- Apr 2003 to Jan 2024
264 permits since 2000 (architect on 254 permits, engineer on 5 permits, designer on 4 permits, authorized agent-others on 2 permits): 210 completed, 3 in progress, 24 never finaled, 27 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 264.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 2, 2024 | In progress filed Jan 2024, not yet issued | 226 Cabrillo St | install new 2 stop interior elevator, between nd and 3rd floor. modify existing guardrail at 3/fDetails
install new 2 stop interior elevator, between nd and 3rd floor. modify existing guardrail at 3/f | $36,000 | |
| Jul 6, 2022 | Expired or cancelled withdrawn Jan 2024 | 226 Cabrillo St | install 3 story interior elevator. 2nd floor: reconfigure den & add window at bedroom# 1 bay. 3rd floor: reconfigure bedrooms# 2 & # 3 to new main bedroom & reconfigure bath# 3.Details
install 3 story interior elevator. 2nd floor: reconfigure den & add window at bedroom# 1 bay. 3rd floor: reconfigure bedrooms# 2 & # 3 to new main bedroom & reconfigure bath# 3. | $165,000 | |
| May 5, 2022 | Never finaled issued May 2022, no final | 4363 26th St | Gama Construction Inc | revision to permit # 202109249141. replace top 12" of 2nd floor north guardrail with 12" h fixed. temperred glass panels.Details
revision to permit # 202109249141. replace top 12" of 2nd floor north guardrail with 12" h fixed. temperred glass panels. | |
| Sep 24, 2021 | Completed final sign-off May 2023 | 4363 26th St | Gama Construction Inc | revision to pa 201802232056. basement level: delete stairs to yard at rear patio. 1/f: relocate laundry and master closet, reduce ceiling height. roof: resize skylight. all levels: revise interior stairs layout.Details
revision to pa 201802232056. basement level: delete stairs to yard at rear patio. 1/f: relocate laundry and master closet, reduce ceiling height. roof: resize skylight. all levels: revise interior stairs layout. | |
| Sep 24, 2021 | Completed final sign-off Mar 2023 | 3227 Broderick St | rev to pa 201907267082 all work is @ 4th floor replace 2 pair of doors w (1) sliding door unit - reposition pocket foor @ rear elevation - resize (2) skylights and delete (1) reconfigure bath/closet area of bedroom - move cabinets @ rear deck room from north to south wall.Details
rev to pa 201907267082 all work is @ 4th floor replace 2 pair of doors w (1) sliding door unit - reposition pocket foor @ rear elevation - resize (2) skylights and delete (1) reconfigure bath/closet area of bedroom - move cabinets @ rear deck room from north to south wall. | ||
| Apr 28, 2021 | Completed final sign-off Sep 2022 | 65 Almaden Ct | Duffin Construction | revision to pa #201801168631. remove (e) n.g. furnace and water heater and install new combo hydronic system. heating is underfloor application.Details
revision to pa #201801168631. remove (e) n.g. furnace and water heater and install new combo hydronic system. heating is underfloor application. | $10,000 |
| Mar 23, 2021 | Never finaled filed Mar 2021, never issued | 40 Lurline St | construct 635 s.f. third story addition to include two bedrooms, one bath, one study, interior stairway to second floor, and 195 s.f. roof deck. new addition to stack over existing second floor footprintDetails
construct 635 s.f. third story addition to include two bedrooms, one bath, one study, interior stairway to second floor, and 195 s.f. roof deck. new addition to stack over existing second floor footprint | $85,000 | |
| Aug 25, 2020 | In progress issued Jun 2026 | 242 Liberty St | vertical and horizontal additions to existing duplex to include: 242 liberty - great room, 3 bedrooms, 3 1/2 baths, media room, laundry, roof deck 244 liberty - great room, 3 bedrooms, 3 1/2 baths, study, laundry, [2] roof decksDetails
vertical and horizontal additions to existing duplex to include: 242 liberty - great room, 3 bedrooms, 3 1/2 baths, media room, laundry, roof deck 244 liberty - great room, 3 bedrooms, 3 1/2 baths, study, laundry, [2] roof decks | $750,000 | |
| Jun 30, 2020 | Completed final sign-off Dec 2020 | 553 15th Av | K. Kinahan Construction | build wood fence, total not to go over 9 feet. 6 feet solid 18-22 inch 50% see thru top for plants to grow in around back yard perimeter.Details
build wood fence, total not to go over 9 feet. 6 feet solid 18-22 inch 50% see thru top for plants to grow in around back yard perimeter. | $35,000 |
| Feb 28, 2020 | Completed final sign-off Mar 2021 | 553 15th Av | K. Kinahan Construction | revision to pa #201802272284. replace 1 sliding door & 1 window w/1 sliding window & 1 hinged door. material-wood cladDetails
revision to pa #201802272284. replace 1 sliding door & 1 window w/1 sliding window & 1 hinged door. material-wood clad | |
| Jan 31, 2020 | Never finaled issued Feb 2022, no final | 474 Valley St | Spectrums General Engineering, Zm Builders Inc | vertical & horizontal addition. 1st floor: entry, garage, 2 bedroom, 2 bath, laundry. 2nd floor: great room, 1 bedroom, 1 bath, one 1/2 bath. 3rd floor: great room, 1 bedroom, 1 bath, one 1/2 bath, laundry. 4th floor: 2 bedrooms, 2 baths. install sprinkler system @ all levels under seperate permit.Details
vertical & horizontal addition. 1st floor: entry, garage, 2 bedroom, 2 bath, laundry. 2nd floor: great room, 1 bedroom, 1 bath, one 1/2 bath. 3rd floor: great room, 1 bedroom, 1 bath, one 1/2 bath, laundry. 4th floor: 2 bedrooms, 2 baths. install sprinkler system @ all levels under seperate permit. | $650,000 |
| Dec 6, 2019 | Completed final sign-off Mar 2024 | 136 Parnassus Av | Wall Construction | ordinance 43-14. legalize 2 bedroom units @ 1st fl. remove interior spiral stairs between 1st and 2nd floors.Details
ordinance 43-14. legalize 2 bedroom units @ 1st fl. remove interior spiral stairs between 1st and 2nd floors. | $108,500 |
| Nov 21, 2019 | Completed final sign-off Oct 2020 | 167 Judson Av | Pio Mcgarr Inc | revision to 201905231484, enclose a 16 sf area under 2nd fl pantry to create a closet. new setback foundation due to shared footing.Details
revision to 201905231484, enclose a 16 sf area under 2nd fl pantry to create a closet. new setback foundation due to shared footing. | $2,200 |
| Oct 17, 2019 | Never finaled issued Dec 2020, no final | 51 Springfield Dr | interior remodel to add 172sf of conditioned space at the 1st fl. new area to include expansion of (e) family room, (n) bath & (n) laundry areaDetails
interior remodel to add 172sf of conditioned space at the 1st fl. new area to include expansion of (e) family room, (n) bath & (n) laundry area | $21,000 | |
| Oct 4, 2019 | Completed final sign-off Mar 2021 | 553 15th Av | K. Kinahan Construction | revision to app#201802272284: replace siding from shingles to stucco at 1st floor front elevation. reconfigure rooms at 3rd floor to convert study to bedroom and walk in closet to study.Details
revision to app#201802272284: replace siding from shingles to stucco at 1st floor front elevation. reconfigure rooms at 3rd floor to convert study to bedroom and walk in closet to study. | |
| Sep 12, 2019 | Completed final sign-off Mar 2021 | 970 Corbett Av | S Q Garage Door | altered site for pa# 2014-0605-7570 s; basement - remove post. 1st floor - extend building 5'-5" into rear yard, reconfigure kitchen & add bathDetails
altered site for pa# 2014-0605-7570 s; basement - remove post. 1st floor - extend building 5'-5" into rear yard, reconfigure kitchen & add bath | |
| Sep 3, 2019 | Completed final sign-off Sep 2019 | 1441 Plymouth Av | Kadima-Schoepp, Inc | revision to permit #201804116021. remove fireplace in living room "in fill".Details
revision to permit #201804116021. remove fireplace in living room "in fill". | $300 |
| Aug 1, 2019 | Completed final sign-off Mar 2021 | 3790 21st St | revision to pa 2015-0410-3305 & 2018-0201-0090. 1st f; - relocate fireplace, reconfigure kitchen, 1/2 bath, pantry areas, revise guardrails @ stairs; 2nd fl - add bath @ bedroom 2, relocate bath & laundry, reconfigure master bath & stairs; 3rd fl - reconfigure baths & stairs, replace hall window w/Details
revision to pa 2015-0410-3305 & 2018-0201-0090. 1st f; - relocate fireplace, reconfigure kitchen, 1/2 bath, pantry areas, revise guardrails @ stairs; 2nd fl - add bath @ bedroom 2, relocate bath & laundry, reconfigure master bath & stairs; 3rd fl - reconfigure baths & stairs, replace hall window w/ | $25,000 | |
| Jul 31, 2019 | Completed final sign-off Mar 2021 | 553 15th Av | K. Kinahan Construction | replace entry stairs & adjacent guardrail walls, in-kind, due to extensive dry rot. replace in-kind w/terrazzo treadsDetails
replace entry stairs & adjacent guardrail walls, in-kind, due to extensive dry rot. replace in-kind w/terrazzo treads | $4,500 |
| Jul 26, 2019 | Completed final sign-off Mar 2023 | 3229 Broderick St | add 4th flr to 3rd flr unit(3229 broderick st) w/ bedroom & bath, study,1/2 bath, family room, (2) roof deck. add interior stairs from 3rd to 4th flr.**maher n/a**Details
add 4th flr to 3rd flr unit(3229 broderick st) w/ bedroom & bath, study,1/2 bath, family room, (2) roof deck. add interior stairs from 3rd to 4th flr.**maher n/a** | $95,000 | |
| Jul 24, 2019 | Completed final sign-off Mar 2023 | 3227 Broderick St | revision to 20181288577, 201811286901: unit 3227 reconfigure room layouts. unit 3229 - reconfigure room layouts. exterior elevation revise window sizesDetails
revision to 20181288577, 201811286901: unit 3227 reconfigure room layouts. unit 3229 - reconfigure room layouts. exterior elevation revise window sizes | ||
| Jul 10, 2019 | Completed final sign-off Mar 2021 | 3790 21st St | revision to pa 2018-0201-0090 & to respond to complaint 201931520 construct wood fence @ north & east property lines to abutt neighbor's 6' high fences. top of (n) fence to be even with top of adjacent fencesDetails
revision to pa 2018-0201-0090 & to respond to complaint 201931520 construct wood fence @ north & east property lines to abutt neighbor's 6' high fences. top of (n) fence to be even with top of adjacent fences | $4,500 | |
| Jun 19, 2019 | Completed final sign-off Mar 2022 | 152 Hartford St | Handyman Heroes Inc. | add new 1236 sq ft apartment at the (e) storage area on the 1/fl. unit to include great room, study, 3 bedrooms, 2 baths. install (n) nfpa 13 sprinkler system at 1/fl.Details
add new 1236 sq ft apartment at the (e) storage area on the 1/fl. unit to include great room, study, 3 bedrooms, 2 baths. install (n) nfpa 13 sprinkler system at 1/fl. | $122,000 |
| May 1, 2019 | Completed final sign-off Aug 2023 | 1634 Alabama St | Rinaldi Construction | 1st flr - remodel storage area behind garage to include 2 bed, 2 bath, install 2 skylights. 2nd flr - enclose lightwell at so. p.l. & expand and remodel (e) bath. add new deck w/stairs to rear yard - replace window & doors at west wall w/2 pair if doors. owner to cancel prior permit for new unit.Details
1st flr - remodel storage area behind garage to include 2 bed, 2 bath, install 2 skylights. 2nd flr - enclose lightwell at so. p.l. & expand and remodel (e) bath. add new deck w/stairs to rear yard - replace window & doors at west wall w/2 pair if doors. owner to cancel prior permit for new unit. | $84,000 |
| Apr 19, 2019 | Completed final sign-off Mar 2020 | 1115 Webster St | revision to pa 2019-0215-3015 - remodel 2nd fl apt 1 - to include insulate (e) walls, replace bath & kitchen, remove non-bearing walls @ kitchen/dining area, remodel closets adjacent to bedrm to (n) full bath; remodel 3rd fl apt 3 - remodel closets adjacent to bedroom to (n) full bathDetails
revision to pa 2019-0215-3015 - remodel 2nd fl apt 1 - to include insulate (e) walls, replace bath & kitchen, remove non-bearing walls @ kitchen/dining area, remodel closets adjacent to bedrm to (n) full bath; remodel 3rd fl apt 3 - remodel closets adjacent to bedroom to (n) full bath | $44,000 | |
| Feb 21, 2019 | Completed final sign-off Jul 2022 | 928 Shotwell St | Dolan Iron Works | application for variance. response to notice of complaint #2018-016911enf (e) front fence exceeds height and permeability. ** maher: n/a **Details
application for variance. response to notice of complaint #2018-016911enf (e) front fence exceeds height and permeability. ** maher: n/a ** | |
| Jan 31, 2019 | Never finaled issued Feb 2020, no final | 985 Greenwich St | remodel 1st floor from 1 car garage & storage to a new adu per ordinance# 162-16 & storage. adu unit to include greatroom, 2 bedrooms, 2 baths, 2 storage rooms. install new nfpa 13-r sprinkler system @ entire 1st floor.Details
remodel 1st floor from 1 car garage & storage to a new adu per ordinance# 162-16 & storage. adu unit to include greatroom, 2 bedrooms, 2 baths, 2 storage rooms. install new nfpa 13-r sprinkler system @ entire 1st floor. | $120,000 | |
| Jan 31, 2019 | Completed final sign-off Nov 2020 | 227 Waller St | Ikb Stone Inc | remodel kitchen & bath; remove some interior walls & install steel beam. enlarge window openings & install wood windowsDetails
remodel kitchen & bath; remove some interior walls & install steel beam. enlarge window openings & install wood windows | $60,000 |
| Dec 18, 2018 | Completed final sign-off Mar 2023 | 3227 Broderick St | remodel 3 story duplex. unit 3227 - add (n) bedrm, bath, laundry & interior stairs to 2nd fl; reconfigure plan at 2nd floor & add sink @ (e) toilet room. unit 3229 - reconfigure plan @ 3rd fl & add 1/2 bathDetails
remodel 3 story duplex. unit 3227 - add (n) bedrm, bath, laundry & interior stairs to 2nd fl; reconfigure plan at 2nd floor & add sink @ (e) toilet room. unit 3229 - reconfigure plan @ 3rd fl & add 1/2 bath | $410,000 | |
| Dec 18, 2018 | Completed final sign-off Jul 2019 | 17 Temple St | Gama Construction Inc | revision to pa 2014-0422-3783 and 2018-0515-9196 add 2 skylights, change framing @ rear 2nd fl deck from cantilever to post & beam. the deck footprint is to remain unchanged - delete rear spiral stiars & deck. reconfigure windows @ east (rear) elevationDetails
revision to pa 2014-0422-3783 and 2018-0515-9196 add 2 skylights, change framing @ rear 2nd fl deck from cantilever to post & beam. the deck footprint is to remain unchanged - delete rear spiral stiars & deck. reconfigure windows @ east (rear) elevation | $25,000 |
| Dec 13, 2018 | Completed final sign-off Aug 2019 | 1256 Francisco St | Alex R Construction | revision to 201804105893, add reoof deck side of 4th fl family room, replace w alum windows at family room with pair of wood french doorsDetails
revision to 201804105893, add reoof deck side of 4th fl family room, replace w alum windows at family room with pair of wood french doors | $30,000 |
| Nov 28, 2018 | Completed final sign-off Mar 2023 | 3227 Broderick St | foundation replacement with new reinforced concrete mat slab. maher n/a.Details
foundation replacement with new reinforced concrete mat slab. maher n/a. | $80,000 | |
| Oct 17, 2018 | Expired or cancelled cancelled Dec 2021 | 107 De Soto St | two story addition along north side of houseDetails
two story addition along north side of house | $41,000 | |
| Sep 13, 2018 | Never finaled issued Oct 2018, no final | 1358 12th Av | revision 201505015177, revise interior floorplans and structural. change skylight locationsDetails
revision 201505015177, revise interior floorplans and structural. change skylight locations | ||
| Jul 23, 2018 | Completed final sign-off Nov 2018 | 501 Rockdale Dr | Green Planet Remodelling Inc | interior remodel to legalize existing family room; remodel (e) bath and storage area, all woork on 1st fl.; add side property line facing window not visible from street.Details
interior remodel to legalize existing family room; remodel (e) bath and storage area, all woork on 1st fl.; add side property line facing window not visible from street. | $34,000 |
| Jun 8, 2018 | Never finaled issued May 2019, no final | 1358 12th Av | Hing Wah Construction Inc | vertical addition. revision to 201505015177. reconfigure 3rd fl plan. convert attic at 3rd fl to (n) bedroom. replace gable roof @ front with hip roof.Details
vertical addition. revision to 201505015177. reconfigure 3rd fl plan. convert attic at 3rd fl to (n) bedroom. replace gable roof @ front with hip roof. | $20,000 |
| May 15, 2018 | Completed final sign-off Jul 2019 | 17 Temple St | this is a revision to permit # 201404223783, revise window sizes & locations at south wall, revise shear wall lalyout at south wall, revise bath & laundry layout at 3rd fl.Details
this is a revision to permit # 201404223783, revise window sizes & locations at south wall, revise shear wall lalyout at south wall, revise bath & laundry layout at 3rd fl. | ||
| May 10, 2018 | Expired or cancelled withdrawn May 2018 | 1163 Shotwell St | revision to permit #201511102199. inset 2 x windows at north side ground fl 3'6" from property line.Details
revision to permit #201511102199. inset 2 x windows at north side ground fl 3'6" from property line. | ||
| Apr 30, 2018 | Completed final sign-off Feb 2019 | 255 Moncada Wy | revision to 201708033741 convert 231 sf garage to bedroom, remove garage dr & install window, provide bike parking @ mudroom. convert (e) bath * closet to 1/2 bath & full bath. add closet @ (e) bedroom maher naDetails
revision to 201708033741 convert 231 sf garage to bedroom, remove garage dr & install window, provide bike parking @ mudroom. convert (e) bath * closet to 1/2 bath & full bath. add closet @ (e) bedroom maher na | $5,000 | |
| Apr 11, 2018 | Completed final sign-off Sep 2019 | 1441 Plymouth Av | Kadima-Schoepp, Inc | interior remodel to include. 1st floor: add new rooms to include 3 bed rooms, 2 baths, family room, and laundr. new interior stairs. 2nd floor: remodel kitchen and bath add 1 bath. replace entry steps and porch.Details
interior remodel to include. 1st floor: add new rooms to include 3 bed rooms, 2 baths, family room, and laundr. new interior stairs. 2nd floor: remodel kitchen and bath add 1 bath. replace entry steps and porch. | $350,000 |
| Apr 11, 2018 | Completed final sign-off Oct 2018 | 210 Ivy St | all work is at unit 210 on 4th fl. remodel kitchen & bath. replace water heater with tankless unit. add two skylights. no structural work.Details
all work is at unit 210 on 4th fl. remodel kitchen & bath. replace water heater with tankless unit. add two skylights. no structural work. | $22,000 | |
| Apr 10, 2018 | Completed final sign-off Aug 2019 | 1256 Francisco St | Alex R Construction | remodel: 1st flr - 2 street entries, garage w/1/2 bath, fam rm w/bath, new int stairs.2md flr - liv rm, din rm, kit 3 bed, 2 baths, ldry rm. 3rd flr - liv rm, din rm, kit 3 bed, 2 baths, ldry rm. 4th flr - fam rm, convert 1/2 bath to full bath, new roof deck.Details
remodel: 1st flr - 2 street entries, garage w/1/2 bath, fam rm w/bath, new int stairs.2md flr - liv rm, din rm, kit 3 bed, 2 baths, ldry rm. 3rd flr - liv rm, din rm, kit 3 bed, 2 baths, ldry rm. 4th flr - fam rm, convert 1/2 bath to full bath, new roof deck. | $450,000 |
| Mar 19, 2018 | Completed final sign-off Jul 2019 | 17 Temple St | Kenneally Construction | to comply with complaint #201838421 revised demo calcs per sf panning ref 201404223783Details
to comply with complaint #201838421 revised demo calcs per sf panning ref 201404223783 | |
| Feb 27, 2018 | Completed final sign-off Mar 2021 | 553 15th Av | K. Kinahan Construction | horizontal addition & interior remodel to include: 1st flr - garage, multi purpose rm, 1/2 bath. 2nd flr - entry, living, dining, kitchen, 1/2 bath, family rm. 3rd flr - (3) bdrms, (3) baths & laundry.Details
horizontal addition & interior remodel to include: 1st flr - garage, multi purpose rm, 1/2 bath. 2nd flr - entry, living, dining, kitchen, 1/2 bath, family rm. 3rd flr - (3) bdrms, (3) baths & laundry. | $450,000 |
| Feb 23, 2018 | Completed final sign-off May 2023 | 4363 26th St | Gama Construction Inc, Ace Drilling & Excavation | vertical & horizontal additions to include: basement- entry, elevator, wine rm, garage. 1st flr - (4) bdrms, (3) baths, laundry. 2nd fl - living, dining, kitchen, 1/2 bath, decks. 3rd fl - family rm, office bath & deck.Details
vertical & horizontal additions to include: basement- entry, elevator, wine rm, garage. 1st flr - (4) bdrms, (3) baths, laundry. 2nd fl - living, dining, kitchen, 1/2 bath, decks. 3rd fl - family rm, office bath & deck. | $650,000 |
| Feb 23, 2018 | Completed final sign-off Apr 2018 | 930 Shotwell St | revision to permit #201501145741. add skylights, reconfigure bathroom & wet bar, for accessory office at rear. to comply with nov #201774311. n/a maherDetails
revision to permit #201501145741. add skylights, reconfigure bathroom & wet bar, for accessory office at rear. to comply with nov #201774311. n/a maher | $5,000 | |
| Feb 1, 2018 | Completed final sign-off Mar 2021 | 3790 21st St | revision to 201504103305, basement move stairs to yard from interior to exterior, shift lite well at sideyard 2' south. 1st fl replace windows and door east wall w 16' sl door with 42" h gaurdrailDetails
revision to 201504103305, basement move stairs to yard from interior to exterior, shift lite well at sideyard 2' south. 1st fl replace windows and door east wall w 16' sl door with 42" h gaurdrail | ||
| Jan 16, 2018 | Completed final sign-off Sep 2022 | 65 Almaden Ct | Duffin Construction | replace internal stairs, install 5 lew skylights, add 2 bedrooms, replace 1/2 bath with full bath at 1st fl enclose atrium, add 1 / 1/2 bath, remodel kitchen and bathDetails
replace internal stairs, install 5 lew skylights, add 2 bedrooms, replace 1/2 bath with full bath at 1st fl enclose atrium, add 1 / 1/2 bath, remodel kitchen and bath | $270,000 |
| Jan 11, 2018 | Expired or cancelled withdrawn Jan 2018 | 625 San Jose Av | 1st fl infill area under e 2nd fl. rear extension remodel area behind garage to include fam rm, bdrm, bath, 1/2 bath, study, remove ext stairs at north lightwell, install new furnace and w htr, 2nd fl enclose roofed porch north elev to create interior stairs, reconfigure 2ndDetails
1st fl infill area under e 2nd fl. rear extension remodel area behind garage to include fam rm, bdrm, bath, 1/2 bath, study, remove ext stairs at north lightwell, install new furnace and w htr, 2nd fl enclose roofed porch north elev to create interior stairs, reconfigure 2nd | $225,000 | |
| Nov 2, 2017 | Completed final sign-off May 2018 | 15 Sunview Dr | Bay C T Construction Inc. | add rooms @ 1st floor to include family room, bath, laundry garage. replace 1st floor window @ front elevation; all work is within (e) envelopeDetails
add rooms @ 1st floor to include family room, bath, laundry garage. replace 1st floor window @ front elevation; all work is within (e) envelope | $41,000 |
| Oct 20, 2017 | Completed final sign-off Oct 2018 | 310 Richland Av | M Bay Area Construction Inc | rear bldg -remodel storage area at 1st floor to include 2 bedrooms & 1 full bath.Details
rear bldg -remodel storage area at 1st floor to include 2 bedrooms & 1 full bath. | $50,000 |
| Oct 17, 2017 | In progress issued Dec 2023 | 46 Homestead St | Pio Mcgarr Inc | horizontal & vertical addition to 3 story sfr.Details
horizontal & vertical addition to 3 story sfr. | $750,000 |
| Oct 12, 2017 | Completed final sign-off Dec 2019 | 2832 Bryant St | W F Construction Co | construct (1) bedroom, (1) bath adu unit @ 1st floor per ord #162-16Details
construct (1) bedroom, (1) bath adu unit @ 1st floor per ord #162-16 | $65,000 |
| Aug 3, 2017 | Completed final sign-off Feb 2019 | 255 Moncada Wy | 1st fl - convert storage to 840 sf of conditioned rooms with mudroom, family room, bedroom, bath. replace furnace & water heater. replace interior stairs to 2nd floor. remove exterior wood stairs @ south elevation. excavate 18" down at crawl space.Details
1st fl - convert storage to 840 sf of conditioned rooms with mudroom, family room, bedroom, bath. replace furnace & water heater. replace interior stairs to 2nd floor. remove exterior wood stairs @ south elevation. excavate 18" down at crawl space. | $84,000 | |
| Jul 13, 2017 | Completed final sign-off Nov 2017 | 408 Elizabeth St | replace fixed door panels at front elevtion with wood siding & trim to match adjacent siding.Details
replace fixed door panels at front elevtion with wood siding & trim to match adjacent siding. | $2,500 | |
| Jul 7, 2017 | Completed final sign-off May 2018 | 1163 Shotwell St | revision to #201511102199. reconfigure 2nd fl landing & stairs from family room to rear yard.Details
revision to #201511102199. reconfigure 2nd fl landing & stairs from family room to rear yard. | $500 | |
| Jun 16, 2017 | Completed final sign-off Jun 2021 | 579 Clipper St | Pio Mcgarr Inc, Tri-Star Home Improvement Inc. | remodel 2 story sfr to 3rd story sfr. with 3 rd floor addition to include 3 bedrms, 2 baths.Details
remodel 2 story sfr to 3rd story sfr. with 3 rd floor addition to include 3 bedrms, 2 baths. | $550,000 |
| Jun 13, 2017 | Completed final sign-off Jul 2018 | 102 Pierce St | Pio Mcgarr Inc | remodel unit 102: remodel kitchen, add sink at toilet room, enlarge opening in wall between sitchen & dining roomDetails
remodel unit 102: remodel kitchen, add sink at toilet room, enlarge opening in wall between sitchen & dining room | $24,300 |
| Jun 9, 2017 | Completed final sign-off Feb 2019 | 255 Moncada Wy | remove walls @ kitchen/dining & remodel kitchen @2nd flr. n/a for maher.Details
remove walls @ kitchen/dining & remodel kitchen @2nd flr. n/a for maher. | $32,000 | |
| May 30, 2017 | Completed final sign-off Jun 2017 | 1578 Fulton St | revision to 201605066738 & 201506098445: add wet bar at basement gym/media room.Details
revision to 201605066738 & 201506098445: add wet bar at basement gym/media room. | $750 | |
| Apr 20, 2017 | Expired or cancelled expired Apr 2022 | 3620 Taraval St | Cole's Construction | 2620 #1 enclose window and install skylight and kitchen const.firewall at skylight along west p.l. enclose door at storage closet. 2620 #2 remodel kitchen and bath, enclose lightwell, add 5 skylights and const. firewall along skylight at east p.l. remodel area behind garage to include bedroomDetails
2620 #1 enclose window and install skylight and kitchen const.firewall at skylight along west p.l. enclose door at storage closet. 2620 #2 remodel kitchen and bath, enclose lightwell, add 5 skylights and const. firewall along skylight at east p.l. remodel area behind garage to include bedroom | $94,500 |
| Apr 7, 2017 | Never finaled issued Apr 2017, no final | 200 Topeka Av | Lyons Building & Associates Inc. | convert storage space @ 1st floor to family room & bath. remodel kitchen & construct (n) stairs to 1st & 2nd floors @ mid level.Details
convert storage space @ 1st floor to family room & bath. remodel kitchen & construct (n) stairs to 1st & 2nd floors @ mid level. | $52,000 |
| Mar 30, 2017 | Completed final sign-off Aug 2018 | 1046 Haight St | Forever Construction, Custom Home Investment Inc. | apt 1046: relocate & remodel kitchen, remodel baths #1, #2, #3, wided door openings @ kitchen & living rms. install new furnance & w/hDetails
apt 1046: relocate & remodel kitchen, remodel baths #1, #2, #3, wided door openings @ kitchen & living rms. install new furnance & w/h | $80,500 |
| Mar 10, 2017 | Never finaled issued Mar 2017, no final | 1468 45th Av | 1470a - expand & remodel unit 1470b - add bath @ 1st floor bedroom add new doors and windows @1st flr rear elevationDetails
1470a - expand & remodel unit 1470b - add bath @ 1st floor bedroom add new doors and windows @1st flr rear elevation | $56,000 | |
| Feb 14, 2017 | Completed final sign-off Feb 2018 | 691 14th St | Schrobsdorff Construction | alter existing restroom to create ada code compliant bathroom. per planning code existing use grocery and liquor store. barrier removal. per planning code, existing use grocery and liquor storeDetails
alter existing restroom to create ada code compliant bathroom. per planning code existing use grocery and liquor store. barrier removal. per planning code, existing use grocery and liquor store | $10,000 |
| Feb 9, 2017 | Completed final sign-off Jun 2017 | 2686 44th Av | Ortizlaw Construction | remodel area at ground floor to include family room, bathroom and closet. relocate water heater.Details
remodel area at ground floor to include family room, bathroom and closet. relocate water heater. | $42,000 |
| Jan 20, 2017 | Expired or cancelled cancelled Feb 2026 | 3808 21st St | Nuport Construction Inc | revision to bldg app#2016-06-13-9729. basement: relocate bath, mech room and wine room. 1st floor: reconfigure bedroom suite. 2nd floor: relocate kitchen, remove window @ entry. rear elevation: reconfigure windows at 1st floor. struct-replace moment frames w/ shear walls.Details
revision to bldg app#2016-06-13-9729. basement: relocate bath, mech room and wine room. 1st floor: reconfigure bedroom suite. 2nd floor: relocate kitchen, remove window @ entry. rear elevation: reconfigure windows at 1st floor. struct-replace moment frames w/ shear walls. | $12,000 |
| Dec 23, 2016 | Never finaled issued Mar 2018, no final | 2563 47th Av | Kevin Sullivan Construction Inc. | add 15'x25' rear 2 story addition to include: 1st flr; add bdrm, bath, laundry & interior stairs. 2nd flr; remodel kitchen, add study & exterior stairs to rear yard & (2) skylights.Details
add 15'x25' rear 2 story addition to include: 1st flr; add bdrm, bath, laundry & interior stairs. 2nd flr; remodel kitchen, add study & exterior stairs to rear yard & (2) skylights. | $120,000 |
| Dec 15, 2016 | Completed final sign-off Apr 2017 | 930 Shotwell St | revision to 2012-0611-2282 - 2nd floor revise layout of stairs, closets & laundries. 3rd floor - add sink @ master bedrooms. roof - add sink & bbq @ roof deckDetails
revision to 2012-0611-2282 - 2nd floor revise layout of stairs, closets & laundries. 3rd floor - add sink @ master bedrooms. roof - add sink & bbq @ roof deck | $2,000 | |
| Nov 3, 2016 | Completed final sign-off May 2017 | 2455 Vallejo St | Luke Gilligan Inc. | revision 201603303424. 1st redesign stairs to 2nd flr/ add wetbar. 2nd flr: open new stairs to flr below. 3rd flr - relocate hall wall, reconfigure mstr bath, delete (2) skylights. 4th flr - replace proposed pocket door w/barn door, enlarge (e) showerDetails
revision 201603303424. 1st redesign stairs to 2nd flr/ add wetbar. 2nd flr: open new stairs to flr below. 3rd flr - relocate hall wall, reconfigure mstr bath, delete (2) skylights. 4th flr - replace proposed pocket door w/barn door, enlarge (e) shower | $4,000 |
| Sep 9, 2016 | Completed final sign-off May 2018 | 1163 Shotwell St | revision to 201511102199 revise patio layout @ rear yard. (n) patio to be 4'x13'-11"Details
revision to 201511102199 revise patio layout @ rear yard. (n) patio to be 4'x13'-11" | $4,200 | |
| Aug 30, 2016 | Completed final sign-off Dec 2016 | 2725 Sutter St | Planet Builders | 1st floor - add family room, bath, laundry closet @ storage area behind garageDetails
1st floor - add family room, bath, laundry closet @ storage area behind garage | $56,000 |
| Aug 25, 2016 | Completed final sign-off Aug 2018 | 1050 Page St | 3rd flr remodel bath, convert dressing room & lightwell to bath #2, convert storage room to laundry, add closet at bedroom #3, infill lightwell on the 3rd floor.Details
3rd flr remodel bath, convert dressing room & lightwell to bath #2, convert storage room to laundry, add closet at bedroom #3, infill lightwell on the 3rd floor. | $41,000 | |
| Aug 9, 2016 | Completed final sign-off Feb 2017 | 537 Gennessee St | Matt Sanford Homes | 2nd flr: relocate opening between kitchen & living room. install (n) fireplace insert, remodel kitchen & bathroom, reconfigure closet & install new exterior door & window, install new exterior stairs to rear yardDetails
2nd flr: relocate opening between kitchen & living room. install (n) fireplace insert, remodel kitchen & bathroom, reconfigure closet & install new exterior door & window, install new exterior stairs to rear yard | $42,000 |
| Jul 26, 2016 | Completed final sign-off Oct 2016 | 300 Sanchez St | Bay Metro Corporation | construct partition walls at reception area. remodel toilet room to full ada complianceDetails
construct partition walls at reception area. remodel toilet room to full ada compliance | $60,000 |
| Jul 12, 2016 | Never finaled issued Nov 2019, no final | 149 Mangels Av | erect 3-story, no basement, single family dwelling. sprinkler under 13r and sprinkler monitoring under sep permits.Details
erect 3-story, no basement, single family dwelling. sprinkler under 13r and sprinkler monitoring under sep permits. | $450,000 | |
| Jun 27, 2016 | Completed final sign-off Sep 2016 | 510 22nd Av | Kevin Lin Construction Inc | replace 4 (e) windows at rear elevation. 1st flr- remove washer/dryer & sink. 2nd flr- convert toilet room to laundry w/sink, reconfigure storage/breakfast room to bath & study. 3rd flr - remodel bathDetails
replace 4 (e) windows at rear elevation. 1st flr- remove washer/dryer & sink. 2nd flr- convert toilet room to laundry w/sink, reconfigure storage/breakfast room to bath & study. 3rd flr - remodel bath | $35,000 |
| Jun 13, 2016 | Expired or cancelled cancelled Feb 2026 | 3808 21st St | changes per boa decision. relocate dormer, reconfigure windows @ rear elevation. ref bpa201511162744Details
changes per boa decision. relocate dormer, reconfigure windows @ rear elevation. ref bpa201511162744 | ||
| May 6, 2016 | Completed final sign-off Jun 2017 | 1578 Fulton St | A F General Contractors Inc | revision to 2015-0609-8445 - remove (2) 2 story bay @ east elevation. add (2) 8'x8' dormers. replace mudroom @ rear elevation with roof deck. remove bay @ 1st fl @ rear elevation. remove (e) stairs @ rear deck. replace fence @ rear deck - reconfigure kitchens @ both unitsDetails
revision to 2015-0609-8445 - remove (2) 2 story bay @ east elevation. add (2) 8'x8' dormers. replace mudroom @ rear elevation with roof deck. remove bay @ 1st fl @ rear elevation. remove (e) stairs @ rear deck. replace fence @ rear deck - reconfigure kitchens @ both units | $55,000 |
| Apr 29, 2016 | Expired or cancelled cancelled Feb 2020 | 372 Laidley St | replace interior stairs to 2nd fl. relocate bedroom, study & sairs @ 1st fl. 2nd fl: add dormer @ front, east side of (e) roof. raise roof at middle section of (e) roof. reconfigure fl. plan to include 3 bedrooms,2 baths. add 6 skylights.Details
replace interior stairs to 2nd fl. relocate bedroom, study & sairs @ 1st fl. 2nd fl: add dormer @ front, east side of (e) roof. raise roof at middle section of (e) roof. reconfigure fl. plan to include 3 bedrooms,2 baths. add 6 skylights. | $150,000 | |
| Apr 20, 2016 | Completed final sign-off Sep 2019 | 515 Octavia St | legalize and remodel studio apartment at 1st fl. install new entry steps at sidewalk. increase size of 1 window and add 2 new windows at studio. relocate trash room in storage area. n/a for maher ordinance no. 155-13.Details
legalize and remodel studio apartment at 1st fl. install new entry steps at sidewalk. increase size of 1 window and add 2 new windows at studio. relocate trash room in storage area. n/a for maher ordinance no. 155-13. | $65,000 | |
| Apr 5, 2016 | Expired or cancelled withdrawn Feb 2017 | 917 Florida St | Hing Wah Construction Inc | revision to pa 2015-0903-6019, revise overall building depth & rear yard setbacks, reconfigure patio layout & revise interior wall demo calculations per revised floor plansDetails
revision to pa 2015-0903-6019, revise overall building depth & rear yard setbacks, reconfigure patio layout & revise interior wall demo calculations per revised floor plans | |
| Mar 30, 2016 | Completed final sign-off May 2017 | 2455 Vallejo St | Luke Gilligan Inc. | 1st floor - relocate stairs to 2nd flr, relocate bathroom; 2nd floor - remodel kitchen & dining areas; 3rd floor - add bathroom & laundry room, remodel master suite, install (3) skylights; 4th floor - add door @ top of stairs, change window & doors to sliding door @ 2nd floor.Details
1st floor - relocate stairs to 2nd flr, relocate bathroom; 2nd floor - remodel kitchen & dining areas; 3rd floor - add bathroom & laundry room, remodel master suite, install (3) skylights; 4th floor - add door @ top of stairs, change window & doors to sliding door @ 2nd floor. | $145,000 |
| Mar 18, 2016 | Completed final sign-off Oct 2016 | 253 Diamond St | Urban Builder General Contracting Inc | 4th floor: remodel kitchen & laundry area, add property line window @ kitchen - widen wall opening between kitchen & dining room. install header. sprinklers under separate permit per ab009.Details
4th floor: remodel kitchen & laundry area, add property line window @ kitchen - widen wall opening between kitchen & dining room. install header. sprinklers under separate permit per ab009. | $45,000 |
| Feb 5, 2016 | Completed final sign-off Feb 2017 | 2138 Jones St | revision to 201308225004 revise approved 2 story unit @ basement & 1st floor to (2) 1 story units, delete approved interior stairway. reconfigure basement plan to great room, bedroom, bath, study, media room. reconfigure 1st floor to great room, (2) bedrooms and bath.Details
revision to 201308225004 revise approved 2 story unit @ basement & 1st floor to (2) 1 story units, delete approved interior stairway. reconfigure basement plan to great room, bedroom, bath, study, media room. reconfigure 1st floor to great room, (2) bedrooms and bath. | $10,000 | |
| Jan 28, 2016 | Completed final sign-off Sep 2017 | 24 Hartford St | Pio Mcgarr Inc | revision to 2015-0918-7463 add 2 windows & relocate wet bar @ 1st floor. replace exterior sliding door with window & relocate kitchen and dining room at 2nd floor. add 3 skylights. revise structural details for entry stairsDetails
revision to 2015-0918-7463 add 2 windows & relocate wet bar @ 1st floor. replace exterior sliding door with window & relocate kitchen and dining room at 2nd floor. add 3 skylights. revise structural details for entry stairs | $3,600 |
| Jan 19, 2016 | Completed final sign-off Aug 2016 | 3658 18th St | Hing Wah Construction Inc | 1/f: move entry to multipurpose room from garage to hall, reconfigure bath #1, relocate laundry; 2/f: add 3 windows, move fireplace at great room; 3/f: add 3 windows & move fireplace @ great room, move wall @ kitchen, reconfigure bath #1, reconfigure closets @ bedrm 1,2,3.Details
1/f: move entry to multipurpose room from garage to hall, reconfigure bath #1, relocate laundry; 2/f: add 3 windows, move fireplace at great room; 3/f: add 3 windows & move fireplace @ great room, move wall @ kitchen, reconfigure bath #1, reconfigure closets @ bedrm 1,2,3. | $24,000 |
| Jan 6, 2016 | Expired or cancelled withdrawn Apr 2017 | 255 Moncada Wy | reconfigure rooms @ 3 levels & horizontal addition add 3 story addition @ rear. 1st fl to include garage, family room, study & bath. 2nd fl to include living, dining, kitche, 1 & 1/2baths, bedroom, 2 decks. 3rd fl to include 3 bedrooms. 2 baths, laundry rm. n/a for maher ordinance no 155-13.Details
reconfigure rooms @ 3 levels & horizontal addition add 3 story addition @ rear. 1st fl to include garage, family room, study & bath. 2nd fl to include living, dining, kitche, 1 & 1/2baths, bedroom, 2 decks. 3rd fl to include 3 bedrooms. 2 baths, laundry rm. n/a for maher ordinance no 155-13. | $440,000 | |
| Dec 22, 2015 | Completed final sign-off Feb 2018 | 7 Bennington St | Brady Construction Inc, Dugarry Construction Inc | 1st flr. remodel storage area behind garage to add bedroom, bath & media room. 2nd flr- remove non bearing wall between living & dining rms, build (n) enclosed stairway to 1st flr, remove deck & stairs @ rear yard.Details
1st flr. remodel storage area behind garage to add bedroom, bath & media room. 2nd flr- remove non bearing wall between living & dining rms, build (n) enclosed stairway to 1st flr, remove deck & stairs @ rear yard. | $85,000 |
| Dec 22, 2015 | Expired or cancelled cancelled Aug 2022 | 1634 Alabama St | add n unit @ 1st flr horizontal addition.remodel storage area behind garage & add 12'x25' 1 story addition w/roof deck @ rear yard. remodel & addition to include 2 bedrooms, bath, multipurpose rm, 2nd fl-expand bathroom into south lightwell, install (n) doors @ (n) rear deck.Details
add n unit @ 1st flr horizontal addition.remodel storage area behind garage & add 12'x25' 1 story addition w/roof deck @ rear yard. remodel & addition to include 2 bedrooms, bath, multipurpose rm, 2nd fl-expand bathroom into south lightwell, install (n) doors @ (n) rear deck. | $94,000 | |
| Dec 15, 2015 | Completed final sign-off Aug 2016 | 685 Victoria St | revision to app#201510018507. rebuild 2nd floor entry porch and stair in kind due to dryrot. extend conditioned space at 1st floor to the area under the porch. add laundry room at 1st floor. fireplace and install new direct vent unit. rebuild chimney in kind.Details
revision to app#201510018507. rebuild 2nd floor entry porch and stair in kind due to dryrot. extend conditioned space at 1st floor to the area under the porch. add laundry room at 1st floor. fireplace and install new direct vent unit. rebuild chimney in kind. | $18,000 | |
| Nov 16, 2015 | Expired or cancelled cancelled Feb 2026 | 3808 21st St | add basement, garage @ 1st floor & room @ attic. basement to have family room & bath; 2nd floor - living, dining, kitchen. 3rd floor-3 bedrooms, 2 baths, (n) 4th floor - family room, 1/2 bath roof deck replace entry stairs. install sprinkler system. 2 new dormersDetails
add basement, garage @ 1st floor & room @ attic. basement to have family room & bath; 2nd floor - living, dining, kitchen. 3rd floor-3 bedrooms, 2 baths, (n) 4th floor - family room, 1/2 bath roof deck replace entry stairs. install sprinkler system. 2 new dormers | $650,000 | |
| Nov 10, 2015 | Completed final sign-off May 2018 | 1163 Shotwell St | remodel storage area @ garage level to include 1034 sf 1 bedroom unit, lower entry,storage rm & stairs to 2nd fl. reconfigure 2nd fl to include living,dining rm, 1/2 bath,reconfigu 3 fl unit to become 4 bedrooms, 3 baths, laundry closet. replace e front stairs, add roof deck,remove shed @ rear yard.Details
remodel storage area @ garage level to include 1034 sf 1 bedroom unit, lower entry,storage rm & stairs to 2nd fl. reconfigure 2nd fl to include living,dining rm, 1/2 bath,reconfigu 3 fl unit to become 4 bedrooms, 3 baths, laundry closet. replace e front stairs, add roof deck,remove shed @ rear yard. | $434,000 | |
| Oct 8, 2015 | Completed final sign-off Sep 2017 | 24 Hartford St | Pio Mcgarr Inc | revision to pa 2015-0918-7463, infill area 2nd fl @ rear yard. remodel area behind garate to include 1 bedroom, 1.5 baths, family room, laundry. reconfigure 2nd fl to include living, dining, kitchen, half bath. recon- figure 3rd fl to include 2 bedrooms, 2 bath, roof deck, add 3 dormersDetails
revision to pa 2015-0918-7463, infill area 2nd fl @ rear yard. remodel area behind garate to include 1 bedroom, 1.5 baths, family room, laundry. reconfigure 2nd fl to include living, dining, kitchen, half bath. recon- figure 3rd fl to include 2 bedrooms, 2 bath, roof deck, add 3 dormers | $290,000 |
| Oct 1, 2015 | Never finaled issued Oct 2015, no final | 3932 23rd St | Dugarry Construction Inc | revision to 201307292931. replace window at east wall with larger window, delete window at north wall, remove door to corridor at north wallDetails
revision to 201307292931. replace window at east wall with larger window, delete window at north wall, remove door to corridor at north wall | |
| Oct 1, 2015 | Completed final sign-off Aug 2016 | 685 Victoria St | 1st fl remodel plan to add 3 bedrooms, 3 baths. relocate inerior stairs. 2nd fl remodel kitchen and bath, remove 1 bath. remove walls at living and dining rooms. relocate interior stairs reduce size of deck.Details
1st fl remodel plan to add 3 bedrooms, 3 baths. relocate inerior stairs. 2nd fl remodel kitchen and bath, remove 1 bath. remove walls at living and dining rooms. relocate interior stairs reduce size of deck. | $220,000 | |
| Sep 18, 2015 | Completed final sign-off Sep 2017 | 24 Hartford St | Pio Mcgarr Inc | foundation replacement & lower the foundations and slab. temporary shoring to facilitate excavation and construction of (n) foundation.Details
foundation replacement & lower the foundations and slab. temporary shoring to facilitate excavation and construction of (n) foundation. | $50,000 |
| Sep 14, 2015 | Completed final sign-off Oct 2016 | 3843 26th St | Box Canyon Builders Dba The Englander | infill open area below 2nd fl at rear yard to include new bedroom and bath. remove interior walls and reconfigure plan at 2nd fl. relocate int. stairs to 1st flDetails
infill open area below 2nd fl at rear yard to include new bedroom and bath. remove interior walls and reconfigure plan at 2nd fl. relocate int. stairs to 1st fl | $42,000 |
| Sep 10, 2015 | Completed final sign-off Aug 2016 | 3658 18th St | Hing Wah Construction Inc | replace proposed roof hatch with stair penthouse.Details
replace proposed roof hatch with stair penthouse. | $18,000 |
| Sep 3, 2015 | Completed final sign-off Jan 2017 | 917 Florida St | Hing Wah Construction Inc | remove 1 story shed at rear yard, replace entry stairs at front. reconfigure storage area at 1st fl. to include 3 bedrooms, 2 baths, laundry. reconfigure 2nd fl. to include bedroom, study, 1 and half baths, greatroom, and rear deck with stairs to yard.Details
remove 1 story shed at rear yard, replace entry stairs at front. reconfigure storage area at 1st fl. to include 3 bedrooms, 2 baths, laundry. reconfigure 2nd fl. to include bedroom, study, 1 and half baths, greatroom, and rear deck with stairs to yard. | $325,000 |