Adam Wing
- Listed as
- architect, designer
- Firm
- Arcsine
- Based in
- Oakland
- On San Francisco permits
- May 2007 to Jan 2024
34 permits since 2000 (architect on 33 permits, designer on 1 permit): 24 completed, 1 in progress, 6 never finaled, 3 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 12, 2024 | In progress filed Jan 2024, not yet issued | 2 New Montgomery St | minor remodel of extg bar, including new millwork, bar equipment and associated electrical and plumbingDetails
minor remodel of extg bar, including new millwork, bar equipment and associated electrical and plumbing | $150,000 | |
| Jul 20, 2023 | Completed final sign-off Jan 2024 | 2663 Filbert St | Dcs Plumbing Llc | 2-bathroom remodels: demo of existing plumbing fixtures and interior finishes, demo of 2 non-load bearing partitions, new plumbing fixtures and finishes, new light fixtures, outlets and switches. no exterior work, no structural work.Details
2-bathroom remodels: demo of existing plumbing fixtures and interior finishes, demo of 2 non-load bearing partitions, new plumbing fixtures and finishes, new light fixtures, outlets and switches. no exterior work, no structural work. | $30,000 |
| Oct 6, 2022 | Completed final sign-off Apr 2023 | 101 Market St | Tcg Builders Inc Dba The Core Group | existing chainlink and steel fence to be extended vertically from approximately 6'0" to 9'3".Details
existing chainlink and steel fence to be extended vertically from approximately 6'0" to 9'3". | $130,000 |
| Dec 9, 2020 | Never finaled issued Jan 2021, no final | 350 Mission St | Hp Build | partial removal and replacement of millwork in the dining room of (e) restaurant. project does not propose a change in use or occupancy. projects does not incl changes to mech or plumb. no changes to (e) kitchen. electrical scope is design build by gc.Details
partial removal and replacement of millwork in the dining room of (e) restaurant. project does not propose a change in use or occupancy. projects does not incl changes to mech or plumb. no changes to (e) kitchen. electrical scope is design build by gc. | $113,949 |
| Aug 20, 2020 | Never finaled filed Aug 2020, never issued | 599 Skyline Bl | Terra Nova Industries | new service elevator & control room within building footprint serving ground & basement levels. associated structural, mechanical, electrical.Details
new service elevator & control room within building footprint serving ground & basement levels. associated structural, mechanical, electrical. | $100,000 |
| Jul 19, 2019 | Completed final sign-off Feb 2020 | 665 Sutter St | Hp Build | interior renovation finishes * lighting no mech or plm., in conjuctin woith 201907176128Details
interior renovation finishes * lighting no mech or plm., in conjuctin woith 201907176128 | $200,000 |
| Jul 17, 2019 | Completed final sign-off Feb 2020 | 524 Post St | Hp Build | interior renovation of (e) cafe. new kitchen equipment, lighting and finishes.Details
interior renovation of (e) cafe. new kitchen equipment, lighting and finishes. | $350,000 |
| May 26, 2017 | Completed final sign-off May 2019 | 905 California St | Hathaway Dinwiddie Co. | revision to app#201612155120 for building envelope title 24 documentation.Details
revision to app#201612155120 for building envelope title 24 documentation. | |
| May 3, 2017 | Completed final sign-off May 2018 | 905 California St | Hathaway Dinwiddie Co. | removal of (1) 610 sf aluminum & glass skylight at unoccupied roof, roof area will remain service access only. no electrical or mechanical work. no modification to (e) load-bearing structural framing. no modifications to (e) accessible site features.Details
removal of (1) 610 sf aluminum & glass skylight at unoccupied roof, roof area will remain service access only. no electrical or mechanical work. no modification to (e) load-bearing structural framing. no modifications to (e) accessible site features. | $15,000 |
| Jan 23, 2017 | Never finaled issued May 2017, no final | 333 Ofarrell St | Cw Horton General Contractor | barrier removal. general renovation of existing parking level and accessibility upgrade along the path of travel. work inclues accessible parking spot restriping to bring up to cook. work tower 111 on floor 1, 6, 7,8, 9, 10, 11Details
barrier removal. general renovation of existing parking level and accessibility upgrade along the path of travel. work inclues accessible parking spot restriping to bring up to cook. work tower 111 on floor 1, 6, 7,8, 9, 10, 11 | $62,000 |
| Dec 28, 2016 | Completed final sign-off May 2019 | 905 California St | Hathaway Dinwiddie Co. | conversion of (e) fitness on 1st flr level to 4 new guestrooms, conversion of (e) business center & guest lounge on 6th flr level to 3 new guest rooms, 1 of which is proposed to be fully accessible modification to other accessible room as levels 1-8 to meet current accessible code req'd. interior..Details
conversion of (e) fitness on 1st flr level to 4 new guestrooms, conversion of (e) business center & guest lounge on 6th flr level to 3 new guest rooms, 1 of which is proposed to be fully accessible modification to other accessible room as levels 1-8 to meet current accessible code req'd. interior.. | $439,810 |
| Dec 15, 2016 | Completed final sign-off May 2019 | 905 California St | Hathaway Dinwiddie Co. | renovation of public areas of (e) hotel. interior work @ (e) lobby, dining & bar includes demo, new partitions, casework, wall, ceiling & floor finishes. elec, plumb work per plans. (e) hvac system to reamin. (e) diffusers may be relocated as required by work. exterior work include new glazed entryDetails
renovation of public areas of (e) hotel. interior work @ (e) lobby, dining & bar includes demo, new partitions, casework, wall, ceiling & floor finishes. elec, plumb work per plans. (e) hvac system to reamin. (e) diffusers may be relocated as required by work. exterior work include new glazed entry | $2,003,538 |
| Aug 2, 2016 | Completed final sign-off Sep 2017 | 333 Ofarrell St | Hathaway Dinwiddie Co. | renovation to (e) women's & men's locker rooms to include demo of lockers, lavatories, urinals, toilet stalls & showers. all items to be renovated to comply with current code & provide (n) finishes. n/a ordinance #155-13Details
renovation to (e) women's & men's locker rooms to include demo of lockers, lavatories, urinals, toilet stalls & showers. all items to be renovated to comply with current code & provide (n) finishes. n/a ordinance #155-13 | $190,000 |
| Jul 8, 2016 | Completed final sign-off May 2019 | 440 Geary St | Plant Construction Co, Lp | 1st floor - removal of (e) infill to expose frame opening for window. addition of 1 new window at 1st flr exterior not visible in public right of way.Details
1st floor - removal of (e) infill to expose frame opening for window. addition of 1 new window at 1st flr exterior not visible in public right of way. | |
| Jun 7, 2016 | Expired or cancelled cancelled Oct 2020 | 1818 Lombard St | extend (e) office & residential units to front property line. enclose (e) roof deck & add (n) roof deck above. renovate (e) garage & add basement & (2) living units above. both units will have bathroom & kitchens. ** maher: n/a **Details
extend (e) office & residential units to front property line. enclose (e) roof deck & add (n) roof deck above. renovate (e) garage & add basement & (2) living units above. both units will have bathroom & kitchens. ** maher: n/a ** | $600,000 | |
| Dec 18, 2015 | Completed final sign-off Jan 2020 | 440 Geary St | Plant Construction Co, Lp | addition of 14 guestrooms, 2 rooms accessible and 12 are for hearing impaired. t.i. includes excercise room on 1st floor.Details
addition of 14 guestrooms, 2 rooms accessible and 12 are for hearing impaired. t.i. includes excercise room on 1st floor. | $1,200,000 |
| Jul 6, 2015 | Never finaled issued Jul 2015, no final | 333 Ofarrell St | Plant Construction Co, Lp | grnd flr: interior demo of non-load bearing walls, finishes, equipment, light fixtures, to comply with ab017, no exterior or stuctural work under permit; maher n/aDetails
grnd flr: interior demo of non-load bearing walls, finishes, equipment, light fixtures, to comply with ab017, no exterior or stuctural work under permit; maher n/a | $7,500 |
| Apr 24, 2015 | Completed final sign-off Apr 2017 | 333 Ofarrell St | Plant Construction Co, Lp | renovation of (e) ground fl lobby to include (n) bar w/ lounge seating & nearby dining areas. alterations to include (n) finishes, lighting, furniture, millwork & food service equipment. scope also includes upgrades to (e) interior ramp to become fully accessible. l/s and sprinklers under sep.permitDetails
renovation of (e) ground fl lobby to include (n) bar w/ lounge seating & nearby dining areas. alterations to include (n) finishes, lighting, furniture, millwork & food service equipment. scope also includes upgrades to (e) interior ramp to become fully accessible. l/s and sprinklers under sep.permit | $2,046,207 |
| Mar 3, 2015 | Completed final sign-off Nov 2017 | 387 Arlington St | horizontal addition to rear of (e) house; approximately 81 sq ft; alteration of (e) half bath & exterior deck.Details
horizontal addition to rear of (e) house; approximately 81 sq ft; alteration of (e) half bath & exterior deck. | $90,000 | |
| Jun 14, 2013 | Expired or cancelled expired May 2015 | 2146 Chestnut St | renoveation of (e) storefront to accomodate new tenant.Details
renoveation of (e) storefront to accomodate new tenant. | $20,000 | |
| Mar 14, 2012 | Completed final sign-off Jul 2012 | 314 Sutter St | Terra Nova Industries, Zebra Awning Co Inc | fabricate & install (3) triangle style steele frame fabric cover. install on (3) mezzanine windows. graphics on center awning.Details
fabricate & install (3) triangle style steele frame fabric cover. install on (3) mezzanine windows. graphics on center awning. | $6,000 |
| Mar 14, 2012 | Completed final sign-off Jul 2012 | 314 Sutter St | Terra Nova Industries, Zebra Awning Co Inc | erect (2) wall projecting, non electric ,double faced sign.Details
erect (2) wall projecting, non electric ,double faced sign. | $6,000 |
| Mar 14, 2012 | Completed final sign-off Aug 2012 | 314 Sutter St | Terra Nova Industries | new paint 1st + mezzanie level. new door hardware including pust button ada access. (2) new lite nenu boards. (e) light location. new fixtures cladding of entry door and window system with trespa wood. ext. store front to remain ext shutters. (n) wood applied.Details
new paint 1st + mezzanie level. new door hardware including pust button ada access. (2) new lite nenu boards. (e) light location. new fixtures cladding of entry door and window system with trespa wood. ext. store front to remain ext shutters. (n) wood applied. | $30,000 |
| Apr 15, 2011 | Completed final sign-off Nov 2011 | 1156 Vallejo St | Momentum Builders Sf Inc | non structural interior renovation to 2nd fl unit #200 of an (e) 4 story bldg. remodel kitchen, master bathroom, master bedroom, guest bedroom & flooring throughout unit. worek is on unit #200 only, 2nd floor. deferred permit on electrical & plumbing. window ufactor .40, lighting changes cec 150kDetails
non structural interior renovation to 2nd fl unit #200 of an (e) 4 story bldg. remodel kitchen, master bathroom, master bedroom, guest bedroom & flooring throughout unit. worek is on unit #200 only, 2nd floor. deferred permit on electrical & plumbing. window ufactor .40, lighting changes cec 150k | $89,000 |
| Mar 30, 2011 | Completed final sign-off Feb 2012 | 2170 Mission St | J M E Construction Services Inc | a new storefront under the existing facade to enclose an additional 42 sq ft. the new storefront will include an entry door, sliding windows & awning. new signage will be under a different permit. no interior work is planned under this permit.Details
a new storefront under the existing facade to enclose an additional 42 sq ft. the new storefront will include an entry door, sliding windows & awning. new signage will be under a different permit. no interior work is planned under this permit. | $15,000 |
| Feb 23, 2011 | Completed final sign-off Mar 2011 | 1818 Lombard St | L P Construction | revision 2008-06-93991: a door was added between (connecting) dwelling units. this door will have deadbolts from each unit.Details
revision 2008-06-93991: a door was added between (connecting) dwelling units. this door will have deadbolts from each unit. | $100 |
| Dec 24, 2009 | Expired or cancelled cancelled May 2020 | 721 Clementina St | remodel first two floors & add 2 additional stories of residential. convert (e) 2nd floor to residential. add roof deck & penthouse for stair above 4th floor.Details
remodel first two floors & add 2 additional stories of residential. convert (e) 2nd floor to residential. add roof deck & penthouse for stair above 4th floor. | $200,000 | |
| Jan 7, 2009 | Completed final sign-off Jul 2009 | 1818 Lombard St | work in 1818 lombard street-revision to pa# 2008-1006-3429-replace ramp/lift with inclined stair liftDetails
work in 1818 lombard street-revision to pa# 2008-1006-3429-replace ramp/lift with inclined stair lift | ||
| Oct 6, 2008 | Completed final sign-off Jul 2009 | 1818 Lombard St | revision to appl #200805192312 - ada compliant ramp to be refplaced by ada compliant lift.Details
revision to appl #200805192312 - ada compliant ramp to be refplaced by ada compliant lift. | ||
| Jun 9, 2008 | Completed final sign-off Mar 2011 | 1818 Lombard St | add third floor addition on top of (e) two story portion of back of house. add dormers to attic and change use from attic to habitable space.Details
add third floor addition on top of (e) two story portion of back of house. add dormers to attic and change use from attic to habitable space. | $240,000 | |
| Mar 6, 2008 | Completed final sign-off May 2008 | 100 Moncada Wy | interior renovation at 1st floor level only: new mill work, replace (e) electrical & plumbing @ wet bar & laundry room; partial removal of 1 wall.Details
interior renovation at 1st floor level only: new mill work, replace (e) electrical & plumbing @ wet bar & laundry room; partial removal of 1 wall. | $20,000 | |
| Jun 15, 2007 | Completed final sign-off Apr 2008 | 52 Tamalpais Tr | remodel bathroom and bedroom on 1st floor. replace single paved windows and doors with new doublae paned to match (e). remodel master bathroom on 2nd floorDetails
remodel bathroom and bedroom on 1st floor. replace single paved windows and doors with new doublae paned to match (e). remodel master bathroom on 2nd floor | $45,000 | |
| May 3, 2007 | Never finaled issued May 2015, no final | 1425 Mendell St | Dajani Construction | to erect 5 stories office building.Details
to erect 5 stories office building. | $450,000 |
| May 3, 2007 | Never finaled issued May 2015, no final | 1425 Mendell St | Dajani Construction | to demolish 2 stories office building.Details
to demolish 2 stories office building. |