Christopher Wener
- Listed as
- architect, engineer
- Firm
- Next Edge
- Based in
- Alpharetta
- On San Francisco permits
- Jun 2023 to Jun 2026
26 permits since 2000 (engineer on 24 permits, architect on 2 permits): 12 completed, 11 in progress, 2 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 11, 2026 | In progress filed Jun 2026, not yet issued | 3301 Lyon St | att: install 90' faux eucalyptus tree w/ 16 (n) antennas, 12 (n) rrus, 4 (n) surge supressors, 1 (n) cabinet on (n) concrete pad, (n) concrete pad for future generator, (n) 400a meter & (n) 400a sub panel, (n) cru block wallDetails
att: install 90' faux eucalyptus tree w/ 16 (n) antennas, 12 (n) rrus, 4 (n) surge supressors, 1 (n) cabinet on (n) concrete pad, (n) concrete pad for future generator, (n) 400a meter & (n) 400a sub panel, (n) cru block wall | $240,000 | |
| Jan 12, 2026 | Completed final sign-off May 2026 | 169 Steuart St | L.D. Strobel Co Ltd | verizon wireless tua: temp wireless facility to install 9 antennas; (1) mw dish; 3 rrus' 200a elec service; conduits; batteriesDetails
verizon wireless tua: temp wireless facility to install 9 antennas; (1) mw dish; 3 rrus' 200a elec service; conduits; batteries | $45,000 |
| Apr 17, 2025 | In progress filed Apr 2025, not yet issued | 2000 Van Ness Av | dish: revision to pa 2023-1205-1923 relocate proposed sector a antenna equipment platform. install (1) (n) frp radomeDetails
dish: revision to pa 2023-1205-1923 relocate proposed sector a antenna equipment platform. install (1) (n) frp radome | ||
| Jan 31, 2025 | Completed final sign-off May 2026 | 15 Fell St | Metropolitan Electrical Construction | at&t install 12(n) antennas on roof within (n) screen walls; install equipment area in basement; install 16 (n) batteries; install (n) elec submeter & ppcDetails
at&t install 12(n) antennas on roof within (n) screen walls; install equipment area in basement; install 16 (n) batteries; install (n) elec submeter & ppc | $175,000 |
| Oct 24, 2024 | In progress filed Oct 2024, not yet issued | 2301 03rd St | dish wireless: install 6 new antennas, 12 new rrus, 1 new equipment rack, 1 new electrical panel. no proposed batteries.Details
dish wireless: install 6 new antennas, 12 new rrus, 1 new equipment rack, 1 new electrical panel. no proposed batteries. | $150,000 | |
| Aug 28, 2024 | In progress filed Aug 2024, not yet issued | 121 Steuart St | dish: install (3)(n) antennas + (1)(n) equipment platform roof top; no proposed batteries; install (n) electrical panelDetails
dish: install (3)(n) antennas + (1)(n) equipment platform roof top; no proposed batteries; install (n) electrical panel | $150,000 | |
| May 22, 2024 | In progress filed May 2024, not yet issued | 215 Fremont St | dish wireless: install (3)(n) antennas inside (3)(n) radomes, (1)(n) cabinet, (1)(n) electrical panel; no proposed batteriesDetails
dish wireless: install (3)(n) antennas inside (3)(n) radomes, (1)(n) cabinet, (1)(n) electrical panel; no proposed batteries | $140,000 | |
| Apr 16, 2024 | In progress filed Apr 2024, not yet issued | 30 Otis St | dish: install (3) new antennas inside (2) new radome and new equipment platform on rooftop with (1) new cabinet. install (1) new transformer. install new submeter. no proposed batteries.Details
dish: install (3) new antennas inside (2) new radome and new equipment platform on rooftop with (1) new cabinet. install (1) new transformer. install new submeter. no proposed batteries. | $350,000 | |
| Feb 28, 2024 | In progress filed Feb 2024, not yet issued | 501 Laguna Honda Bl | dish: install (3)(n) antennas within (n) frp screen on roof; install (6)(n) rrvs; install (1)(n) cabinet; no proposed batteries; install (n) 200a breaker & (n) power cabinet.Details
dish: install (3)(n) antennas within (n) frp screen on roof; install (6)(n) rrvs; install (1)(n) cabinet; no proposed batteries; install (n) 200a breaker & (n) power cabinet. | $115,000 | |
| Feb 15, 2024 | In progress filed Feb 2024, not yet issued | 888 Brannan St | dish: install (3)(n) antennas, (6)(n) rrvs, (1)(n) cabinet rack, (1)(n) emon-omon; no batteries proposed.Details
dish: install (3)(n) antennas, (6)(n) rrvs, (1)(n) cabinet rack, (1)(n) emon-omon; no batteries proposed. | $125,000 | |
| Dec 19, 2023 | In progress filed Dec 2023, not yet issued | 310 Townsend St | dish wireless: remove 3 e antennas & 1 e radume; install 3 n antennas & 1 n radome. remove 2 e cabinets & install 1 n caninet. no proposal batteriesDetails
dish wireless: remove 3 e antennas & 1 e radume; install 3 n antennas & 1 n radome. remove 2 e cabinets & install 1 n caninet. no proposal batteries | $90,000 | |
| Dec 12, 2023 | In progress issued Jan 2024 | 55 Francisco St | Modus Rex Llc | dish revision to 202207279373. revise fiber poc to zayo, revise antenna screen attachment detail. install new 15 amp receptacle, no change to rf report, no visual change. remove batteries from scope of workDetails
dish revision to 202207279373. revise fiber poc to zayo, revise antenna screen attachment detail. install new 15 amp receptacle, no change to rf report, no visual change. remove batteries from scope of work | |
| Dec 5, 2023 | In progress issued Oct 2024 | 2000 Van Ness Av | Synergy Dba Solar Universe-Brentwood | dish: remove 6 (e) antennas and screen boxes. remove 2 (e) cabinets. install 3 new antennas inside 3 new screen boxes. install 1 new cabinet. no batteries. re-use (e) 200a meterDetails
dish: remove 6 (e) antennas and screen boxes. remove 2 (e) cabinets. install 3 new antennas inside 3 new screen boxes. install 1 new cabinet. no batteries. re-use (e) 200a meter | $90,000 |
| Nov 7, 2023 | Completed final sign-off Dec 2023 | 334 Mason St | Modus Rex Llc | dish: revision to 202203160088. revise 200 a to 100a. remove gen plug & transfer switch, no change to previous approved antennas, equipmemt, rf report, no proposed batteriesDetails
dish: revision to 202203160088. revise 200 a to 100a. remove gen plug & transfer switch, no change to previous approved antennas, equipmemt, rf report, no proposed batteries | |
| Oct 30, 2023 | Completed final sign-off Mar 2025 | 300 02nd Av | Synergy Dba Solar Universe-Brentwood | dish: remove (e) antennas & equipment; install 3(n) antennas within 2(n) screen radomes; install 1(n) cabinet; install (n) electrical panel; no proposed batteriesDetails
dish: remove (e) antennas & equipment; install 3(n) antennas within 2(n) screen radomes; install 1(n) cabinet; install (n) electrical panel; no proposed batteries | $50,000 |
| Oct 12, 2023 | Completed final sign-off May 2024 | 220 Jackson St | Modus Rex Llc | revision to 202209222982. relocate cable tray. revise equipment platform. revise antenna mounting. no change to rf report. no proposed batteries.Details
revision to 202209222982. relocate cable tray. revise equipment platform. revise antenna mounting. no change to rf report. no proposed batteries. | |
| Oct 2, 2023 | Completed final sign-off May 2024 | 201 Spear St | Modus Rex Llc | revision to 202208160573, reuse e platform j. revise fiber box enclosure, no change to approved antennnas or batteriesDetails
revision to 202208160573, reuse e platform j. revise fiber box enclosure, no change to approved antennnas or batteries | |
| Oct 2, 2023 | Completed final sign-off Dec 2023 | 655 Beach St | Modus Rex Llc | revison to pa# 202207279375, revise equipment platform j, revise fiber box enclosure, no change to approved antennas or batteries.Details
revison to pa# 202207279375, revise equipment platform j, revise fiber box enclosure, no change to approved antennas or batteries. | |
| Sep 13, 2023 | Completed final sign-off Mar 2024 | 250 Montgomery St | Modus Rex Llc | revision to 202208311620: revise fiber p.o.c. revise 100 a,p breaker to 125 amp breaker. no change to approved rf report, no change to approved betteriesDetails
revision to 202208311620: revise fiber p.o.c. revise 100 a,p breaker to 125 amp breaker. no change to approved rf report, no change to approved betteries | |
| Sep 7, 2023 | Never finaled issued Sep 2023, no final | 570 Beale St | Tilson Technology Management Inc | dish wireless - remove 6(e) sprint antennas, 2(e) sprint cabinets & assoicated equipment; install 3 (n) dish antennas, 6(n) rrus, 1(n) cabinet; use (3) frp screening; no proposed batteries; install (n) electrical panelDetails
dish wireless - remove 6(e) sprint antennas, 2(e) sprint cabinets & assoicated equipment; install 3 (n) dish antennas, 6(n) rrus, 1(n) cabinet; use (3) frp screening; no proposed batteries; install (n) electrical panel | $115,000 |
| Jun 26, 2023 | Completed final sign-off Dec 2023 | 429 Castro St | Modus Rex Llc | dish: remove (e) sprint equipment and antenas, insatll (3) (n) antennas inside (2) (n) radomes, install (1) (n) cabinet, install (n) power and fiber trunks, re-use (e) telco conduit, no proposed batteriesDetails
dish: remove (e) sprint equipment and antenas, insatll (3) (n) antennas inside (2) (n) radomes, install (1) (n) cabinet, install (n) power and fiber trunks, re-use (e) telco conduit, no proposed batteries | $130,000 |
| Jun 22, 2023 | Completed final sign-off May 2024 | 500 California St | Modus Rex Llc | dish install 3 (n) antennas; install 2 (n) radomes & 1(n) frp box; install 6 (n) rrus/ 1(n) cabinet, power & telco conduits, 1(n) transformer, 1(n) emon-dmon. no proposed batteriesDetails
dish install 3 (n) antennas; install 2 (n) radomes & 1(n) frp box; install 6 (n) rrus/ 1(n) cabinet, power & telco conduits, 1(n) transformer, 1(n) emon-dmon. no proposed batteries | $150,000 |
| Jun 22, 2023 | Never finaled issued Jul 2023, no final | 334 Mason St | Modus Rex Llc | dish: revisiuon to 202203160088, revise location of gamma sector from facade mount to roof mount and screened in 2 n radomes. revise rrh model from 8 n mti to 8 n samsung. revise fiber poc. revise elec scope, remove batteriesDetails
dish: revisiuon to 202203160088, revise location of gamma sector from facade mount to roof mount and screened in 2 n radomes. revise rrh model from 8 n mti to 8 n samsung. revise fiber poc. revise elec scope, remove batteries | |
| Jun 21, 2023 | Completed final sign-off Oct 2023 | 1800 Sutter St | Modus Rex Llc | revision to pa# 202211307426. remove batteries from scope of work. remove proposed att fiber from scope of work. install (n) zayo fiber. install 6 samsung rrh instead of 6 (n) mti rrh. install (n) 1 ph 50 kva 480v to 120/240v step-down transformer.Details
revision to pa# 202211307426. remove batteries from scope of work. remove proposed att fiber from scope of work. install (n) zayo fiber. install 6 samsung rrh instead of 6 (n) mti rrh. install (n) 1 ph 50 kva 480v to 120/240v step-down transformer. | |
| Jun 7, 2023 | Expired or cancelled cancelled Jan 2026 | 890 Jackson St | dish wireless: revision to pa 2022-0914-2387 relocate emon dmon, transfer switch & gen plug from exterior to interior of building; revise fiter poc to electrical room; remove batteries from scopeDetails
dish wireless: revision to pa 2022-0914-2387 relocate emon dmon, transfer switch & gen plug from exterior to interior of building; revise fiter poc to electrical room; remove batteries from scope | ||
| Jun 1, 2023 | Completed final sign-off Aug 2023 | 220 Golden Gate Av | Modus Rex Llc | dish wireless revision to 202205315291. revise scope of work to incluse decom of e sprint fac ility and to locate dish antennas and equipment into e sprint lease areas. remove batteries from scope of work.Details
dish wireless revision to 202205315291. revise scope of work to incluse decom of e sprint fac ility and to locate dish antennas and equipment into e sprint lease areas. remove batteries from scope of work. |