I E General Const Inc
- Based in
- San Mateo
- On San Francisco permits
- Nov 2012 to Aug 2026
- Last 24 months
- 8 permits filed
69 permits since 2000: 48 completed, 8 in progress, 8 never finaled, 5 expired or cancelled.
Of the 8 never-finaled permits, 1 is 3 to 5 years old, 2 are 5 to 10 years old, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 13, 2026 | In progress issued Aug 2026 | 1031 Noriega St | interior remodel: convert existing ground floor stoarage to new habitable space with 2 bedrooms, 2 bathrooms, 1 mudroom and 1 family room. reconfigure 2nd floor. replace existing windows and add 2 skylights. replace & relocate exiting furnace and water heater & build new deck.Details
interior remodel: convert existing ground floor stoarage to new habitable space with 2 bedrooms, 2 bathrooms, 1 mudroom and 1 family room. reconfigure 2nd floor. replace existing windows and add 2 skylights. replace & relocate exiting furnace and water heater & build new deck. | $200,000 |
| Jul 31, 2026 | In progress issued Aug 2026 | 555 Fulton St | meps for permit 2025122928895 for suite bDetails
meps for permit 2025122928895 for suite b | $250,000 |
| May 26, 2026 | In progress issued May 2026 | 1031 Noriega St | to comply w/ nov# 202652111. rebuild damaged exterior front stairway.Details
to comply w/ nov# 202652111. rebuild damaged exterior front stairway. | $25,000 |
| Mar 31, 2026 | In progress issued May 2026 | 2348 Jerrold Av | new ada toilet. additional sprinklers. new exterior doorDetails
new ada toilet. additional sprinklers. new exterior door | $30,000 |
| Jan 22, 2026 | In progress issued Mar 2026 | 35 Russia Av | revision to pa #2022-0923-3018 & 2025-0911-5095 (exterior wall 7 cmu infill at new adus london st). change from steel to cmu.Details
revision to pa #2022-0923-3018 & 2025-0911-5095 (exterior wall 7 cmu infill at new adus london st). change from steel to cmu. | $40,000 |
| Dec 29, 2025 | In progress issued Jun 2026 | 555 Fulton St | suite b- ground floor. copmmerical ti of (n) pottery and wood working studio. new ada lift, restrooms and handraill. no exterior work or structural and mep deferred.Details
suite b- ground floor. copmmerical ti of (n) pottery and wood working studio. new ada lift, restrooms and handraill. no exterior work or structural and mep deferred. | $20,000 |
| Sep 11, 2025 | In progress issued Nov 2025 | 35 Russia Av | new infill at (e)london st.revision to 202209233018: garage door openings.Details
new infill at (e)london st.revision to 202209233018: garage door openings. | $5,000 |
| Oct 10, 2024 | Completed final sign-off Feb 2025 | 1589 Sacramento St | unit #8: remodel existing kitchen in kind, replacing fixtures, no change in layout.Details
unit #8: remodel existing kitchen in kind, replacing fixtures, no change in layout. | $15,000 |
| Jun 21, 2024 | Completed final sign-off May 2026 | 15 Faxon Av | to comply with nov 201763735, 201930206, and 201931171. convert (e) basement to bedroom and bathroom on g/f. reconfigure (e) kitchen and bathroom on 2/f. build new deck at rear yard on 2/f.Details
to comply with nov 201763735, 201930206, and 201931171. convert (e) basement to bedroom and bathroom on g/f. reconfigure (e) kitchen and bathroom on 2/f. build new deck at rear yard on 2/f. | $80,000 |
| Aug 24, 2023 | Completed final sign-off Dec 2023 | 1214 48th Av | (1) kitchen and (1) bathroom remodel in kind: replace fixtures and tile work. no change in floor layout layout. no change in wall layout. no structural work.Details
(1) kitchen and (1) bathroom remodel in kind: replace fixtures and tile work. no change in floor layout layout. no change in wall layout. no structural work. | $20,000 |
| Sep 23, 2022 | In progress issued Sep 2024 | 35 Russia Av | construction of 4 adu's to replace 8 (e) indoor parking spaces. (e) structure to remain. replace 4 garage doors with brick surfaced exterior wall with windows. construct storage loft above a section of new units. (n) electrical, plumbing & hvac. (n) cabinets, appliances, fixtures, & finishes.Details
construction of 4 adu's to replace 8 (e) indoor parking spaces. (e) structure to remain. replace 4 garage doors with brick surfaced exterior wall with windows. construct storage loft above a section of new units. (n) electrical, plumbing & hvac. (n) cabinets, appliances, fixtures, & finishes. | $150,000 |
| Oct 19, 2021 | Completed final sign-off Dec 2021 | 35 Russia Av | units e & l: each unit: remodel kitchen & 1 bathroom. relocate (e) panel for both unit. no alteration of wall. window & door.Details
units e & l: each unit: remodel kitchen & 1 bathroom. relocate (e) panel for both unit. no alteration of wall. window & door. | $60,000 |
| Oct 19, 2021 | Never finaled issued Oct 2021, no final | 210 Broderick St | apt 4: to obtain a final inspection for work approved under pa201808147288. all work is complete.Details
apt 4: to obtain a final inspection for work approved under pa201808147288. all work is complete. | |
| Feb 24, 2021 | Completed final sign-off Jan 2022 | 971 Duncan St | administrative permit: change address of approved pa 202002164353 to 971 duncan st.Details
administrative permit: change address of approved pa 202002164353 to 971 duncan st. | |
| Feb 10, 2021 | Never finaled issued Feb 2021, no final | 969 Duncan St | remodel (e) kitchen and 2 bathrooms by replacing cabinets, tiles and fixtures. no change on floor plan.Details
remodel (e) kitchen and 2 bathrooms by replacing cabinets, tiles and fixtures. no change on floor plan. | $10,000 |
| Sep 12, 2020 | Completed final sign-off Mar 2021 | 117 Wisconsin St | (unit h): tenant improvement - demo existing kitchen. new flooring, new kitchen cab + appliances, paint.Details
(unit h): tenant improvement - demo existing kitchen. new flooring, new kitchen cab + appliances, paint. | $35,000 |
| Aug 20, 2020 | Completed final sign-off Oct 2020 | 35 Russia Av | unit k - remodel bathroom (30 sf) and kitchen (60 sf)in-kind. replace bathroom & kitchen fixtures. no walls movingDetails
unit k - remodel bathroom (30 sf) and kitchen (60 sf)in-kind. replace bathroom & kitchen fixtures. no walls moving | $3,000 |
| Aug 17, 2020 | Completed final sign-off Nov 2020 | 35 Russia Av | staircase and side walls damaged by car accident. replace / repair broken brick at front stairs & reinstall handrail. repair less than 50% of staircase. repair consist of leaving undamaged brick section in place and replacing damaged layer of brick to match existing. all work in kind.Details
staircase and side walls damaged by car accident. replace / repair broken brick at front stairs & reinstall handrail. repair less than 50% of staircase. repair consist of leaving undamaged brick section in place and replacing damaged layer of brick to match existing. all work in kind. | $3,000 |
| Jan 28, 2019 | Completed final sign-off Mar 2019 | 35 Russia Av | unit f: replace kitchen and fixture & countertop. replace bathroom fixture & tile. no change to existing floor plan. all work in unit f.Details
unit f: replace kitchen and fixture & countertop. replace bathroom fixture & tile. no change to existing floor plan. all work in unit f. | $10,000 |
| Jan 28, 2019 | Completed final sign-off Nov 2019 | 1158 Jamestown Av | to comply w/ n.o.v 201803142 & 201807181. remove unpermitted kitchenDetails
to comply w/ n.o.v 201803142 & 201807181. remove unpermitted kitchen | $1,000 |
| Dec 5, 2018 | Completed final sign-off Jun 2019 | 2425 24th St | revision to pa #201809130014. 2nd fl reconfigure #2427 - convert living room to bedroom, remodel kitchen & bath. 3rd fl (#2425) add (1) new full bath.Details
revision to pa #201809130014. 2nd fl reconfigure #2427 - convert living room to bedroom, remodel kitchen & bath. 3rd fl (#2425) add (1) new full bath. | $50,000 |
| Dec 3, 2018 | Completed final sign-off Nov 2019 | 178 Brighton Av | 2nd floor: remove (e) interior stair to garage. add shower to master bath, infill existing lightwell with new skylight & fire rated proerty line windowDetails
2nd floor: remove (e) interior stair to garage. add shower to master bath, infill existing lightwell with new skylight & fire rated proerty line window | $5,000 |
| Sep 13, 2018 | Completed final sign-off Jun 2019 | 2425 24th St | convert living room to bedroom, reconfigure 2425 layout. also, comply with nov 201614651 and 201758111.Details
convert living room to bedroom, reconfigure 2425 layout. also, comply with nov 201614651 and 201758111. | $50,000 |
| Sep 4, 2018 | Completed final sign-off Nov 2019 | 178 Brighton Av | remodel 1st floor to new living space & remodel 2nd floors including kitchen & bathroom; new skylight, infill (3) stair lightwell and new entrance door @ 1st floor.Details
remodel 1st floor to new living space & remodel 2nd floors including kitchen & bathroom; new skylight, infill (3) stair lightwell and new entrance door @ 1st floor. | $99,000 |
| Aug 31, 2018 | Completed final sign-off Sep 2018 | 35 Russia Av | remodel (e) kitchen and batrhoom (replace in unit h & q) no structural work.Details
remodel (e) kitchen and batrhoom (replace in unit h & q) no structural work. | $25,000 |
| Aug 30, 2018 | Completed final sign-off Nov 2018 | 80 Missouri St | remove all previous tenant fixtures including fireplaces and platform; all decorative elements in show room; remove all gas lines & electrical wires from fireplaces on 1st floor. per ab-017 ada deferred.Details
remove all previous tenant fixtures including fireplaces and platform; all decorative elements in show room; remove all gas lines & electrical wires from fireplaces on 1st floor. per ab-017 ada deferred. | $5,000 |
| Aug 14, 2018 | Never finaled issued Aug 2018, no final | 210 Broderick St | reconfigure unit #4 to add one new bedroom and one new bathroomDetails
reconfigure unit #4 to add one new bedroom and one new bathroom | $70,000 |
| Jun 19, 2018 | Completed final sign-off Oct 2018 | 1589 Sacramento St | interior remodel at unit #3: add one new bath and laundry, relocate existing kitchen & bathroom.Details
interior remodel at unit #3: add one new bath and laundry, relocate existing kitchen & bathroom. | $45,000 |
| Mar 6, 2018 | Completed final sign-off Jul 2018 | 195 Ledyard St | convert (e) bath into 2 new baths on 1st. reconfigure 1st flr layout, relocate w/h & furnance, reconfigure master bedroom & bath, remodel kitchen and bath and add laundry rm on 2nd flrDetails
convert (e) bath into 2 new baths on 1st. reconfigure 1st flr layout, relocate w/h & furnance, reconfigure master bedroom & bath, remodel kitchen and bath and add laundry rm on 2nd flr | $50,000 |
| Feb 28, 2018 | Completed final sign-off Sep 2018 | 35 Russia Av | unit #d: bathroom and kitchen remodel in kind. replace fixtures and install new tiles, new laminate flooring. no change in layout. maher n/aDetails
unit #d: bathroom and kitchen remodel in kind. replace fixtures and install new tiles, new laminate flooring. no change in layout. maher n/a | $10,000 |
| Nov 20, 2017 | Completed final sign-off Feb 2018 | 195 Ledyard St | restore 9 (e) unpermitted windows w/ (n) wood windows to comply with nov # 2017931712; no change in (e) openingDetails
restore 9 (e) unpermitted windows w/ (n) wood windows to comply with nov # 2017931712; no change in (e) opening | $3,000 |
| Nov 3, 2017 | Completed final sign-off Jun 2018 | 31 Leese St | revision to 201701237688, change from gas wall heat to new furnaceDetails
revision to 201701237688, change from gas wall heat to new furnace | |
| Sep 21, 2017 | Completed final sign-off Jul 2018 | 141 Lexington St | reconfigure interior layout on 2nd and 3rd fl per plan. keeping (e) bathrooms on 2nd & 3rd floor per plan.Details
reconfigure interior layout on 2nd and 3rd fl per plan. keeping (e) bathrooms on 2nd & 3rd floor per plan. | $40,000 |
| Mar 17, 2017 | Expired or cancelled withdrawn Jul 2017 | 65 San Pablo Av | remodel masternedroom and bath. relocate one full bathroom. remodel kitchen an 2nd flr. convert (e) storage to a master bedroom and bath in basement, relocate furnance & wh in basementDetails
remodel masternedroom and bath. relocate one full bathroom. remodel kitchen an 2nd flr. convert (e) storage to a master bedroom and bath in basement, relocate furnance & wh in basement | $40,000 |
| Mar 8, 2017 | Completed final sign-off Mar 2017 | 35 Russia Av | to obtain a final inspection for work approved under pa#201509248023. plumbing & electricval final sign-off required.Details
to obtain a final inspection for work approved under pa#201509248023. plumbing & electricval final sign-off required. | |
| Jan 23, 2017 | Completed final sign-off Jun 2018 | 31 Leese St | relocate kitchen in unit #5, convert (e) kitchen to (n) bedroom; move non-bearing wall between unit 2 & unit 5; add (n) tankless water heater to unit 2 & unit 5.Details
relocate kitchen in unit #5, convert (e) kitchen to (n) bedroom; move non-bearing wall between unit 2 & unit 5; add (n) tankless water heater to unit 2 & unit 5. | $20,000 |
| Jan 20, 2017 | Completed final sign-off May 2017 | 2429 24th St | ground floor: revision to app#201612195339: 1) relocate bathroom. 2)relocate bedroom. 3)remove nonbearing wall and convert bedroom to living room.Details
ground floor: revision to app#201612195339: 1) relocate bathroom. 2)relocate bedroom. 3)remove nonbearing wall and convert bedroom to living room. | |
| Jan 11, 2017 | Completed final sign-off Jun 2018 | 31 Leese St | #2 & #5- bathroom remodel, no structural work, total 2 bathrooms.Details
#2 & #5- bathroom remodel, no structural work, total 2 bathrooms. | $20,000 |
| Dec 19, 2016 | Completed final sign-off May 2017 | 2429 24th St | g/f: rev pa#201611142614: relocate (e) bathroom, relocate bedroom & convert bedroom to living room;Details
g/f: rev pa#201611142614: relocate (e) bathroom, relocate bedroom & convert bedroom to living room; | $20,000 |
| Nov 14, 2016 | Expired or cancelled expired Jul 2019 | 2429 24th St | one kitchen and one bathroom remodel. non structuralDetails
one kitchen and one bathroom remodel. non structural | $10,000 |
| Jun 30, 2016 | Completed final sign-off Feb 2017 | 2828 Judah St | replace four existing street facing windows that will be aluminum-clad with wood slider windows.Details
replace four existing street facing windows that will be aluminum-clad with wood slider windows. | $2,500 |
| May 9, 2016 | Completed final sign-off Jul 2016 | 35 Russia Av | kitchen and bathroom remodel on unit #b and #p. no walls moved, removed, added or infilled. all existing layouts to remain unchanged.Details
kitchen and bathroom remodel on unit #b and #p. no walls moved, removed, added or infilled. all existing layouts to remain unchanged. | $30,000 |
| Mar 28, 2016 | Completed final sign-off May 2016 | 3622 22nd St | to comply with complaint 201606301, add new partition wall with pocked door on 1st floor. convert (e) bedroom to office on 1st floor.Details
to comply with complaint 201606301, add new partition wall with pocked door on 1st floor. convert (e) bedroom to office on 1st floor. | $2,000 |
| Mar 2, 2016 | Completed final sign-off Nov 2016 | 3123 San Jose Av | add 2 playrooms and 1 storage. relocate one bathroom on 1st floor. relocate w/h & furnace; replace (e) deck with (n) landing; replace (e) doors at rear on 2nd flr with (n) door and window, replace (e) windows at rear on 1st floor.Details
add 2 playrooms and 1 storage. relocate one bathroom on 1st floor. relocate w/h & furnace; replace (e) deck with (n) landing; replace (e) doors at rear on 2nd flr with (n) door and window, replace (e) windows at rear on 1st floor. | $30,000 |
| Feb 18, 2016 | Never finaled issued Feb 2016, no final | 35 Russia Av | comply with nov 201689142, item #2Details
comply with nov 201689142, item #2 | $2,000 |
| Feb 9, 2016 | Never finaled issued Feb 2016, no final | 3295 Mission St | lighting plan revision to pa201504305025; title 24 compliance.Details
lighting plan revision to pa201504305025; title 24 compliance. | $5,000 |
| Dec 7, 2015 | Completed final sign-off Oct 2016 | 2427 24th St | revision to pa #201508194682 - comply w/nov #201582421: remove all plaster & replace w/new sheetrock. replace new tankless water heater. add two new furnace. remodel bathrooms & kitchens. convert storage to laundry for #2429. repair/replace front port of stairs in kind.Details
revision to pa #201508194682 - comply w/nov #201582421: remove all plaster & replace w/new sheetrock. replace new tankless water heater. add two new furnace. remodel bathrooms & kitchens. convert storage to laundry for #2429. repair/replace front port of stairs in kind. | $85,000 |
| Oct 30, 2015 | Completed final sign-off May 2021 | 331 Pennsylvania Av | change use from institution to residential. add rear deck & carport. demolition of all interior non-load bearing partition walls,all plumbing fixtures to be removed, interior structural walls and supports to be exposed,Details
change use from institution to residential. add rear deck & carport. demolition of all interior non-load bearing partition walls,all plumbing fixtures to be removed, interior structural walls and supports to be exposed, | $50,000 |
| Sep 24, 2015 | Expired or cancelled expired Jan 2017 | 35 Russia Av | 2nd & 3rd flr -units m & j: kitchen and bath remodelDetails
2nd & 3rd flr -units m & j: kitchen and bath remodel | $20,000 |
| Sep 4, 2015 | Completed final sign-off Sep 2015 | 355 Pennsylvania Av | replace shower tub & tile.Details
replace shower tub & tile. | $3,000 |
| Aug 19, 2015 | Expired or cancelled expired Jul 2019 | 2427 24th St | kitchen & bathroom remodel. no structural work.Details
kitchen & bathroom remodel. no structural work. | $20,000 |
| Jul 23, 2015 | Completed final sign-off Sep 2015 | 277 Shipley St | unit d: replace kitchen cabinets and counter top.Details
unit d: replace kitchen cabinets and counter top. | $10,000 |
| Jul 21, 2015 | Completed final sign-off Oct 2015 | 1177 California St | #1214 - replace kitchen & bath cabinets, countertop, fixtures, appliances, & floor finishes. add shut off valves at kitchen & bathrooms. replace light fixtrues, & add light fixture in living room. comply with cec 150.0(k) 5.Details
#1214 - replace kitchen & bath cabinets, countertop, fixtures, appliances, & floor finishes. add shut off valves at kitchen & bathrooms. replace light fixtrues, & add light fixture in living room. comply with cec 150.0(k) 5. | $50,000 |
| May 11, 2015 | Completed final sign-off Oct 2015 | 578 05th Av | replace front windows in-kind (with aluminium); u-factors not > 0.32.Details
replace front windows in-kind (with aluminium); u-factors not > 0.32. | $3,000 |
| Apr 30, 2015 | Completed final sign-off Jul 2016 | 3295 Mission St | comply with nov 201540921 enlarge existing bathrm new ada bath, remodel small bath. relocate existing rear door to center line. not visible from streetDetails
comply with nov 201540921 enlarge existing bathrm new ada bath, remodel small bath. relocate existing rear door to center line. not visible from street | $40,000 |
| Oct 23, 2014 | Completed final sign-off Apr 2015 | 2587 37th Av | add 2 bedrooms and 2 baths on the 1st fl (696 sq ft) relocate water heater and furnaceDetails
add 2 bedrooms and 2 baths on the 1st fl (696 sq ft) relocate water heater and furnace | $20,000 |
| Oct 14, 2014 | Completed final sign-off May 2015 | 234 Mallorca Wy | repair roof deck in kind approx 15x19. maher not req. call district inspector prior to start of work.Details
repair roof deck in kind approx 15x19. maher not req. call district inspector prior to start of work. | $15,000 |
| Oct 10, 2014 | Never finaled issued Oct 2014, no final | 225 Valencia St | revise 201406047451, remove 2 small offices and one conference room at 2nd flr, make one opening at existing wall at 1st floor. maher n/aDetails
revise 201406047451, remove 2 small offices and one conference room at 2nd flr, make one opening at existing wall at 1st floor. maher n/a | $4,000 |
| Oct 6, 2014 | Expired or cancelled cancelled Jan 2020 | 277 Shipley St | unit legalization ordinance# 43-14. legalize unit f @ basement with 1 bedroom, 1 bathroom & 1 kitchen @ basement. ** maher: compliance with ordinance no# 155-13 not required **Details
unit legalization ordinance# 43-14. legalize unit f @ basement with 1 bedroom, 1 bathroom & 1 kitchen @ basement. ** maher: compliance with ordinance no# 155-13 not required ** | $300 |
| Oct 6, 2014 | Completed final sign-off Jan 2016 | 371 Staples Av | unit legalization ordinance# 43-14. legalize 2 bedrooms, 1 bathroom & 1 kitchen in-law unit @ ground floor.Details
unit legalization ordinance# 43-14. legalize 2 bedrooms, 1 bathroom & 1 kitchen in-law unit @ ground floor. | $7,850 |
| Sep 16, 2014 | Never finaled issued Sep 2014, no final | 1433 17th St | replace 14 windows in kind, u factor 0.46Details
replace 14 windows in kind, u factor 0.46 | $3,000 |
| Aug 18, 2014 | Completed final sign-off Apr 2015 | 1589 Sacramento St | interior remodel for unit 4 & 5. relocate bathrooms for both units. relocate kitchen for unit 4Details
interior remodel for unit 4 & 5. relocate bathrooms for both units. relocate kitchen for unit 4 | $20,000 |
| Jul 30, 2014 | Completed final sign-off Nov 2014 | 277 Shipley St | replace kitchen cabinet & countertop in unit b onlyDetails
replace kitchen cabinet & countertop in unit b only | $10,000 |
| Jul 29, 2014 | Completed final sign-off Aug 2017 | 80 Missouri St | extend existing corridor & add two doors at ground floor at existing warehouse & storage. n/a for maherDetails
extend existing corridor & add two doors at ground floor at existing warehouse & storage. n/a for maher | $3,000 |
| Jul 16, 2014 | Completed final sign-off Sep 2017 | 80 Missouri St | change of use for ground floor of (e) warehouse to gym. build men's / women's toilet rooms. work area. group class commercial studio. reception area. ** compliance with ordinance no# 155-13 not required ** panic hardware doors for second exit to be field verified. adbDetails
change of use for ground floor of (e) warehouse to gym. build men's / women's toilet rooms. work area. group class commercial studio. reception area. ** compliance with ordinance no# 155-13 not required ** panic hardware doors for second exit to be field verified. adb | $140,000 |
| Jun 4, 2014 | Never finaled issued Jun 2014, no final | 225 Valencia St | relocate reestroom for 1st and 2nd flr; add kitchen at 1st and 2nd flr; compliance with ord 155-13 not required.Details
relocate reestroom for 1st and 2nd flr; add kitchen at 1st and 2nd flr; compliance with ord 155-13 not required. | $60,000 |
| May 23, 2014 | Completed final sign-off Sep 2014 | 148 Idora Av | repair window water leak damaged (1st and 2nd flr) total 12Details
repair window water leak damaged (1st and 2nd flr) total 12 | $20,000 |
| May 9, 2014 | Completed final sign-off Jun 2015 | 1414 44th Av | add 1 play room and 1 bathroom at first level.Details
add 1 play room and 1 bathroom at first level. | $20,000 |
| Nov 20, 2012 | Completed final sign-off Sep 2018 | 1935 34th Av | rear addition on first floor, two bedrooms. to comply w/ nov #200235444 to legalize a bathroom and family room at first floor.Details
rear addition on first floor, two bedrooms. to comply w/ nov #200235444 to legalize a bathroom and family room at first floor. | $30,000 |