Ross Levy
- Listed as
- architect, authorized agent-others
- Firm
- Levy Art+Architecture
- Based in
- San Francisco
- On San Francisco permits
- Aug 2001 to Jun 2026
186 permits since 2000 (architect on 182 permits, authorized agent-others on 10 permits): 119 completed, 6 in progress, 30 never finaled, 31 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 186.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 3, 2026 | In progress issued Jun 2026 | 1100 Sacramento St | Blair Burke General Contractors Inc | apt#208: interior remodel: 1) primary bath relocated fixtures & new finishes.2) relocate walk-in closet. 3)(n) interior doors in select locations 4) electrical & plumbing via separate permit, no structural work, no change to building envelopeDetails
apt#208: interior remodel: 1) primary bath relocated fixtures & new finishes.2) relocate walk-in closet. 3)(n) interior doors in select locations 4) electrical & plumbing via separate permit, no structural work, no change to building envelope | $65,000 |
| Apr 30, 2026 | In progress filed Apr 2026, not yet issued | 1286 Guerrero St | legalize 1 (e) udu (#8) per planning code 207.3.permit 1 (e) udu (#9) as adu per state.f/s as noted but sep permit on 4/f and pulbic spaces only.upgrade water meter.add booster pump. to comply with nov201984145.ref dcp 2025-000321prj.Details
legalize 1 (e) udu (#8) per planning code 207.3.permit 1 (e) udu (#9) as adu per state.f/s as noted but sep permit on 4/f and pulbic spaces only.upgrade water meter.add booster pump. to comply with nov201984145.ref dcp 2025-000321prj. | $32,500 | |
| Apr 8, 2026 | Completed final sign-off Aug 2026 | 1160 Howard St | Rescom Realty And Development Llc | 1/fl-commercial ti to include (n) bakery sales counter/coffee bar (relocate existing) remodel seating area. (n) electrical and plumbing work via separate permit. no exterior work.Details
1/fl-commercial ti to include (n) bakery sales counter/coffee bar (relocate existing) remodel seating area. (n) electrical and plumbing work via separate permit. no exterior work. | $134,800 |
| Feb 12, 2026 | In progress issued Jul 2026 | 1573 34th Av | Blair Burke General Contractors Inc | new 3rd story vertical addition to (e) sfd and interior remodel @ 1st & 2md story to include: remodel & expand (e) kitchen, and 2 (e) bathjs, new primary bedroom and abath, new windows @ addition, (e)courtyard and rear elevation, replace (e) foundation for new clg hgt @ 1st story, new structuralDetails
new 3rd story vertical addition to (e) sfd and interior remodel @ 1st & 2md story to include: remodel & expand (e) kitchen, and 2 (e) bathjs, new primary bedroom and abath, new windows @ addition, (e)courtyard and rear elevation, replace (e) foundation for new clg hgt @ 1st story, new structural | $850,000 |
| Jan 30, 2026 | In progress issued Aug 2026 | 2461 Washington St | L H Construction | enlarge existing garage door openingDetails
enlarge existing garage door opening | $42,000 |
| Nov 18, 2025 | Completed final sign-off Jul 2026 | 2087 44th Av | Pederson Construction Inc | interior remodel of single family dwelling to include new kitchen w relocated equipment, new expandded opening between kitchen and living rm, new skylight @ kitchen, new electrical and plumbing, sep permit.no change to building envelope.Details
interior remodel of single family dwelling to include new kitchen w relocated equipment, new expandded opening between kitchen and living rm, new skylight @ kitchen, new electrical and plumbing, sep permit.no change to building envelope. | $32,365 |
| Jun 27, 2025 | Completed final sign-off Jun 2026 | 1500 06th Av | Connemara Fine Trim Inc Dba Highland Bui | revision to pa #202207198809. ref pa 202412136808. 1)new mech platform at roof. 2) framing revisions at decks. 3) new concreate footing at existing posts.Details
revision to pa #202207198809. ref pa 202412136808. 1)new mech platform at roof. 2) framing revisions at decks. 3) new concreate footing at existing posts. | $5,000 |
| Mar 26, 2025 | Completed final sign-off Jun 2026 | 1912 09th Av | North Bay Construction | alter site to pa #202309066000: partial removal (e) flat roof, select interior walls & single glazed windows. (n) partial flat roof w/ buildable envelope (no increase height), (n) interior remodel 2/f: (n) primary bath, remodel (e) kitchen, (n) windows front facade, kitchen, living & primary bath.Details
alter site to pa #202309066000: partial removal (e) flat roof, select interior walls & single glazed windows. (n) partial flat roof w/ buildable envelope (no increase height), (n) interior remodel 2/f: (n) primary bath, remodel (e) kitchen, (n) windows front facade, kitchen, living & primary bath. | |
| Dec 13, 2024 | Completed final sign-off Jun 2026 | 1500 06th Av | Connemara Fine Trim Inc Dba Highland Bui | revision to pa#202207198809 for small expansion of permitted addition to sfh to include: 1) increase of 12" to 1st floor permitted addition. 2) change in opening per rev6 clouds. no change to elect, plumbing & mech plan from previous permit. no change to plumbingDetails
revision to pa#202207198809 for small expansion of permitted addition to sfh to include: 1) increase of 12" to 1st floor permitted addition. 2) change in opening per rev6 clouds. no change to elect, plumbing & mech plan from previous permit. no change to plumbing | $5,626 |
| Nov 5, 2024 | Completed final sign-off Dec 2024 | 1141 Wisconsin St | Pristine Builders Group | to comply with nov# 202426394 previously obtained for pa: 202407156513. ref permit 202407156513. repair and replace in kind existing entry stairs, and treads. (more than 50% replacement)Details
to comply with nov# 202426394 previously obtained for pa: 202407156513. ref permit 202407156513. repair and replace in kind existing entry stairs, and treads. (more than 50% replacement) | $5,000 |
| Oct 22, 2024 | In progress filed Oct 2024, not yet issued | 472 Union St | remodel ground floor kitchen & bathroom. convert (e) habitable sapce to a new adu unit. utilize state adu programa ca gov sect 65852.21.Details
remodel ground floor kitchen & bathroom. convert (e) habitable sapce to a new adu unit. utilize state adu programa ca gov sect 65852.21. | $25,000 | |
| Aug 29, 2024 | Completed final sign-off Jun 2025 | 216 Sussex St | Pederson Construction Inc | alteration of (e) single family dwelling to consist of : remodel (e) kitchen w/(n) fixtures and finishes. reuse (e) appliance in same location. remodel (e) full bath w/(n) fixtures and finsihes. relocated plumbing fixtures. (n) laundry room, relocated w&d. remove (e) closet and window @ masterDetails
alteration of (e) single family dwelling to consist of : remodel (e) kitchen w/(n) fixtures and finishes. reuse (e) appliance in same location. remodel (e) full bath w/(n) fixtures and finsihes. relocated plumbing fixtures. (n) laundry room, relocated w&d. remove (e) closet and window @ master | $97,381 |
| Mar 5, 2024 | Completed final sign-off Oct 2025 | 752 27th St | Brennan Strong Hold Construction Inc | replace all exterior windows and doors. minor interior remodel. replace existing staircase from level 2-3. remodel 3rd fl bathroom and primary bathroom. remodel existing kitchenDetails
replace all exterior windows and doors. minor interior remodel. replace existing staircase from level 2-3. remodel 3rd fl bathroom and primary bathroom. remodel existing kitchen | $550,000 |
| Oct 30, 2023 | In progress filed Oct 2023, not yet issued | 258 Noe St | install roll up security gate. acknowledge req plan code 145.1 per #2 & a munal solid gate pre #3. exterior onlyDetails
install roll up security gate. acknowledge req plan code 145.1 per #2 & a munal solid gate pre #3. exterior only | $10,000 | |
| Sep 6, 2023 | Completed final sign-off Jun 2026 | 1912 09th Av | removal of(e)flat roof over 2-story bldg envelope @ rear, select interior walls(e) single glazed windoes & doors @conditioned space.replace in-kind flat roof in rear yard setback (no increase in bldg envelope) & (n) shed and flat roof overDetails
removal of(e)flat roof over 2-story bldg envelope @ rear, select interior walls(e) single glazed windoes & doors @conditioned space.replace in-kind flat roof in rear yard setback (no increase in bldg envelope) & (n) shed and flat roof over | $300,000 | |
| Jul 18, 2023 | Expired or cancelled revoked Oct 2023 | 472 Union St | administrative permit to document "house-keeping" unit. correct record to show (e) housekeeping unit as legal. comply with nov under separate permit (202200496). no work to be performed under this permit.Details
administrative permit to document "house-keeping" unit. correct record to show (e) housekeeping unit as legal. comply with nov under separate permit (202200496). no work to be performed under this permit. | ||
| Jun 9, 2023 | Never finaled issued Jun 2023, no final | 2866 Pine St | to comply with bid nov #202033991 dated 5/26/2020, remove non-load bearing partitions between kitchen & living room side of fridgeDetails
to comply with bid nov #202033991 dated 5/26/2020, remove non-load bearing partitions between kitchen & living room side of fridge | $2,000 | |
| Mar 15, 2023 | Never finaled issued Mar 2023, no final | 279 Vicente St | Ewen Utting Inc. | foundation replacement and redevelopment of (e) g/f. new interior stair (replace (e) non-conforming). new bathroom at 2/f. replace all windows.Details
foundation replacement and redevelopment of (e) g/f. new interior stair (replace (e) non-conforming). new bathroom at 2/f. replace all windows. | $200,000 |
| Dec 15, 2022 | Never finaled filed Dec 2022, never issued | 827 Peru Av | addition to single family homeDetails
addition to single family home | $175,000 | |
| Sep 15, 2022 | Expired or cancelled expired Sep 2026 | 2866 Pine St | comply with nov 202033991.remove non compliant stairs and laundry rm. rebuild stairs withing buildable area. new 1 hour wall at pl less than 9'.Details
comply with nov 202033991.remove non compliant stairs and laundry rm. rebuild stairs withing buildable area. new 1 hour wall at pl less than 9'. | $8,000 | |
| Aug 16, 2022 | Completed final sign-off Jun 2025 | 65 Graystone Tr | Pristine Builders Group | revision to pa#202108247069 replace front door in (e) frame; elongate windows at 2n fl primar bath; new sliding glass door roof equipment (separate permit); new 2nd floor bathroom - window. all new windows to be aluminum clad woodDetails
revision to pa#202108247069 replace front door in (e) frame; elongate windows at 2n fl primar bath; new sliding glass door roof equipment (separate permit); new 2nd floor bathroom - window. all new windows to be aluminum clad wood | $8,500 |
| Jul 19, 2022 | Completed final sign-off Jun 2026 | 1500 06th Av | Connemara Fine Trim Inc Dba Highland Bui | horizontal addition & interior alteration. expand (e) remodeled kitchen and sitting room off rear. (n) bath @ (e) 1st fl. expand 2 bedrooms off rear. (n) bath @ (e) 2nd fl, (n) waterproof deck @ (e) 2nd fl. structural upgrade as req'd. mep via separate permit. (n) windows & doors at addition .Details
horizontal addition & interior alteration. expand (e) remodeled kitchen and sitting room off rear. (n) bath @ (e) 1st fl. expand 2 bedrooms off rear. (n) bath @ (e) 2nd fl, (n) waterproof deck @ (e) 2nd fl. structural upgrade as req'd. mep via separate permit. (n) windows & doors at addition . | $145,000 |
| Jun 10, 2022 | Completed final sign-off Feb 2024 | 100 Alpine Tr | amend pa# 202109218872. replace foundation with mat slab. no other changes proposed.Details
amend pa# 202109218872. replace foundation with mat slab. no other changes proposed. | ||
| May 23, 2022 | Never finaled filed May 2022, never issued | 411 Edna St | Planart Construction Corp | remodel existing sfd to include:new low-sloped nroof at (e)bedroom,new front dormer expansion,new interior stair well to 3rd fl,new infill @ corner of 2nd fl,new interior layout,plumbing & electrical work via separate permit. revision to bpa #2017/07141958.planning prj#2021-008884.Details
remodel existing sfd to include:new low-sloped nroof at (e)bedroom,new front dormer expansion,new interior stair well to 3rd fl,new infill @ corner of 2nd fl,new interior layout,plumbing & electrical work via separate permit. revision to bpa #2017/07141958.planning prj#2021-008884. | $15,000 |
| May 16, 2022 | Completed final sign-off Feb 2025 | 300 Surrey St | exterior facade work including: altering a bay projection, improvements to the entry and steps leading from the street to the entry, and improvement to an existing deck on top of the garage.Details
exterior facade work including: altering a bay projection, improvements to the entry and steps leading from the street to the entry, and improvement to an existing deck on top of the garage. | $50,000 | |
| May 12, 2022 | Never finaled issued Oct 2022, no final | 457 38th Av | Pristine Builders Group | int alt 1st fl - (n) master bedrm, (n) master bathroom, (n) family room of unconditioned space; 2nd fl - remodel (e) kitchen & (e) bath; 3rd fl - (n) bath & laundry closets; (n) 3 story stair, structural upgrade as req'd; (n) radiant in-flr heat sys, plumb & elect work via separate permit; (n)Details
int alt 1st fl - (n) master bedrm, (n) master bathroom, (n) family room of unconditioned space; 2nd fl - remodel (e) kitchen & (e) bath; 3rd fl - (n) bath & laundry closets; (n) 3 story stair, structural upgrade as req'd; (n) radiant in-flr heat sys, plumb & elect work via separate permit; (n) | $375,000 |
| Mar 31, 2022 | Expired or cancelled expired Nov 2025 | 2025 Castro St | Blair Burke General Contractors Inc | revision to pa# 202112104131. replace in-kind rain screen on facade. add wdw at side + skylight at deck.Details
revision to pa# 202112104131. replace in-kind rain screen on facade. add wdw at side + skylight at deck. | $10,000 |
| Oct 8, 2021 | Completed final sign-off Dec 2021 | 2383 Bush St | Blair Burke General Contractors Inc | revision to pa 2020-1113-8888 moving rear window & re structure of rear wallDetails
revision to pa 2020-1113-8888 moving rear window & re structure of rear wall | |
| Sep 17, 2021 | Completed final sign-off Dec 2024 | 1141 Wisconsin St | Pristine Builders Group | remodel & expand single family dwelling. to include: (n) horizontal addition to rear within set back. structural upgrade as reqd. interior remodel throughout. plumbing & elect via separate permit. solar panels via separate permit.Details
remodel & expand single family dwelling. to include: (n) horizontal addition to rear within set back. structural upgrade as reqd. interior remodel throughout. plumbing & elect via separate permit. solar panels via separate permit. | $350,000 |
| Aug 24, 2021 | Expired or cancelled expired Jun 2025 | 65 Graystone Tr | rev pa 202104279407: kitchen & bathroom, new interior finishes. replacment of non-street facing windows & doors in-kind. voluntary seismic upgrade. no work visible from street/ no front alterationsDetails
rev pa 202104279407: kitchen & bathroom, new interior finishes. replacment of non-street facing windows & doors in-kind. voluntary seismic upgrade. no work visible from street/ no front alterations | $387,000 | |
| Jul 14, 2021 | Completed final sign-off Feb 2024 | 3109 Fillmore St | P F Construction Co | convert existing retail on 2/f to camabes sales & consumption louge: new ada bathroom, new service storage; new finishes. new filtration and ventilation system.Details
convert existing retail on 2/f to camabes sales & consumption louge: new ada bathroom, new service storage; new finishes. new filtration and ventilation system. | $187,000 |
| Jun 10, 2021 | Completed final sign-off Feb 2022 | 1176 Potrero Av | change of use to light manufacturing and wholesale storage. no alterations proposed.Details
change of use to light manufacturing and wholesale storage. no alterations proposed. | ||
| Jun 7, 2021 | Completed final sign-off Feb 2022 | 1176 Potrero Av | sign, " retro city fashions", projecting, non - electricDetails
sign, " retro city fashions", projecting, non - electric | ||
| Jun 1, 2021 | Completed final sign-off Nov 2021 | 5 Winfield St | Blair Burke General Contractors Inc | revision to pa 201412173930. swap shower and toilet locations in master bath. add a glass door to adjacent deck. change wood siding to stucco siding on south and east walls.Details
revision to pa 201412173930. swap shower and toilet locations in master bath. add a glass door to adjacent deck. change wood siding to stucco siding on south and east walls. | $5,000 |
| Feb 8, 2021 | Completed final sign-off Aug 2022 | 1907 Diamond St | Blair Burke General Contractors Inc | minor window & door altesations. not at the front facade including structural. remodel (e) kitchen and 3 baths, new interior finishes. new windows and doors with insulated glazzing, new bldg insul, new hvac, wh, and skylithg. mep via separate permits.Details
minor window & door altesations. not at the front facade including structural. remodel (e) kitchen and 3 baths, new interior finishes. new windows and doors with insulated glazzing, new bldg insul, new hvac, wh, and skylithg. mep via separate permits. | $150,000 |
| Dec 8, 2020 | Expired or cancelled cancelled Aug 2022 | 2235 Mission St | F J Sandoval Co | (#1): convert ground floor retail to preschool. rehang doors for egress from occupied mezzanine. renovate (e) non-ada restroom, add fixtures for childrens useDetails
(#1): convert ground floor retail to preschool. rehang doors for egress from occupied mezzanine. renovate (e) non-ada restroom, add fixtures for childrens use | $15,000 |
| Nov 13, 2020 | Completed final sign-off Dec 2021 | 2383 Bush St | Blair Burke General Contractors Inc | amend to 202008131673: add 3-stop elevator, relocating (e) door at rear elevation, adding a plant on (e) floors, add a car turner in the garage; 14 recessed and surface mounted light fixtures that will be added/relocated (sheet e.1).Details
amend to 202008131673: add 3-stop elevator, relocating (e) door at rear elevation, adding a plant on (e) floors, add a car turner in the garage; 14 recessed and surface mounted light fixtures that will be added/relocated (sheet e.1). | $120,000 |
| Sep 2, 2020 | Never finaled issued Sep 2020, no final | 3636 21st St | Blair Burke General Contractors Inc | revision to pa #2015-0115-5832: revise lower 1-story residential stair (wood framed) to a poured in-place concrete stair.Details
revision to pa #2015-0115-5832: revise lower 1-story residential stair (wood framed) to a poured in-place concrete stair. | |
| Aug 21, 2020 | Completed final sign-off May 2026 | 3753 21st St | Blair Burke General Contractors Inc | 273 sq ft expansion of existing 3rd floor over existing habitable space & new adjacent roof decksDetails
273 sq ft expansion of existing 3rd floor over existing habitable space & new adjacent roof decks | $187,000 |
| Aug 10, 2020 | Never finaled filed Aug 2020, never issued | 1651 Treat Av | new detached dwelling unit on through lot. (existing unit structure to remain). new single family, 3-story, type vb on ripley street frontage.Details
new detached dwelling unit on through lot. (existing unit structure to remain). new single family, 3-story, type vb on ripley street frontage. | $350,000 | |
| Mar 11, 2020 | Completed final sign-off Aug 2024 | 201 Middle Point Rd | Planart Construction Corp | revision to permit application #201708013571s. reducing bldg envelope, update rear facade, change to flat roofDetails
revision to permit application #201708013571s. reducing bldg envelope, update rear facade, change to flat roof | |
| Feb 27, 2020 | Completed final sign-off Dec 2021 | 3141 17th St | Bradford Construction | new ada compliant restroom. new employee training area, new floor sinks. no structural work. various interior upgrades & alterations, existing hvac system remainDetails
new ada compliant restroom. new employee training area, new floor sinks. no structural work. various interior upgrades & alterations, existing hvac system remain | $31,750 |
| Jan 22, 2020 | Completed final sign-off Oct 2021 | 3500 22nd St | Planart Construction Corp | voluntary seismic stregnthening at store frontDetails
voluntary seismic stregnthening at store front | $25,000 |
| Dec 27, 2019 | Completed final sign-off May 2021 | 258 Noe St | 1) interior retail remodel for recreational cannabis. 2)sprinkler and ada compliance. 3)remove vinyl siding and remodel exterior and fencing.Details
1) interior retail remodel for recreational cannabis. 2)sprinkler and ada compliance. 3)remove vinyl siding and remodel exterior and fencing. | $128,500 | |
| Dec 11, 2019 | Expired or cancelled cancelled Jan 2026 | 2650 Green St | new cummins rs50 generator to be installed @ rear of houseDetails
new cummins rs50 generator to be installed @ rear of house | $25,000 | |
| Nov 19, 2019 | Completed final sign-off Jan 2023 | 534 Texas St | revision to app#201112301504. change siding to stuccoDetails
revision to app#201112301504. change siding to stucco | $200 | |
| Sep 19, 2019 | Completed final sign-off Nov 2023 | 115 Pacheco St | Lung Fung Const & Elec Co, Abbeyside Construction Inc | remodel & expansion of (e) sfh including new horizontal addition to rear, interior remodel. barrier removal for univeral access, facade work & restoration, structural upgrade as required. no new additional rooms.Details
remodel & expansion of (e) sfh including new horizontal addition to rear, interior remodel. barrier removal for univeral access, facade work & restoration, structural upgrade as required. no new additional rooms. | $750,000 |
| Aug 15, 2019 | Expired or cancelled cancelled Dec 2021 | 5174 03rd St | vertical addition. modify (e) garage and add 4 new dwelling units. maher n/a.Details
vertical addition. modify (e) garage and add 4 new dwelling units. maher n/a. | $870,000 | |
| Jun 21, 2019 | Completed final sign-off Jan 2021 | 3555 23rd St | Structoris Inc. | replace in kind extg wood egress stairs, associated landings and decks.Details
replace in kind extg wood egress stairs, associated landings and decks. | $30,000 |
| May 22, 2019 | Completed final sign-off Nov 2021 | 3500 22nd St | Planart Construction Corp | exterior remodel to store front and entryway. accessible business entry retrofit. new ceramic tile on wainscot and entry. terazzo stair replacement.Details
exterior remodel to store front and entryway. accessible business entry retrofit. new ceramic tile on wainscot and entry. terazzo stair replacement. | $25,000 |
| May 21, 2019 | Completed final sign-off Aug 2020 | 1520 Taylor St | Martin Heagney, Elkabetz Inc. **See Notes** | unit # 603: remove, new walls extend kitchen into hallway, build wall between kitchen and office, extend bath walls in bedroomDetails
unit # 603: remove, new walls extend kitchen into hallway, build wall between kitchen and office, extend bath walls in bedroom | $25,000 |
| Mar 28, 2019 | Expired or cancelled cancelled Jan 2025 | 70 Joost Av | add 3rd fl. renovate existing for new stair, structural & life safety upgrades as required. add 3 bedroooms/2 baths, remove 1 bedroom.Details
add 3rd fl. renovate existing for new stair, structural & life safety upgrades as required. add 3 bedroooms/2 baths, remove 1 bedroom. | $500,000 | |
| Mar 6, 2019 | Completed final sign-off Jan 2020 | 26 Hodges Al | Moroso Construction Inc | replace rear glass wall on main level not visible from st or other propertiesDetails
replace rear glass wall on main level not visible from st or other properties | $28,000 |
| Feb 21, 2019 | Expired or cancelled cancelled Apr 2020 | 26 Hodges Al | at front horizontal addition, add 72 sq ft closet to 3rd floor master suite.Details
at front horizontal addition, add 72 sq ft closet to 3rd floor master suite. | $14,000 | |
| Jan 25, 2019 | Completed final sign-off Dec 2019 | 3636 21st St | Blair Burke General Contractors Inc | rev to pa# 20150115832; resolution of complaint 201801225 ienf (#20189972/201896523) plans indicate additional demo due to structural requirements and means & methods of constructionDetails
rev to pa# 20150115832; resolution of complaint 201801225 ienf (#20189972/201896523) plans indicate additional demo due to structural requirements and means & methods of construction | |
| Dec 5, 2018 | Expired or cancelled cancelled Jan 2026 | 496 Natoma St | minor facade alteration for security & repair on west facade onlyDetails
minor facade alteration for security & repair on west facade only | $4,250 | |
| Nov 6, 2018 | Completed final sign-off Jan 2019 | 4026 24th St | Planart Construction Corp | revision to permit #201805229760. revision of main bar with reduction of equipment. change to be a serving counter only.Details
revision to permit #201805229760. revision of main bar with reduction of equipment. change to be a serving counter only. | |
| Jun 27, 2018 | Completed final sign-off Sep 2018 | 444 30th St | Blair Burke General Contractors Inc | revision to #201403261745. reduction in scope no remodel work at 3rd fl bath or bedroom closet. existing to remain.Details
revision to #201403261745. reduction in scope no remodel work at 3rd fl bath or bedroom closet. existing to remain. | |
| May 22, 2018 | Completed final sign-off Jan 2019 | 4026 24th St | Planart Construction Corp | tenant improvement of (e) shell to inlcude; commercial kitchen; trash room; food storage, walk in cooler/freezer; interior remodel for restaurantDetails
tenant improvement of (e) shell to inlcude; commercial kitchen; trash room; food storage, walk in cooler/freezer; interior remodel for restaurant | $265,000 |
| May 18, 2018 | Completed final sign-off Jun 2021 | 2586 Great Hy | Blair Burke General Contractors Inc | interior alterations: demo partitions on ground floor & install new bathroom & laundry; new stair; new rear windows; relocate kitchen to 3rd floor; new finishes & fixtures throughout. no work visible from streetDetails
interior alterations: demo partitions on ground floor & install new bathroom & laundry; new stair; new rear windows; relocate kitchen to 3rd floor; new finishes & fixtures throughout. no work visible from street | $419,000 |
| May 18, 2018 | Completed final sign-off Jan 2019 | 4026 24th St | Planart Construction Corp | ti of (e) commercial restaurant shell to include walls & counters for future restaurantDetails
ti of (e) commercial restaurant shell to include walls & counters for future restaurant | $100,000 |
| May 11, 2018 | Completed final sign-off May 2021 | 278 15th Av | Lee And Son Construction Inc. | horizontal & remodel to (e) sfd into 2 units include new kitchen, bedroom & dinning room to 1st floor. remodel (e) kitchen on 2nd floor. remodel 2 bedrooms on 3rd floor. remodel (e) living room. plumbing & electrical work under separate permit.Details
horizontal & remodel to (e) sfd into 2 units include new kitchen, bedroom & dinning room to 1st floor. remodel (e) kitchen on 2nd floor. remodel 2 bedrooms on 3rd floor. remodel (e) living room. plumbing & electrical work under separate permit. | $225,000 |
| Dec 28, 2017 | Expired or cancelled cancelled Jan 2020 | 274 15th Av | Lmnop-Design Inc. | horizontal adddition. addition of rear stairs and interior remodel of dwelling. including (n) beds, (n) baths (n) kitchen.Details
horizontal adddition. addition of rear stairs and interior remodel of dwelling. including (n) beds, (n) baths (n) kitchen. | $500,000 |
| Nov 27, 2017 | Expired or cancelled expired Nov 2021 | 3636 21st St | Blair Burke General Contractors Inc | replace (e) retaining walls with new soldier pile walls. new concrete pation and hot tub. replace (e) fencing with new cedar fencing. all work in backDetails
replace (e) retaining walls with new soldier pile walls. new concrete pation and hot tub. replace (e) fencing with new cedar fencing. all work in back | $21,000 |
| Sep 27, 2017 | Never finaled filed Sep 2017, never issued | 3359 Cesar Chavez St | renovations for life safety & ada compliance in conjunction w/ conditional use applicaiton. no additions or alterations to the exterior, with the exception of a fire exit on the west wall.Details
renovations for life safety & ada compliance in conjunction w/ conditional use applicaiton. no additions or alterations to the exterior, with the exception of a fire exit on the west wall. | $110,000 | |
| Aug 21, 2017 | Expired or cancelled cancelled Jul 2024 | 2109 22nd St | horizontal & vertical addition. remodel & addiiton to existing 2 unit dwellings. incl (n) 2 new dwelling w/ 2 bedrooms, 1 bath & 1 kitchen each. interior remodel of 2 (e) efficiency dwelling. plumbing & elec via separate permit.Details
horizontal & vertical addition. remodel & addiiton to existing 2 unit dwellings. incl (n) 2 new dwelling w/ 2 bedrooms, 1 bath & 1 kitchen each. interior remodel of 2 (e) efficiency dwelling. plumbing & elec via separate permit. | $350,000 | |
| Aug 18, 2017 | Completed final sign-off Jan 2019 | 1102 Dolores St | Planart Construction Corp | interior remodel of dwelling to include 1)new bathroom, 2)remodel extg bathroom, 3)plmg and electrical work.Details
interior remodel of dwelling to include 1)new bathroom, 2)remodel extg bathroom, 3)plmg and electrical work. | $30,500 |
| Aug 1, 2017 | Completed final sign-off Aug 2024 | 201 Middle Point Rd | remodel & expand an (e) sfd to include (n) horizontal addition to rear, (2)stories high. structural upgrade as required. interior remodel of part of the (e) building. plumbing & electrical work via separate permit.Details
remodel & expand an (e) sfd to include (n) horizontal addition to rear, (2)stories high. structural upgrade as required. interior remodel of part of the (e) building. plumbing & electrical work via separate permit. | $125,000 | |
| Jul 14, 2017 | Never finaled issued Oct 2018, no final | 411 Edna St | Planart Construction Corp | remodel main floor. raise entire structure +/-6" for headroom at (n) lower bedroom. reconfigure front stairs.Details
remodel main floor. raise entire structure +/-6" for headroom at (n) lower bedroom. reconfigure front stairs. | $200,000 |
| Jun 16, 2017 | Never finaled issued Jun 2017, no final | 1649 Treat Av | demolition of laundry room at rear of home; repair of roof and facade as needed at area of laundry room demolition.Details
demolition of laundry room at rear of home; repair of roof and facade as needed at area of laundry room demolition. | $12,000 | |
| Jun 6, 2017 | Completed final sign-off Dec 2017 | 3733 22nd St | Pederson Construction | remodel ground fl, interior remodel to include (e) bedroom, (e) full bath, plumbing work in bathroom. electrical work in bedroom, bath & deck.Details
remodel ground fl, interior remodel to include (e) bedroom, (e) full bath, plumbing work in bathroom. electrical work in bedroom, bath & deck. | $15,000 |
| Apr 28, 2017 | Never finaled issued May 2017, no final | 640 Davis St | Maggetti Construction Inc | unit 18, electrical work in bedroom, bathrooms, kitchen, & living room. reference 2017.04.20.5261 n/a for maherDetails
unit 18, electrical work in bedroom, bathrooms, kitchen, & living room. reference 2017.04.20.5261 n/a for maher | $5,000 |
| Apr 12, 2017 | Never finaled issued Jul 2017, no final | 327 Capitol Av | Proforma Construction Inc. | upgrade to existing structure & foundation. revision to permit 201603162235.Details
upgrade to existing structure & foundation. revision to permit 201603162235. | $35,000 |
| Mar 23, 2017 | Completed final sign-off Oct 2018 | 333 Day St | Mascheroni Construction | revision to app#201509046246 - sprinklers not required.Details
revision to app#201509046246 - sprinklers not required. | |
| Mar 13, 2017 | Completed final sign-off Jun 2019 | 1770 Noe St | Hing Wah Construction Inc | adu per ord #162-16. proposed accessory dwelling unit added to a portion of the (e) basement area. propose foundation improvements to accomodate the adu were approved under a separate permit. the proposed adu is a (1)bedroom unit, including kitchen & a living space & patio.Details
adu per ord #162-16. proposed accessory dwelling unit added to a portion of the (e) basement area. propose foundation improvements to accomodate the adu were approved under a separate permit. the proposed adu is a (1)bedroom unit, including kitchen & a living space & patio. | $75,000 |
| Dec 28, 2016 | Completed final sign-off Mar 2019 | 95 Laidley St | Hing Wah Construction Inc | upgrade extg concrete foundation. partial replacement of bldg footings and slab at extg basement and porch. new beams and posts at basement & 1st floor.Details
upgrade extg concrete foundation. partial replacement of bldg footings and slab at extg basement and porch. new beams and posts at basement & 1st floor. | $80,000 |
| Nov 4, 2016 | Never finaled filed Nov 2016, never issued | 40 Mirabel Av | roof deck added to extg single family house.Details
roof deck added to extg single family house. | $25,000 | |
| Sep 29, 2016 | Completed final sign-off Apr 2017 | 118 Winfield St | Kevin Webb Construction Inc | interior remodel of bathroom and closet. no envelope or area changes. plumbing and electrical work included.Details
interior remodel of bathroom and closet. no envelope or area changes. plumbing and electrical work included. | $50,000 |
| Apr 20, 2016 | Never finaled issued Sep 2016, no final | 640 Davis St | Maggetti Construction Inc | unit #18 - replace extg brick bay window with new sunroom window, replace 3 extg windows, remodel extg kitchen, remodel 2 bathrooms, replace extg fan and water heater. n/a ordinance #155-13Details
unit #18 - replace extg brick bay window with new sunroom window, replace 3 extg windows, remodel extg kitchen, remodel 2 bathrooms, replace extg fan and water heater. n/a ordinance #155-13 | $65,000 |
| Mar 16, 2016 | Completed final sign-off Dec 2020 | 327 Capitol Av | change of use from religious facility to child care up to 90 children. renovate extg structure for upgrades for licensed pre-school including; ada, mechanical, life safety and seismic.Details
change of use from religious facility to child care up to 90 children. renovate extg structure for upgrades for licensed pre-school including; ada, mechanical, life safety and seismic. | $225,000 | |
| Feb 24, 2016 | Completed final sign-off Nov 2016 | 825 Rhode Island St | Ampex Engineering & Co | structural revision at 2nd floor framing plan, s2.2 under bpa#201307313187-s1 per plan.Details
structural revision at 2nd floor framing plan, s2.2 under bpa#201307313187-s1 per plan. | $5,000 |
| Feb 8, 2016 | Completed final sign-off Sep 2016 | 1 Bernice St | Blair Burke General Contractors Inc | interior remodel of (e) live work space, including 1)reconfigure/relocate of existing kitchen, 2) new stair to mezzanine, 3)new mezzanine configuration(reduces sq ft). 4) new bathroom on mezzanine one. 5) plmg & electrical work on seperate permit.Details
interior remodel of (e) live work space, including 1)reconfigure/relocate of existing kitchen, 2) new stair to mezzanine, 3)new mezzanine configuration(reduces sq ft). 4) new bathroom on mezzanine one. 5) plmg & electrical work on seperate permit. | $220,000 |
| Jan 28, 2016 | Completed final sign-off Apr 2016 | 536 Steiner St | Pederson Construction | rev. to pa#201511132495 - revision to remove columns (2) @ basement, replace with (n) wide flange steel beam.Details
rev. to pa#201511132495 - revision to remove columns (2) @ basement, replace with (n) wide flange steel beam. | $2,500 |
| Dec 15, 2015 | Never finaled issued May 2016, no final | 498 Natoma St | S & I Construction, Inc | refurbish (e) commerical space, upgrade entry & bathrooms for full ada compliance. no structural work, no exterior alteration.Details
refurbish (e) commerical space, upgrade entry & bathrooms for full ada compliance. no structural work, no exterior alteration. | $50,000 |
| Oct 26, 2015 | Never finaled issued Sep 2020, no final | 135 Ripley St | rear building. to erect 2 stoires, 1 basement, single family dwelling.Details
rear building. to erect 2 stoires, 1 basement, single family dwelling. | $950,000 | |
| Oct 21, 2015 | Never finaled issued Jul 2018, no final | 1286 Sanchez St | Brennan Strong Hold Construction Inc | two-story addition with required structural upgrades. roof deck above 3rd story addition. interior improvement for bedrooms & baths @ 2nd floor. 3 bedrooms & 2 baths.Details
two-story addition with required structural upgrades. roof deck above 3rd story addition. interior improvement for bedrooms & baths @ 2nd floor. 3 bedrooms & 2 baths. | $250,000 |
| Sep 4, 2015 | Completed final sign-off Oct 2018 | 333 Day St | Mascheroni Construction | renovation of single family dwelling including vertical expanding 3rd story into (e) attic to provide (3) (n) bedrooms & 1 (n) bath. interior remodel of (e) 2 story with (n) kitchen, dining & living room. plumbing & electrical work (via separate permit.Details
renovation of single family dwelling including vertical expanding 3rd story into (e) attic to provide (3) (n) bedrooms & 1 (n) bath. interior remodel of (e) 2 story with (n) kitchen, dining & living room. plumbing & electrical work (via separate permit. | $150,000 |
| Sep 2, 2015 | Completed final sign-off Jan 2018 | 444 30th St | Blair Burke General Contractors Inc | new rear yard deck.Details
new rear yard deck. | $50,000 |
| Aug 21, 2015 | Completed final sign-off Mar 2017 | 1928 Vallejo St | Johnstone - Mc Auliffe Const. Inc. | add new roof deck, add new stair to roof deck from third floor. remove portion og the roof ceiling on the 3rd flr to roof deck.Details
add new roof deck, add new stair to roof deck from third floor. remove portion og the roof ceiling on the 3rd flr to roof deck. | $50,000 |
| Jul 23, 2015 | Never finaled issued Jun 2017, no final | 714 Kansas St | Ace Drilling & Excavation | demolish single family residenceDetails
demolish single family residence | $50,000 |
| Jun 8, 2015 | Completed final sign-off Sep 2015 | 2714 Pacific Av | Capomastro Group:Acalifornia Corp. | revision to pa#201411181796 to accomodate field conditions, revise beam at kitchen doors, remove skylight, move interior walls.Details
revision to pa#201411181796 to accomodate field conditions, revise beam at kitchen doors, remove skylight, move interior walls. | |
| May 14, 2015 | Expired or cancelled withdrawn Nov 2019 | 4320 24th St | renovation of (e) single family dwelling including 1. (n) 3rd story vertical adition with 3 bedrooms and 2 baths 2. expand width of (e) 1st story room and deck in rear 3. interior remodel of (e) floors 4. structural work as req'd 5. fire sprinklers/plumbing/electrical. work via separate permitDetails
renovation of (e) single family dwelling including 1. (n) 3rd story vertical adition with 3 bedrooms and 2 baths 2. expand width of (e) 1st story room and deck in rear 3. interior remodel of (e) floors 4. structural work as req'd 5. fire sprinklers/plumbing/electrical. work via separate permit | $370,000 | |
| May 5, 2015 | Completed final sign-off Nov 2015 | 124 Clarendon Av | Lung Fung Const & Elec Co | revision to pa# 201408274890 & 201409244232 widen & replace garage door, remove man door , improve front facade, driveway,widen curb cut.Details
revision to pa# 201408274890 & 201409244232 widen & replace garage door, remove man door , improve front facade, driveway,widen curb cut. | $5,000 |
| Feb 18, 2015 | Completed final sign-off Mar 2019 | 3312 17th St | Eignor Construction Inc. | horiz addition @1st story com'l. infill of (e) lightwell @ 2nd & 3rd story new entry & exit stairs fr dwg. facade wk @(e)bldg. interior remodel (e) efficiency dwg unis. vert. addition of 4/f mezz w/2 new dwgs. fire sprinklers & elect wrk via seperate permit; add 2 bedrms & 2 kitchens & 2 bath.Details
horiz addition @1st story com'l. infill of (e) lightwell @ 2nd & 3rd story new entry & exit stairs fr dwg. facade wk @(e)bldg. interior remodel (e) efficiency dwg unis. vert. addition of 4/f mezz w/2 new dwgs. fire sprinklers & elect wrk via seperate permit; add 2 bedrms & 2 kitchens & 2 bath. | $527,068 |
| Jan 15, 2015 | Expired or cancelled expired Nov 2021 | 3636 21st St | Blair Burke General Contractors Inc, Design Line Construction | renovate & expand; horizontal add 2-story over basement by variance; vertical add; extend habitable space on (e) 3rd level; complete interior retrofit; roof terrace add; full seismic retrofit; fire sprinklers; property line windows per above; bldg envelop upgrades; facade improvement & restoration;Details
renovate & expand; horizontal add 2-story over basement by variance; vertical add; extend habitable space on (e) 3rd level; complete interior retrofit; roof terrace add; full seismic retrofit; fire sprinklers; property line windows per above; bldg envelop upgrades; facade improvement & restoration; | $1,000,000 |
| Dec 24, 2014 | Completed final sign-off Mar 2019 | 3312 17th St | Eignor Construction Inc. | to comply with nov 201333381. repair fire damage, seismic upgrade install automatic fire sprinkler system and reconfigure exit stairs for code compliance. sprinklers under separate permit.Details
to comply with nov 201333381. repair fire damage, seismic upgrade install automatic fire sprinkler system and reconfigure exit stairs for code compliance. sprinklers under separate permit. | $150,000 |
| Nov 24, 2014 | Completed final sign-off Mar 2018 | 1042 Jackson St | Ren Lei Construction Co | vertical addition of 1 floor to create an additional residential unit. 4 bedrooms and 2 baths and 1 new kitchen in the new unit. job is including three units.Details
vertical addition of 1 floor to create an additional residential unit. 4 bedrooms and 2 baths and 1 new kitchen in the new unit. job is including three units. | $350,000 |
| Nov 18, 2014 | Completed final sign-off Sep 2015 | 2714 Pacific Av | Capomastro Group:Acalifornia Corp. | expand e rear yard deck to side pl, remodel e bath, kitchen, new wood doors at rear and replace with metal window side and add skylight. interior remodel for plans, paint front and rear of house.Details
expand e rear yard deck to side pl, remodel e bath, kitchen, new wood doors at rear and replace with metal window side and add skylight. interior remodel for plans, paint front and rear of house. | $75,000 |
| Sep 8, 2014 | Expired or cancelled expired Dec 2017 | 444 30th St | Blair Burke General Contractors Inc | revision to appl #2014.0326.1745: new retaining wall & structural mat slab at rear first floor. new wood deck over existing patio at rear yard at grade (2 ft).Details
revision to appl #2014.0326.1745: new retaining wall & structural mat slab at rear first floor. new wood deck over existing patio at rear yard at grade (2 ft). | $18,000 |
| Aug 27, 2014 | Completed final sign-off Nov 2015 | 124 Clarendon Av | Lung Fung Const & Elec Co | interior renovations including kitchens and baths. new windows at rear of house with lateral upgrades. voluntary structural upgradesDetails
interior renovations including kitchens and baths. new windows at rear of house with lateral upgrades. voluntary structural upgrades | $100,000 |