Block 0266, lot 008
98 Battery St
- City’s use
- Commercial Office
- Built
- 1907
- Stories
- 7
- Rooms
- 12 bathrooms
- Building
- 65,675 sq ft
- Lot
- 12,401 sq ft
- Zoning
- C3O
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
110 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 24, 2026 | In progress issued Oct 2026 | 98 Battery St | Modern Construction Inc | revision 3 to pa 202510298348: outside protal material cladding change new framing added at the exterior in order to support sheet metal. existing to be removedDetails
revision 3 to pa 202510298348: outside protal material cladding change new framing added at the exterior in order to support sheet metal. existing to be removed | |
| Sep 11, 2026 | In progress issued Sep 2026 | 98 Battery St | Modern Construction Inc | add mechanical t24 to pa: 2026.0812.6428Details
add mechanical t24 to pa: 2026.0812.6428 | |
| Aug 12, 2026 | In progress issued Aug 2026 | 98 Battery St | Modern Construction Inc | revise pa#2025-1029-8348 to document actual field conditions, no material changes to project or construction scope.Details
revise pa#2025-1029-8348 to document actual field conditions, no material changes to project or construction scope. | $60,000 |
| Jun 8, 2026 | In progress issued Jun 2026 | 98 Battery St | Modern Construction Inc | add title 24 electrical to main entry and elevator lobby. ref permit 202510298348.Details
add title 24 electrical to main entry and elevator lobby. ref permit 202510298348. | |
| Apr 7, 2026 | In progress issued Jun 2026 | 98 Battery St | Modern Construction Inc | minor non structural lobby door support and building attachment. single story non structural commercial tenant improvement. ref 202510298348Details
minor non structural lobby door support and building attachment. single story non structural commercial tenant improvement. ref 202510298348 | $3,000 |
| Dec 23, 2025 | In progress filed Dec 2025, not yet issued | 98 Battery St | suite b: remove fountain soda machine.Details
suite b: remove fountain soda machine. | ||
| Oct 29, 2025 | In progress issued Jan 2026 | 98 Battery St | Modern Construction Inc | single story non-structural commercial t.i. project entry finishes, storefront, and exterior lighting to be replaced in kind. interior finishes and lighting to be replaced. no structural work. ref. permit 201912119260Details
single story non-structural commercial t.i. project entry finishes, storefront, and exterior lighting to be replaced in kind. interior finishes and lighting to be replaced. no structural work. ref. permit 201912119260 | $60,000 |
| Jun 5, 2025 | Completed final sign-off Jun 2025 | 195 Pine St | Ha Fire Protection | install fire supression system for kitchen hood and ductDetails
install fire supression system for kitchen hood and duct | $6,500 |
| Jun 13, 2024 | Completed final sign-off Jul 2025 | 191 Pine St | Hybrid City Construction Inc | revision to pa#201912119260. minor ceiling framing layout requested by bid to document changes infield.Details
revision to pa#201912119260. minor ceiling framing layout requested by bid to document changes infield. | |
| Apr 4, 2024 | Completed final sign-off Jul 2025 | 98 Battery St | Crime Watch Security Sys Llc | t.i. install additional devices to the (e) fire alarm system to adequately cover the new restaurant c suite 103-104 combinedDetails
t.i. install additional devices to the (e) fire alarm system to adequately cover the new restaurant c suite 103-104 combined | $23,120 |
| Feb 8, 2024 | Completed final sign-off Jul 2025 | 191 Pine St | Hybrid City Construction Inc | revision to pa# 201912119260. minor framing changes and layout. request by bid to document changes in fieldDetails
revision to pa# 201912119260. minor framing changes and layout. request by bid to document changes in field | |
| Nov 8, 2023 | In progress issued Nov 2023 | 98 Battery St | Sabah International Incorporated | 1st flr: elevator modernization scope of work as follow: addition of (1) smoke detector at 1st flr. addition of (1) smoke detector inside elevator. addition of (1) fire alarm relay - no building permit# for elevator modification.Details
1st flr: elevator modernization scope of work as follow: addition of (1) smoke detector at 1st flr. addition of (1) smoke detector inside elevator. addition of (1) fire alarm relay - no building permit# for elevator modification. | $13,333 |
| Oct 20, 2023 | Completed final sign-off Jan 2024 | 98 Battery St | Sam's Neon & Elec. Signs | ste b: to erect a non-electric, double faced wall sign, "locali mediterranean"Details
ste b: to erect a non-electric, double faced wall sign, "locali mediterranean" | $2,000 |
| Jul 13, 2022 | Completed final sign-off Sep 2022 | 98 Battery St | City Mechanical Inc | 3/f: air handler replacementDetails
3/f: air handler replacement | $150,000 |
| Jul 13, 2022 | Completed final sign-off Sep 2022 | 98 Battery St | City Mechanical Inc | 5/flr - air handler replacementDetails
5/flr - air handler replacement | $150,000 |
| Apr 28, 2022 | Completed final sign-off Jun 2022 | 98 Battery St | City Mechanical Inc | 2nd fl: air handler replacement.Details
2nd fl: air handler replacement. | $145,000 |
| Mar 10, 2022 | Completed final sign-off Mar 2022 | 98 Battery St | C B 2 Builders Incorporated | suite 302: furniture/ module workstation plan only. ref pa# 202105190608.Details
suite 302: furniture/ module workstation plan only. ref pa# 202105190608. | |
| Feb 18, 2022 | Completed final sign-off Mar 2024 | 98 Battery St | Ravig Inc Dba Salient Global Technologi | verizon site modification. remove and replace 8 (e) antennas w/8 (n) antennas. remove and replace 4 (e) rrus-32 b66a units with 4 (n) radio 8443 units. remove and replace 4 (e) rrus-11 with 4 (n) radio 4449 units. see plans for further detail.Details
verizon site modification. remove and replace 8 (e) antennas w/8 (n) antennas. remove and replace 4 (e) rrus-32 b66a units with 4 (n) radio 8443 units. remove and replace 4 (e) rrus-11 with 4 (n) radio 4449 units. see plans for further detail. | $40,000 |
| Feb 11, 2022 | Never finaled issued Feb 2022, no final | 98 Battery St | City Mechanical Inc | 6/f: hvac improvements.Details
6/f: hvac improvements. | $130,000 |
| Jul 14, 2021 | Completed final sign-off Oct 2021 | 98 Battery St | City Mechanical Inc | 4th floor: hvac improvementsDetails
4th floor: hvac improvements | $195,000 |
| May 19, 2021 | Completed final sign-off Mar 2022 | 98 Battery St | C B 2 Builders Incorporated | 3rd fl, ste 302 office ti. demo breakroom ktichen and partial wall demo at breakroom for new interior window. provide new countertops, cabinets and fixtures at breakroom. provide new finishes throughout. no exterior of site workDetails
3rd fl, ste 302 office ti. demo breakroom ktichen and partial wall demo at breakroom for new interior window. provide new countertops, cabinets and fixtures at breakroom. provide new finishes throughout. no exterior of site work | $122,475 |
| Mar 19, 2021 | Completed final sign-off Feb 2022 | 199 Pine St | Tritek Construction Inc. | install bi-fold door in front of existing entrance as a gate to enclose recessed entrance when store is closed for business.Details
install bi-fold door in front of existing entrance as a gate to enclose recessed entrance when store is closed for business. | $25,000 |
| Mar 15, 2021 | Completed final sign-off Apr 2023 | 98 Battery St | Modern Construction Inc | ste #500: revision to pa# 201901049678. remove demising wall from plan & saving exit doors. mep will be on seperate permit. upgrade (e) restrooms to be accessible.Details
ste #500: revision to pa# 201901049678. remove demising wall from plan & saving exit doors. mep will be on seperate permit. upgrade (e) restrooms to be accessible. | $105,000 |
| Sep 12, 2020 | Completed final sign-off Dec 2020 | 98 Battery St | Modern Construction Inc | (ste 220) title 24 for pa# 201911207809Details
(ste 220) title 24 for pa# 201911207809 | |
| Sep 3, 2020 | Completed final sign-off Oct 2020 | 98 Battery St | Premium Roofing & Waterproofing Inc | reroofing-must comply with cool roofing requirements per 2019 ca 141.ob2bDetails
reroofing-must comply with cool roofing requirements per 2019 ca 141.ob2b | $110,000 |
| Aug 20, 2020 | Completed final sign-off Mar 2021 | 98 Battery St | Johnson Controls Security Solutions Llc | suite 500: requested per field inspector "as built" extg fire alarm alteration. "as built requested.Details
suite 500: requested per field inspector "as built" extg fire alarm alteration. "as built requested. | |
| Apr 28, 2020 | Completed final sign-off Sep 2020 | 98 Battery St | Tot'l Environm'l /Pwer Sym Inc Dba:Teps | to obtain final inspection for pa #2014-1125-2538Details
to obtain final inspection for pa #2014-1125-2538 | |
| Feb 19, 2020 | Completed final sign-off Apr 2020 | 98 Battery St | Crime Watch Security Sys Llc | ti modify existing fire alarm system to provide notification in new rooms in suite #201 (#220). ref pa #201911207809. maher naDetails
ti modify existing fire alarm system to provide notification in new rooms in suite #201 (#220). ref pa #201911207809. maher na | $5,000 |
| Dec 30, 2019 | Completed final sign-off Jul 2025 | 191 Pine St | Hybrid City Construction Inc | mechanical for existing t.i. reference permit #201912119260Details
mechanical for existing t.i. reference permit #201912119260 | $100,000 |
| Dec 11, 2019 | Completed final sign-off Jul 2025 | 191 Pine St | Hybrid City Construction Inc | proposed interior tenant improvement for restaurantDetails
proposed interior tenant improvement for restaurant | $200,000 |
| Dec 10, 2019 | Completed final sign-off Jul 2025 | 191 Pine St | Hybrid City Construction Inc | demolish interior walls and merge 2 tenant spaces into 1Details
demolish interior walls and merge 2 tenant spaces into 1 | $5,000 |
| Nov 20, 2019 | Completed final sign-off Dec 2020 | 98 Battery St | Modern Construction Inc | #220: remove partition walls and construct new partition walls, doors, and sidelight. maher naDetails
#220: remove partition walls and construct new partition walls, doors, and sidelight. maher na | $120,000 |
| Sep 19, 2019 | Never finaled issued Jan 2020, no final | 191 Pine St | street spaceDetails
street space | ||
| Aug 12, 2019 | Expired or cancelled withdrawn Jul 2022 | 199 Pine St | install roll-up security grill gateat entrance.*maher n/a**Details
install roll-up security grill gateat entrance.*maher n/a** | $5,000 | |
| Jul 11, 2019 | Never finaled issued Jul 2019, no final | 187 Pine St | Excel Signs | to erect 41"x 139" "the dental practice/sf" . non illuminated wall sign.Details
to erect 41"x 139" "the dental practice/sf" . non illuminated wall sign. | $900 |
| Jul 11, 2019 | Never finaled issued Jul 2019, no final | 187 Pine St | Excel Signs | to erect 14"x 60" "the dental pracitice/sf" reception sign. non illuminatedDetails
to erect 14"x 60" "the dental pracitice/sf" reception sign. non illuminated | $250 |
| Jul 11, 2019 | Never finaled issued Jul 2019, no final | 187 Pine St | Excel Signs | to erect 24"x 30" "the dental practice" blade sign. non illuminatedDetails
to erect 24"x 30" "the dental practice" blade sign. non illuminated | $750 |
| Apr 17, 2019 | Completed final sign-off Sep 2020 | 98 Battery St | revision to pa 2019-0131-1746 including ansul adding 2 horn strobes for ti ref pa 2019-0104-9678Details
revision to pa 2019-0131-1746 including ansul adding 2 horn strobes for ti ref pa 2019-0104-9678 | ||
| Mar 28, 2019 | Completed final sign-off Sep 2019 | 187 Pine St | United California Access & Security Sys | comply w/ abe program, ordiance 51-16 -barrier removal; install entry door power door operator n/a maher.Details
comply w/ abe program, ordiance 51-16 -barrier removal; install entry door power door operator n/a maher. | $3,000 |
| Feb 27, 2019 | Expired or cancelled cancelled Jan 2026 | 98 Battery St | establish address, no workDetails
establish address, no work | ||
| Feb 13, 2019 | Never finaled issued Feb 2019, no final | 98 Battery St | Acco Engineered Systems Inc. Dba Acco En | install 1 outdoor diaxin unit; (1) indoor daikin unitDetails
install 1 outdoor diaxin unit; (1) indoor daikin unit | $8,000 |
| Jan 31, 2019 | Completed final sign-off Sep 2020 | 98 Battery St | Johnson Controls Security Solutions Llc | adding (2) horn strobes for t.i., ref pa#201901049678Details
adding (2) horn strobes for t.i., ref pa#201901049678 | $4,000 |
| Jan 24, 2019 | Never finaled issued Jan 2019, no final | 98 Battery St | Shield Fire & Safety Solutions Inc | installation of ansul fire system for ventless hood pre piped. ref mep pa #201804176569 n/a for maherDetails
installation of ansul fire system for ventless hood pre piped. ref mep pa #201804176569 n/a for maher | $1,500 |
| Jan 10, 2019 | Never finaled issued Jan 2019, no final | 187 Pine St | per request from owner, document and create address 187 pine street at block 0266, lot 008.Details
per request from owner, document and create address 187 pine street at block 0266, lot 008. | ||
| Jan 4, 2019 | Completed final sign-off Apr 2023 | 98 Battery St | Modern Construction Inc | #500 - remove (e) partition walls, ceiling tiles and flooring. install new non structural walls, doors. side lights, power outlets, relocate (e) lights install new finishesDetails
#500 - remove (e) partition walls, ceiling tiles and flooring. install new non structural walls, doors. side lights, power outlets, relocate (e) lights install new finishes | $105,000 |
| May 31, 2018 | Never finaled issued Sep 2018, no final | 199 Pine St | Reeve-Knight Construction Inc. | remove (e) sign box and installation of flush perforated metal panel to support future tenant signage. relocation of blade pangel signage to match adjacent neighbor heights relocation of junction box within new perforated panel. sign permit deferred. **maher n/a**Details
remove (e) sign box and installation of flush perforated metal panel to support future tenant signage. relocation of blade pangel signage to match adjacent neighbor heights relocation of junction box within new perforated panel. sign permit deferred. **maher n/a** | $28,000 |
| Apr 17, 2018 | Never finaled issued May 2018, no final | 98 Battery St | install one piece free standing equipment, self circulating hood. n/a for maherDetails
install one piece free standing equipment, self circulating hood. n/a for maher | $500 | |
| Oct 17, 2017 | Never finaled issued Aug 2018, no final | 199 Pine St | Sign Of Light | re-face (1) existing wall sign (panel in existing frame, existing electrical to remain). n/a maher ordinanceDetails
re-face (1) existing wall sign (panel in existing frame, existing electrical to remain). n/a maher ordinance | $1,000 |
| Oct 17, 2017 | Never finaled issued Aug 2018, no final | 199 Pine St | Sign Of Light | re-face (2) existing projecting signs (panel in existing frame, existing electrical to remain). n/a maher ordinanceDetails
re-face (2) existing projecting signs (panel in existing frame, existing electrical to remain). n/a maher ordinance | $1,500 |
| Oct 2, 2017 | Completed final sign-off Jan 2018 | 199 Pine St | Tritek Construction Inc. | demo of existing partitions, relocation of electrical/relocate electrical/add wall electrical/remove lighting. no plumbingDetails
demo of existing partitions, relocation of electrical/relocate electrical/add wall electrical/remove lighting. no plumbing | $33,000 |
| Aug 2, 2016 | Never finaled issued Aug 2016, no final | 98 Battery St | K K Electric & Alarm Company | 4/f- plan check inssued permit #201602260627 & 201606079296, addition 1 strobe/horn per elec inspector under current job 201606079296. ref to previous fire alarm permits 200703065561, 201509227695Details
4/f- plan check inssued permit #201602260627 & 201606079296, addition 1 strobe/horn per elec inspector under current job 201606079296. ref to previous fire alarm permits 200703065561, 201509227695 | $800 |
| Jun 7, 2016 | Completed final sign-off Jan 2017 | 98 Battery St | Modern Construction Inc | unit #500: remove (e) walls, doors & ceiling to install (n) non-structural walls, doors, side light and associated power and communicating outlets, relocate (e) lightDetails
unit #500: remove (e) walls, doors & ceiling to install (n) non-structural walls, doors, side light and associated power and communicating outlets, relocate (e) light | $70,000 |
| May 5, 2016 | Never finaled issued May 2016, no final | 98 Battery St | Johnson Controls Security Solutions Llc | to obtain final inspection for work approved under pa# 201104204445. all work is completeDetails
to obtain final inspection for work approved under pa# 201104204445. all work is complete | |
| Feb 26, 2016 | Completed final sign-off Jan 2017 | 98 Battery St | Modern Construction Inc | 4th flr: ste 400,demo existing partition wall, reconstruction new partition walls, door relocate lighting & install finishes; maher n/aDetails
4th flr: ste 400,demo existing partition wall, reconstruction new partition walls, door relocate lighting & install finishes; maher n/a | $75,000 |
| Sep 25, 2015 | Never finaled issued Oct 2015, no final | 98 Battery St | Modern Construction Inc | suite 220: title 24 for pa 2015-0804-3252. maher naDetails
suite 220: title 24 for pa 2015-0804-3252. maher na | $10,000 |
| Sep 22, 2015 | Completed final sign-off Jun 2016 | 98 Battery St | Johnson Controls Security Solutions Llc | suite #200: t.i. that needs to add 5 horn strobes per inspector. ref app#201507131326. n/a for maher.Details
suite #200: t.i. that needs to add 5 horn strobes per inspector. ref app#201507131326. n/a for maher. | $8,000 |
| Aug 4, 2015 | Completed final sign-off Oct 2015 | 98 Battery St | Modern Construction Inc | #220- demo and reconstruction new partition walls, doors, and finishes. install new lighting and outlet. n/a for maher. lighting and tilte 24 under separate permit (all mechanical to remain)Details
#220- demo and reconstruction new partition walls, doors, and finishes. install new lighting and outlet. n/a for maher. lighting and tilte 24 under separate permit (all mechanical to remain) | $90,000 |
| Jul 13, 2015 | Completed final sign-off Jun 2016 | 98 Battery St | Modern Construction Inc | suite 202 (2/f): install new walls, doors, interior glazing & relocate/replace lighting fixtures, counter top & sink; maher n/a.Details
suite 202 (2/f): install new walls, doors, interior glazing & relocate/replace lighting fixtures, counter top & sink; maher n/a. | $115,000 |
| Nov 25, 2014 | Expired or cancelled expired Sep 2020 | 98 Battery St | Tot'l Environm'l /Pwer Sym Inc Dba:Teps | install new 14'x26' equipment platform with equipment cabinets on roof top, install new screen wall 2 rru's pre-sector, 4 sectors total, (8) antennas total, install new 35 kw natural gas generator. n/a ordinance #155-13.Details
install new 14'x26' equipment platform with equipment cabinets on roof top, install new screen wall 2 rru's pre-sector, 4 sectors total, (8) antennas total, install new 35 kw natural gas generator. n/a ordinance #155-13. | $150,000 |
| Apr 14, 2014 | Never finaled issued Apr 2014, no final | 195 Pine St | street space w/mtaDetails
street space w/mta | ||
| Feb 10, 2014 | Completed final sign-off Jul 2014 | 195 Pine St | Smith Development & Construction Comp | revision to appl #2013.05.07.6313: revised floor plan for value engineering, reduce scope of work -electrical fixtures, equipment & plumbing. compliance with ordinance 155-13 not required. structural supports for two ahu, 1 cu, and 1 ef.Details
revision to appl #2013.05.07.6313: revised floor plan for value engineering, reduce scope of work -electrical fixtures, equipment & plumbing. compliance with ordinance 155-13 not required. structural supports for two ahu, 1 cu, and 1 ef. | |
| Dec 17, 2013 | Completed final sign-off Jun 2014 | 98 Battery St | Modern Construction Inc | #402 - build non-structural prtition walls, doors, & side lights. replace existing lights. title 24 & electrical under separate permit.Details
#402 - build non-structural prtition walls, doors, & side lights. replace existing lights. title 24 & electrical under separate permit. | $50,000 |
| May 31, 2013 | Never finaled issued Jun 2013, no final | 98 Battery St | Slc Inc | removal of (e) towerstream facility-9 antennas, 6 mounts, an equipment enclosure & cat 5 cablesDetails
removal of (e) towerstream facility-9 antennas, 6 mounts, an equipment enclosure & cat 5 cables | $500 |
| May 7, 2013 | Completed final sign-off Jul 2014 | 195 Pine St | Golden State Construction Grp Inc | 1st floor-tenant improvement to (e) building space-1st floor of (e) building. plumbing, mechanical, electrical & building. new floor, coffee & soda bar. new partitons, new restrooms, new cooler. new heating equipment for pre packaged food. no exterior work; separate permit for exterior signage.Details
1st floor-tenant improvement to (e) building space-1st floor of (e) building. plumbing, mechanical, electrical & building. new floor, coffee & soda bar. new partitons, new restrooms, new cooler. new heating equipment for pre packaged food. no exterior work; separate permit for exterior signage. | $315,000 |
| Nov 13, 2012 | Never finaled issued Jun 2014, no final | 195 Pine St | Athiva Services Inc. | to erect electric, projecting, double-faced sign. ** maher: compliance with ordinance no# 155-13 not required **Details
to erect electric, projecting, double-faced sign. ** maher: compliance with ordinance no# 155-13 not required ** | $5,000 |
| Nov 13, 2012 | Never finaled issued Jun 2014, no final | 195 Pine St | Athiva Services Inc. | to erect electric, wall, single faced sign. ** maher: compliance with ordinance no# 155-13 not required **Details
to erect electric, wall, single faced sign. ** maher: compliance with ordinance no# 155-13 not required ** | $5,000 |
| Nov 13, 2012 | Never finaled issued Jun 2014, no final | 195 Pine St | Athiva Services Inc. | to erect electric, wall (hang in window), single faced sign. ** maher: compliance with ordinance no# 155-13 not required **Details
to erect electric, wall (hang in window), single faced sign. ** maher: compliance with ordinance no# 155-13 not required ** | $2,000 |
| Nov 8, 2012 | Expired or cancelled withdrawn Jun 2013 | 195 Pine St | Golden State Construction Grp Inc | interior remodel of extg convenience store. plumbing for coffee bar,beve rage bar, hand sink and toilets. new porcelain tile floor. new clg. grid and tiles throughout. new light fixutres. exterior signage shall be submitted for permit by sign vender.no exterior 0Details
interior remodel of extg convenience store. plumbing for coffee bar,beve rage bar, hand sink and toilets. new porcelain tile floor. new clg. grid and tiles throughout. new light fixutres. exterior signage shall be submitted for permit by sign vender.no exterior 0 | $125,000 |
| Sep 10, 2012 | Completed final sign-off Jan 2013 | 98 Battery St | Modern Construction Inc | install new doors, interior glazing & relocate 2 light fixtures.Details
install new doors, interior glazing & relocate 2 light fixtures. | $35,000 |
| Jul 25, 2011 | Completed final sign-off Aug 2011 | 98 Battery St | Modern Construction Inc | suite 250:reference permit #201106137959 to correct type 1 building to type 2 building. permit issued for record keeping purpose.Details
suite 250:reference permit #201106137959 to correct type 1 building to type 2 building. permit issued for record keeping purpose. | |
| Jul 1, 2011 | Completed final sign-off Aug 2011 | 98 Battery St | C H M Mechanical Inc. | 2nd floor, suite 250:alteration to extg hvac duct system. architectural ref: 201106137959.Details
2nd floor, suite 250:alteration to extg hvac duct system. architectural ref: 201106137959. | $3,500 |
| Jun 13, 2011 | Completed final sign-off Aug 2011 | 98 Battery St | Modern Construction Inc | 2nd floor #250 -remove (e) walls, door, light fixtures. install new walls, door, interior glazing. mep under separate permit.Details
2nd floor #250 -remove (e) walls, door, light fixtures. install new walls, door, interior glazing. mep under separate permit. | $50,000 |
| Apr 20, 2011 | Completed final sign-off Jun 2016 | 98 Battery St | Tyco Integrated Security | replace non functional panel with new control panel at the same location. connect existing equipment using existing wire to new panel for monitoring on 1st floorDetails
replace non functional panel with new control panel at the same location. connect existing equipment using existing wire to new panel for monitoring on 1st floor | $4,600 |
| Mar 26, 2010 | Completed final sign-off May 2010 | 98 Battery St | Ward Alan Emery Construction Inc. | 4th floor -combine two adjoining suites into one. add fire-rated door assembly. new drywall partitions. note: no electrical or mechanical work.Details
4th floor -combine two adjoining suites into one. add fire-rated door assembly. new drywall partitions. note: no electrical or mechanical work. | $2,600 |
| Jun 3, 2009 | Never finaled issued Jun 2009, no final | 199 Pine St | street space & mta permit. ref 200810224781.Details
street space & mta permit. ref 200810224781. | ||
| Apr 29, 2009 | Never finaled issued Apr 2009, no final | 199 Pine St | street space permit only.Details
street space permit only. | ||
| Oct 22, 2008 | Completed final sign-off Jul 2009 | 199 Pine St | t.i. for verizon wireless, store remodel to change floor plan, mechanical, plumbing, electrical & framings. no structural work.Details
t.i. for verizon wireless, store remodel to change floor plan, mechanical, plumbing, electrical & framings. no structural work. | $132,795 | |
| Aug 11, 2008 | Never finaled issued Aug 2008, no final | 195 Pine St | Elro Manufacturing Company | reface existing signDetails
reface existing sign | |
| Feb 14, 2008 | Completed final sign-off Jun 2011 | 98 Battery St | Western Awnings And Canvas | new canvas awning 9'7" wide x 6'7" projection over storefront entryDetails
new canvas awning 9'7" wide x 6'7" projection over storefront entry | $1,400 |
| Feb 14, 2008 | Expired or cancelled expired Jun 2011 | 98 Battery St | Western Awnings And Canvas | painted sign ( 2 sides) on canvas awningDetails
painted sign ( 2 sides) on canvas awning | $290 |
| Jan 22, 2008 | Expired or cancelled cancelled Jan 2026 | 98 Battery St | painted sign on awning. awning on separate permit.Details
painted sign on awning. awning on separate permit. | $290 | |
| Jan 22, 2008 | Expired or cancelled cancelled Jan 2026 | 98 Battery St | erect canvas and steel tube awning at front entrance to hadi's deli.Details
erect canvas and steel tube awning at front entrance to hadi's deli. | $1,400 | |
| Nov 27, 2007 | Completed final sign-off Mar 2008 | 98 Battery St | Dajani Construction | install 1 handicap counter, 1 espresso counter, shelves. plumbing to accomodate sinks for new cafeDetails
install 1 handicap counter, 1 espresso counter, shelves. plumbing to accomodate sinks for new cafe | $10,000 |
| Jul 12, 2007 | Completed final sign-off Aug 2007 | 195 Pine St | Tong's Construction | minor revision to approved plans, pa 200703055442, relocate bathroom fixtures from locations on approved plans as enclosed.Details
minor revision to approved plans, pa 200703055442, relocate bathroom fixtures from locations on approved plans as enclosed. | |
| May 15, 2007 | Never finaled issued May 2007, no final | 191 Pine St | Tong's Construction | erect non-electronic single faced sign.Details
erect non-electronic single faced sign. | |
| May 15, 2007 | Never finaled issued May 2007, no final | 191 Pine St | Tong's Construction | erect electronic single faced projecting sign.Details
erect electronic single faced projecting sign. | |
| Mar 6, 2007 | Completed final sign-off Mar 2007 | 98 Battery St | Innovative Technologies | relocate manual pull station to exit at 6th fl.Details
relocate manual pull station to exit at 6th fl. | $500 |
| Mar 5, 2007 | Completed final sign-off Aug 2007 | 191 Pine St | Tong's Construction | remodel extg restaurant, (t.i.)install new flooring, wall covering and lighting. add 2 new bathrooms with new floor and wall finishes and lighting. upgrade main entry to be ada compliant. establish new occupant load.Details
remodel extg restaurant, (t.i.)install new flooring, wall covering and lighting. add 2 new bathrooms with new floor and wall finishes and lighting. upgrade main entry to be ada compliant. establish new occupant load. | $85,000 |
| Feb 27, 2007 | Completed final sign-off Aug 2007 | 191 Pine St | remove existing food service counter, flooring and wall covering surfaces in preparation for remodel. non structural demolition per ab-017Details
remove existing food service counter, flooring and wall covering surfaces in preparation for remodel. non structural demolition per ab-017 | $10,000 | |
| Jul 17, 2006 | Completed final sign-off May 2007 | 98 Battery St | Ward Alan Emery Construction Inc. | 4th floor, suite 402 - new drywall partitions, acoustic ceiling, doors, finishes. note: electrical and hvac on separate permits. demo wall to corridor to install dated doors.Details
4th floor, suite 402 - new drywall partitions, acoustic ceiling, doors, finishes. note: electrical and hvac on separate permits. demo wall to corridor to install dated doors. | $90,000 |
| Jun 27, 2006 | Completed final sign-off Oct 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | interior soft demo, new drywall partition, doors, finishes, acoustic ceiling/note electrical and mechanical on seperate permitDetails
interior soft demo, new drywall partition, doors, finishes, acoustic ceiling/note electrical and mechanical on seperate permit | $90,000 |
| Jun 7, 2006 | Completed final sign-off Jul 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | suite# 400. revision to pa# 2006/05/04/0759. change d.a. checklist page 2 of 2, item # 7 "visual alarm from" upgrade to full compliance "to" "none existinge & not required by code."Details
suite# 400. revision to pa# 2006/05/04/0759. change d.a. checklist page 2 of 2, item # 7 "visual alarm from" upgrade to full compliance "to" "none existinge & not required by code." | |
| May 4, 2006 | Completed final sign-off Jul 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | new drywall, prtn, acoustic lay-in clg, doors,finishes. mech elec sep permit and hvac.all non structural 4th floorDetails
new drywall, prtn, acoustic lay-in clg, doors,finishes. mech elec sep permit and hvac.all non structural 4th floor | $92,000 |
| Feb 24, 2006 | Completed final sign-off Oct 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | demo existing wall finishes. all work on lobby only. apply layer of drywall over existing surfaces, new drywall ceiling with soffit, replace existing doors (glass) with new. electrical on seperate permit.Details
demo existing wall finishes. all work on lobby only. apply layer of drywall over existing surfaces, new drywall ceiling with soffit, replace existing doors (glass) with new. electrical on seperate permit. | $28,000 |
| Feb 24, 2006 | Completed final sign-off Aug 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | new drywall non bearing partitions, new suspended ceiling, doors, frames & finishes.Details
new drywall non bearing partitions, new suspended ceiling, doors, frames & finishes. | $112,000 |
| Feb 21, 2006 | Completed final sign-off Oct 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | build 1-hr fire rated coridor tunnel/electric and mech on seperate permitDetails
build 1-hr fire rated coridor tunnel/electric and mech on seperate permit | $108,000 |
| Dec 29, 2005 | Completed final sign-off May 2006 | 191 Pine St | rise up the exist type 1 duct in the horizontal section from about 1'-10" heighter on ground floor.Details
rise up the exist type 1 duct in the horizontal section from about 1'-10" heighter on ground floor. | $800 | |
| Nov 15, 2005 | Completed final sign-off Oct 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | interior construction: t.i. rated tunnel corridor 3rd floor elec. on separate permitDetails
interior construction: t.i. rated tunnel corridor 3rd floor elec. on separate permit | $28,000 |
| Nov 2, 2005 | Completed final sign-off Jan 2006 | 98 Battery St | Cal-Air Inc | remove exist 10 ton split system & replacing it with new split system (10 ton) reusing existing duct. in kind air conditioning system replace in kind #4738Details
remove exist 10 ton split system & replacing it with new split system (10 ton) reusing existing duct. in kind air conditioning system replace in kind #4738 | $24,618 |
| Sep 1, 2005 | Expired or cancelled expired Aug 2006 | 98 Battery St | Ward Alan Emery Construction Inc. | interior alteration,remove interior drywall partitions.all non structural.new work,electrical & mechDetails
interior alteration,remove interior drywall partitions.all non structural.new work,electrical & mech | $14,000 |
| Aug 29, 2005 | Expired or cancelled expired Jul 2006 | 98 Battery St | Western Roofing Service | reroofingDetails
reroofing | $15,000 |
| Mar 14, 2005 | Expired or cancelled expired Jul 2006 | 98 Battery St | Pro-Ad Sign Co | erect: electric, wall, projecting,duble faced, directDetails
erect: electric, wall, projecting,duble faced, direct | |
| Aug 31, 2004 | Completed final sign-off Sep 2004 | 191 Pine St | Universal Fire Equipment Company | renew expired 200307159479- for final inspectionDetails
renew expired 200307159479- for final inspection | |
| Aug 19, 2004 | Completed final sign-off Sep 2004 | 191 Pine St | Fay Tat Construction Co | renew 200307240253 & 200304011221.Details
renew 200307240253 & 200304011221. | |
| Apr 30, 2004 | Never finaled issued Apr 2004, no final | 98 Battery St | demolition (e) 2nd/4th restroom,upgrade restroom to handicap,voluntary upgradeDetails
demolition (e) 2nd/4th restroom,upgrade restroom to handicap,voluntary upgrade | $35,000 | |
| Jul 24, 2003 | Expired or cancelled expired Sep 2004 | 191 Pine St | Fay Tat Construction Co | revision to orig permit 993373 appl #200304011211. relocation of makeup fan.Details
revision to orig permit 993373 appl #200304011211. relocation of makeup fan. | |
| Jul 15, 2003 | Expired or cancelled expired Sep 2004 | 191 Pine St | Universal Fire Equipment Company | install fire suppression pcl-460 wet chemical to protect hood, duct, plenum and cooking equipment unDetails
install fire suppression pcl-460 wet chemical to protect hood, duct, plenum and cooking equipment un | $2,100 |
| Apr 1, 2003 | Expired or cancelled expired Sep 2004 | 191 Pine St | Fay Tat Construction Co | install kitchen equipment & type 1 grease hood, install grease exhust duct and make0up fan w/ducts.pDetails
install kitchen equipment & type 1 grease hood, install grease exhust duct and make0up fan w/ducts.p | $22,000 |
| Nov 29, 2001 | Completed final sign-off Feb 2002 | 98 Battery St | M C Metal Inc | window washing tie backDetails
window washing tie back | $4,600 |
| Jun 16, 2000 | Expired or cancelled expired Dec 2000 | 191 Pine St | Details
| $5,700 |
Find contractors for work like this