John Laws
- Listed as
- architect, authorized agent-others, engineer
- Firm
- Structural Design Engineer
- Based in
- San Francisco
- On San Francisco permits
- Sep 2002 to May 2014
24 permits since 2000 (engineer on 20 permits, architect on 3 permits, authorized agent-others on 1 permit): 17 completed, 2 never finaled, 5 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 5, 2014 | Completed final sign-off May 2016 | 1751 Carroll Av | Nibbi Bros Assoc Inc. | revision to addendum 1 - foundation and superstructure for appl. 2012.1107.3775s1. compliance with ordinance no. 155-13 not required.Details
revision to addendum 1 - foundation and superstructure for appl. 2012.1107.3775s1. compliance with ordinance no. 155-13 not required. | |
| Jan 30, 2013 | Expired or cancelled expired Aug 2023 | 1355 Market St | Durkin Signs & Graphics Inc | erect electric, projecting, double faced sign.Details
erect electric, projecting, double faced sign. | $100,000 |
| Jul 30, 2012 | Completed final sign-off Oct 2012 | 1407 Montgomery St | All Bay Construction Inc | revision to guardrail curb on permit app#201201132198 unit#3Details
revision to guardrail curb on permit app#201201132198 unit#3 | |
| Mar 12, 2012 | Completed final sign-off Feb 2014 | 17 Alta St | Eignor Construction Inc. | remodel & add'n to(e)historic residen. ext'r work include removal of shingle cladding @ front elevation & orig siding underneath be repaired/restored. at rear a small add'n be contructed w/(n)siding, roofing, doors, windows. int'r, 1st fl remodeled kitchen, dining rm & powder rm. 2nd fl: (n) bedrm.Details
remodel & add'n to(e)historic residen. ext'r work include removal of shingle cladding @ front elevation & orig siding underneath be repaired/restored. at rear a small add'n be contructed w/(n)siding, roofing, doors, windows. int'r, 1st fl remodeled kitchen, dining rm & powder rm. 2nd fl: (n) bedrm. | $150,000 |
| Jan 13, 2012 | Completed final sign-off Oct 2012 | 1407 Montgomery St | All Bay Construction Inc | revision to appl #2011.08.04.1754 - removal of (e) guardrails & install (n) code compliant guardrail. removal of (e) terra cotta decking & replace with (n) like kind. replace (e) flashing at parapet & replace with (n) like kind.Details
revision to appl #2011.08.04.1754 - removal of (e) guardrails & install (n) code compliant guardrail. removal of (e) terra cotta decking & replace with (n) like kind. replace (e) flashing at parapet & replace with (n) like kind. | $11,000 |
| Dec 22, 2011 | Never finaled issued Feb 2012, no final | 52 Middle Point Rd | Cahill-Nibbi Joint Venture | az all thread tie down system is being proposed for use on the project cal & plans to review by dbi to allow z4 system to be used by constractor. ref. to pa #200912223722.Details
az all thread tie down system is being proposed for use on the project cal & plans to review by dbi to allow z4 system to be used by constractor. ref. to pa #200912223722. | $80,000 |
| Jul 27, 2011 | Expired or cancelled expired Jun 2014 | 1000 Francisco St | Clay Young, Gen'l Contractor | revision to pa# 2011/04/07/3642. this consists of additional voluntary structural upgrades. the original cost of construction in the original permit includes this work.Details
revision to pa# 2011/04/07/3642. this consists of additional voluntary structural upgrades. the original cost of construction in the original permit includes this work. | |
| Jul 12, 2011 | Expired or cancelled expired Jun 2014 | 1000 Francisco St | Clay Young, Gen'l Contractor | new parapet roof for sun room @ 2nd floor. new custom wood windows for sunroom that will be similar to (e) 2nd floor. structural upgrades to sunroom @ 2nd floor.Details
new parapet roof for sun room @ 2nd floor. new custom wood windows for sunroom that will be similar to (e) 2nd floor. structural upgrades to sunroom @ 2nd floor. | $56,000 |
| Jun 22, 2011 | Completed final sign-off Feb 2013 | 701 Golden Gate Av | Cahill Contractors Inc | tower crane foundation.Details
tower crane foundation. | $7,500 |
| Jun 7, 2011 | Never finaled issued Jun 2011, no final | 1270 Sanchez St | Teamwrkx Inc. | revision to 200812098151, new pier and grade beam foundation for steel momement frameDetails
revision to 200812098151, new pier and grade beam foundation for steel momement frame | $2,500 |
| Apr 7, 2011 | Expired or cancelled expired Jun 2014 | 1000 Francisco St | Clay Young, Gen'l Contractor | basement: floor in be lowered 6" norm of column line 3. new stair from 1st floor to basement. rehabilitation will include new office, bath, laundry. new concrete floor throughout. 1st floor: kitchen & powder room remodeled. 2nd floor: bedrooms & baths reconfigured & remodeled. structural improvementDetails
basement: floor in be lowered 6" norm of column line 3. new stair from 1st floor to basement. rehabilitation will include new office, bath, laundry. new concrete floor throughout. 1st floor: kitchen & powder room remodeled. 2nd floor: bedrooms & baths reconfigured & remodeled. structural improvement | $550,000 |
| Oct 20, 2010 | Completed final sign-off Oct 2012 | 1407 Montgomery St | Saarman Construction,Ltd. | repair dryrot damage, repair deficiencient waterproofing. in kind window replacement.all work courtyard of building, not visible from street.Details
repair dryrot damage, repair deficiencient waterproofing. in kind window replacement.all work courtyard of building, not visible from street. | $200,000 |
| Apr 7, 2010 | Completed final sign-off Sep 2011 | 365 Fulton St | Cahill Contractors Inc | building of foundation for tower crane to be used during construction of new bldg (pa #200807116520-s).Details
building of foundation for tower crane to be used during construction of new bldg (pa #200807116520-s). | $4,500 |
| Oct 13, 2009 | Completed final sign-off Jan 2010 | 2301 Mission St | Tuck Aire Htg &Air Cond. Corpdba Atlas H | install 5 furnaces, 2 roof packaged units, ductwork, 11 fire/smoke dampers, 1 supply fan, 1 roof exhaust fan, 5 bathroom fans. ref pa#2009-0722-3207 for t.i.Details
install 5 furnaces, 2 roof packaged units, ductwork, 11 fire/smoke dampers, 1 supply fan, 1 roof exhaust fan, 5 bathroom fans. ref pa#2009-0722-3207 for t.i. | $206,000 |
| Sep 26, 2007 | Completed final sign-off Jul 2008 | 3745 Divisadero St | Landi Construction Company | volentary structural strengthening & remodel unit 5.replace 18 windows in kitchens, bathrooms and dining rooms.Details
volentary structural strengthening & remodel unit 5.replace 18 windows in kitchens, bathrooms and dining rooms. | $40,000 |
| Aug 15, 2007 | Completed final sign-off Nov 2007 | 536 Laidley St | Grey Gates Construction | unit #536-revision to pa# 200705312610 to revise retaining wall detail. retaining wall is no longer required to return soilDetails
unit #536-revision to pa# 200705312610 to revise retaining wall detail. retaining wall is no longer required to return soil | |
| May 8, 2007 | Completed final sign-off Feb 2010 | 1900 Geary Bl | seismic, access upgrades & renovation. renovate the (e) pool building & gymnasium . the (e) recreation center bldg. & pool locker rooms will be removed & replaced with a new one story bldg. site improvements include a new playground, play structures and new accessible ramps and entrances.Details
seismic, access upgrades & renovation. renovate the (e) pool building & gymnasium . the (e) recreation center bldg. & pool locker rooms will be removed & replaced with a new one story bldg. site improvements include a new playground, play structures and new accessible ramps and entrances. | ||
| Nov 8, 2006 | Completed final sign-off Nov 2006 | 1000 Sutter St | Donald S. Maclean, Inc | renew pa# 200508291431 for final inspection.Details
renew pa# 200508291431 for final inspection. | |
| Jul 22, 2005 | Completed final sign-off Jan 2006 | 252 Grattan St | Phollies Inc | remodel kitchen. lower unit. replace bearing wall. between dining room and kitchen. with steel beam.Details
remodel kitchen. lower unit. replace bearing wall. between dining room and kitchen. with steel beam. | $85,000 |
| Jun 16, 2005 | Completed final sign-off Oct 2007 | 420 Berry St | indicator piles as show on plansDetails
indicator piles as show on plans | $96,250 | |
| Oct 28, 2004 | Completed final sign-off May 2005 | 1301 Polk St | revision to permit appln #2002/07/29/2568s sidewalk structural repairDetails
revision to permit appln #2002/07/29/2568s sidewalk structural repair | $47,000 | |
| Oct 19, 2004 | Completed final sign-off Jan 2005 | 222 Kearny St | Richlen Construction | oti-2 6/f, el, me, ls, spDetails
oti-2 6/f, el, me, ls, sp | $85,000 |
| Jul 28, 2003 | Expired or cancelled expired Jun 2004 | 2338 Pine St | underpin approx 3 lineal ft under (e) ftg.Details
underpin approx 3 lineal ft under (e) ftg. | $1,000 | |
| Sep 18, 2002 | Completed final sign-off Feb 2008 | 278 Roosevelt Wy | to erect single family residenceDetails
to erect single family residence | $275,000 |