12 permits since 2000 (engineer on 12 permits): 9 completed, 3 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 25, 2024 | Completed final sign-off Aug 2024 | 180 Montgomery St | Bcci Construction Company | 13, 22nd, 24th, 25th floor: installation of steel framing at underside of 25th floor. anchorage of non structural mep equipment at 13th and 22nd, 24t and 25th floors. ref pa#202311130699, 202311140779,202312212904,202312212906Details
13, 22nd, 24th, 25th floor: installation of steel framing at underside of 25th floor. anchorage of non structural mep equipment at 13th and 22nd, 24t and 25th floors. ref pa#202311130699, 202311140779,202312212904,202312212906 | $70,000 |
| May 23, 2023 | Completed final sign-off Jun 2024 | 425 Market St | Golden Gate Fire Protection Inc | revision to pa# 202303163764, including structural drawings.Details
revision to pa# 202303163764, including structural drawings. | |
| Jun 22, 2022 | Never finaled issued Jul 2022, no final | 465 California St | Ge Construction Contractors Inc | structural work to replace sidewalk elevator beams to suppport surrounding sidewalk and construct and elevator pit to support a new elevtor system elec. work that will retain (e) feeders but upgrade fixtures in he new elevator pit and the (e) (adjacent) machine room. approx. 12.5 cu yds excavation.Details
structural work to replace sidewalk elevator beams to suppport surrounding sidewalk and construct and elevator pit to support a new elevtor system elec. work that will retain (e) feeders but upgrade fixtures in he new elevator pit and the (e) (adjacent) machine room. approx. 12.5 cu yds excavation. | $480,000 |
| Oct 14, 2020 | Never finaled issued Apr 2021, no final | 1 Market St | Dpr Construction | ste 200, 2/f: structural modifications for t.i under pa # 202009265068. scope includes structural support for moveable partition in main event space. support for roll down fire door.Details
ste 200, 2/f: structural modifications for t.i under pa # 202009265068. scope includes structural support for moveable partition in main event space. support for roll down fire door. | $10,000 |
| Aug 27, 2020 | Completed final sign-off Oct 2020 | 455 Market St | Dpr Construction | revision to pa#2019-1217-9718. new floor sink penetrations through the 23rd floor.Details
revision to pa#2019-1217-9718. new floor sink penetrations through the 23rd floor. | $3,500 |
| Apr 25, 2019 | Completed final sign-off Jan 2022 | 2121 Webster St | Black Mountain Development | unit 804 (gph4): interior fitout of (e) shell, ref approved bpa#201311222660, relocating (e) stair, new interior partitions, all new finishes, sprinkler/mechanical systems under seperate permit.Details
unit 804 (gph4): interior fitout of (e) shell, ref approved bpa#201311222660, relocating (e) stair, new interior partitions, all new finishes, sprinkler/mechanical systems under seperate permit. | $2,000,000 |
| Feb 13, 2019 | Completed final sign-off Jul 2021 | 455 Market St | Rudolph Commercial Interiors Inc, Rci | structural drawing for seismic bracing at the shelving system/open storage on 2nd fl.Details
structural drawing for seismic bracing at the shelving system/open storage on 2nd fl. | |
| Feb 13, 2019 | Completed final sign-off Jul 2021 | 455 Market St | Rudolph Commercial Interiors Inc, Rci | structure drawing for movable partition in the conference room on 3rd fl.Details
structure drawing for movable partition in the conference room on 3rd fl. | $1,200,000 |
| Jul 25, 2017 | Completed final sign-off Oct 2020 | 2121 Webster St | Black Mountain Development | penthouse #gph-2 remodel fit-out of (e) shell to include new partitions, elevator, lighting, finishes, new interior stair and structural modifications with new entry. mep. & sprinklers under seperate permit. ref. to pa#201311222660Details
penthouse #gph-2 remodel fit-out of (e) shell to include new partitions, elevator, lighting, finishes, new interior stair and structural modifications with new entry. mep. & sprinklers under seperate permit. ref. to pa#201311222660 | $1,764,000 |
| Jul 19, 2017 | Completed final sign-off Jun 2019 | 2121 Webster St | Black Mountain Development | 8/f to 9/f penthouse #3- revision to pa#201705126475 to include stuctural work and change of style for new stair on penthouse unit #3Details
8/f to 9/f penthouse #3- revision to pa#201705126475 to include stuctural work and change of style for new stair on penthouse unit #3 | $20,000 |
| Apr 21, 2017 | Never finaled issued May 2017, no final | 33 03rd St | Cahill Contractors Llc. | basement to 8/f- voluntary strengthening upgrade to correct short colulmn conditions at specific locations around the vehicle ramp, entrance and exit to garage. n/a ordinance #155-13Details
basement to 8/f- voluntary strengthening upgrade to correct short colulmn conditions at specific locations around the vehicle ramp, entrance and exit to garage. n/a ordinance #155-13 | $700,000 |
| Dec 5, 2014 | Completed final sign-off Jun 2021 | 1095 Market St | Skanska Usa Building Inc, Build Group Inc. | seismic renovation to 1095 market street foundation, basement & full structure.n/a for maher ordinance.Details
seismic renovation to 1095 market street foundation, basement & full structure.n/a for maher ordinance. | $1,500,000 |