Esquivel Grading & Paving, Inc.
- Based in
- San Francisco
- On San Francisco permits
- Apr 2021 to Sep 2023
- Last 24 months
- 0 permits filed
21 permits since 2000: 4 in progress, 16 never finaled, 1 expired or cancelled.
Of the 16 never-finaled permits, 16 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 28, 2023 | In progress issued Apr 2024 | 1003 Market St | reconstructing a portion of basement under sidewalk, will include mew reinforced concrete slab and new steel beamsDetails
reconstructing a portion of basement under sidewalk, will include mew reinforced concrete slab and new steel beams | $180,000 |
| Sep 5, 2023 | Never finaled issued Sep 2023, no final | 1 Taylor St | demo & replacement of topping sidewalk, partial demo of basement roof slab & reconstruction w/traffic signal foundation concrete belowDetails
demo & replacement of topping sidewalk, partial demo of basement roof slab & reconstruction w/traffic signal foundation concrete below | $20,000 |
| Sep 5, 2023 | Expired or cancelled cancelled Jul 2026 | 1182 Market St | concrete topping sidewalk replacement & removal of (e) traffic signal poleDetails
concrete topping sidewalk replacement & removal of (e) traffic signal pole | $20,000 |
| Aug 30, 2023 | In progress issued Oct 2023 | 201 Eddy St | sidewalk replacement and waterproofing over sub-sidewalk basement roof slab. pole support for new street light and traffic signal.Details
sidewalk replacement and waterproofing over sub-sidewalk basement roof slab. pole support for new street light and traffic signal. | $120,407 |
| Aug 22, 2023 | In progress issued Oct 2023 | 216 Eddy St | sidewalk replacement and waterproofing over sub-sidewalk basement roof slab.Details
sidewalk replacement and waterproofing over sub-sidewalk basement roof slab. | $105,164 |
| Jun 26, 2023 | Never finaled issued Aug 2023, no final | 302 Ellis St | sidewalk replacement and waterproofing over sub-sidewalk basement adjustment of elevator frame to new sidewalk upgradeDetails
sidewalk replacement and waterproofing over sub-sidewalk basement adjustment of elevator frame to new sidewalk upgrade | $57,427 |
| Jun 6, 2023 | Never finaled issued Aug 2023, no final | 225 Taylor St | alteration of subsidewalk basement roof slab to install new sidewalkDetails
alteration of subsidewalk basement roof slab to install new sidewalk | $252,598 |
| Apr 18, 2023 | Never finaled issued Aug 2023, no final | 55 Taylor St | alteration of sub-sidewalk basement roof slab to install new sidewalk.Details
alteration of sub-sidewalk basement roof slab to install new sidewalk. | $252,599 |
| Mar 13, 2023 | Never finaled issued Aug 2023, no final | 162 Taylor St | alteration of subsidewalk basement roof slab to install new sidewalkDetails
alteration of subsidewalk basement roof slab to install new sidewalk | $80,903 |
| Mar 9, 2023 | Never finaled issued Jun 2023, no final | 948 Market St | replace sub sidewalk basement roof slab affected by gtraffic signal poles and curb rampsDetails
replace sub sidewalk basement roof slab affected by gtraffic signal poles and curb ramps | $300,000 |
| Feb 23, 2023 | Never finaled issued Apr 2023, no final | 136 Taylor St | alteration of subsidewalk basement roof slab to install new sidewalkDetails
alteration of subsidewalk basement roof slab to install new sidewalk | $88,345 |
| Dec 15, 2022 | Never finaled issued Jun 2023, no final | 2 Turk St | replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps.Details
replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps. | $300,000 |
| Sep 21, 2022 | In progress issued Oct 2023 | 982 Market St | replace sub-sidewalk basement roof slab affected by traffic signal poles and curb rampsDetails
replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps | $300,000 |
| Jun 15, 2022 | Never finaled issued Apr 2023, no final | 111 Taylor St | modification to existing basement roof to accomodate sidewalk modification by sfdpw.Details
modification to existing basement roof to accomodate sidewalk modification by sfdpw. | $20,000 |
| May 18, 2022 | Never finaled issued Apr 2023, no final | 108 Taylor St | modify portion of sub sidewalk basement over sidewalk to accomodate public works improvement projectDetails
modify portion of sub sidewalk basement over sidewalk to accomodate public works improvement project | $150,000 |
| Apr 5, 2021 | Never finaled issued Apr 2022, no final | 995 Market St | alteration of subsidewalk basement roof slab to install new acessible curb ramps and installaion of new light pole foundations inside sub sidewalk basement.Details
alteration of subsidewalk basement roof slab to install new acessible curb ramps and installaion of new light pole foundations inside sub sidewalk basement. | $57,750 |
| Apr 5, 2021 | Never finaled issued Apr 2022, no final | 201 06th St | alteration of subsidewalk basement roof slab to install new accessible curb ramp and installation of new light pole founddation inside basement.Details
alteration of subsidewalk basement roof slab to install new accessible curb ramp and installation of new light pole founddation inside basement. | $123,960 |
| Apr 2, 2021 | Never finaled issued Apr 2022, no final | 35 06th St | alteration of sub sidewalk basement roof slab to install new accessible curb ramps.Details
alteration of sub sidewalk basement roof slab to install new accessible curb ramps. | $34,000 |
| Apr 1, 2021 | Never finaled issued Apr 2022, no final | 20 06th St | alteration of subsidewalk basement roof slab to install new accessible curb ramp.Details
alteration of subsidewalk basement roof slab to install new accessible curb ramp. | $66,000 |
| Apr 1, 2021 | Never finaled issued Apr 2022, no final | 26 06th St | alteration of subsidewalk basement roof slab to install new accessible sidewalk slab to support curb rampDetails
alteration of subsidewalk basement roof slab to install new accessible sidewalk slab to support curb ramp | $20,000 |
| Apr 1, 2021 | Never finaled issued Apr 2022, no final | 139 06th St | alteration of subsidewalk basement roof slab to install new sidewalkDetails
alteration of subsidewalk basement roof slab to install new sidewalk | $100,000 |