- Jul 2001 to Sep 2023
21 permits since 2000 (architect on 19 permits, authorized agent-others on 2 permits): 13 completed, 5 never finaled, 3 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 1, 2023 | Completed final sign-off Nov 2023 | 1848 Noriega St | in response to abe# 201911188332, replace entry door hardware w/ lever type, request determination of technical infeasibility for intem 5, level landing, item 7, floor with 1/2" & item 14 manuvering.Details
in response to abe# 201911188332, replace entry door hardware w/ lever type, request determination of technical infeasibility for intem 5, level landing, item 7, floor with 1/2" & item 14 manuvering. | $300 | |
| Dec 16, 2020 | Expired or cancelled cancelled Nov 2024 | 66 Clifford Tr | relocate garage door and install in new location. to be align with front facade.Details
relocate garage door and install in new location. to be align with front facade. | $8,000 | |
| Nov 3, 2020 | Expired or cancelled cancelled Jan 2026 | 1857 11th Av | replace windows and siding, renovate kitchen and three bath roomsDetails
replace windows and siding, renovate kitchen and three bath rooms | $200,000 | |
| Dec 30, 2019 | Completed final sign-off Oct 2022 | 101 Horne Av | Arana Group, Inc. | convert (e) auditorium to art gallery.life & safety upgrades, (n) exterior egress stair, exit signage (fire sprinkler riser & sprinklers deferred) for art gallery.ada barrier removal (n) entry ramp & accessible multi-user all gender restroom. **maher applicable**Details
convert (e) auditorium to art gallery.life & safety upgrades, (n) exterior egress stair, exit signage (fire sprinkler riser & sprinklers deferred) for art gallery.ada barrier removal (n) entry ramp & accessible multi-user all gender restroom. **maher applicable** | $3,000,000 |
| Jun 12, 2018 | Completed final sign-off Dec 2022 | 600 Arguello Bl | priority plan review. renovation of (e) pool bldg. scope of work includes seismic retrofit of the (e) structure. (n) mep. addition of a mechanical enclosure, ada barrier removal. (n) locker room layout. (n) fire sprinkler & fire alarm systems on separate submittals.Details
priority plan review. renovation of (e) pool bldg. scope of work includes seismic retrofit of the (e) structure. (n) mep. addition of a mechanical enclosure, ada barrier removal. (n) locker room layout. (n) fire sprinkler & fire alarm systems on separate submittals. | $5,000,000 | |
| Jan 10, 2018 | Never finaled issued Jan 2018, no final | 70 Elk St | Roebuck Construction | amendment to bldg permit set addendum #1 201406249343-s1, change to ext. restroomds 106 & 107 gender designation per city ordinance. per 11b-213.2 only one restroom in single user cluster is required to be accessible. restroom 107 is not required to be accessible.Details
amendment to bldg permit set addendum #1 201406249343-s1, change to ext. restroomds 106 & 107 gender designation per city ordinance. per 11b-213.2 only one restroom in single user cluster is required to be accessible. restroom 107 is not required to be accessible. | |
| Aug 22, 2017 | Completed final sign-off Apr 2021 | 901 Presidio Av | Makai Solutions | replacement of overhead rollup doors, replacement of bus lifts, replacement of swing gatesDetails
replacement of overhead rollup doors, replacement of bus lifts, replacement of swing gates | $2,500,000 |
| Jan 9, 2017 | Never finaled issued Feb 2017, no final | 100 Larkin St | demolish existing walls and doors and replace with new walls and doors in kind. maher not reqDetails
demolish existing walls and doors and replace with new walls and doors in kind. maher not req | $25,000 | |
| Feb 4, 2015 | Completed final sign-off Jun 2016 | 993 Gilman Av | new children's play structures, alterations of restrooms for ada compliance and replacement of light poles and fixtures.Details
new children's play structures, alterations of restrooms for ada compliance and replacement of light poles and fixtures. | $728,000 | |
| Feb 2, 2015 | Never finaled issued May 2016, no final | 3223 Ortega St | city job -ada accessibility upgades incl ramps, accessible seating,restrm upgrades&associated work. gardener storage bldg to replace(e) storage containers. sports field renovations incl irrigation, landscaping & parking lot improvements, public way curb ramp improvements.Details
city job -ada accessibility upgades incl ramps, accessible seating,restrm upgrades&associated work. gardener storage bldg to replace(e) storage containers. sports field renovations incl irrigation, landscaping & parking lot improvements, public way curb ramp improvements. | $3,400,000 | |
| Dec 4, 2014 | Completed final sign-off Sep 2015 | 2899 19th Av | Hoi's Construction | trocadero clubhouse- replace in kind existing wood porch deck, guardrails, steps and ramp, remove accessibility barriers.Details
trocadero clubhouse- replace in kind existing wood porch deck, guardrails, steps and ramp, remove accessibility barriers. | $140,000 |
| Mar 7, 2014 | Never finaled issued Mar 2014, no final | 3555 19th St | rev. to pa# 201006295547 to incorporate building inspector requested changes to site perimeter gates and unreasonable hardship request with equivalent facilitation for the pool building main entrance.Details
rev. to pa# 201006295547 to incorporate building inspector requested changes to site perimeter gates and unreasonable hardship request with equivalent facilitation for the pool building main entrance. | $20,000 | |
| Nov 15, 2013 | Completed final sign-off Apr 2015 | 2407 Great Hy | renovation of extg restroom including new roof. electrical, plumbing and general ada improvements.Details
renovation of extg restroom including new roof. electrical, plumbing and general ada improvements. | $363,000 | |
| Nov 15, 2013 | Completed final sign-off Apr 2015 | 1401 Great Hy | renovation of extg restroom incuding roof. electrical, plumbing and general ada improvements.Details
renovation of extg restroom incuding roof. electrical, plumbing and general ada improvements. | $357,000 | |
| May 1, 2013 | Completed final sign-off Feb 2016 | 1901 Geary Bl | scope of work includes renovation of (e) one story public restroom & storage building.Details
scope of work includes renovation of (e) one story public restroom & storage building. | $375,000 | |
| Apr 15, 2013 | Completed final sign-off Sep 2014 | 1000 Ocean Av | Granite Rock Company | remove & replace 1 door & several windowsDetails
remove & replace 1 door & several windows | $160,000 |
| Jul 17, 2012 | Completed final sign-off May 2015 | 70 Elk St | to make (ada) acessible: path of travel. restrooms, doors, drinking foundation, mechanical, electrical work to the site & restrooms, drinking fountain. incl conc. slab in restrooms. new landscape work to the site.Details
to make (ada) acessible: path of travel. restrooms, doors, drinking foundation, mechanical, electrical work to the site & restrooms, drinking fountain. incl conc. slab in restrooms. new landscape work to the site. | $1,261,382 | |
| Jan 3, 2012 | Never finaled issued Aug 2012, no final | 2101 Washington St | erect 1 story, type 5-b, storage for sf rec & park department equip. landscape materials in middle of the park.Details
erect 1 story, type 5-b, storage for sf rec & park department equip. landscape materials in middle of the park. | $250,000 | |
| May 8, 2007 | Completed final sign-off Feb 2010 | 1900 Geary Bl | seismic, access upgrades & renovation. renovate the (e) pool building & gymnasium . the (e) recreation center bldg. & pool locker rooms will be removed & replaced with a new one story bldg. site improvements include a new playground, play structures and new accessible ramps and entrances.Details
seismic, access upgrades & renovation. renovate the (e) pool building & gymnasium . the (e) recreation center bldg. & pool locker rooms will be removed & replaced with a new one story bldg. site improvements include a new playground, play structures and new accessible ramps and entrances. | ||
| Nov 29, 2004 | Completed final sign-off Oct 2007 | 620 Noriega St | new 400 sq. ft. horizontal addition over (e) garage. work to add new bedroom, family room & bathroom. install new skylight & replace 9 (e) windows.Details
new 400 sq. ft. horizontal addition over (e) garage. work to add new bedroom, family room & bathroom. install new skylight & replace 9 (e) windows. | $80,000 | |
| Jul 3, 2001 | Expired or cancelled expired Jan 2006 | 99 Grove St | upgrade of existing fire alarm systemDetails
upgrade of existing fire alarm system | $325,000 |