- On San Francisco permits
- Nov 2013 to Nov 2026
763 permits since 2000 (engineer on 665 permits, architect on 44 permits, designer on 32 permits, authorized agent-others on 21 permits, pmt consultant/expediter on 2 permits): 535 completed, 66 in progress, 46 never finaled, 116 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the 100 most recent of their permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- Wong Construction Inc (11), Sincere Construction Company Inc (10), G B U Construction Development (4), Hong's General Construction Inc (4), J P F Construction (4), Bai Construction (3), O'pro Construction Inc. (3), Yu Kwan Construction Co. (3), Dliu Construction (2), I E General Const Inc (2), Jdesignbuild (2), Leonard Schendel Const.Co (2), 3b T's Construction Company, Axel8 Construction, Bao Hengda Inc, Best Level Construction Inc, D L Construction, Doherty Restoration, Inc., E. Arias & Co, Egoodat Inc, Fale Construction, Gao Wu Construction Inc, Gdh Roofing & Building Inc, Gee Construction Co Inc, H & Bo Construction Inc., J C General Construction, L & G Construction, Lsr Maintenance Llc, Modern Construction Inc, Mr Wu Construction, Nexus Construction Hub, Q & Qq Construction Inc, Ryz Construction Inc, S C Construction Company, Threemile Construction, Tritec Construction Co Inc--See Notes, Wing Chow Construction, Zm Builders Inc
- Architects
- Dane Bunton, Janet Campbell, Xie Xing "Bill" Guan
- Engineers
- Nathan Williams
- Authorized agents
- Behnam Afshar
Where they worked
- Single-family 46
- Multi-family (2-family, apartments) 28
- Commercial 26
- Other or unknown 0
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
Showing the 100 most recent of 763.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 6, 2026 | In progress filed Nov 2026, not yet issued | 374 19th Av | seismic retrofit of soft story comply with sfebc 4d mandatory seismic retrofit per 2025 cebc appendix a4. comply with 202663641.Details
seismic retrofit of soft story comply with sfebc 4d mandatory seismic retrofit per 2025 cebc appendix a4. comply with 202663641. | $90,000 | |
| Nov 6, 2026 | In progress filed Nov 2026, not yet issued | 1269 Silver Av | add new bathroom in the attic, no change to roof height, only e) spaceDetails
add new bathroom in the attic, no change to roof height, only e) space | $20,000 | |
| Oct 26, 2026 | In progress filed Oct 2026, not yet issued | 1625 Polk St | revision to 202604169602 and 202604280276. revise shear walls on 1st flDetails
revision to 202604169602 and 202604280276. revise shear walls on 1st fl | ||
| Oct 23, 2026 | In progress filed Oct 2026, not yet issued | 1350 04th Av | interior remodel 1st floor, 2nd floor and 3rd floor. | $200,000 | |
| Oct 21, 2026 | In progress issued Nov 2026 | 342 09th St | Nexus Construction Hub | create new opening in two existing concrete wall on the first floor. opening size are 7' wide by 7' tall, and 11' wide by 7'-8" tall (interior load bearing wall)Details
create new opening in two existing concrete wall on the first floor. opening size are 7' wide by 7' tall, and 11' wide by 7'-8" tall (interior load bearing wall) | $35,000 |
| Oct 9, 2026 | In progress issued Oct 2026 | 65 Turquoise Wy | Wong Construction Inc | replace existing front stair with new stair in kind.Details
replace existing front stair with new stair in kind. | $40,000 |
| Sep 29, 2026 | In progress issued Oct 2026 | 1269 Silver Av | J P F Construction | interior remodel: 1) 2nd floor add new bath, bedroom, and laundry room. 2) 1st floor to add new bathroom, new bedroom and new entertainment room.Details
interior remodel: 1) 2nd floor add new bath, bedroom, and laundry room. 2) 1st floor to add new bathroom, new bedroom and new entertainment room. | $200,000 |
| Sep 24, 2026 | In progress issued Sep 2026 | 615 23rd Av | revision to pa 202609047748 remove footings on the 1st fl; remain existing garage door size; remove skylightDetails
revision to pa 202609047748 remove footings on the 1st fl; remain existing garage door size; remove skylight | ||
| Sep 8, 2026 | In progress filed Sep 2026, not yet issued | 55 Oliver St | revision to pa# 2026-0702-4523. revise shear walls, floor joists, add new concrete footing, posts and beams. no exterior work.Details
revision to pa# 2026-0702-4523. revise shear walls, floor joists, add new concrete footing, posts and beams. no exterior work. | ||
| Sep 4, 2026 | In progress issued Sep 2026 | 615 23rd Av | Gdh Roofing & Building Inc | add new bath, bedrooms & office in the 1st fl. add new stair, bathrooms, remove interior walls in the 2nd fl.Details
add new bath, bedrooms & office in the 1st fl. add new stair, bathrooms, remove interior walls in the 2nd fl. | $180,000 |
| Aug 28, 2026 | In progress issued Sep 2026 | 615 23rd Av | infill existing light well | $6,000 | |
| Aug 28, 2026 | Expired or cancelled withdrawn Sep 2026 | 615 23rd Av | interio remodel: relocate stair, bathroom, remove interior walls in the 2nd/f. add new bedrooms & office in the 1st/f. (infill lightwell under seperated permit 202608287394)Details
interio remodel: relocate stair, bathroom, remove interior walls in the 2nd/f. add new bedrooms & office in the 1st/f. (infill lightwell under seperated permit 202608287394) | $200,000 | |
| Aug 21, 2026 | In progress issued Oct 2026 | 1775 47th Av | J P F Construction | interior remodel with remove interior walls, new deck and stair in the rear yard. infill interior stair.Details
interior remodel with remove interior walls, new deck and stair in the rear yard. infill interior stair. | $20,000 |
| Aug 13, 2026 | In progress issued Aug 2026 | 1031 Noriega St | I E General Const Inc | interior remodel: convert existing ground floor stoarage to new habitable space with 2 bedrooms, 2 bathrooms, 1 mudroom and 1 family room. reconfigure 2nd floor. replace existing windows and add 2 skylights. replace & relocate exiting furnace and water heater & build new deck.Details
interior remodel: convert existing ground floor stoarage to new habitable space with 2 bedrooms, 2 bathrooms, 1 mudroom and 1 family room. reconfigure 2nd floor. replace existing windows and add 2 skylights. replace & relocate exiting furnace and water heater & build new deck. | $200,000 |
| Aug 12, 2026 | In progress issued Oct 2026 | 1422 Powell St | Ryz Construction Inc | interior remodel in the 2nd floor on existing unit.Details
interior remodel in the 2nd floor on existing unit. | $40,000 |
| Aug 11, 2026 | In progress filed Aug 2026, not yet issued | 2221 Pacific Av | adu at basement per ord# 162-16 within (e) envelope. convert basement space into 2 adu (unit# 6 & # 7). kitchan, living room, 2 bedroom, 2 bathroms on each adu. 1st floor-unit# 1: relocate kitchen. convert original kitchen space into new bedroom. add 1 full bahroom at hallway space. adu conversion &Details
adu at basement per ord# 162-16 within (e) envelope. convert basement space into 2 adu (unit# 6 & # 7). kitchan, living room, 2 bedroom, 2 bathroms on each adu. 1st floor-unit# 1: relocate kitchen. convert original kitchen space into new bedroom. add 1 full bahroom at hallway space. adu conversion & | $200,000 | |
| Aug 7, 2026 | In progress issued Sep 2026 | 869 Washington St | Sincere Construction Company Inc | convert store front entrance into ada complianceDetails
convert store front entrance into ada compliance | $8,000 |
| Jul 28, 2026 | In progress issued Jul 2026 | 1625 Polk St | Sincere Construction Company Inc | residential: seismic retrofit of soft story comply with sfebc 4d mandatory seismic retrofit per 2025 cebc appendix a4. commercial soft story pa # 202604280276Details
residential: seismic retrofit of soft story comply with sfebc 4d mandatory seismic retrofit per 2025 cebc appendix a4. commercial soft story pa # 202604280276 | $90,000 |
| Jul 17, 2026 | In progress filed Jul 2026, not yet issued | 3557 Geary Bl | add rooms in the commercial space for proposed piano studioDetails
add rooms in the commercial space for proposed piano studio | $90,000 | |
| Jul 7, 2026 | In progress issued Jul 2026 | 1830 Lyon St | G B U Construction Development | voluntary structural strenthening in the rear garage.Details
voluntary structural strenthening in the rear garage. | $20,000 |
| Jul 2, 2026 | In progress issued Jul 2026 | 55 Oliver St | Hong's General Construction Inc | interior remodel/convert 1st fl into living space. 2nd fl - add new deck in the rear; 1st fl - add new bathrooms, new office, new bedrooms, new living room and storageDetails
interior remodel/convert 1st fl into living space. 2nd fl - add new deck in the rear; 1st fl - add new bathrooms, new office, new bedrooms, new living room and storage | $150,000 |
| Jun 26, 2026 | In progress issued Jul 2026 | 2172 Pacific Av | Q & Qq Construction Inc | unit #1: interior refurbishment & bathroom remodel. (n) non-load partition wall in garage for laundry room. electrical refurbishment.Details
unit #1: interior refurbishment & bathroom remodel. (n) non-load partition wall in garage for laundry room. electrical refurbishment. | $25,000 |
| May 29, 2026 | In progress issued Jun 2026 | 2932 21st St | Lsr Maintenance Llc | interior remodel to the front apt units.Details
interior remodel to the front apt units. | $200,000 |
| May 15, 2026 | In progress filed May 2026, not yet issued | 342 09th St | remove storage room & infill the front door entrance ramp in the 1st/f (interior work only)Details
remove storage room & infill the front door entrance ramp in the 1st/f (interior work only) | $15,000 | |
| May 12, 2026 | Completed final sign-off Sep 2026 | 901 Irving St | Wong Construction Inc | revision to pa# 202603278474: add new ada bath and remove (e) posts in the ground floor.Details
revision to pa# 202603278474: add new ada bath and remove (e) posts in the ground floor. | $20,000 |
| May 5, 2026 | In progress issued May 2026 | 1108 Stockton St | Sincere Construction Company Inc | revision to pa 202506249362 replace existing slab with new concrete slab in the basement levelDetails
revision to pa 202506249362 replace existing slab with new concrete slab in the basement level | $15,000 |
| Apr 28, 2026 | In progress issued Jul 2026 | 1621 Polk St | Sincere Construction Company Inc | soft story retrofit per sfebc chapter 4d engineering criteria cebc appendix a-4 (commercial). provide accessible restroom upgrade (d.a. checklist). this permit for commercial spaces. residential soft story under pa 202604169602Details
soft story retrofit per sfebc chapter 4d engineering criteria cebc appendix a-4 (commercial). provide accessible restroom upgrade (d.a. checklist). this permit for commercial spaces. residential soft story under pa 202604169602 | $90,000 |
| Apr 24, 2026 | Completed final sign-off Jun 2026 | 235 Holyoke St | Hong's General Construction Inc | to comply with nov 202426211 - infill internal stair, addition of bathroom and walls, and bathroom remodel.Details
to comply with nov 202426211 - infill internal stair, addition of bathroom and walls, and bathroom remodel. | $10,000 |
| Apr 21, 2026 | In progress issued Sep 2026 | 65 Upland Dr | Sincere Construction Company Inc | replace existing footing with new concrete footing.Details
replace existing footing with new concrete footing. | $30,000 |
| Mar 27, 2026 | Completed final sign-off Sep 2026 | 901 Irving St | Wong Construction Inc | voluntary structural strengthening .replace front entry at commercial unitDetails
voluntary structural strengthening .replace front entry at commercial unit | $90,000 |
| Mar 9, 2026 | Completed final sign-off Jun 2026 | 554 Head St | L & G Construction | 1.wall removal on the 2nd floor. 2. 2nd floor relocate kitchen and add new bathroom ground level to comply to nov #202545967.Details
1.wall removal on the 2nd floor. 2. 2nd floor relocate kitchen and add new bathroom ground level to comply to nov #202545967. | $10,000 |
| Feb 6, 2026 | In progress issued Oct 2026 | 836 Lyon St | G B U Construction Development | add new retaining wall in the rear yardDetails
add new retaining wall in the rear yard | $40,000 |
| Jan 16, 2026 | In progress filed Jan 2026, not yet issued | 1458 09th Av | legalize the new bedroom in the rear of the building | $30,000 | |
| Jan 9, 2026 | In progress filed Jan 2026, not yet issued | 230 Eureka St | construct new concrete retaining walls and new roof in the garage.Details
construct new concrete retaining walls and new roof in the garage. | $40,000 | |
| Dec 10, 2025 | In progress issued Feb 2026 | 1378 30th Av | Zm Builders Inc | 2nd/f: kitchen & bathroom remodel, add 1 office, 1 master bathroom, relocate stairs. 1st/f: add 2 bedrooms, 2 bathrooms & 1 media room w/wet bar (938 sf), replace heating to radiant heat, upgrade panel to 200 ampDetails
2nd/f: kitchen & bathroom remodel, add 1 office, 1 master bathroom, relocate stairs. 1st/f: add 2 bedrooms, 2 bathrooms & 1 media room w/wet bar (938 sf), replace heating to radiant heat, upgrade panel to 200 amp | $289,158 |
| Dec 5, 2025 | In progress issued Jan 2026 | 1625 Polk St | Sincere Construction Company Inc | voluntary strentheing of exising concrete retaining wall in the rear of the bldg.Details
voluntary strentheing of exising concrete retaining wall in the rear of the bldg. | $30,000 |
| Nov 21, 2025 | Completed final sign-off Feb 2026 | 471 19th Av | Wong Construction Inc | add new anchor bolts in the existing concrete footings.Details
add new anchor bolts in the existing concrete footings. | $10,000 |
| Oct 24, 2025 | In progress issued Oct 2025 | 1625 Polk St | Sincere Construction Company Inc | add concrete footing in the basement level.Details
add concrete footing in the basement level. | $60,000 |
| Oct 24, 2025 | In progress filed Oct 2025, not yet issued | 919 Capitol Av | garage lvl: convert garage to living space 644 sf: add 2 bedrooms, 1 bath, 1 family rm & wet bar. 2nd/f: add new bath, rear deck. comply w/ all nov's (201699061, 202423928, 201699051, 202423192, 202423663, 202314995, 202423291, 202540923, 201698141)Details
garage lvl: convert garage to living space 644 sf: add 2 bedrooms, 1 bath, 1 family rm & wet bar. 2nd/f: add new bath, rear deck. comply w/ all nov's (201699061, 202423928, 201699051, 202423192, 202423663, 202314995, 202423291, 202540923, 201698141) | $180,000 | |
| Oct 22, 2025 | In progress issued Aug 2026 | 439 Duboce Av | Egoodat Inc | repair damaged structure by: replace existing footing with new concrete footing. comply with nov #202543420. proposed front entry and facade alteration add power door operator on the front door.Details
repair damaged structure by: replace existing footing with new concrete footing. comply with nov #202543420. proposed front entry and facade alteration add power door operator on the front door. | $30,000 |
| Oct 17, 2025 | In progress issued Oct 2025 | 200 Colon Av | Hong's General Construction Inc | add 1 more bathroom on main floor.Details
add 1 more bathroom on main floor. | $20,000 |
| Oct 3, 2025 | Completed final sign-off Jan 2026 | 484 Guerrero St | Doherty Restoration, Inc. | revision to 202212228969: revise wall layout in 1st/fDetails
revision to 202212228969: revise wall layout in 1st/f | |
| Sep 3, 2025 | Completed final sign-off Feb 2026 | 531 Bowdoin St | Bao Hengda Inc | rev to pa# 2025-0318-2500: remove one skylight in the roof, add beam in the 2nd fl. and remove footing in the first fl. add two burner stove on first flr.Details
rev to pa# 2025-0318-2500: remove one skylight in the roof, add beam in the 2nd fl. and remove footing in the first fl. add two burner stove on first flr. | |
| Aug 27, 2025 | Completed final sign-off Oct 2025 | 855 41st Av | J P F Construction | relocate the retaining walls in the basement level. reconfigure layout in the 1st floor. enlarge basement level, new wet bar. delete skylight in the roof. revison to pa #202207299584. comply to nov #202428123Details
relocate the retaining walls in the basement level. reconfigure layout in the 1st floor. enlarge basement level, new wet bar. delete skylight in the roof. revison to pa #202207299584. comply to nov #202428123 | $10,000 |
| Aug 27, 2025 | In progress filed Aug 2025, not yet issued | 3864 24th St | reconfigure layout in the coffee shop. relocate bathroom and add (n) walls in the rear of the building. ref 202507281718 and revision 202503212787Details
reconfigure layout in the coffee shop. relocate bathroom and add (n) walls in the rear of the building. ref 202507281718 and revision 202503212787 | $50,000 | |
| Aug 15, 2025 | In progress issued Mar 2026 | 827 Goettingen St | Best Level Construction Inc | interior remodel: install smoke detector, reroute electrical conduit in the 1st floor, enlarge corridor in the 1st floor, seal skylight in the roof. comply to complaint # 202421718 and 202421722Details
interior remodel: install smoke detector, reroute electrical conduit in the 1st floor, enlarge corridor in the 1st floor, seal skylight in the roof. comply to complaint # 202421718 and 202421722 | $10,000 |
| Aug 15, 2025 | Completed final sign-off Aug 2026 | 2100 Van Ness Av | Bai Construction | voluntary strenghthening new plywood and lateral ties at roof and new lateral ties at mezzanine, legalize ada bath on the 1st floor and add power door operator in the front door.Details
voluntary strenghthening new plywood and lateral ties at roof and new lateral ties at mezzanine, legalize ada bath on the 1st floor and add power door operator in the front door. | $150,000 |
| Aug 8, 2025 | In progress filed Aug 2025, not yet issued | 40 Gaven St | revision to 201705055874. revise concrete footings and wood beamsDetails
revision to 201705055874. revise concrete footings and wood beams | ||
| Jul 28, 2025 | Completed final sign-off Apr 2026 | 31 Mangels Av | O'pro Construction Inc. | interior remodel/convert part of ground/f into living space. 2nd fl kitchen wall demo & replace rear sliding door. relocate walls in the bedroom of 2nd fl. 1st fl to add new bath & laundry room. relocate walls in 1st fl.Details
interior remodel/convert part of ground/f into living space. 2nd fl kitchen wall demo & replace rear sliding door. relocate walls in the bedroom of 2nd fl. 1st fl to add new bath & laundry room. relocate walls in 1st fl. | $90,000 |
| Jul 11, 2025 | In progress filed Jul 2025, not yet issued | 1178 Union St | replace (e) stucco facade to be new hardie shingle | $25,000 | |
| Jul 11, 2025 | Completed final sign-off Apr 2026 | 1318 31st Av | G B U Construction Development | comply with nov 201888261. provide new concrete underpinning pits along property line.Details
comply with nov 201888261. provide new concrete underpinning pits along property line. | $40,000 |
| Jul 9, 2025 | In progress issued Jul 2025 | 2450 20th Av | G B U Construction Development, H & Bo Construction Inc. | revision 201803153794, change foundation design. change interior layout of unit to be legalized to comply with nov 201755441Details
revision 201803153794, change foundation design. change interior layout of unit to be legalized to comply with nov 201755441 | $150,000 |
| Jun 24, 2025 | In progress issued Jun 2025 | 1108 Stockton St | Sincere Construction Company Inc | replace existing plywood with new plywood in the first floor and add new concrete footing in the basement level.Details
replace existing plywood with new plywood in the first floor and add new concrete footing in the basement level. | $60,000 |
| Jun 13, 2025 | In progress filed Jun 2025, not yet issued | 377 Bay St | replace existing roof rafters with new roof rafters. | $40,000 | |
| Jun 10, 2025 | Completed final sign-off Jan 2026 | 356 Mount Vernon Av | S C Construction Company | remove posts, add new beam in the first flDetails
remove posts, add new beam in the first fl | $15,000 |
| May 22, 2025 | Completed final sign-off Aug 2025 | 2973 16th St | Bai Construction | facade repair work in accordance with approved facade survey #17622-2eDetails
facade repair work in accordance with approved facade survey #17622-2e | $10,000 |
| May 21, 2025 | In progress issued May 2025 | 1108 Stockton St | Sincere Construction Company Inc | ground floor for (e) sheetroock to be removed and restored with 1-hour fire-rated at property line and (n) ada bathroom. ground floor wall approximate 60'x10'hDetails
ground floor for (e) sheetroock to be removed and restored with 1-hour fire-rated at property line and (n) ada bathroom. ground floor wall approximate 60'x10'h | $20,000 |
| May 9, 2025 | In progress issued Nov 2025 | 180 De Soto St | Hong's General Construction Inc | provide temporary shoring to facilitate excavation & construction of this proposed remodel per pa# 202503253026Details
provide temporary shoring to facilitate excavation & construction of this proposed remodel per pa# 202503253026 | $8,000 |
| May 6, 2025 | Completed final sign-off Jun 2026 | 1841 24th Av | 3b T's Construction Company | build new kitchenette on ground floor. infill (e) lightwell on second floor. reconfigure and remodel (e) kitchen on second floor.Details
build new kitchenette on ground floor. infill (e) lightwell on second floor. reconfigure and remodel (e) kitchen on second floor. | $50,000 |
| Apr 23, 2025 | Completed final sign-off May 2025 | 1324 Pacific Av | Yu Kwan Construction Co. | to obtain final inspection for work approved under pa# 201608023968. all work is complete.Details
to obtain final inspection for work approved under pa# 201608023968. all work is complete. | |
| Apr 23, 2025 | Completed final sign-off May 2025 | 1324 Pacific Av | Yu Kwan Construction Co. | to obtain final inspection for work approved under pa# 201411060876, 201606170317, 201809281731. all work is complete.Details
to obtain final inspection for work approved under pa# 201411060876, 201606170317, 201809281731. all work is complete. | |
| Apr 23, 2025 | Completed final sign-off May 2025 | 1324 Pacific Av | Yu Kwan Construction Co. | to obtain final inspection for work approved under pa# 202102164654, 202208261423. all work is complete.Details
to obtain final inspection for work approved under pa# 202102164654, 202208261423. all work is complete. | |
| Apr 23, 2025 | Completed final sign-off Oct 2025 | 1162 Bowdoin St | O'pro Construction Inc. | interior remodel - add 1 bath and laundry room in the 1st fl; add new bedroom in the 1st fl; reconfigure layout in the 2nd flDetails
interior remodel - add 1 bath and laundry room in the 1st fl; add new bedroom in the 1st fl; reconfigure layout in the 2nd fl | $80,000 |
| Mar 26, 2025 | In progress filed Mar 2025, not yet issued | 2059 Fulton St | volutary structural strengthening in the building | $15,000 | |
| Mar 18, 2025 | In progress filed Mar 2025, not yet issued | 1333 42nd Av | replace e footing and slab with new concrete footing and slabDetails
replace e footing and slab with new concrete footing and slab | $120,000 | |
| Mar 4, 2025 | In progress issued Mar 2025 | 377 Bay St | Wong Construction Inc | volutary structrual strengthening in the buildlingDetails
volutary structrual strengthening in the buildling | $60,000 |
| Feb 11, 2025 | In progress issued Apr 2025 | 741 University St | Mr Wu Construction, Gao Wu Construction Inc | ground flr: add 2 bedrooms and 3 full bath. add (1) family room. 2/f: remodel (e) kitchen. remove (e) wall at kitchen area. remodel 2 bedroom and relocate 1 bed. remodel and relocate 2 full bath. add (1) full bath. remove (e) stair to g/f. add stair from 2/f to rear yard. add skylight andDetails
ground flr: add 2 bedrooms and 3 full bath. add (1) family room. 2/f: remodel (e) kitchen. remove (e) wall at kitchen area. remodel 2 bedroom and relocate 1 bed. remodel and relocate 2 full bath. add (1) full bath. remove (e) stair to g/f. add stair from 2/f to rear yard. add skylight and | $200,000 |
| Jan 31, 2025 | Completed final sign-off Jul 2026 | 1262 20th Av | Wing Chow Construction | addition : rear yard addition 91 sf, 3 story addition of total space 3x 91sf =273sf. (n) bathroom addition at 2nd and 3rd floor. ground floor to be garage and storage onlyDetails
addition : rear yard addition 91 sf, 3 story addition of total space 3x 91sf =273sf. (n) bathroom addition at 2nd and 3rd floor. ground floor to be garage and storage only | $30,000 |
| Jan 21, 2025 | Completed final sign-off Oct 2025 | 1619 Noe St | Jdesignbuild | remodel and reconfigure e 2 story single family dwelling. relocate e kitchen, relocate e bath 2nd fl.add 1 bath,bdrm, powder room, movie room and laundry at gr fl. relocate furnace and replace water heater. replace e windows in kind.Details
remodel and reconfigure e 2 story single family dwelling. relocate e kitchen, relocate e bath 2nd fl.add 1 bath,bdrm, powder room, movie room and laundry at gr fl. relocate furnace and replace water heater. replace e windows in kind. | $150,000 |
| Jan 21, 2025 | Completed final sign-off Jun 2026 | 1743 Larkin St | Fale Construction, E. Arias & Co | at 3/f: top unit remodel/relocate (e) kitchen and bathroom. remodel (e) kitchen to home office, add master bath to (e) bedroom, new furnace and w/h. new laundry.Details
at 3/f: top unit remodel/relocate (e) kitchen and bathroom. remodel (e) kitchen to home office, add master bath to (e) bedroom, new furnace and w/h. new laundry. | $89,000 |
| Dec 31, 2024 | Completed final sign-off Mar 2025 | 2239 29th Av | Wong Construction Inc | ref 201708286040 t0 abate nov 202429645 to include relocate the stairs and wood deck to the rear yard of building.Details
ref 201708286040 t0 abate nov 202429645 to include relocate the stairs and wood deck to the rear yard of building. | $8,000 |
| Dec 20, 2024 | Expired or cancelled expired Apr 2026 | 1555 41st Av | D L Construction | rehabilitate (e) bathroom at 2/f. install 2nd bathroom at 2/f. rahabilitate (e) bath 1. install new storage, laundry, and bathroom at 1/f. 1/f not habitable due to insufficient head height.Details
rehabilitate (e) bathroom at 2/f. install 2nd bathroom at 2/f. rahabilitate (e) bath 1. install new storage, laundry, and bathroom at 1/f. 1/f not habitable due to insufficient head height. | $60,000 |
| Dec 20, 2024 | Completed final sign-off Nov 2025 | 726 Clement St | O'pro Construction Inc. | comply to nov# 202315250: remove wall in the 3rd floor kitchen. repair all fire damage - sister joistsDetails
comply to nov# 202315250: remove wall in the 3rd floor kitchen. repair all fire damage - sister joists | $8,000 |
| Dec 6, 2024 | Completed final sign-off Apr 2025 | 2505 Sacramento St | Wong Construction Inc | add 2 doors @ corridor of 1st floorDetails
add 2 doors @ corridor of 1st floor | $8,000 |
| Nov 27, 2024 | In progress issued Dec 2024 | 375 Richland Av | Jdesignbuild | remodel (e) single family home. (n) skylight & (n) laundry at 3rd fl. add two half baths. replace & relocate water heater & furnace. replace all windows within (e) opening in kind. repair dry rot front exterior staircaseDetails
remodel (e) single family home. (n) skylight & (n) laundry at 3rd fl. add two half baths. replace & relocate water heater & furnace. replace all windows within (e) opening in kind. repair dry rot front exterior staircase | $100,000 |
| Nov 22, 2024 | In progress issued Dec 2025 | 3868 24th St | 1/f: add concrete footing, slab and replace existing floor to be new floor in vacant commercial.Details
1/f: add concrete footing, slab and replace existing floor to be new floor in vacant commercial. | $35,000 | |
| Nov 15, 2024 | In progress issued Sep 2025 | 3868 24th St | Leonard Schendel Const.Co | commercial: soft story retrofit per sfebc chapter 4d. 2022 cebc appendix a-4Details
commercial: soft story retrofit per sfebc chapter 4d. 2022 cebc appendix a-4 | $20,000 |
| Nov 15, 2024 | In progress issued Sep 2025 | 3864 24th St | Leonard Schendel Const.Co | residential: soft story retrofit per sfebc chapter 4d. 2022 cebc appendix a-4. to comply with nov# 2022-00114Details
residential: soft story retrofit per sfebc chapter 4d. 2022 cebc appendix a-4. to comply with nov# 2022-00114 | $40,000 |
| Nov 1, 2024 | Completed final sign-off Dec 2024 | 5830 Geary Bl | Wong Construction Inc | replace existing exhaust duct with new exhaust duct in the rear of the buildling. comply with complaint 202427114Details
replace existing exhaust duct with new exhaust duct in the rear of the buildling. comply with complaint 202427114 | $4,000 |
| Oct 16, 2024 | In progress issued Oct 2026 | 1902 Webster St | Modern Construction Inc | convert b into r-3. replace windows inkind at rear. 3rd floor: add m.bedroom, bath, 1/2 bath, playroom, n deck 2nd floor: add 3 bedrooms, 3 baths, laundry. 1st floor: add living , kitchen, dining, family room, half bath. basement: add int.stairs, garage, bath, sauna, ,media rms n curb cutDetails
convert b into r-3. replace windows inkind at rear. 3rd floor: add m.bedroom, bath, 1/2 bath, playroom, n deck 2nd floor: add 3 bedrooms, 3 baths, laundry. 1st floor: add living , kitchen, dining, family room, half bath. basement: add int.stairs, garage, bath, sauna, ,media rms n curb cut | $100,000 |
| Sep 20, 2024 | Completed final sign-off Dec 2024 | 1238 Stockton St | Wong Construction Inc | repair facade cladding in kind in front of bldg. no interior layout changeDetails
repair facade cladding in kind in front of bldg. no interior layout change | $30,000 |
| Sep 18, 2024 | Completed final sign-off Oct 2025 | 855 41st Av | J P F Construction | relocate the retaining walls in the basement. revision to pa# 202207299584. to comply to nov #202428123. excavate basement and enlarge to be a study room, add new bath at basementDetails
relocate the retaining walls in the basement. revision to pa# 202207299584. to comply to nov #202428123. excavate basement and enlarge to be a study room, add new bath at basement | $8,000 |
| Sep 3, 2024 | In progress filed Sep 2024, not yet issued | 1055 Washington St | seismic retrofit of soft story to comply with sfbc 4d mandatory seismic retrofit per 2016 cebc appendix a4Details
seismic retrofit of soft story to comply with sfbc 4d mandatory seismic retrofit per 2016 cebc appendix a4 | $100,000 | |
| Aug 23, 2024 | Completed final sign-off Jul 2025 | 531 36th Av | building a new wood deck in the rear of the building.Details
building a new wood deck in the rear of the building. | $30,000 | |
| Jul 19, 2024 | Expired or cancelled withdrawn Jul 2026 | 1625 Polk St | voluntary structural strengthening in the building (see bldg comments)Details
voluntary structural strengthening in the building (see bldg comments) | $150,000 | |
| Jul 9, 2024 | Completed final sign-off Jan 2025 | 1400 Geneva Av | Dliu Construction | to comply w/ nov# 202424621: replace (e) stair with new stair in kind. repair in kind.Details
to comply w/ nov# 202424621: replace (e) stair with new stair in kind. repair in kind. | $40,000 |
| Jun 28, 2024 | In progress issued Jul 2024 | 901 Pine St | Axel8 Construction | revision to pa 202212239112 revise concrete footings and wood beamsDetails
revision to pa 202212239112 revise concrete footings and wood beams | |
| Jun 21, 2024 | Completed final sign-off May 2026 | 15 Faxon Av | I E General Const Inc | to comply with nov 201763735, 201930206, and 201931171. convert (e) basement to bedroom and bathroom on g/f. reconfigure (e) kitchen and bathroom on 2/f. build new deck at rear yard on 2/f.Details
to comply with nov 201763735, 201930206, and 201931171. convert (e) basement to bedroom and bathroom on g/f. reconfigure (e) kitchen and bathroom on 2/f. build new deck at rear yard on 2/f. | $80,000 |
| Jun 18, 2024 | Completed final sign-off Jan 2025 | 1801 Union St | Bai Construction | replace damaged rot at corner of retail store. repair exterior siding in kind.Details
replace damaged rot at corner of retail store. repair exterior siding in kind. | $5,000 |
| May 31, 2024 | Completed final sign-off Jan 2025 | 12 Neptune St | Dliu Construction | to comply w/ complaint# 202423669 & 202423323. construct new concrete footing along property line and repair (e) exterior siding above new concrete footing.Details
to comply w/ complaint# 202423669 & 202423323. construct new concrete footing along property line and repair (e) exterior siding above new concrete footing. | $30,000 |
| May 28, 2024 | In progress filed May 2024, not yet issued | 57 Loomis St | warehouse ti to include (n) bathroom and addition of (n) interior walls.Details
warehouse ti to include (n) bathroom and addition of (n) interior walls. | $40,000 | |
| May 17, 2024 | Completed final sign-off Jun 2025 | 2751 Greenwich St | Tritec Construction Co Inc--See Notes | construct new concrete retaining wall in the rear yard to replace existing in kindDetails
construct new concrete retaining wall in the rear yard to replace existing in kind | $20,000 |
| May 10, 2024 | In progress filed May 2024, not yet issued | 273 20th Av | englarge garage door in the front of the building. | $4,000 | |
| May 7, 2024 | In progress filed May 2024, not yet issued | 3180 San Bruno Av | enlarge meter room in the front of the building. | $10,000 | |
| May 3, 2024 | Completed final sign-off Jul 2025 | 312 Stratford Dr | Threemile Construction | two bathroom (e) remodel, kitchen (e) relocated. add two new bathroom and one office. convert family room into bedroom. relcoate water heater. replace windows (11).Details
two bathroom (e) remodel, kitchen (e) relocated. add two new bathroom and one office. convert family room into bedroom. relcoate water heater. replace windows (11). | $40,000 |
| Apr 30, 2024 | Completed final sign-off Apr 2025 | 2027 22nd Av | Wong Construction Inc | replace (e) footing with new concrete footing and new wood beam in the second floor.Details
replace (e) footing with new concrete footing and new wood beam in the second floor. | $40,000 |
| Apr 25, 2024 | Completed final sign-off May 2024 | 1040 Montgomery St | J C General Construction | existing deck to be removed on the roof. complaint #202421767Details
existing deck to be removed on the roof. complaint #202421767 | $3,000 |
| Apr 23, 2024 | Completed final sign-off May 2024 | 1100 Fulton St | Sincere Construction Company Inc | revision to 201701137203. relocate plywood shear walls & moment frames. no exterior work.Details
revision to 201701137203. relocate plywood shear walls & moment frames. no exterior work. | |
| Apr 11, 2024 | Completed final sign-off Jul 2024 | 2185 Fillmore St | Wong Construction Inc | enlarge ada bathroom in the 1st floor.Details
enlarge ada bathroom in the 1st floor. | $30,000 |
| Mar 29, 2024 | Completed final sign-off Sep 2026 | 1151 Kearny St | Gee Construction Co Inc | revision to pa 201709158522 revise shear wallsDetails
revision to pa 201709158522 revise shear walls |