- Mar 2017 to May 2026
17 permits since 2000 (engineer on 16 permits, architect on 1 permit): 11 completed, 5 in progress, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 13, 2026 | In progress issued Sep 2026 | 147 Natoma St | replacing and modifying the sidewalk, as well as modifying the sub-sidewalk basement to accommodate the new sidewalk gradesDetails
replacing and modifying the sidewalk, as well as modifying the sub-sidewalk basement to accommodate the new sidewalk grades | $15,000 | |
| Feb 9, 2026 | In progress issued Sep 2026 | 149 New Montgomery St | Bauman Landscape & Construction Inc. | replacing and modifying the sidewalk and abondoining an (e) subsidewalk basement. ref streetscape permit # 2025 exc- 024-3sDetails
replacing and modifying the sidewalk and abondoining an (e) subsidewalk basement. ref streetscape permit # 2025 exc- 024-3s | $110,000 |
| Dec 17, 2025 | In progress filed Dec 2025, not yet issued | 50 Stow Lake Dr | replacement of existing boatshed with new boatshed on driven wood piles w/wood roof & sidingDetails
replacement of existing boatshed with new boatshed on driven wood piles w/wood roof & siding | $1,300,000 | |
| Dec 2, 2025 | In progress issued Jan 2026 | 124 02nd St | Bauman Landscape & Construction Inc. | replacing and modifying the sidewalk topping slab and the sub-sidewalk basement to accommodete a new street light foundationDetails
replacing and modifying the sidewalk topping slab and the sub-sidewalk basement to accommodete a new street light foundation | $54,000 |
| Sep 21, 2022 | In progress issued Oct 2023 | 982 Market St | Esquivel Grading & Paving, Inc. | replace sub-sidewalk basement roof slab affected by traffic signal poles and curb rampsDetails
replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps | $300,000 |
| Apr 3, 2018 | Completed final sign-off May 2021 | 101 Natoma St | Phoenix Electric Co. | new traffic signal pole foundation in subsidewalk basement.Details
new traffic signal pole foundation in subsidewalk basement. | $10,000 |
| Apr 3, 2018 | Completed final sign-off May 2021 | 601 Mission St | Phoenix Electric Co. | new traffic signal pole foundation in subsidewalk basement.Details
new traffic signal pole foundation in subsidewalk basement. | $60,000 |
| Apr 3, 2018 | Completed final sign-off May 2021 | 28 02nd St | Phoenix Electric Co. | pedestrian light pole support at sub sidewalk basement. n/a for maherDetails
pedestrian light pole support at sub sidewalk basement. n/a for maher | $10,000 |
| Apr 3, 2018 | Completed final sign-off May 2021 | 85 02nd St | Phoenix Electric Co. | new traffic signal pole foundation in subsidewalk basement. n/a for maherDetails
new traffic signal pole foundation in subsidewalk basement. n/a for maher | $60,000 |
| Mar 14, 2018 | Completed final sign-off May 2021 | 171 02nd St | Phoenix Electric Co. | 1-a traffice pole support at subsidewalk basementDetails
1-a traffice pole support at subsidewalk basement | $10,000 |
| Mar 14, 2018 | Completed final sign-off May 2021 | 121 02nd St | Phoenix Electric Co. | 1-a traffice pole support at subsidewalk basementDetails
1-a traffice pole support at subsidewalk basement | $10,000 |
| Jan 11, 2018 | Completed final sign-off May 2021 | 141 02nd St | Phoenix Electric Co. | new pedestrian light pole support at sub-sidewalk basement. maher naDetails
new pedestrian light pole support at sub-sidewalk basement. maher na | $10,000 |
| Jan 11, 2018 | Completed final sign-off May 2021 | 181 02nd St | Phoenix Electric Co. | new pedestrian light pole support at sub-sidewalk basement. maher naDetails
new pedestrian light pole support at sub-sidewalk basement. maher na | $10,000 |
| Jan 11, 2018 | Completed final sign-off May 2021 | 85 02nd St | Phoenix Electric Co. | new pedestrian light pole support at sub-sidewalk basement. maher naDetails
new pedestrian light pole support at sub-sidewalk basement. maher na | $10,000 |
| Jan 11, 2018 | Completed final sign-off May 2021 | 601 Mission St | Phoenix Electric Co. | new pedestrian light pole support at sub-sidewalk basement. maher naDetails
new pedestrian light pole support at sub-sidewalk basement. maher na | $10,000 |
| Sep 29, 2017 | Completed final sign-off May 2021 | 301 Brannan St | Phoenix Electric Co. | subsidewalk basement roof repair to install traffic signal pole foundation and installation of new pedestrian light pole. maher naDetails
subsidewalk basement roof repair to install traffic signal pole foundation and installation of new pedestrian light pole. maher na | $60,000 |
| Mar 28, 2017 | Never finaled issued Apr 2017, no final | 50 Bowling Green Dr | repair concrete abutement wall @ alvord lake tunnel in golden gate park. (wall location close to sharon art studio). n/a maher ordinanceDetails
repair concrete abutement wall @ alvord lake tunnel in golden gate park. (wall location close to sharon art studio). n/a maher ordinance | $200,000 |