Michael Tauber
- Listed as
- architect, authorized agent-others
- Firm
- Michael Tauber Architecture
- Based in
- San Francisco
- On San Francisco permits
- May 2006 to Aug 2026
89 permits since 2000 (architect on 88 permits, authorized agent-others on 1 permit): 70 completed, 7 in progress, 6 never finaled, 6 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 19, 2026 | In progress issued Sep 2026 | 3 Presidio Tr | Black Mountain Development | revision to 202606042559, int remodel @ all floors. add bathroom @ 2nd fl, remodel primary closet. add laundry room @ 2nd flr. new lighting & electrical throughout. remove 2 interior stairs. new hvac @ 3rd floor. also, revise scope of work for pa 202606042559 to: remodel of 6 bathrooms 1 kitcenDetails
revision to 202606042559, int remodel @ all floors. add bathroom @ 2nd fl, remodel primary closet. add laundry room @ 2nd flr. new lighting & electrical throughout. remove 2 interior stairs. new hvac @ 3rd floor. also, revise scope of work for pa 202606042559 to: remodel of 6 bathrooms 1 kitcen | $95,000 |
| Jul 23, 2026 | In progress issued Jul 2026 | 1347 40th Av | Healthy Building Science Inc | revision to #202603167679. material change to wall assembly located in exterior breezeway. replace gympsum with lp fireblock osb to provide fire protection for exterior application.Details
revision to #202603167679. material change to wall assembly located in exterior breezeway. replace gympsum with lp fireblock osb to provide fire protection for exterior application. | |
| Apr 14, 2026 | In progress issued May 2026 | 1347 40th Av | Healthy Building Science Inc | convert existing conditioned space on street level to adu.Details
convert existing conditioned space on street level to adu. | $185,000 |
| Feb 24, 2026 | Completed final sign-off Aug 2026 | 595 Pacific Av | Principal Builders Inc. | 2nd fl - office ti installation of new non-bearing partitions, ceilings, power/data and finishes. structural & mep deferredDetails
2nd fl - office ti installation of new non-bearing partitions, ceilings, power/data and finishes. structural & mep deferred | $1,407,813 |
| Jan 28, 2026 | Completed final sign-off Jul 2026 | 595 Pacific Av | Principal Builders Inc. | 3rd floor: ti non-structural partitions , ceiling power data and finishes. mep deferred.Details
3rd floor: ti non-structural partitions , ceiling power data and finishes. mep deferred. | $652,080 |
| Jun 6, 2025 | Completed final sign-off Apr 2026 | 2121 Webster St | Black Mountain Development | gph3: replace exterior window and door system-west wall on one floor. provide new concrete curb for new window/door sill. patch and repair finishes around window replacement.Details
gph3: replace exterior window and door system-west wall on one floor. provide new concrete curb for new window/door sill. patch and repair finishes around window replacement. | $15,000 |
| May 27, 2025 | In progress issued Jun 2025 | 280 Spear St | Black Mountain Development | remove closet in the media room and add 2x soffitsDetails
remove closet in the media room and add 2x soffits | $1,000 |
| Feb 12, 2025 | In progress issued Feb 2025 | 1750 Taylor St | Black Mountain Development | unit #305: remodel primary bathroom and closet, remodel bath 2 and powder room, new cabinetry in bedroom 2 and entry, reconfigure kitchen including new appliances and finishes. new lighting throughout, new tile and waterproofing at balconies. replace in kind window wall on west bedroom and northDetails
unit #305: remodel primary bathroom and closet, remodel bath 2 and powder room, new cabinetry in bedroom 2 and entry, reconfigure kitchen including new appliances and finishes. new lighting throughout, new tile and waterproofing at balconies. replace in kind window wall on west bedroom and north | $100,000 |
| Sep 20, 2024 | In progress filed Sep 2024, not yet issued | 160 Ewing Tr | O'kane Construction Llc | repair water damage at dining rm/kitchen sliding patio door, kitchen replacement in kind (not shown on drawings), relocate ground floor laundry and bathroom, replace in kind rear sliding door, replace in kind 4 windows in (e) jamb w/smaller windows.Details
repair water damage at dining rm/kitchen sliding patio door, kitchen replacement in kind (not shown on drawings), relocate ground floor laundry and bathroom, replace in kind rear sliding door, replace in kind 4 windows in (e) jamb w/smaller windows. | $105,000 |
| Aug 28, 2024 | Completed final sign-off May 2025 | 1101 Green St | Black Mountain Development | layout change for interior remodel of bathrooms, kitchen & closets. replace floorings, re-paint entire space, replace doors, replace kitchen appliances w/energy efficient modles, replace window shade. replace all lighting outlets & controls. revision to pa 202405142083Details
layout change for interior remodel of bathrooms, kitchen & closets. replace floorings, re-paint entire space, replace doors, replace kitchen appliances w/energy efficient modles, replace window shade. replace all lighting outlets & controls. revision to pa 202405142083 | $50,000 |
| Jul 17, 2024 | Completed final sign-off Mar 2025 | 1750 Taylor St | Baxter Construction | unit 2302: remodel 2 bathrooms & kitchen, replace plumbing fixture in kind. no structural or exterior workDetails
unit 2302: remodel 2 bathrooms & kitchen, replace plumbing fixture in kind. no structural or exterior work | $125,000 |
| May 16, 2024 | Completed final sign-off Sep 2024 | 2121 Webster St | Black Mountain Development | remodel laundry room. remove (e) lower cabinetry and plumbing fixtures. install (n) cabinetry & plumbing fixturesDetails
remodel laundry room. remove (e) lower cabinetry and plumbing fixtures. install (n) cabinetry & plumbing fixtures | $10,000 |
| Feb 28, 2024 | In progress filed Feb 2024, not yet issued | 477 Bryant St | change of occupancy from b to r-3, renovate (e) bath and kitchen.Details
change of occupancy from b to r-3, renovate (e) bath and kitchen. | $40,000 | |
| Nov 21, 2023 | Completed final sign-off Mar 2024 | 2121 Webster St | Black Mountain Development | bedroom 3- remove (e) cabinetry. bulkhead diffuser and recessed downlights then patch ceiling. install furniture by others and relocate (e) downlights. siting room- remove cabinetry, non structural walls, (e) diffuser bulkhead, recessed downlights, patch ceiling. relocate diffuser and downlights...Details
bedroom 3- remove (e) cabinetry. bulkhead diffuser and recessed downlights then patch ceiling. install furniture by others and relocate (e) downlights. siting room- remove cabinetry, non structural walls, (e) diffuser bulkhead, recessed downlights, patch ceiling. relocate diffuser and downlights... | $10,000 |
| Nov 21, 2023 | Completed final sign-off Mar 2024 | 2121 Webster St | Black Mountain Development | add new closet at entryway. dining room- remove (e) recessed downlight and replace with (n) chandelier. replace bathroom vanities in kind.Details
add new closet at entryway. dining room- remove (e) recessed downlight and replace with (n) chandelier. replace bathroom vanities in kind. | $10,000 |
| Aug 16, 2023 | Completed final sign-off Dec 2025 | 1080 Chestnut St | Black Mountain Development | replace non confirming railing w/new code compliant guards, replace drain at 1 balcany. add topping and waterproofing to (e) balcony surface to improve slope drainage at north and east balconies. add new pedestal pavers at all balcaniesDetails
replace non confirming railing w/new code compliant guards, replace drain at 1 balcany. add topping and waterproofing to (e) balcony surface to improve slope drainage at north and east balconies. add new pedestal pavers at all balcanies | $20,000 |
| Dec 14, 2022 | Completed final sign-off Jun 2023 | 1254 06th Av | Alder Construction | 1/f: remodel kitchen in rear of building. no change in square footageDetails
1/f: remodel kitchen in rear of building. no change in square footage | $68,000 |
| Nov 22, 2022 | Completed final sign-off Mar 2024 | 595 Pacific Av | Trust Construction Company Inc | revision to pa# 201806212538. revise sheet a.2 in lobby eliminate the wall at lobby entrance to stair vestibule and leave exisitng door to vestibule as shown in the existing/demo plan.Details
revision to pa# 201806212538. revise sheet a.2 in lobby eliminate the wall at lobby entrance to stair vestibule and leave exisitng door to vestibule as shown in the existing/demo plan. | |
| Nov 9, 2022 | Completed final sign-off Nov 2024 | 1080 Chestnut St | Black Mountain Development | 18 fl: demo (e) int walls and finishes. construct new walls, ceilings, install new plumbing, cabinetry, and appliances. paint and new floor finishes.Details
18 fl: demo (e) int walls and finishes. construct new walls, ceilings, install new plumbing, cabinetry, and appliances. paint and new floor finishes. | $400,000 |
| Jun 11, 2021 | Completed final sign-off May 2023 | 117 Frederick St | Stonebridge Construction Inc, Maximo Construction | remodel kitchen, new lighting, cabinets and appliances.Details
remodel kitchen, new lighting, cabinets and appliances. | $75,000 |
| Mar 24, 2021 | Completed final sign-off Feb 2022 | 45 Crescent Av | One Stop Shop Construction | revise app#201811266628 and 201903014172. 1) relocate kitchen and bathroom to approved permit #201811266628 and 201903014172. 2) revise structural drawings for arch. design changesDetails
revise app#201811266628 and 201903014172. 1) relocate kitchen and bathroom to approved permit #201811266628 and 201903014172. 2) revise structural drawings for arch. design changes | |
| Nov 9, 2020 | Completed final sign-off Dec 2022 | 1990 Newcomb Av | tenant improvement for sfpuc office and deck railing: install fire separation wall, non bearing partitions, new cabinetry, breakroom, remodel restrooms, new flooring, ceiling, new mechanical, new electrical and lighting, restripe parking for ada, new dock railingDetails
tenant improvement for sfpuc office and deck railing: install fire separation wall, non bearing partitions, new cabinetry, breakroom, remodel restrooms, new flooring, ceiling, new mechanical, new electrical and lighting, restripe parking for ada, new dock railing | $1,000,000 | |
| Sep 2, 2020 | Completed final sign-off Jun 2021 | 33 Alta St | Fontana Construction, Inc. | interior renovation of (e) bathroom, new finishes, lighting, door, plumbing fixtures & fittingsDetails
interior renovation of (e) bathroom, new finishes, lighting, door, plumbing fixtures & fittings | $35,000 |
| Sep 2, 2020 | Completed final sign-off Sep 2021 | 706 Mission St | Black Mountain Development | unit 17a: replace (3) toilets, reconfigure master closet, lower ceiling in living room, dining room, family room, & master bedroom to add recessed lighting, create soffits for downlights in bedrooms, install window shades. mech & fire protection are deferred under separate permitDetails
unit 17a: replace (3) toilets, reconfigure master closet, lower ceiling in living room, dining room, family room, & master bedroom to add recessed lighting, create soffits for downlights in bedrooms, install window shades. mech & fire protection are deferred under separate permit | $100,000 |
| Aug 22, 2020 | Completed final sign-off Feb 2021 | 1656 Beach St | Fontana Construction, Inc. | revision to bpa#201705317985. reduced scope of work, bedroom changes & fire place removal elminated. revised kitchen & bathroom layout - new architect/engineer, new drawings.Details
revision to bpa#201705317985. reduced scope of work, bedroom changes & fire place removal elminated. revised kitchen & bathroom layout - new architect/engineer, new drawings. | |
| Jan 14, 2020 | Expired or cancelled withdrawn Jan 2021 | 2740 Union St | addition of a roof deck(less than 500 s.f.) and stair penthouse. relocate 3rd flr units front door, upgrade hanrail and guards. sprinklers under separate permit.Details
addition of a roof deck(less than 500 s.f.) and stair penthouse. relocate 3rd flr units front door, upgrade hanrail and guards. sprinklers under separate permit. | $125,000 | |
| Nov 18, 2019 | Completed final sign-off Jan 2021 | 108 11th Av | Urban Builder General Contracting Inc | rev pa# 201902072362; new condenser unit and update to title 24Details
rev pa# 201902072362; new condenser unit and update to title 24 | |
| Jun 12, 2019 | Completed final sign-off Nov 2019 | 595 Pacific Av | One Stop Shop Construction | 3rd fl: interior t.i. sf office: installation of new cabinetry, new bearing partitions, break room, new floor & new ceiling.Details
3rd fl: interior t.i. sf office: installation of new cabinetry, new bearing partitions, break room, new floor & new ceiling. | $300,000 |
| Jun 10, 2019 | Completed final sign-off Sep 2021 | 1365 04th St | Yerba Buena Builders Inc | ti - interior only install of new cabinetry, non-bearing walls, partitions, break room, some new floors, some ceiling, mech, electrical & fire protection/srpinkler work deferred and under separate permitDetails
ti - interior only install of new cabinetry, non-bearing walls, partitions, break room, some new floors, some ceiling, mech, electrical & fire protection/srpinkler work deferred and under separate permit | $75,000 |
| May 30, 2019 | Completed final sign-off Aug 2020 | 595 Pacific Av | M-Projects | installation of new cabinetry, non-bearing partitions; interior window partitions, break room, new flooring & new ceiling @ 5th floor. ti @ 5th fl - mep deferredDetails
installation of new cabinetry, non-bearing partitions; interior window partitions, break room, new flooring & new ceiling @ 5th floor. ti @ 5th fl - mep deferred | $300,000 |
| Apr 25, 2019 | Never finaled issued Apr 2019, no final | 2121 Webster St | Black Mountain Development | 5/f - unit #501 - remove non-structural walls as noted and reconfigure. remove portion of master bath, cap utility, use area as additional closet space. construct new walls, install new plumbing, new cabinetry and appliances, paint, install cardio/video systemDetails
5/f - unit #501 - remove non-structural walls as noted and reconfigure. remove portion of master bath, cap utility, use area as additional closet space. construct new walls, install new plumbing, new cabinetry and appliances, paint, install cardio/video system | $500,000 |
| Apr 19, 2019 | Completed final sign-off Oct 2020 | 2375 Bay St | Fontana Construction, Inc. | interior work only - remodel kitchen, bathrooms and closets. provide (n) outlets and lights in those areasDetails
interior work only - remodel kitchen, bathrooms and closets. provide (n) outlets and lights in those areas | $200,000 |
| Feb 7, 2019 | Completed final sign-off Jan 2021 | 108 11th Av | Urban Builder General Contracting Inc | renovation includes repairs to front facade & stairs, 3rd fl window change, rear yard addition interior renovation & landscape improvements. kitchen & bath remodel. addition of bathroom.Details
renovation includes repairs to front facade & stairs, 3rd fl window change, rear yard addition interior renovation & landscape improvements. kitchen & bath remodel. addition of bathroom. | $350,000 |
| Oct 18, 2018 | Completed final sign-off May 2022 | 301 Main St | Black Mountain Development | renovation of apt 37b - demo of non-bearing walls & drop ceiling; construct new walls & ceiling, install new finishes and plumbing fixtures to replace existing. mep and fire sprinkler to be under separate permitDetails
renovation of apt 37b - demo of non-bearing walls & drop ceiling; construct new walls & ceiling, install new finishes and plumbing fixtures to replace existing. mep and fire sprinkler to be under separate permit | $1,000,000 |
| Sep 13, 2018 | Completed final sign-off Oct 2021 | 777 06th Av | Sincere Construction Company Inc | (n) accessory dwelling unit per ord# 162-16 in previously unfinished ground flr. change from u occupancy to r for adu. mechanical & fire suppresssion under separate permit. soft story filed under pa# 2017-0905-6829.Details
(n) accessory dwelling unit per ord# 162-16 in previously unfinished ground flr. change from u occupancy to r for adu. mechanical & fire suppresssion under separate permit. soft story filed under pa# 2017-0905-6829. | $125,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | Black Mountain Development | construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph7.)Details
construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph7.) | $840,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | Black Mountain Development | construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph1.)Details
construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph1.) | $840,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | Black Mountain Development | build out of (2) unfinished condo units ph1 & ph7 including: demo existing wall. new (1) hour separation wall w/ communicating door.Details
build out of (2) unfinished condo units ph1 & ph7 including: demo existing wall. new (1) hour separation wall w/ communicating door. | $20,000 |
| Aug 7, 2018 | Completed final sign-off Oct 2018 | 595 Pacific Av | removal of non bearing partitions, ceiling tiles, liighting and switches, eztension of non-bearing walls to underside of structure, new lighting & switches, and minor patch work. mech/fire protection under sep permit. all work in suite 100Details
removal of non bearing partitions, ceiling tiles, liighting and switches, eztension of non-bearing walls to underside of structure, new lighting & switches, and minor patch work. mech/fire protection under sep permit. all work in suite 100 | $25,000 | |
| Jun 21, 2018 | Completed final sign-off Mar 2024 | 595 Pacific Av | Trust Construction Company Inc | lobby area on ground floor. demo of non-structural walls, floor finishes. installation of (n) window systems, installation of stone panels, (n) flooringDetails
lobby area on ground floor. demo of non-structural walls, floor finishes. installation of (n) window systems, installation of stone panels, (n) flooring | $110,000 |
| Apr 11, 2018 | Completed final sign-off Jun 2018 | 595 Pacific Av | M-Projects | 4th floor: revision to app#201711103710 for sf health department.Details
4th floor: revision to app#201711103710 for sf health department. | |
| Mar 22, 2018 | Completed final sign-off Jun 2019 | 4355 Geary Bl | Yerba Buena Builders Inc | ground floor: t.i. of 3035 sq ft office. scope of work to include the following: remove (e) ceiling, new non bearing partitions, new finishes including casework ada restroom upgrades. mech, elec, & sprinklers system deferred under separate permit.Details
ground floor: t.i. of 3035 sq ft office. scope of work to include the following: remove (e) ceiling, new non bearing partitions, new finishes including casework ada restroom upgrades. mech, elec, & sprinklers system deferred under separate permit. | $250,000 |
| Mar 14, 2018 | Never finaled issued Mar 2018, no final | 2501 Harrison St | Stonebridge Construction Inc | remodel of kitchen - new cabinetry and fixtures, new lightning in unit #16.Details
remodel of kitchen - new cabinetry and fixtures, new lightning in unit #16. | $25,000 |
| Mar 5, 2018 | Never finaled issued Mar 2018, no final | 4355 Geary Bl | Yerba Buena Builders Inc | remove non bearing partitions select (e) cabinetry, selected doors, store front lighting, flooring/finishes, suspended ceiling and (e) plm fixtures/cap utilities per ab-017. ti under sep permit inc - mech/ele/fire protectionDetails
remove non bearing partitions select (e) cabinetry, selected doors, store front lighting, flooring/finishes, suspended ceiling and (e) plm fixtures/cap utilities per ab-017. ti under sep permit inc - mech/ele/fire protection | $12,500 |
| Dec 6, 2017 | Expired or cancelled cancelled Jan 2026 | 595 Pacific Av | remodel of two restrooms on 3rd floor.Details
remodel of two restrooms on 3rd floor. | $60,000 | |
| Dec 6, 2017 | Completed final sign-off Sep 2018 | 595 Pacific Av | 2nd floors - remodel of two restrooms for ada compliant and tileDetails
2nd floors - remodel of two restrooms for ada compliant and tile | $20,000 | |
| Nov 10, 2017 | Completed final sign-off Jun 2018 | 595 Pacific Av | M-Projects | 4th fl: ti of office - installation of new cabinets, non-bearing partition walls, remodel restrooms, breakrooms. mep under seperate permit. demo under permit #201710201791. fully sprinklered building.Details
4th fl: ti of office - installation of new cabinets, non-bearing partition walls, remodel restrooms, breakrooms. mep under seperate permit. demo under permit #201710201791. fully sprinklered building. | $350,000 |
| Oct 20, 2017 | Completed final sign-off Nov 2017 | 595 Pacific Av | M-Projects | interio demo only. remove all non bearing partitions, e cabinetry, remove and salavage 1 closet door. remove all e restroom partitions, sinks, faucets, countertop. remove and salvage all restroom accessories. ti under sep permit incl ele,mech,fireDetails
interio demo only. remove all non bearing partitions, e cabinetry, remove and salavage 1 closet door. remove all e restroom partitions, sinks, faucets, countertop. remove and salvage all restroom accessories. ti under sep permit incl ele,mech,fire | $5,000 |
| Sep 15, 2017 | Completed final sign-off May 2018 | 35 Clement St | barrier removal. upgrade existing bath to ada chp 11 b standardsDetails
barrier removal. upgrade existing bath to ada chp 11 b standards | $15,000 | |
| Aug 28, 2017 | Completed final sign-off Nov 2017 | 595 Pacific Av | One Stop Shop Construction | suite 240tenant improvementof 3538 office. remove & replace (e) ceiling tile throughout the office, (n) non-bearing partitions, (n) doors, & some lighting upgrades.Details
suite 240tenant improvementof 3538 office. remove & replace (e) ceiling tile throughout the office, (n) non-bearing partitions, (n) doors, & some lighting upgrades. | $27,500 |
| Aug 22, 2017 | Completed final sign-off Dec 2018 | 146 05th Av | 1st fl: bathroom remodel reconfigure laundry/storage area (n) service sink in garage.Details
1st fl: bathroom remodel reconfigure laundry/storage area (n) service sink in garage. | $35,000 | |
| Aug 11, 2017 | Completed final sign-off Jul 2020 | 2106 22nd St | Alef Construction Corp | horizontal addition of a bedroom & bathroom. renovate (e) kitchen & bathroom. new outdoor patio. replace (e) furnace.Details
horizontal addition of a bedroom & bathroom. renovate (e) kitchen & bathroom. new outdoor patio. replace (e) furnace. | $250,000 |
| Aug 11, 2017 | Expired or cancelled withdrawn Apr 2018 | 4338 26th St | horizontal addition of master bedroom & master bathroom on 2nd floor. a great room on the 1st floor & a family room on basement. renovate (e) powder room & guest bathroom. new deck & patio.Details
horizontal addition of master bedroom & master bathroom on 2nd floor. a great room on the 1st floor & a family room on basement. renovate (e) powder room & guest bathroom. new deck & patio. | $600,000 | |
| Apr 25, 2017 | Completed final sign-off Jan 2018 | 1182 Market St | Angotti & Reilly Inc. | suite 425: t.i. for new cabinet, replace extg sink and water heater at breakspace, new non bearing partitions, new doors, ada upgrades at entry and restrooms and extend extg ducts to new rooms,reswitch extg lighting.Details
suite 425: t.i. for new cabinet, replace extg sink and water heater at breakspace, new non bearing partitions, new doors, ada upgrades at entry and restrooms and extend extg ducts to new rooms,reswitch extg lighting. | $165,382 |
| Apr 10, 2017 | Completed final sign-off Jan 2018 | 595 Pacific Av | One Stop Shop Construction | convert storage to office and unisex restroom, remodel 2 restrooms on 1st floor. no exterior work. two existing bathrooms to be upgraded to fully comply w/ adaDetails
convert storage to office and unisex restroom, remodel 2 restrooms on 1st floor. no exterior work. two existing bathrooms to be upgraded to fully comply w/ ada | $85,000 |
| Feb 13, 2017 | Expired or cancelled withdrawn Jul 2017 | 4326 Cesar Chavez St | new roof/canopy extension to rear of houseDetails
new roof/canopy extension to rear of house | $75,000 | |
| Jan 19, 2017 | Completed final sign-off Jan 2018 | 535 15th Av | Urban Builder General Contracting Inc | rev. to approved pa#201606039075. scope includes changes on 3/f reconfiguration,window changes on n/s. switch deck railing from glass to cable, hvac change from furnace to radiant heating.Details
rev. to approved pa#201606039075. scope includes changes on 3/f reconfiguration,window changes on n/s. switch deck railing from glass to cable, hvac change from furnace to radiant heating. | |
| Jan 6, 2017 | Expired or cancelled cancelled Sep 2019 | 544 Clayton St | to comply with nov 201637301 - reverting non-permitted attic of occupancy back to last permitted use as an attic. restore original configuration of room on lower floor. install new tube skylights at roofDetails
to comply with nov 201637301 - reverting non-permitted attic of occupancy back to last permitted use as an attic. restore original configuration of room on lower floor. install new tube skylights at roof | $70,000 | |
| Dec 14, 2016 | Completed final sign-off Feb 2017 | 595 Pacific Av | One Stop Shop Construction | unit #120, ti: remove lay-in ceiling in open office space & extend (e)walls at perimeter of open office to underside of structure above,replace lighting with high efficacy fixtures,provide new power door opener & actuation bars.Details
unit #120, ti: remove lay-in ceiling in open office space & extend (e)walls at perimeter of open office to underside of structure above,replace lighting with high efficacy fixtures,provide new power door opener & actuation bars. | $30,000 |
| Oct 25, 2016 | Completed final sign-off Feb 2017 | 240 Liberty St | unit b - kitchen & bathroom remodel, add gas line to kitchen, add lighting at kitchen and living room. add vent at kitchen.Details
unit b - kitchen & bathroom remodel, add gas line to kitchen, add lighting at kitchen and living room. add vent at kitchen. | $60,000 | |
| Aug 11, 2016 | Completed final sign-off Mar 2017 | 1000 Mason St | Fontana Construction, Inc. | #503- interior remodel, kitchen, master bath, powder room and closet, new electrical outlets & lighting in remodel area. n/a ordinance #155-13Details
#503- interior remodel, kitchen, master bath, powder room and closet, new electrical outlets & lighting in remodel area. n/a ordinance #155-13 | $100,000 |
| Mar 31, 2016 | Completed final sign-off Jun 2017 | 369 Oak St | Seamus R Cudden | infill (e) overhanging second floor for horizontal expansion into rear yard on first floor. reconfigure (e) rear deck reconfigure access to deck for upper unit.Details
infill (e) overhanging second floor for horizontal expansion into rear yard on first floor. reconfigure (e) rear deck reconfigure access to deck for upper unit. | $125,000 |
| Mar 22, 2016 | Completed final sign-off Jun 2017 | 369 Oak St | remodel interior adding an additional full master bathroom, (n) lighting and electrical and (n) heating. new insulation in exterior walls, replace in kind wood windows. kitchen remodel.Details
remodel interior adding an additional full master bathroom, (n) lighting and electrical and (n) heating. new insulation in exterior walls, replace in kind wood windows. kitchen remodel. | $135,000 | |
| Jan 29, 2016 | Completed final sign-off Mar 2016 | 595 Pacific Av | One Stop Shop Construction | #115: demolish existing non bearing partitions to connect storage room to #115,remove plumbing at sink and at plumbing prep. & cap utilities as necessary in vacant tenant space,no new construction,demo per sfbc ab-017. full accessibility will be submitted under future t.i. permit when space occupy.Details
#115: demolish existing non bearing partitions to connect storage room to #115,remove plumbing at sink and at plumbing prep. & cap utilities as necessary in vacant tenant space,no new construction,demo per sfbc ab-017. full accessibility will be submitted under future t.i. permit when space occupy. | $2,000 |
| Jan 29, 2016 | Never finaled filed Jan 2016, never issued | 371 Oak St | relocate door to rear yard.Details
relocate door to rear yard. | $15,000 | |
| Jan 29, 2016 | Never finaled filed Jan 2016, never issued | 369 Oak St | infill (e) overhanging 2nd floor (371 oak street) for horizontal expansion into rear yard on 1st floor (369 oak street). remodel interior of 369 oak street. adding an additional full master bathroom. kitchen & bath remodel. new lighting, electrical & hvac. reconfig (e) rear deck.Details
infill (e) overhanging 2nd floor (371 oak street) for horizontal expansion into rear yard on 1st floor (369 oak street). remodel interior of 369 oak street. adding an additional full master bathroom. kitchen & bath remodel. new lighting, electrical & hvac. reconfig (e) rear deck. | $210,000 | |
| Dec 18, 2015 | Completed final sign-off May 2016 | 1 Beach St | Rockaway Construction Inc. | suite 300 improvement to existing interior only, minor demolitoin of non-load bearing partitions, doors, frames, & hardward & construction of non load bearing partitoins, new doors, frames glazing & select finishes. n/a maher ordinanceDetails
suite 300 improvement to existing interior only, minor demolitoin of non-load bearing partitions, doors, frames, & hardward & construction of non load bearing partitoins, new doors, frames glazing & select finishes. n/a maher ordinance | $50,000 |
| Nov 24, 2015 | Completed final sign-off May 2018 | 832 Fell St | Daoust Design And Construction | seismic upgrade. replace siding at walls to receive plywood in kind, add 5/8" gyp bd to walls and ceiling of garage, add 3 skylights, add trough drain at west wall, pint and flooring. all work in rear garrage houseDetails
seismic upgrade. replace siding at walls to receive plywood in kind, add 5/8" gyp bd to walls and ceiling of garage, add 3 skylights, add trough drain at west wall, pint and flooring. all work in rear garrage house | $60,000 |
| Jul 14, 2014 | Completed final sign-off Dec 2014 | 170 Columbus Av | One Stop Shop Construction | #280- demolition of non-bearing partitions at private offices in suite 280 per ab-017Details
#280- demolition of non-bearing partitions at private offices in suite 280 per ab-017 | $5,000 |
| Dec 9, 2013 | Completed final sign-off Jun 2014 | 150 Columbus Av | One Stop Shop Construction | t.i. at lower level - remodel existing restrooms, add breakroom including cabinets and sink. new walls to create 2 small rooms. add glas wall with 2 doors at now loungeDetails
t.i. at lower level - remodel existing restrooms, add breakroom including cabinets and sink. new walls to create 2 small rooms. add glas wall with 2 doors at now lounge | $125,000 |
| Dec 9, 2013 | Completed final sign-off Dec 2014 | 2923 Harrison St | K And D Construction Inc | revision to pa#2012-0328-7050. keep (e) concrete slabs & foundations. eliminate stairs in previous permit. remove some lighting -d1,d2,d3. eliminate cove in kitchen/living room. eliminate fireplace.Details
revision to pa#2012-0328-7050. keep (e) concrete slabs & foundations. eliminate stairs in previous permit. remove some lighting -d1,d2,d3. eliminate cove in kitchen/living room. eliminate fireplace. | |
| Aug 8, 2013 | Completed final sign-off Sep 2013 | 170 Columbus Av | Bbc Construction Inc. | 4th floor; t.i consisting of removing partitions, 3 new partitions, restroom ada upgrades, new cabinets, new finishes. reswitch (e) lighting, new lighting to replace (e) in 3 offices. new electrical outletsDetails
4th floor; t.i consisting of removing partitions, 3 new partitions, restroom ada upgrades, new cabinets, new finishes. reswitch (e) lighting, new lighting to replace (e) in 3 offices. new electrical outlets | $134,074 |
| Feb 12, 2013 | Completed final sign-off Apr 2013 | 690 05th St | Oak Park Construction | revision to pa# 2012-1226-6870-hardship request, slope of (e) parking is 2.75%. exceeds 2%Details
revision to pa# 2012-1226-6870-hardship request, slope of (e) parking is 2.75%. exceeds 2% | |
| Dec 26, 2012 | Completed final sign-off Apr 2013 | 690 05th St | Oak Park Construction | new reception area, break room and new partition walls to create conference room on 1st floor. accessibility upgrades to parking area, path of travel from the parking area and accessible restrooms, new snack bar on 2nd floor, new floor finishes throughout.Details
new reception area, break room and new partition walls to create conference room on 1st floor. accessibility upgrades to parking area, path of travel from the parking area and accessible restrooms, new snack bar on 2nd floor, new floor finishes throughout. | $150,000 |
| Nov 30, 2012 | Completed final sign-off Jan 2013 | 170 Columbus Av | Bbc Construction Inc. | #110 - tenant improvement including new non-rated partitions, accessbiility upgrades, new door, relocate lights, add new cabient with sink.Details
#110 - tenant improvement including new non-rated partitions, accessbiility upgrades, new door, relocate lights, add new cabient with sink. | $20,000 |
| Jan 12, 2012 | Completed final sign-off Oct 2012 | 371 11th St | A/C Construction | new openings between 2 formely separate bldgs (now 1 building with lot line adjustment) new restrooms, handrails and bar area. all m.e.p. under separate permit.Details
new openings between 2 formely separate bldgs (now 1 building with lot line adjustment) new restrooms, handrails and bar area. all m.e.p. under separate permit. | $45,329 |
| Aug 23, 2011 | Completed final sign-off Sep 2011 | 170 Columbus Av | Bbc Construction Inc. | office ti on 3rd floor, ste 310. new walls, remove 2 data and 2 duplex outlets. new data and duplex outletsDetails
office ti on 3rd floor, ste 310. new walls, remove 2 data and 2 duplex outlets. new data and duplex outlets | $5,000 |
| Dec 29, 2010 | Completed final sign-off Jun 2011 | 217 Upper Tr | excavate at gr floor and convert into laundry/exercise room, walk in closet/master bath. work to include new concrete slab, lighting, new fixtures and finishes. demolish e bath and fixtures to be replaced in master bath. remove 2 furnaces and replace with single furnace. add new on demand hot waterDetails
excavate at gr floor and convert into laundry/exercise room, walk in closet/master bath. work to include new concrete slab, lighting, new fixtures and finishes. demolish e bath and fixtures to be replaced in master bath. remove 2 furnaces and replace with single furnace. add new on demand hot water | $80,000 | |
| Oct 20, 2010 | Completed final sign-off Jan 2011 | 217 Upper Tr | bathroom remodel.wall change. remove e plumbing fixtures, finishes, and lighting. new finishes, cabinetry, lighting, plumbing fixtures.replacing extg in kind. relocate non-bearing wall.Details
bathroom remodel.wall change. remove e plumbing fixtures, finishes, and lighting. new finishes, cabinetry, lighting, plumbing fixtures.replacing extg in kind. relocate non-bearing wall. | $20,000 | |
| Jul 12, 2010 | Never finaled issued Jul 2010, no final | 311 Steiner St | 2nd fl: replace e cabinet in kitchen,add 2 new dedicated elec outlets. bath: remove e plumbing fixtures, finishes,ltg, replace. 1st fl: remodel bath, add new shower head and finishes. garage: enlarge door opening, replace driveway and flat work in setback. voluntary structural in garage wallDetails
2nd fl: replace e cabinet in kitchen,add 2 new dedicated elec outlets. bath: remove e plumbing fixtures, finishes,ltg, replace. 1st fl: remodel bath, add new shower head and finishes. garage: enlarge door opening, replace driveway and flat work in setback. voluntary structural in garage wall | $75,000 | |
| Apr 22, 2010 | Completed final sign-off Jun 2010 | 220 Bush St | add fixed cabinets, upgrade e door by adjusting closer and relocating push and pulls on door to meet accessibility. no exterior work.Details
add fixed cabinets, upgrade e door by adjusting closer and relocating push and pulls on door to meet accessibility. no exterior work. | $3,000 | |
| Dec 30, 2008 | Completed final sign-off Oct 2009 | 450 Bryant St | D.P. Stearns | t.i.-constr. of int. partition walls for (n) seminar rms., music rms., sound studio & off. space. improv. to (e) restrms. & constr. of (n) restrm. @ the 2/f, accessibility upgrades including addition of lift bet. 1 & 2 levels. removal/replacement of rear exit stairs. lighting/mech/plumbing upgradeDetails
t.i.-constr. of int. partition walls for (n) seminar rms., music rms., sound studio & off. space. improv. to (e) restrms. & constr. of (n) restrm. @ the 2/f, accessibility upgrades including addition of lift bet. 1 & 2 levels. removal/replacement of rear exit stairs. lighting/mech/plumbing upgrade | $740,000 |
| Dec 7, 2007 | Completed final sign-off Jul 2009 | 546 12th Av | rear yard addition on basement, first & second floors. remodel kitchen, add bathroom on 2nd floor, relocate plbg @ basement level, remove portion of wall at existing kitchen, replace existing windows, add new elec @ remodeled spaces.Details
rear yard addition on basement, first & second floors. remodel kitchen, add bathroom on 2nd floor, relocate plbg @ basement level, remove portion of wall at existing kitchen, replace existing windows, add new elec @ remodeled spaces. | $150,000 | |
| Oct 2, 2007 | Expired or cancelled expired May 2011 | 4332 19th St | replace brick stairs in kind,new pull down ladder for atticDetails
replace brick stairs in kind,new pull down ladder for attic | $5,000 | |
| Jan 23, 2007 | Completed final sign-off Oct 2007 | 49 Richland Av | code upgrade for condominium conversion, to correct with 3r report #3r-4563.Details
code upgrade for condominium conversion, to correct with 3r report #3r-4563. | $8,000 | |
| Dec 7, 2006 | Completed final sign-off Jul 2007 | 33 Alta St | Fontana Construction, Inc. | addition to existing remodel permit,200607086911.new work:remove liv rm 1st fl,gyp bd ceiling and gypsum bd at 2 walls 2nd floor,rec room walls.new light/speakers @ lv rm,new gyp bd.lights,outlets,rec room, extend seismic upgrade to 2nd fl walls rec room, repair dryrot and efficient framing as nec,Details
addition to existing remodel permit,200607086911.new work:remove liv rm 1st fl,gyp bd ceiling and gypsum bd at 2 walls 2nd floor,rec room walls.new light/speakers @ lv rm,new gyp bd.lights,outlets,rec room, extend seismic upgrade to 2nd fl walls rec room, repair dryrot and efficient framing as nec, | $75,000 |
| Jul 18, 2006 | Completed final sign-off Jul 2007 | 33 Alta St | Fontana Construction, Inc. | kitchen remodel, remove non bearing wall, (e) gyp.bd & provide new cabinetry, electrical, lighting & plumbing fixtures. provide voluntary seismic upgrade at 1/f walls, improve existing footings.Details
kitchen remodel, remove non bearing wall, (e) gyp.bd & provide new cabinetry, electrical, lighting & plumbing fixtures. provide voluntary seismic upgrade at 1/f walls, improve existing footings. | $50,000 |
| Jul 18, 2006 | Completed final sign-off Aug 2007 | 3939 Washington St | Fontana Construction, Inc. | remodel 2 bathroomsa, remove finishes, provide new finishes, lighting & electrical & new plumbing fixtures,one @1/f & one @3/f.remove sink in powder room,add countertop & vessel sink @2/f.remove finishes (tile)in master bath & replace,remove sonces,replace with new sconces @3/fDetails
remodel 2 bathroomsa, remove finishes, provide new finishes, lighting & electrical & new plumbing fixtures,one @1/f & one @3/f.remove sink in powder room,add countertop & vessel sink @2/f.remove finishes (tile)in master bath & replace,remove sonces,replace with new sconces @3/f | $50,000 |
| May 15, 2006 | Completed final sign-off Jul 2007 | 33 Alta St | Fontana Construction, Inc. | replace rotten rear wall (new rated) w/1 hr rated wall. remove & replace electrical outlets from wall, remove (e) window & replace with 3/4 hr rated window. remove cabinets & cap plumbing in kitchen. remove & replace asphaltt shingle roofing & replace built up roof. remove & replace (e)roof deck.Details
replace rotten rear wall (new rated) w/1 hr rated wall. remove & replace electrical outlets from wall, remove (e) window & replace with 3/4 hr rated window. remove cabinets & cap plumbing in kitchen. remove & replace asphaltt shingle roofing & replace built up roof. remove & replace (e)roof deck. | $12,000 |