94 permits since 2000 (engineer on 71 permits, architect on 17 permits, designer on 6 permits): 74 completed, 5 in progress, 8 never finaled, 7 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 18, 2026 | In progress issued Aug 2026 | 177 Golden Gate Av | Elm Roofing Contractors Inc Dba Element | revision to 202512172006 and 202605141263. like for like ceiling removal and leave it exposed. replace wall, floor, and ceiling finishes for offices 102 - 108.Details
revision to 202512172006 and 202605141263. like for like ceiling removal and leave it exposed. replace wall, floor, and ceiling finishes for offices 102 - 108. | |
| May 14, 2026 | In progress issued May 2026 | 177 Golden Gate Av | Elm Roofing Contractors Inc Dba Element | revision to pa# 202512172006 convert existing 2nd floor restroom into an accessible restroom, extend walls per engineering plansDetails
revision to pa# 202512172006 convert existing 2nd floor restroom into an accessible restroom, extend walls per engineering plans | |
| Nov 10, 2025 | Completed final sign-off Sep 2026 | 250 Ortega St | Bro Builders Renovations | interior kitchen remodel, reconfigure hallway bathroom and rear bedroom bathroom at second floor (top second floor)Details
interior kitchen remodel, reconfigure hallway bathroom and rear bedroom bathroom at second floor (top second floor) | $40,000 |
| May 22, 2024 | Completed final sign-off Jun 2025 | 278 28th Av | Mountain Top Construction Llc | revision to 202211297266. add site drainage at backyard. reconfigure master bath and middle bedroom at 2nd fl. replace furnace with new furnace and heat pump. add laundry room to basementDetails
revision to 202211297266. add site drainage at backyard. reconfigure master bath and middle bedroom at 2nd fl. replace furnace with new furnace and heat pump. add laundry room to basement | $30,000 |
| Apr 30, 2024 | Completed final sign-off Jun 2025 | 278 28th Av | Mountain Top Construction Llc | revision to 202211297266. new footing at garage storage area.Details
revision to 202211297266. new footing at garage storage area. | $50,000 |
| Nov 28, 2023 | In progress filed Nov 2023, not yet issued | 1181 Church St | remove e rear staircase and 2nd level deck. replace with new staircase and deck w eleastomick. deck covering over new structural framing and foundationDetails
remove e rear staircase and 2nd level deck. replace with new staircase and deck w eleastomick. deck covering over new structural framing and foundation | $75,000 | |
| Nov 28, 2023 | In progress filed Nov 2023, not yet issued | 1177 Church St | remove e rear staircase and 2nd level deck. replace with new staircase and deck w eleastomick. deck covering over new structural framing and foundationDetails
remove e rear staircase and 2nd level deck. replace with new staircase and deck w eleastomick. deck covering over new structural framing and foundation | $75,000 | |
| Oct 24, 2023 | Completed final sign-off Nov 2024 | 132 Cortland Av | Edri Construction Inc *See Notes* | revision to pa# 202210124235. add egress window to basement.Details
revision to pa# 202210124235. add egress window to basement. | $9,500 |
| Aug 29, 2023 | Expired or cancelled withdrawn Apr 2024 | 2183 Mission St | interior alteration for a dining area, kitchen area, existing ada compliant restrooms to remain. walk-in ref & freezer, service sink, new plumbing, new lighting, new electrical panel, grease trap. adding 2nd story floor. increase space.Details
interior alteration for a dining area, kitchen area, existing ada compliant restrooms to remain. walk-in ref & freezer, service sink, new plumbing, new lighting, new electrical panel, grease trap. adding 2nd story floor. increase space. | $150,000 | |
| Aug 14, 2023 | Completed final sign-off Jun 2024 | 1459 Oak St | Saint Lazarus General Construction | replace e brick foundation in westside for new concrete foundation (33 linear feet)Details
replace e brick foundation in westside for new concrete foundation (33 linear feet) | $30,000 |
| Jun 15, 2023 | Expired or cancelled cancelled Jan 2026 | 3755 Balboa St | accessible business entrance program per ordinamce 51-16 alter front exterior door swing abe #202001070699Details
accessible business entrance program per ordinamce 51-16 alter front exterior door swing abe #202001070699 | $1,000 | |
| Feb 27, 2023 | Completed final sign-off Apr 2023 | 71 Rondel Pl | as is built final plan, windows sizes, storage room floor plan, maintain original enttry dimensions. revision to pa# 202108206804. to reflect as-built changes in field.Details
as is built final plan, windows sizes, storage room floor plan, maintain original enttry dimensions. revision to pa# 202108206804. to reflect as-built changes in field. | ||
| Dec 29, 2022 | Never finaled filed Dec 2022, never issued | 131 Mallorca Wy | convert (e) first floor rear area into an adu per ord 95-17.Details
convert (e) first floor rear area into an adu per ord 95-17. | $60,000 | |
| Nov 29, 2022 | Completed final sign-off Jun 2025 | 278 28th Av | Mountain Top Construction Llc | build a 3 story rear addition,kitchen interior remodel and master bathroom remodel.Details
build a 3 story rear addition,kitchen interior remodel and master bathroom remodel. | $700,000 |
| Nov 16, 2022 | Completed final sign-off Apr 2023 | 131 Mallorca Wy | My Construction Group Inc | second floor remodel. remodel kitchen on 2nd floor; add one bathroom adjacent to existing kitchen. all work on 2nd floor. change one 2nd floor bedroom to office.Details
second floor remodel. remodel kitchen on 2nd floor; add one bathroom adjacent to existing kitchen. all work on 2nd floor. change one 2nd floor bedroom to office. | $50,000 |
| Nov 10, 2022 | In progress issued Apr 2025 | 1618 Quesada Av | Mission Home Remodeling Inc | one-story rear buiding addition. interior bedroom remodel. deck addition over (e) garage lightwell.Details
one-story rear buiding addition. interior bedroom remodel. deck addition over (e) garage lightwell. | $80,000 |
| Oct 12, 2022 | Completed final sign-off Nov 2024 | 132 Cortland Av | Edri Construction Inc *See Notes* | 2 story interior remodel. kitchen and bath remodel (kitchen & 1 bathroom under pa202207188732). relocate (e) 1/f bathroom. add powder room on 1st fl. relocate 1st fl bedroom.add 1 bathroom to 2/f. amend to pa 202207188732Details
2 story interior remodel. kitchen and bath remodel (kitchen & 1 bathroom under pa202207188732). relocate (e) 1/f bathroom. add powder room on 1st fl. relocate 1st fl bedroom.add 1 bathroom to 2/f. amend to pa 202207188732 | $100,000 |
| Jun 17, 2022 | Completed final sign-off Dec 2023 | 201 Folsom St | Edri Construction Inc *See Notes* | unit #41c: revision to pa# 202112073853. stair layout alteration (interior).Details
unit #41c: revision to pa# 202112073853. stair layout alteration (interior). | |
| Mar 21, 2022 | Never finaled filed Mar 2022, never issued | 714 Niagara Av | construct (2) bedrms, (1) bathrm, laundry/utility area, & stairs to 2nd floor @ basement area. provide (n) exterior exit door to sidewalk & street. replace existing garage door. relocate existing water heater & install (n) furnace & heating system.upgrade elect.upgrade (e)wood deck @ 2nd floor.Details
construct (2) bedrms, (1) bathrm, laundry/utility area, & stairs to 2nd floor @ basement area. provide (n) exterior exit door to sidewalk & street. replace existing garage door. relocate existing water heater & install (n) furnace & heating system.upgrade elect.upgrade (e)wood deck @ 2nd floor. | $185,000 | |
| Dec 7, 2021 | Completed final sign-off Dec 2023 | 201 Folsom St | Edri Construction Inc *See Notes* | rev to pa202106283334: steel staircase redesign.Details
rev to pa202106283334: steel staircase redesign. | |
| Aug 20, 2021 | Completed final sign-off Apr 2023 | 71 Rondel Pl | revision to pa 201904178237. replace 2 water heater tanks into tankless wh. relocate sink. add washer/dryer/fau. plumbing and electrical revision as needed.Details
revision to pa 201904178237. replace 2 water heater tanks into tankless wh. relocate sink. add washer/dryer/fau. plumbing and electrical revision as needed. | ||
| Jul 27, 2021 | Completed final sign-off Oct 2021 | 2901 16th St | 4-Mac Construction | revision to pa 2020-0507-7352 existing sloped entry to remain and add power door operator per information sheet da-04Details
revision to pa 2020-0507-7352 existing sloped entry to remain and add power door operator per information sheet da-04 | $3,200 |
| Jun 28, 2021 | Completed final sign-off Dec 2023 | 201 Folsom St | Edri Construction Inc *See Notes* | penthouse b: existing vacant space for an interior remodel for 4 bedroom sfd with 4.5 baths, kitchen, dining, living, bar area. all existing perimeter enclosures to remain.Details
penthouse b: existing vacant space for an interior remodel for 4 bedroom sfd with 4.5 baths, kitchen, dining, living, bar area. all existing perimeter enclosures to remain. | $550,000 |
| Oct 21, 2020 | Expired or cancelled cancelled Jan 2026 | 4284 24th St | revision to (e) pa 201910235348. new doors at same location and same size to 2/f patio, barn door and closet door. new doors (exterior) are not visible from street.Details
revision to (e) pa 201910235348. new doors at same location and same size to 2/f patio, barn door and closet door. new doors (exterior) are not visible from street. | $6,000 | |
| Oct 23, 2019 | Completed final sign-off Mar 2021 | 4284 24th St | Bay General Contractor | to comply with nov 201972611 replace/repair existing foundation to correct clearance from adjacent propertyDetails
to comply with nov 201972611 replace/repair existing foundation to correct clearance from adjacent property | $10,000 |
| Apr 17, 2019 | Completed final sign-off Apr 2023 | 71 Rondel Pl | excavate to lower basement floor slab to create storage and media/home office. structural upgrade. replace (e) foundation on the front side of the property. add powder room in basement.Details
excavate to lower basement floor slab to create storage and media/home office. structural upgrade. replace (e) foundation on the front side of the property. add powder room in basement. | $100,000 | |
| Aug 27, 2018 | Completed final sign-off May 2021 | 2535 33rd Av | Acme Builders | plan revision as requested by inspector for #201707313327. update foundation condition to match existing in project.Details
plan revision as requested by inspector for #201707313327. update foundation condition to match existing in project. | $15,000 |
| Jan 2, 2018 | Completed final sign-off Nov 2020 | 247 Madrid St | Umadhay Construction & Design | construction of 2 bedroom, 1 study room, 1 bath, bar sink, family room @ 1st floor. circular stair to 2nd floor. remodel toiet & add 1 bath @ 2nd floor, install 5x10 lightwell.Details
construction of 2 bedroom, 1 study room, 1 bath, bar sink, family room @ 1st floor. circular stair to 2nd floor. remodel toiet & add 1 bath @ 2nd floor, install 5x10 lightwell. | $180,000 |
| Oct 12, 2017 | Completed final sign-off Feb 2018 | 770 California St | J T & M Hardwood Flooring Construcing | #206- non-structural interior remodel, relocate (e) kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13Details
#206- non-structural interior remodel, relocate (e) kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13 | $30,000 |
| Oct 12, 2017 | Expired or cancelled cancelled Jan 2026 | 691 Post St | #102- non-structural interior remodel, relocate (e) kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13Details
#102- non-structural interior remodel, relocate (e) kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13 | $30,000 | |
| Aug 25, 2017 | Completed final sign-off Jun 2018 | 972 Bush St | Mendez-Ortiz Contractors | apt 25: interior remodel. remodel existing bath. provide new 1/2 bath. relocate existing kitchen. provide new office.Details
apt 25: interior remodel. remodel existing bath. provide new 1/2 bath. relocate existing kitchen. provide new office. | $40,000 |
| Jul 31, 2017 | Completed final sign-off May 2021 | 2535 33rd Av | interior alteration - remodel (e) 2 bathrooms and kitchen. replace interior staircase, legalize 1st floor bathroom & family roomDetails
interior alteration - remodel (e) 2 bathrooms and kitchen. replace interior staircase, legalize 1st floor bathroom & family room | $52,000 | |
| Jun 9, 2017 | Completed final sign-off Sep 2017 | 729 Jones St | J T & M Hardwood Flooring Construcing | #206: interior remodel - relocate kitchen, remodel (e) bathroom. provide new home office. no structural work maher naDetails
#206: interior remodel - relocate kitchen, remodel (e) bathroom. provide new home office. no structural work maher na | $30,000 |
| Jun 9, 2017 | Completed final sign-off Mar 2018 | 745 Hyde St | Mendez-Ortiz Contractors | #23: interior remodel - relocate kitchen, remodel (e) bathroom. provide new home office. no structural workDetails
#23: interior remodel - relocate kitchen, remodel (e) bathroom. provide new home office. no structural work | $25,000 |
| Feb 9, 2017 | Completed final sign-off Aug 2017 | 5320 Geary Bl | Taico Builder Inc | remove existing bar, replace with new cabinetry, plumbing, lighting, new door; (4) exhaust fans in bathroom.Details
remove existing bar, replace with new cabinetry, plumbing, lighting, new door; (4) exhaust fans in bathroom. | $19,000 |
| Jan 10, 2017 | Completed final sign-off Apr 2017 | 745 Hyde St | Mendez-Ortiz Contractors | 0n 3rd floor - apt #33 -interior remodel: relocate kitchen, remodel exisitng bathroom, provide new home office. n/a maher ordinanceDetails
0n 3rd floor - apt #33 -interior remodel: relocate kitchen, remodel exisitng bathroom, provide new home office. n/a maher ordinance | $35,000 |
| Nov 1, 2016 | Completed final sign-off Feb 2017 | 887 Bush St | Mendez-Ortiz Contractors | non structural interior remodel apt 607. relocarte e kitchen, e living and e bedroom. remodel e bath. egress window not req 6th fl above grade per cbc 1029.1Details
non structural interior remodel apt 607. relocarte e kitchen, e living and e bedroom. remodel e bath. egress window not req 6th fl above grade per cbc 1029.1 | $35,000 |
| Sep 29, 2016 | Completed final sign-off Dec 2016 | 1140 Sutter St | Palmera Construction Co | interior remodel apt 410: non-structural alteration, relocate kitchen. remodel (e) bathroom. provide new bedroom. no egress window required 4th floor above gradeDetails
interior remodel apt 410: non-structural alteration, relocate kitchen. remodel (e) bathroom. provide new bedroom. no egress window required 4th floor above grade | $40,000 |
| Jul 22, 2016 | Completed final sign-off Sep 2016 | 770 California St | Mendez-Ortiz Contractors | #302 interior remodel - relocate kitchen & (e) bath. provide new bedroom maher naDetails
#302 interior remodel - relocate kitchen & (e) bath. provide new bedroom maher na | $30,000 |
| Jul 22, 2016 | Completed final sign-off Nov 2016 | 775 Post St | Sean M O'reilly | #501 interior remodel - relocate kitchen. remodel (e) bath. provide new bedroom and bathroom. maher na add new bathroomDetails
#501 interior remodel - relocate kitchen. remodel (e) bath. provide new bedroom and bathroom. maher na add new bathroom | $50,000 |
| Jul 22, 2016 | Completed final sign-off Nov 2016 | 1808 Pacific Av | Mendez-Ortiz Contractors | apt #503 interior remodel - relocate kitchen & remodel (e) bath. provide new bedroom. add new bathroomDetails
apt #503 interior remodel - relocate kitchen & remodel (e) bath. provide new bedroom. add new bathroom | $50,000 |
| Jun 27, 2016 | Completed final sign-off Oct 2016 | 1106 Bush St | J T & M Hardwood Flooring Construcing | #403 - interior remodel, non-structural alteration, relocate (e) kitchen, remodel existing bathroom, provide new bedroom, total 2 bedrooms. n/a ordinance #155-13Details
#403 - interior remodel, non-structural alteration, relocate (e) kitchen, remodel existing bathroom, provide new bedroom, total 2 bedrooms. n/a ordinance #155-13 | $35,000 |
| Jun 27, 2016 | Never finaled issued Jul 2016, no final | 770 California St | M H M Construction | #209- interior remodel, relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13Details
#209- interior remodel, relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13 | $25,000 |
| Jun 27, 2016 | Completed final sign-off Sep 2016 | 760 Geary St | M H M Construction | #507- interior remodel, remove non-load bearing wall to relocate kitchen, provide new bedroom. n/a ordinance #155-13Details
#507- interior remodel, remove non-load bearing wall to relocate kitchen, provide new bedroom. n/a ordinance #155-13 | $20,000 |
| Jan 27, 2016 | Never finaled issued Feb 2016, no final | 770 California St | M H M Construction | #207- interior remodel, relocate kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13Details
#207- interior remodel, relocate kitchen, remodel (e) bathroom, provide new bedroom. n/a ordinance #155-13 | $30,000 |
| Dec 22, 2015 | Expired or cancelled withdrawn Apr 2016 | 1200 Valencia St | M H M Construction | #6- interior remodel, non structural alteration, relocate kitchen, remodel (e) bathroom, provide new den. n/a ordinance #155-13Details
#6- interior remodel, non structural alteration, relocate kitchen, remodel (e) bathroom, provide new den. n/a ordinance #155-13 | $30,000 |
| Dec 9, 2015 | Completed final sign-off Mar 2016 | 500 Hyde St | M H M Construction | #205-interior remodel #205, remove non-load bearing walls to relocate kitchen, remodel (e) bath, provide new bedroom.Details
#205-interior remodel #205, remove non-load bearing walls to relocate kitchen, remodel (e) bath, provide new bedroom. | $45,000 |
| Dec 9, 2015 | Completed final sign-off Oct 2016 | 1140 Sutter St | Palmera Construction Co | #504-interior remodel #504, non-structural alteration, relocate kitchen, remodel (e) bathroom, provide new bedroom, no egress window required 5/f above grade. n/a ordinance #155-13Details
#504-interior remodel #504, non-structural alteration, relocate kitchen, remodel (e) bathroom, provide new bedroom, no egress window required 5/f above grade. n/a ordinance #155-13 | $45,000 |
| Oct 21, 2015 | Never finaled issued Oct 2015, no final | 795 Geary St | M H M Construction | unit #102: interior remodel: provide 2 new bedrooms, 1 new study, 2 new bathrooms at the basement. remodel (e) kitchen on 1st flr. provide new spiral stairs within the unit. sprinklers under sep permit. maher naDetails
unit #102: interior remodel: provide 2 new bedrooms, 1 new study, 2 new bathrooms at the basement. remodel (e) kitchen on 1st flr. provide new spiral stairs within the unit. sprinklers under sep permit. maher na | $55,000 |
| Oct 14, 2015 | Completed final sign-off Dec 2015 | 254 Divisadero St | M H M Construction | unit #2: interior remodel - relocate existing kitchen, provide new bedroom, remodel (e) bath, replace 1 window in kind at side lightwell, not visible from street.Details
unit #2: interior remodel - relocate existing kitchen, provide new bedroom, remodel (e) bath, replace 1 window in kind at side lightwell, not visible from street. | $30,000 |
| Oct 7, 2015 | Completed final sign-off Mar 2016 | 130 Frederick St | M H M Construction | unit 204: interior remodel, relocate kitchen. provide new bedroom and bathroom. remodel (e) bath. new laundry room framing & foundation work below. completed under pa 2014-0820-4265Details
unit 204: interior remodel, relocate kitchen. provide new bedroom and bathroom. remodel (e) bath. new laundry room framing & foundation work below. completed under pa 2014-0820-4265 | $40,000 |
| Sep 10, 2015 | Completed final sign-off Feb 2016 | 821 Duncan St | Lindquist Custom Construction Inc | replace old concrete foundation on west wall. install proper drainage and new sump pumpDetails
replace old concrete foundation on west wall. install proper drainage and new sump pump | $40,000 |
| Feb 11, 2015 | Never finaled issued Feb 2015, no final | 765 Sutter St | Shelter | apt.#105: interior remodel, relocate existing kitchen and living room, provide new bedroom and den. n/a ordinance #155-13Details
apt.#105: interior remodel, relocate existing kitchen and living room, provide new bedroom and den. n/a ordinance #155-13 | $40,000 |
| Dec 22, 2014 | Completed final sign-off Feb 2015 | 760 Geary St | M H M Construction | #601 - revision to p.a. #2014.1029.0176: revise layout of bedroom and bathroom. n/a maher ordinanceDetails
#601 - revision to p.a. #2014.1029.0176: revise layout of bedroom and bathroom. n/a maher ordinance | |
| Dec 10, 2014 | Completed final sign-off Jun 2015 | 500 Hyde St | M H M Construction | #103- interior remodel: remove non-load bearing walls to relocate kitchen, provide new bedroom, remodel (e) bath.Details
#103- interior remodel: remove non-load bearing walls to relocate kitchen, provide new bedroom, remodel (e) bath. | $30,000 |
| Nov 26, 2014 | Completed final sign-off Feb 2015 | 760 Geary St | M H M Construction | interior remodel #305- relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13Details
interior remodel #305- relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13 | $40,000 |
| Nov 5, 2014 | Completed final sign-off Mar 2015 | 745 Hyde St | M H M Construction | interior remodel apt #1: relocate kitchen, remodel (e) bath, remodel existing bathroom. provide new bedroom; maher n/aDetails
interior remodel apt #1: relocate kitchen, remodel (e) bath, remodel existing bathroom. provide new bedroom; maher n/a | $30,000 |
| Oct 29, 2014 | Completed final sign-off Mar 2015 | 1035 Pine St | M H M Construction | apt #105: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom.Details
apt #105: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom. | $40,000 |
| Oct 29, 2014 | Completed final sign-off May 2015 | 770 California St | M H M Construction | apt #106: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom; maher n/aDetails
apt #106: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom; maher n/a | $30,000 |
| Oct 29, 2014 | Completed final sign-off Feb 2015 | 760 Geary St | M H M Construction | apt #601: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom; maher n/aDetails
apt #601: interior remodel: relocate kitchen, remodel existing bathroom, provide new bedroom; maher n/a | $40,000 |
| Oct 22, 2014 | Completed final sign-off Sep 2015 | 2165 Larkin St | M H M Construction | interior remodel #105: relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13Details
interior remodel #105: relocate kitchen, remodel existing bathroom, provide new bedroom. n/a ordinance #155-13 | $25,000 |
| Oct 22, 2014 | Completed final sign-off Jan 2015 | 1541 Larkin St | Rainbow Choy Hung & Co | interior remodel #2: remodel (e) kitchen, remodel (2) existing bathrooms, replace (e) furnace, replace all windows within unit, none visable from street.Details
interior remodel #2: remodel (e) kitchen, remodel (2) existing bathrooms, replace (e) furnace, replace all windows within unit, none visable from street. | $40,000 |
| Sep 18, 2014 | Completed final sign-off Dec 2014 | 1035 Pine St | M H M Construction | unit #504: interior remodel apt 504-remove non-load bearing walls to relocate kitchen & bath, provide new den, remodel (e) bedroom,Details
unit #504: interior remodel apt 504-remove non-load bearing walls to relocate kitchen & bath, provide new den, remodel (e) bedroom, | $35,000 |
| Aug 6, 2014 | Completed final sign-off Dec 2014 | 600 Stanyan St | M H M Construction | unit #101: revise approved pa 201403191091, provide bath on 2nd floor, relocate new bath on ground floor, revise kitchen layout on ground floor, provide laundry on ground floor; maher n/aDetails
unit #101: revise approved pa 201403191091, provide bath on 2nd floor, relocate new bath on ground floor, revise kitchen layout on ground floor, provide laundry on ground floor; maher n/a | $8,000 |
| Aug 6, 2014 | Completed final sign-off Dec 2014 | 1035 Pine St | M H M Construction | unit #101; interior remodel, remodel (e) kitchen and bedroom, relocate (e) bath, provide new bedroom, office and bath.Details
unit #101; interior remodel, remodel (e) kitchen and bedroom, relocate (e) bath, provide new bedroom, office and bath. | $45,000 |
| Aug 6, 2014 | Never finaled issued Aug 2014, no final | 500 Hyde St | M H M Construction | unit #105: interior remodel, remove non-load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bath.Details
unit #105: interior remodel, remove non-load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bath. | $30,000 |
| Aug 6, 2014 | Completed final sign-off May 2015 | 770 California St | M H M Construction | unit #201: interior remodel, relocate kitchen and bathroom, provide new bedroom.Details
unit #201: interior remodel, relocate kitchen and bathroom, provide new bedroom. | $30,000 |
| Jun 18, 2014 | Completed final sign-off Aug 2014 | 2001 Pierce St | M H M Construction | #35- interior remodel apt.#35, remove non-load bearing walls, relocate kitchen, provide new bedroom, remodel (e) bath. n/a ordinance #155-13.Details
#35- interior remodel apt.#35, remove non-load bearing walls, relocate kitchen, provide new bedroom, remodel (e) bath. n/a ordinance #155-13. | $25,000 |
| Mar 12, 2014 | Completed final sign-off Jul 2014 | 1808 Pacific Av | M H M Construction | interior remodel at apt 701. remove non load bearing walls to relocate kitchen. provide new bedroom. remodel e bath. replace window in kind in lightwell.Details
interior remodel at apt 701. remove non load bearing walls to relocate kitchen. provide new bedroom. remodel e bath. replace window in kind in lightwell. | $30,000 |
| Mar 12, 2014 | Completed final sign-off Jul 2014 | 1808 Pacific Av | M H M Construction | interior remodel apt 301. remove non load bearing walls to relocate kitchen. provide new bedroom. remodel e bath. replace window in kind in lightwell.Details
interior remodel apt 301. remove non load bearing walls to relocate kitchen. provide new bedroom. remodel e bath. replace window in kind in lightwell. | $30,000 |
| Nov 13, 2013 | Completed final sign-off Jan 2014 | 1735 Van Ness Av | M H M Construction | provide plans for approved 201311051111. interior remodel apt 301. remove non load bearing walls to relocate kitchen. provide new office. removel e bath. provide new bath. elec/plumbing as necessaryDetails
provide plans for approved 201311051111. interior remodel apt 301. remove non load bearing walls to relocate kitchen. provide new office. removel e bath. provide new bath. elec/plumbing as necessary | $15,000 |
| Nov 13, 2013 | Completed final sign-off Jan 2014 | 1345 Clement St | M H M Construction | interior remodel apt 302. remove non load bearing walls to relocate kitchen. provide new bedroom. e bath electrical and plumbing work as necessary.Details
interior remodel apt 302. remove non load bearing walls to relocate kitchen. provide new bedroom. e bath electrical and plumbing work as necessary. | $25,000 |
| Sep 11, 2013 | Completed final sign-off Dec 2013 | 972 Bush St | M H M Construction | apt #2: interior remodel - remove non-load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bath, electrical & plumbing work as necessary, replace lighting with high efficacy lighting.Details
apt #2: interior remodel - remove non-load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bath, electrical & plumbing work as necessary, replace lighting with high efficacy lighting. | $20,000 |
| Sep 4, 2013 | Completed final sign-off Apr 2014 | 31 Cuvier St | De Star Construction | remodel rooms down for 33 cuvier, provide new interior stairs for open spatial connection. provide 2 new full bathrooms, new bedroom, new family room & storage.Details
remodel rooms down for 33 cuvier, provide new interior stairs for open spatial connection. provide 2 new full bathrooms, new bedroom, new family room & storage. | $50,000 |
| Sep 4, 2013 | Completed final sign-off Nov 2013 | 500 Hyde St | M H M Construction | unit #608: interior remodel. remove non load bearing walls to relocate kitchen. provide new bedroom remodel e bath. electrical and plumbing work as necessary. replace lighting with high effiacacy lightingDetails
unit #608: interior remodel. remove non load bearing walls to relocate kitchen. provide new bedroom remodel e bath. electrical and plumbing work as necessary. replace lighting with high effiacacy lighting | $20,000 |
| Sep 4, 2013 | Completed final sign-off Oct 2013 | 3149 California St | M H M Construction | unit #11e: revision to approved pa# 201308214833: existing wall at kitchen to remain. remove special inspection observation requirement for wood framing.Details
unit #11e: revision to approved pa# 201308214833: existing wall at kitchen to remain. remove special inspection observation requirement for wood framing. | |
| Aug 28, 2013 | Completed final sign-off Apr 2014 | 31 Cuvier St | De Star Construction | rebuild entry dry rotted wood front staris, reduce width of stairs to have 3ft minimum or width. new stairs to have code complying risers & treadsDetails
rebuild entry dry rotted wood front staris, reduce width of stairs to have 3ft minimum or width. new stairs to have code complying risers & treads | $8,000 |
| Aug 28, 2013 | Completed final sign-off Nov 2013 | 254 Divisadero St | M H M Construction | unit #7-interior remodel remove non load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bathroom. replace 1 windows at side ligthwell, not visible from the street. electrical & plumbing work as necessary. replace lighting with high efficacy lightingDetails
unit #7-interior remodel remove non load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bathroom. replace 1 windows at side ligthwell, not visible from the street. electrical & plumbing work as necessary. replace lighting with high efficacy lighting | $20,000 |
| Aug 28, 2013 | Completed final sign-off Nov 2013 | 745 Hyde St | M H M Construction | unit #30-interior remodel remove non load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting with high efficacy lightingDetails
unit #30-interior remodel remove non load bearing walls to relocate kitchen. provide new bedroom, remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting with high efficacy lighting | $20,000 |
| Aug 21, 2013 | Never finaled issued Aug 2013, no final | 3149 California St | M H M Construction | unit #11e-remove non load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting with high efficacy lightingDetails
unit #11e-remove non load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting with high efficacy lighting | $20,000 |
| Apr 5, 2013 | Completed final sign-off Jun 2013 | 50 Laguna St | M H M Construction | 6th floor apt #609 interior remodel: remove non-load bearing walls to relocate kitchen. provide (n) bedroom. remodel (e) bath. replace (e0 windows facing lightwell, electrical and plumbing as necessary. replace lighting with high efficacy lighting.Details
6th floor apt #609 interior remodel: remove non-load bearing walls to relocate kitchen. provide (n) bedroom. remodel (e) bath. replace (e0 windows facing lightwell, electrical and plumbing as necessary. replace lighting with high efficacy lighting. | $20,000 |
| Mar 11, 2013 | Completed final sign-off May 2013 | 745 Hyde St | M H M Construction | interior remodel apt#32. remove non-load bearing walls to relocate kitchen. provide (n) bedroom. remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting w/ high efficacy lighting.Details
interior remodel apt#32. remove non-load bearing walls to relocate kitchen. provide (n) bedroom. remodel (e) bathroom. electrical & plumbing work as necessary. replace lighting w/ high efficacy lighting. | $20,000 |
| Mar 11, 2013 | Completed final sign-off Jun 2013 | 887 Bush St | M H M Construction | apt #404: interior remodel at apt#404. remove non-load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bath. electrical & plumbing as necessary. replace lighting w/ high efficacy lighting.Details
apt #404: interior remodel at apt#404. remove non-load bearing walls to relocate kitchen. provide new bedroom. remodel (e) bath. electrical & plumbing as necessary. replace lighting w/ high efficacy lighting. | $20,000 |
| Feb 22, 2013 | Completed final sign-off Aug 2013 | 101 Lunado Wy | Peter Liu Construction Inc | reconfigure e bathrooms at 3rd floor per plan. remodel e bathroom, laundry and kitchen at 2nd floor per plan. remove e partition wall and provide new beamDetails
reconfigure e bathrooms at 3rd floor per plan. remodel e bathroom, laundry and kitchen at 2nd floor per plan. remove e partition wall and provide new beam | $38,000 |
| Jan 2, 2013 | Completed final sign-off Mar 2013 | 500 Leavenworth St | M H M Construction | interior remodel, apt 209. remove non load bearing wall to relocate kitchen. provide new bedroom. remodel (e) bath, replace 1 (e) window per plan. (not visible from street) electrical and plubming work as necessary. replace lighting with hi lighting.Details
interior remodel, apt 209. remove non load bearing wall to relocate kitchen. provide new bedroom. remodel (e) bath, replace 1 (e) window per plan. (not visible from street) electrical and plubming work as necessary. replace lighting with hi lighting. | $20,000 |
| Mar 22, 2012 | Completed final sign-off Aug 2012 | 1015 Battery St | install or build trellis on interior front terrace on ground floor, no outside work will be done. also, to correct record from occupancy class b to occupancy class a-2 ref app 201112050030Details
install or build trellis on interior front terrace on ground floor, no outside work will be done. also, to correct record from occupancy class b to occupancy class a-2 ref app 201112050030 | $10,000 | |
| Feb 23, 2012 | Completed final sign-off May 2012 | 310 Stanyan St | Alex R Construction | install 1 wall and 2 doors at kitchen and move and install electrical plug. change toilet and sink in bathDetails
install 1 wall and 2 doors at kitchen and move and install electrical plug. change toilet and sink in bath | $1,500 |
| Mar 16, 2011 | Completed final sign-off Nov 2011 | 1120 Church St | Alex R Construction | front bldg unit #1120 - interior alterations in basement of unit #1 - add bathroom, master bedroom with walk-in closet, spiral stair.Details
front bldg unit #1120 - interior alterations in basement of unit #1 - add bathroom, master bedroom with walk-in closet, spiral stair. | $50,000 |
| Oct 22, 2010 | Expired or cancelled cancelled Aug 2022 | 207 Bartlett St | Alex R Construction | comply w/nov #201041631Details
comply w/nov #201041631 | $4,000 |
| Apr 23, 2010 | Completed final sign-off Nov 2011 | 1120 Church St | foundation upgrade from brick foundation to concrete foundation (reinforced) foundation, recess basement finish floor as per plans.Details
foundation upgrade from brick foundation to concrete foundation (reinforced) foundation, recess basement finish floor as per plans. | $45,000 | |
| Oct 9, 2009 | Completed final sign-off Nov 2011 | 1120 Church St | new 1-car garage in existing basement; remodel existing bath in basement.Details
new 1-car garage in existing basement; remodel existing bath in basement. | $25,000 | |
| Aug 11, 2009 | Expired or cancelled cancelled Jan 2026 | 55 Tingley St | Erick's Construction Inc | ||
| Oct 12, 2007 | Completed final sign-off Jun 2008 | 430 Jersey St | Occidental Express | replace rear stairs and landing in-kind. stairs are in exact same location and dimensions are same as existing.Details
replace rear stairs and landing in-kind. stairs are in exact same location and dimensions are same as existing. | $22,000 |
| Mar 1, 2005 | Completed final sign-off Sep 2005 | 435 Broadway | National Earthquake Engineers, Inc. | seismic retrofit revision to original appl#9806960 special procedure.Details
seismic retrofit revision to original appl#9806960 special procedure. | $15,000 |