minor revision to building pa# 200608048633, revision clarifies intent to install 1 new smoke guard and 1 local smoke detector at (e) 3rd floor elevator | |
| Dec 15, 2006 | Completed final sign-off Sep 2007 | 1999 Pacific Av | interior renovation and 13 sq.ft. horizontal additioin of bay window at north facade. shear wall at garage, new french doors and window at ground level.Details
interior renovation and 13 sq.ft. horizontal additioin of bay window at north facade. shear wall at garage, new french doors and window at ground level. | $105,400 | |
| Nov 20, 2006 | Completed final sign-off Dec 2006 | 1999 Pacific Av | renew pa#9608268s for final inspection only.Details
renew pa#9608268s for final inspection only. | ||
| Sep 1, 2006 | Completed final sign-off Oct 2008 | 2695 19th Av | demolish 1 story indoor swimming pool bldg.Details
demolish 1 story indoor swimming pool bldg. | ||
| Aug 4, 2006 | Completed final sign-off Jun 2008 | 6221 Geary Bl | J M A Construction | capital improvements to exist 3-story office bldg w/ childcare. include 1st floor toilet room upgrades, new guardrails/handrails @ entry, new drinking fountain @ 1st floor, new exit signage @ 1st floor, new curb ramp & sidewalk.Details
capital improvements to exist 3-story office bldg w/ childcare. include 1st floor toilet room upgrades, new guardrails/handrails @ entry, new drinking fountain @ 1st floor, new exit signage @ 1st floor, new curb ramp & sidewalk. | $183,430 |
| Sep 30, 2005 | Never finaled issued Aug 2007, no final | 2695 19th Av | to erect swimming pool.Details
to erect swimming pool. | ||
| Sep 30, 2005 | Completed final sign-off Jul 2008 | 820 Battery St | James E Roberts-Obayashi Corporation | t.i. for child care facility for low income families-1st floor,new occupancy.Details
t.i. for child care facility for low income families-1st floor,new occupancy. | $400,000 |
| Oct 9, 2001 | Expired or cancelled expired Oct 2003 | 3151 Sacramento St | revision to app #886282 revised stair for rear units 3 and 4Details
revision to app #886282 revised stair for rear units 3 and 4 | $11,575 | |
| Mar 30, 2001 | Expired or cancelled expired Oct 2008 | 1331 Green St | erect a one story single family dwellingDetails